Operations
Operations of funding partners in Haiti, as each partner reports them. Data as of October 18, 2026.
| Stock at October 18, 2026, US$ millions | Flow, US$ millions | |||||||||
|---|---|---|---|---|---|---|---|---|---|---|
| Stock at October 18, 2026, US$ millions | ||||||||||
| Operation | Stage | Sector | Departments | Approval or start | Closing | Approved (net commitment, US$ at the data date) definition | Disbursed to date definition | Undisbursed definition | Disbursed in FY2026-27 definition | |
| Total, funding partners (128 operations) | 828.0sum of those reporting, 122 of 127 | 569.8sum of those reporting, 62 of 127 | No total12.3, 9 of 127 operations | Not reported | ||||||
| Haiti Economic Governance Reform Operation | Closed | Energy | Not reported | Jan 2005 | Mar 2006 | 61.0 | 61.2 | 0.0 | None to date | |
| Rebuilding Energy Infrastructure and Access | Closed | Energy | Ouest, Centre, Sud, Nord, Artibonite | Sep 2012 | Aug 2020 | 55.7 | 42.6 | 0.0 | None to date | |
| Renewable Energy for All | Under way | Energy | Sud, Artibonite, Nord-Ouest, Ouest, Centre, Grande Anse, Sud-Est, Nord | Oct 2017 | Jun 2027 | 50.1 | 12.3 | 12.3 | None to date | |
| Scaling Smart, Solar, Energy Access Microgrids | Approved | Energy | Not reported | Mar 2020 | Sep 2028 | 45.7 | Not reported | Not reported | Not reported | |
| Rehabilitation of the Péligre hydroelectric power plant | Closed | Energy | Ouest | Feb 2011 | Jun 2022 | 38.9 | 32.4 | Not reported | None to date | |
| Operation and management of the Caracol Power Plant | Closed | Energy | Nord-Est, Nord | May 2013 | Oct 2024 | 36.2 | 36.2 | Not reported | None to date | |
| Institutional Transformation and Modernization Program of the Energy Sector I | Closed | Energy | Not reported | Jul 2011 | Aug 2011 | 35.0 | 35.0 | Not reported | None to date | |
| Improving Electricity Access | Under way | Energy | Not reported | Nov 2019 | Dec 2026 | 31.5 | 28.0 | Not reported | None to date | |
| Power III (SDR-23.1) | Closed | Energy | Not reported | Jul 1982 | Not reported | 26.0 | 24.9 | 0.0 | None to date | |
| POWER V | Closed | Energy | Not reported | Jun 1989 | Jan 1999 | 23.2 | 25.5 | 0.0 | None to date | |
| Power IV-a | Closed | Energy | Not reported | Nov 1984 | Not reported | 22.1 | 26.7 | 0.0 | None to date | |
| Institutional Transformation and Modernization Program of the Energy Sector III | Closed | Energy | Not reported | Jun 2013 | Sep 2013 | 22.0 | 22.0 | Not reported | None to date | |
| Supplementary Financing for the Peligre Hydroelectric Plant | Closed | Energy | Not reported | Dec 2011 | Apr 2019 | 20.0 | 20.3 | Not reported | None to date | |
| Additional Financing: Haiti Renewable Energy For All | Under way | Energy | Not reported | Oct 2024 | Jun 2027 | 19.6 | Not reported | Not reported | Not reported | |
| Rehabilitation of Electricity Distribution System in Port au Prince | Closed | Energy | Not reported | Dec 2006 | Jun 2018 | 18.1 | 15.8 | Not reported | None to date | |
| Global Subnational Climate Fund (SnCF Global) – Equity | Under way | Energy | Not reported | Nov 2020 | Apr 2040 | 17.9 | 1.2 | Not reported | None to date | |
| Semi-autonomous Electricity Supply | Closed | Energy | Ouest | Dec 2007 | Dec 2013 | 17.5 | Not reported | Not reported | Not reported | |
| North Park power generation, transmission and distribution facilities | Closed | Energy | Not reported | Sep 2011 | May 2013 | 17.5 | 3.1 | Not reported | None to date | |
| POWER II | Closed | Energy | Not reported | Apr 1979 | Not reported | 16.5 | 16.5 | 0.0 | None to date | |
| Rehabilitation of Peligre Transmission Line | Closed | Energy | Not reported | Dec 2014 | Not reported | 16.0 | Not reported | Not reported | Not reported | |
| POWER I | Closed | Energy | Not reported | Jun 1976 | Not reported | 16.0 | 16.0 | 0.0 | None to date | |
| Haiti Modern Energy Services For All | Under way | Energy | Not reported | Oct 2017 | Apr 2028 | 15.7 | Not reported | Not reported | Not reported | |
| Reduce the cases of malaria | Closing | Energy | Ouest | Jan 2021 | Dec 2025 | 15.2 | 15.2 | Not reported | None to date | |
| Rehabilitate five substations in Port au Prince | Closed | Energy | Not reported | Jul 2011 | Apr 2013 | 14.9 | 7.4 | Not reported | None to date | |
| Rehabilitation of the Electricity Distribution System in Port-au-Prince | Closed | Energy | Not reported | Jul 2010 | Feb 2018 | 14.0 | 14.2 | Not reported | None to date | |
| Reinforcement of transmission lines and road infrastructure rehabilitation | Closed | Energy | Not reported | Nov 2010 | Not reported | 12.5 | Not reported | Not reported | Not reported | |
| Péligre Hydroelectric Plant Rehabilitation Program | Closed | Energy | Not reported | Dec 2008 | Dec 2016 | 12.5 | 32.3 | Not reported | None to date | |
| Institutional Transformation and Modernization Program of the Energy Sector II | Closed | Energy | Not reported | Jun 2012 | Jul 2012 | 12.0 | 12.0 | Not reported | None to date | |
| HT Electricity Project | Closed | Energy | Ouest, Sud-Est, Artibonite, Sud, Nord | Aug 2006 | Aug 2013 | 9.9 | 10.3 | 0.0 | None to date | |
| Technical, Operational and Programmatic Support (TOPS) | Closing | Energy | Not reported | Jul 2021 | Jul 2026 | 8.1 | 6.0 | Not reported | None to date | |
| Rehabilitation of the Peligre Transmission Line | Closed | Energy | Not reported | Dec 2014 | Dec 2019 | 7.7 | 7.8 | Not reported | None to date | |
| Renewable Energy for All | Approved | Energy | Sud-Est | Oct 2025 | Not reported | 7.1 | Not reported | Not reported | Not reported | |
| Access to electricity | Closing | Energy | Ouest | Jan 2018 | Jun 2025 | 6.9 | 7.0 | Not reported | None to date | |
| Improving Electricity Access | Closed | Energy | Not reported | Nov 2019 | Not reported | 6.5 | Not reported | Not reported | Not reported | |
| 4-MEGAWATT solar electricity generation plant at Caracol industrial park | Closed | Energy | Not reported | Aug 2020 | Aug 2026 | 6.2 | 6.2 | Not reported | None to date | |
| WINECO 2 | Closed | Energy | Not reported | Jun 2021 | Not reported | 5.7 | 5.7 | Not reported | None to date | |
| Barbancourt | Closed | Energy | Not reported | Nov 2023 | Not reported | 5.0 | 5.0 | Not reported | None to date | |
| Delimart | Stopped | Energy | Not reported | Oct 2019 | Not reported | 4.5 | 4.5 | Not reported | None to date | |
| Rehabilitation of Electrical Facilities | Closed | Energy | Ouest | Nov 2005 | Dec 2012 | 4.1 | Not reported | Not reported | Not reported | |
| Technical Assistance (Jacmel) - Phase III | Closed | Energy | Not reported | Mar 2005 | Mar 2011 | 4.0 | Not reported | Not reported | Not reported | |
| AEF-I-P10000353-002 | Closed | Energy | Not reported | Jul 2009 | Mar 2024 | 4.0 | 4.0 | Not reported | None to date | |
| SRUC task order under clean energy non-CPC IQC. | Closed | Energy | Not reported | Dec 2012 | Sep 2021 | 3.6 | 3.6 | Not reported | None to date | |
| Operate and maintain the 10-MW generation plant and distribution grid | Closed | Energy | Nord, Nord-Est | Feb 2020 | Sep 2024 | 3.5 | 3.5 | Not reported | None to date | |
| Institutional Transformation and Modernization of the Energy Sector III | Closed | Energy | Not reported | Jun 2013 | Not reported | 3.0 | Not reported | Not reported | Not reported | |
| Solengy Haiti: Co-Loan for Solar PV Solutions | Under way | Energy | Not reported | Dec 2024 | Not reported | 3.0 | 3.0 | Not reported | None to date | |
| Solengy Haiti | Under way | Energy | Not reported | Dec 2024 | Not reported | 3.0 | 3.0 | Not reported | None to date | |
| Solar PV ground mount and battery storage for the rural village of Dondon | Closed | Energy | Not reported | Jan 2021 | Dec 2022 | 3.0 | 2.7 | Not reported | None to date | |
| Energy Utility Partnership - USEA | Closed | Energy | Not reported | Sep 2007 | Sep 2018 | 2.9 | 3.4 | Not reported | None to date | |
| Additional Financing Haiti Renewable Energy for All | Under way | Energy | Artibonite | Sep 2020 | Jun 2027 | 2.9 | Not reported | Not reported | Not reported | |
| Battery Energy Storage System to maximize the use of surplus energy | Closed | Energy | Not reported | Dec 2021 | Not reported | 2.7 | Not reported | Not reported | Not reported | |
Page 1 of 3 Next
Sources
- IATI: terms of use set by the publisher
- IDA Statement of Credits and Grants: World Bank data, CC BY 4.0 (https://datacatalog.worldbank.org/public-licenses).
- IDB projects dataset: terms of use set by the publisher
- IFC Finances One: terms of use set by the publisher
- USAspending: terms of use set by the publisher
- World Bank Projects: terms of use set by the publisher
Data as of October 18, 2026. Data and definitions
Cite this page
HaitiDocs. Operations. Partner portfolio, data as of October 18, 2026. https://www.haitidocs.org/portfolio/projects?stage=all§or=energy