Rehabilitation of the Electricity Distribution System in Port-au-Prince

US$ millions unless stated. Haitian fiscal year, October to September. FY2026-27 began October 1, 2026.

Objective

Contribute to the uninterrupted and quality power supply to the Port au Prince population, as well as to the improvement of the financial and management situation of Electricité de Haiti. Support the development of high, medium and low voltage works initially included in the original operation (HA-L1014), as well as other works within the project's components that may help respond to the effects of the earthquake on the power distribution system.

As published by IDB projects dataset, in its original language.

Partner
IDB Group, IDB
Sector
Energy
Stage
Closed since February 16, 2018
Approval
July 21, 2010
Closing
February 16, 2018
Instrument
Grant, Sovereign Guaranteed
Effectiveness
Not reported
Last transaction
June 30, 2017
Operation ID
HA-L1035
Life cycle4 stages, 9 dates

Stage history

StageFrom
ApprovedJuly 21, 2010
Under waySeptember 22, 2010
ClosingJune 30, 2017
ClosedFebruary 16, 2018

Dated events

EventDateSource
ApprovalJuly 21, 2010IDB projects dataset
First commitmentJuly 21, 2010Transactions
SigningSeptember 22, 2010IDB projects dataset
Planned startMarch 22, 2011IATI
Actual startFebruary 25, 2013IATI
First disbursementFebruary 28, 2013Transactions
Last disbursementJune 30, 2017Transactions
Closing dateJune 30, 2017IATI
Actual endFebruary 16, 2018IATI

Financing

Table 1.Financing, US$ millions

FinancierAmountUS$ millionsRoleSource
IDB14.0InstitutionIDB projects dataset

Table 2.Position at the data date by source (stocks), US$ millions

This pageUS$ millionsSourceIATIUS$ millions
Commitment14.0IDB projects dataset14.0
Disbursed14.2IATI14.2
UndisbursedNot reported
Total cost14.0IDB projects dataset

Each amount is given as the source publishes it, converted to US$. IATI column: the commitments and disbursements the partner reports to IATI, converted to US$. Amounts by source

This page uses IDB projects dataset for the commitment and IATI for disbursements.

Changes to the operationnot reported
Original closing date
Not reported
Closing date extensions
Not reported
Restructurings
Not reported
Emergency component
Not reported

New commitments and disbursements by fiscal year

Disbursements, US$ millions
FY2009-10, not reportedn.r.09-10FY2012-13, US$0.4 million0.412-13FY2013-14, US$0.4 million0.413-14FY2014-15, US$6.5 million714-15FY2015-16, US$5.6 million615-16FY2016-17, US$1.3 million116-17FY2009-10, not reportedn.r.09-10FY2012-13, US$0.4 million0.412-13FY2013-14, US$0.4 million0.413-14FY2014-15, US$6.5 million714-15FY2015-16, US$5.6 million615-16FY2016-17, US$1.3 million116-17

Table 3.New commitments and disbursements by fiscal year (flows), US$ millions

FY2009-10US$ millionsFY2012-13US$ millionsFY2013-14US$ millionsFY2014-15US$ millionsFY2015-16US$ millionsFY2016-17US$ millions
New commitments14.0Not reportedNot reportedNot reportedNot reportedNot reported
DisbursementsNot reported0.40.46.55.61.3
Cumulative disbursementsNot reported0.40.87.312.914.2

Records and documents

Transactions32 records, July 21, 2010 to June 30, 2017

Table 4.Transactions, US$ millions

DateMeasureAmountUS$ millionsSourceMethod
July 21, 2010Commitment14.0IDB projects datasetcommitment at approval date
February 28, 2013Disbursements0.3IATIIATI disbursement (transaction type 3), paid to another organization
May 31, 2013Disbursements0.1IATIIATI disbursement (transaction type 3), paid to another organization
September 30, 2013Disbursements<0.1IATIIATI disbursement (transaction type 3), paid to another organization
October 31, 2013Disbursements0.1IATIIATI disbursement (transaction type 3), paid to another organization
May 31, 2014Disbursements0.1IATIIATI disbursement (transaction type 3), paid to another organization
June 30, 2014Disbursements0.1IATIIATI disbursement (transaction type 3), paid to another organization
October 31, 2014Disbursements<0.1IATIIATI disbursement (transaction type 3), paid to another organization
November 30, 2014Disbursements2.2IATIIATI disbursement (transaction type 3), paid to another organization
February 28, 2015Disbursements<0.1IATIIATI disbursement (transaction type 3), paid to another organization
April 30, 2015Disbursements<0.1IATIIATI disbursement (transaction type 3), paid to another organization
June 30, 2015Disbursements0.6IATIIATI disbursement (transaction type 3), paid to another organization
July 31, 2015Disbursements0.4IATIIATI disbursement (transaction type 3), paid to another organization
August 31, 2015Disbursements0.4IATIIATI disbursement (transaction type 3), paid to another organization
September 30, 2015Disbursements2.9IATIIATI disbursement (transaction type 3), paid to another organization
October 31, 2015Disbursements2.2IATIIATI disbursement (transaction type 3), paid to another organization
December 31, 2015Disbursements1.9IATIIATI disbursement (transaction type 3), paid to another organization
January 31, 2016Disbursements0.1IATIIATI disbursement (transaction type 3), paid to another organization
February 29, 2016Disbursements0.3IATIIATI disbursement (transaction type 3), paid to another organization
April 30, 2016Disbursements0.2IATIIATI disbursement (transaction type 3), paid to another organization
May 31, 2016Disbursements0.6IATIIATI disbursement (transaction type 3), paid to another organization
June 30, 2016Disbursements0.3IATIIATI disbursement (transaction type 3), paid to another organization
July 31, 2016Disbursements<0.1IATIIATI disbursement (transaction type 3), paid to another organization
September 30, 2016Disbursements0.1IATIIATI disbursement (transaction type 3), paid to another organization
October 31, 2016Disbursements0.1IATIIATI disbursement (transaction type 3), paid to another organization
December 31, 2016Disbursements0.2IATIIATI disbursement (transaction type 3), paid to another organization
January 31, 2017Disbursements0.1IATIIATI disbursement (transaction type 3), paid to another organization
February 28, 2017Disbursements0.2IATIIATI disbursement (transaction type 3), paid to another organization
March 31, 2017Disbursements0.1IATIIATI disbursement (transaction type 3), paid to another organization
April 30, 2017Disbursements0.1IATIIATI disbursement (transaction type 3), paid to another organization
May 31, 2017Disbursements0.5IATIIATI disbursement (transaction type 3), paid to another organization
June 30, 2017Disbursements0.1IATIIATI disbursement (transaction type 3), paid to another organization
Terms5 of 6 reported
Finance type
110 Standard grant
Flow type
20 Other official flows, excluding export credits
Aid type
C01 Project-type interventions
Tied status
5 Untied
Collaboration type
4 Multilateral outflows
Humanitarian
Not reported
Funds passed on50 transactions
ReceiverTransactionDateUS$ millions
Elmecen S.ADisbursementJune 30, 20170.1
Experts Conseils et AssociesDisbursementJune 30, 2017<0.1
INDRA Sistemas S.ADisbursementMay 31, 20170.2
INDRA Sistemas S.ADisbursementMay 31, 20170.2
Elmecen S.ADisbursementApril 30, 20170.1
INDRA Sistemas S.ADisbursementMarch 31, 20170.1
INDRA Sistemas S.A.DisbursementFebruary 28, 20170.2
Elmecen S.ADisbursementJanuary 31, 20170.1
Elmecen S.ADisbursementDecember 31, 20160.2
Experts Conseils et AssociesDisbursementDecember 31, 2016<0.1
Elmecen S.ADisbursementOctober 31, 20160.1
Elmecen S.ADisbursementOctober 31, 2016<0.1
Aecom Consulting IncDisbursementSeptember 30, 20160.1
Experts Conseils et AssociesDisbursementJuly 31, 2016<0.1
Elmecen S.ADisbursementJune 30, 20160.2
Aecom Consulting Inc.DisbursementJune 30, 20160.2
Aecom Consulting Inc.DisbursementMay 31, 20160.2
Esd Engineering and Service SRLDisbursementMay 31, 20160.3
Esd Engineering and Service SRLDisbursementMay 31, 2016<0.1
Esd Engineering and Service SRLDisbursementMay 31, 20160.1
Elmecen S.ADisbursementApril 30, 20160.2
Esd Engineering and Service SRLDisbursementFebruary 29, 20160.3
Elmecen S.ADisbursementJanuary 31, 20160.1
Esd Engineering and Service SRLDisbursementDecember 31, 20150.9
Elmecen S.ADisbursementDecember 31, 20150.5
Experts Conseils et AssociesDisbursementDecember 31, 2015<0.1
Esd Engineering and Service SRLDisbursementDecember 31, 20150.2
Aecom Consulting Inc.DisbursementDecember 31, 20150.2
Esd Engineering and Service SRLDisbursementOctober 31, 20150.3
Esd Engineering and Service SRLDisbursementOctober 31, 20151.9
Esd Engineering and Service SRLDisbursementSeptember 30, 20152.6
Esd Engineering and Service SRLDisbursementSeptember 30, 20150.2
Elmecen S aDisbursementSeptember 30, 20150.1
Esd Engineering and Service SRLDisbursementAugust 31, 20150.3
Aecom Consulting IncDisbursementAugust 31, 2015<0.1
Esd Engineering and Service SRLDisbursementJuly 31, 20150.4
Don 2349GR-HA EDH REH Reseau DIST PAPDisbursementJune 30, 20150.1
Elmecen S aDisbursementJune 30, 20150.2
Esd Enineering and Service SRLDisbursementJune 30, 20150.4
Aecom Consulting IncDisbursementApril 30, 2015<0.1
Aecom Consulting IncDisbursementFebruary 28, 2015<0.1
Esd Engineering and Service SRLDisbursementNovember 30, 20142.2
Experts Conseils et AssociesDisbursementOctober 31, 2014<0.1
Aecom Consultants Inc.DisbursementJune 30, 20140.1
Don 2349GR-HA EDH REH Reseau DIST PAPDisbursementMay 31, 2014<0.1
Aecom Consulting IncDisbursementMay 31, 20140.1
Aecom Consultnats IncDisbursementOctober 31, 20130.1
Experts Conseils et AssociesDisbursementSeptember 30, 2013<0.1
Keijzer ComputerDisbursementMay 31, 20130.1
ECEM SADisbursementFebruary 28, 20130.3
Identifiers2 identifiers
SystemIdentifierSource
IATI identifierXI-IATI-IADB-HA-L1035IATI
IDB operationHA-L1035Operation record

Partner documents

Procurement notices (2)

Sources

Data as of October 18, 2026
SourceRead on
IATIOctober 18, 2026
IATIOctober 18, 2026
IDB projects datasetOctober 18, 2026
Cite this page

HaitiDocs. Rehabilitation of the Electricity Distribution System in Port-au-Prince. Partner portfolio, data as of October 18, 2026. https://www.haitidocs.org/portfolio/projects/IDB%3AHA-L1035