HT Electricity Project
US$ millions unless stated. Haitian fiscal year, October to September. FY2026-27 began October 1, 2026.
Objective
Contribute to the sustainable improvement in the quality of electricity services to customers and to the strengthening of the financial and operational performance of the electricity public utility (EDH).
As published by World Bank Projects, in its original language.
Description
The objective of the Electricity Loss Reduction Project is to contribute to the sustainable improvement in the quality of electricity services in Haiti to customers and to the strengthening of the financial and operational performance of the electricity public utility (EPH). The project will implement the following three components. The first component, improvement in the Electricite d'Haiti (EDH) management systems and practices towards a more customer oriented approach, includes incorporation of both the Customer Management System (CMS) and Technical Service Management System (TSMS); application of new procedures and rules; support for restructuring of the EDH anti-fraud unit; and construction of new facilities for a CMS, TSMS, call center. The second component, improvement in quality and reliability of services and increased
more
revenue collection of EDH for selected groups of customers, several subcomponents including: selection of personnel for the socio-economically mixed zone and for the Large Customers Unit (LCU); improvement of quality of service to, and increase EDH's revenue from the socio-economically mixed zone through the application of a new customer oriented management approach, and regularization of EDH's large consumers through the application of the new customer-oriented management approach. The third component, participatory approach, project management, monitoring and impact evaluation, and replication strategy, groups all the supporting activities necessary for the successful implementation of the first two components.
- Partner
- World Bank Group, IDA
- Sector
- Energy
- Stage
- Closed since August 31, 2013
- Approval
- August 3, 2006
- Closing
- August 31, 2013
- Instrument
- IBRD/IDA financing, IDA
- Undisbursed gap
- −0.4: the IDA statement values undisbursed credits in special drawing rights at the current exchange rate
- Effectiveness
- July 31, 2007
- Departments
- Ouest, Sud-Est, Artibonite, Sud, Nord
- Last transaction
- January 31, 2014
- Operation ID
- P098531
Life cycle5 stages, 13 dates
Stage history
| Stage | From |
|---|---|
| Planned | January 19, 2006 |
| Approved | August 3, 2006 |
| Under way | August 3, 2006 |
| Closing | August 31, 2013 |
| Closed | August 31, 2013 |
Dated events
| Event | Date | Source |
|---|---|---|
| Concept review | January 19, 2006 | World Bank Projects |
| Appraisal | April 5, 2006 | World Bank Projects |
| Planned start | June 8, 2006 | IATI |
| Negotiation | June 22, 2006 | World Bank Projects |
| Actual start | August 3, 2006 | IATI |
| Approval | August 3, 2006 | World Bank Projects |
| First commitment | August 3, 2006 | Transactions |
| Effectiveness | July 31, 2007 | World Bank Projects |
| First disbursement | May 31, 2011 | Transactions |
| Actual end | August 31, 2013 | IATI |
| Closing date | August 31, 2013 | IATI |
| Last disbursement | October 31, 2013 | Transactions |
| Completion report due | May 22, 2014 | World Bank Projects |
Undisbursed: US$0.0 million on September 30, 2026, with closing on August 31, 2013.
Financing
Table 1.Financing, US$ millions
| Financier | AmountUS$ millions | Role | Source |
|---|---|---|---|
| Local Sources of Borrowing Country | 1.5 | Counterpart | World Bank Projects |
| IDA Grant | 6.0 | Institution | World Bank Projects |
Table 2.Related operations, US$ millions
| Operation | Relation | Partner | Stage | CommitmentUS$ millions |
|---|---|---|---|---|
| HT (AF) Electricity Loss Reduction Project | Additional financing or child operation | World Bank Group | Closed | 5.0 |
Table 3.Position at the data date by source (stocks), US$ millions
| This pageUS$ millions | Source | |
|---|---|---|
| Commitment | 9.9 | IDA Statement of Credits and Grants |
| Disbursed | 10.3 | IDA Statement of Credits and Grants |
| Undisbursed | 0.0 | IDA Statement of Credits and Grants |
| Total cost | 7.5 | World Bank Projects |
World Bank amounts. Approved: Net commitment, the amount approved less cancellations, in US$ at the data date. Disbursed to date: The disbursements of the IDA statement and the Projects API to date, in US$. Undisbursed: The undisbursed balance the IDA statement publishes, in US$ at the data date. Amounts by source
Changes to the operationnot reported
- Original closing date
- Not reported
- Closing date extensions
- Not reported
- Restructurings
- Not reported
- Emergency component
- Not reported
New commitments and disbursements by fiscal year
Table 4.New commitments and disbursements by fiscal year (flows), US$ millions
| FY2005-06US$ millions | FY2008-09US$ millions | FY2010-11US$ millions | FY2011-12US$ millions | FY2012-13US$ millions | FY2013-14US$ millions | |
|---|---|---|---|---|---|---|
| New commitments | 6.0 | 5.0 | Not reported | Not reported | Not reported | −1.1 |
| Disbursements | Not reported | Not reported | 1.0 | 1.8 | 2.3 | 0.1 |
| Cumulative disbursements | Not reported | Not reported | 6.0 | 7.9 | 10.2 | 10.3 |
The running total starts at the opening balance of US$5.0 million.
Records and documents
Transactions45 records, August 3, 2006 to January 31, 2014
Table 5.Transactions, US$ millions
| Date | Measure | AmountUS$ millions | Source | Method |
|---|---|---|---|---|
| August 3, 2006 | Commitment | 6.0 | IDA Statement of Credits and Grants | credit original principal at board approval |
| September 8, 2009 | Commitment | 5.0 | IDA Statement of Credits and Grants | credit original principal at board approval |
| January 31, 2014 | Commitment | −0.5 | IDA Statement of Credits and Grants | cancellation: increase in cumulative cancelled amount between snapshots (non-USD credit: includes exchange revaluation) |
| January 31, 2014 | Commitment | −0.6 | IDA Statement of Credits and Grants | cancellation: increase in cumulative cancelled amount between snapshots (non-USD credit: includes exchange revaluation) |
| April 30, 2011 | Disbursements | 2.9 | IDA Statement of Credits and Grants | cumulative at first snapshot (opening balance) |
| April 30, 2011 | Disbursements | 2.1 | IDA Statement of Credits and Grants | cumulative at first snapshot (opening balance) |
| May 31, 2011 | Disbursements | <0.1 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| May 31, 2011 | Disbursements | <0.1 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| June 30, 2011 | Disbursements | 0.2 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| June 30, 2011 | Disbursements | 0.5 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| July 31, 2011 | Disbursements | 0.1 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| July 31, 2011 | Disbursements | <0.1 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| August 31, 2011 | Disbursements | <0.1 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| August 31, 2011 | Disbursements | 0.1 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| September 30, 2011 | Disbursements | 0.1 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| September 30, 2011 | Disbursements | <0.1 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| October 31, 2011 | Disbursements | 0.1 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| October 31, 2011 | Disbursements | 0.1 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| January 31, 2012 | Disbursements | <0.1 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| January 31, 2012 | Disbursements | 0.2 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| February 29, 2012 | Disbursements | 0.2 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| February 29, 2012 | Disbursements | 0.4 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| March 31, 2012 | Disbursements | 0.1 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| March 31, 2012 | Disbursements | 0.1 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| May 31, 2012 | Disbursements | 0.2 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| May 31, 2012 | Disbursements | 0.1 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| June 30, 2012 | Disbursements | 0.1 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| June 30, 2012 | Disbursements | <0.1 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| July 31, 2012 | Disbursements | 0.2 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| August 31, 2012 | Disbursements | 0.1 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| September 30, 2012 | Disbursements | 0.1 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| October 31, 2012 | Disbursements | 0.3 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| October 31, 2012 | Disbursements | 0.1 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| November 30, 2012 | Disbursements | <0.1 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| December 31, 2012 | Disbursements | 0.3 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| January 31, 2013 | Disbursements | 0.1 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| January 31, 2013 | Disbursements | 0.2 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| March 31, 2013 | Disbursements | 0.1 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| April 30, 2013 | Disbursements | <0.1 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| June 30, 2013 | Disbursements | 0.1 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| September 30, 2013 | Disbursements | 1.1 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| September 30, 2013 | Disbursements | <0.1 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| October 31, 2013 | Disbursements | 0.1 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| November 30, 2013 | Disbursements | −0.0 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| January 31, 2014 | Disbursements | −0.0 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
Terms4 of 6 reported
- Finance type
- 110 Standard grant
- Flow type
- Not reported
- Aid type
- C01 Project-type interventions
- Tied status
- 5 Untied
- Collaboration type
- 2 Multilateral inflows
- Humanitarian
- Not reported
Locations5 departments, 7 places named, 14 places with coordinates
| Departments | Ouest, Sud-Est, Artibonite, Sud, Nord |
| Places named by the source | Cap-Haitien, Gonaives, Jacmel, Les Cayes, Petit Goave, Port-au-Prince, Republic of Haiti |
| Places with coordinates | 14 |
Results indicators17 indicators
| Indicator | Baseline | Target | Latest value | Date of latest value |
|---|---|---|---|---|
| 1.1.Number of customers in CMS database | 0 | 185,315 | 224,052 | August 31, 2013 |
| 1.2. Number of customers in TSMS database | 0 | 180,315 | 224,052 | August 31, 2013 |
| 1.3. Number of EDH employees trained to use CMS and TSMS (not cumulative) | 0 | 435 | 296 | August 31, 2013 |
| 1.4. Active Customers/employee ratio | 80 | 100 | 98 | August 31, 2013 |
| 5.2. Number of satisfied customers (large customers) | TBD | 1,270 | TBD | August 31, 2013 |
| 5.3. Employees satisfied with new system | 0 | 625 | TBD | August 31, 2013 |
| Cash Recovery Index - large customers | Not reported | 85% | Not reported | Not reported |
| Financial Management Plan | No financial management plan in place | Implementation of (i) an accounting system, (ii) definition of manual of procedures, and (iii) inventory of assets with supportfrom accounting assistance. | EDH Financial tool by September 2013, Extensive financial audit by Q1-2014. | August 31, 2013 |
| Number of EDH employees satisfied with the project | 0 | 1938 | TBD | February 28, 2013 |
| Number of EDH employees trained to attend and follow up on large customers | 0 | 20 | 28 | August 31, 2013 |
| Number of large customers regularized | 0 | 1270 | 1320 | August 31, 2013 |
| Percentage of large customers served at least 12 hours per day on average | Not reported | 60% | 75% | February 28, 2013 |
| Small customers served at least six hours a day on average | Not reported | 50% | 100% | August 31, 2013 |
| Successful training of MTPTC staff to supervise performance indicators | Not trained | Staff dedicated to sector performance review trained | Energy Cell created in MTPTEC, coordinator of the unit hired. | August 31, 2013 |
| TA to EDH management | Sub standard procedures | Implementation of new procedures for: - Financial Management - Internal Control - Human Resources - Technical Management | Gap analysis done, recommended new procedures for Commercial and IT. | August 31, 2013 |
| Cash Recovery Index | Not reported | 40.00 | 26.70 | November 30, 2013 |
| Percentage of customers served at least 6 hours per day on average in the zones served by EDH | 20% | 50% | 100% | August 31, 2013 |
Ratings30 ratings
| Rating | Value | Date |
|---|---|---|
| IEG bankqualityofsupervision | Moderately Unsatisfactory | December 30, 2014 |
| IEG borrowcompliance | Moderately Unsatisfactory | December 30, 2014 |
| IEG borrowimplementation | Moderately Unsatisfactory | December 30, 2014 |
| IEG evaltype | ES | December 30, 2014 |
| IEG evaluation_riskdo | High | December 30, 2014 |
| IEG icrquality | Satisfactory | December 30, 2014 |
| IEG mequality | Modest | December 30, 2014 |
| IEG outcome | Unsatisfactory | December 30, 2014 |
| IEG overallbankperf | Moderately Unsatisfactory | December 30, 2014 |
| IEG overallborrowperf | Moderately Unsatisfactory | December 30, 2014 |
| ICR bankqualityentry | Not Rated | May 22, 2014 |
| ICR banksupervision | Not Rated | May 22, 2014 |
| ICR banksupervision | Moderately Unsatisfactory | May 22, 2014 |
| ICR banksupervision | Substantial | May 22, 2014 |
| ICR banksupervision | Moderately Satisfactory | May 22, 2014 |
| ICR borrgovt | Moderately Satisfactory | May 22, 2014 |
| ICR borrimplegency | Moderately Unsatisfactory | May 22, 2014 |
| ICR borroverall | Moderately Unsatisfactory | May 22, 2014 |
| ICR completion_riskdo | Moderately Satisfactory | May 22, 2014 |
| ICR completion_riskdo | Substantial | May 22, 2014 |
| ICR completion_riskdo | High | May 22, 2014 |
| ICR outratingind | Moderately Unsatisfactory | May 22, 2014 |
| ICR overallrating | Moderately Satisfactory | May 22, 2014 |
| ISR Counterpart Funding | Satisfactory | September 12, 2013 |
| ISR Financial Management | Satisfactory | September 12, 2013 |
| ISR Monitoring and Evaluation | Moderately Satisfactory | September 12, 2013 |
| ISR Overall Implementation Progress (IP) | Moderately Unsatisfactory | September 12, 2013 |
| ISR Procurement | Satisfactory | September 12, 2013 |
| ISR Progress towards achievement of PDO | Moderately Satisfactory | September 12, 2013 |
| ISR Project Management | Moderately Satisfactory | September 12, 2013 |
Identifiers6 identifiers
| System | Identifier | Source |
|---|---|---|
| IATI identifier | 44000-P098531 | IATI |
| IDA credit or grant | IDAH2510 | IDA Statement of Credits and Grants |
| IDA credit or grant | IDAH5100 | IDA Statement of Credits and Grants |
| World Bank loan | IDA-H2510 | World Bank Projects |
| World Bank loan | IDA-H5100 | World Bank Projects |
| World Bank project | P098531 | Operation record |
Where sources differ2 fields
| Field | Source | Value | Used |
|---|---|---|---|
| Commitment | IDA Statement of Credits and Grants | US$9.9 million | ✓ |
| Commitment | World Bank Projects | US$6.0 million | |
| Status | World Bank Projects | Closed | ✓ |
| Status | IATI | Active |
Partner documents19 documents
- Record on projects.worldbank.org, projects.worldbank.org
- Haiti - Electricity Project, December 30, 2014, documents.worldbank.org
- Haiti - Electricity Loss Development Project, April 30, 2014, documents.worldbank.org
- Haiti - HT Electricity Project : P098531 - Implementation Status Results Report : Sequence 13, September 12, 2013, documents.worldbank.org
- Haiti - HT Electricity Project : P098531 - Implementation Status Results Report : Sequence 12, March 25, 2013, documents.worldbank.org
- Haiti - Electricity Loss Reduction Project : restructuring (Vol. 1 of 2) : Main report, February 28, 2013, documents.worldbank.org
- Haiti - Electricity Loss Reduction Project : restructuring (Vol. 2 of 2) : Data sheet, February 28, 2013, documents.worldbank.org
- Haiti - HT Electricity Project : P098531 - Implementation Status Results Report : Sequence 11, May 21, 2012, documents.worldbank.org
- Haiti - HT Electricity Project : P098531 - Implementation Status Results Report : Sequence 10, August 13, 2011, documents.worldbank.org
- Haiti - HT Electricity Project : P098531 - Implementation Status Results Report : Sequence 09, February 20, 2011, documents.worldbank.org
- Second Amendment to the Financing Agreement for H251 and First Amendment to the Financing Agreement for H510 Conformed, July 2, 2010, documents.worldbank.org
- Haiti - Electricity Loss Reduction Project : restructuring, June 29, 2010, documents.worldbank.org
- Additional Financing for Financing Agreement for Grant H510-HT Conformed, November 2, 2009, documents.worldbank.org
- Haiti - Additional financing for the Electricity Loss Reduction Project, July 29, 2009, documents.worldbank.org
- Financing Agreement, Grant H251-HT Conformed, September 11, 2006, documents.worldbank.org
- Haiti - Electricity Loss Reduction Project : procurement plan, August 15, 2006, documents.worldbank.org
- Haiti - Electricity Loss Reduction Project, June 29, 2006, documents.worldbank.org
- Haiti - Electricity Project, April 19, 2006, documents.worldbank.org
- Haiti - Electricity Loss Reduction Project, April 13, 2006, documents.worldbank.org
Procurement notices (2)
- Contract Awards, projects.worldbank.org
- Procurement Notices, projects.worldbank.org
Sources
- IATI record (d-portal): terms of use set by the publisher
- IDA statement of credits and grants (dataset): World Bank data, CC BY 4.0 (https://datacatalog.worldbank.org/public-licenses).
- Transactions: terms of use set by the publisher
- Operation record: terms of use set by the publisher
- World Bank project page: terms of use set by the publisher
- World Bank documents: terms of use set by the publisher
Data as of October 18, 2026
| Source | Read on |
|---|---|
| IATI | October 18, 2026 |
| IDA Statement of Credits and Grants | October 18, 2026 |
| World Bank Projects | October 18, 2026 |
| World Bank documents | October 18, 2026 |