Objective

The objectives of the Project are to (a) strengthen energy policy and planning capacity, (b) to improve the sustainability and resilience of the electricity sector and to restore and expand access to reliable electricity services, and (c) provide financial assistance to the electricity sector in case of an emergency.

As published by World Bank Projects, in its original language.

Description

The objectives of the Rebuilding Energy Infrastructure and Access Project for Haiti are to (a) strengthen the recipient's energy policy and planning capacity; (b) improve the sustainability and resilience of the recipient’s electricity sector and restore and expand access to reliable electricity services; and (c) provide financial assistance in case of an energy sector emergency. The project has three components. (1) Strengthening energy sector institutions and improving energy access. (2) Enhancing Electricite d'Haiti (EDH's) performance and rehabilitating and expanding infrastructure. (3) Energy sector risk and emergency response contingent reserve component will provide support upon occurrence of an energy sector emergency through: (a) the carrying out of emergency recovery and rehabilitation activities; and/or (b) technical assistance to support Ministry of Public

more

Works, Transport, Energy and Communication (MTPTEC) and EDH in its response to an energy sector emergency.

Partner
World Bank Group, World Bank
Sector
Energy
Stage
Closed since August 31, 2020
Approval
September 27, 2012
Closing
August 31, 2020
Instrument
IBRD/IDA financing, Grants
Undisbursed gap
13.1: trust funds are not in the IDA statement, which gives undisbursed amounts for IDA money only; the IDA statement values undisbursed credits in special drawing rights at the current exchange rate
Borrower
Republic of Haiti
Implementing agency
EDH,MTPTC, UCP Energie
Effectiveness
February 6, 2013
Departments
Ouest, Centre, Sud, Nord, Artibonite
Last transaction
July 31, 2022
Operation ID
P127203
Life cycle5 stages, 14 dates

Stage history

StageFrom
PlannedJuly 7, 2011
ApprovedSeptember 27, 2012
Under waySeptember 27, 2012
ClosingAugust 31, 2020
ClosedAugust 31, 2020

Dated events

EventDateSource
Concept reviewJuly 7, 2011World Bank Projects
Planned startMarch 29, 2012IATI
AppraisalJuly 16, 2012World Bank Projects
NegotiationAugust 14, 2012World Bank Projects
Actual startSeptember 27, 2012IATI
ApprovalSeptember 27, 2012World Bank Projects
First commitmentSeptember 27, 2012Transactions
DisclosureOctober 2, 2012World Bank Projects
EffectivenessFebruary 6, 2013World Bank Projects
First disbursementApril 30, 2013Transactions
Actual endAugust 31, 2020IATI
Closing dateAugust 31, 2020IATI
Last disbursementMarch 31, 2021Transactions
Completion report dueJuly 28, 2021World Bank Projects

Undisbursed: US$0.0 million on September 30, 2026, with closing on August 31, 2020.

Financing

Table 1.Financing, US$ millions

FinancierAmountUS$ millionsRoleSource
IDA Grant90.0InstitutionWorld Bank Projects
Clean Technology Fund10.0Trust fundWorld Bank Projects

Table 2.Position at the data date by source (stocks), US$ millions

This pageUS$ millionsSourceIATIUS$ millions
Commitment55.7IDA Statement of Credits and Grants49.0
Disbursed42.6IDA Statement of Credits and Grants42.6
Undisbursed0.0IDA Statement of Credits and Grants
Total cost100.0World Bank Projects

World Bank amounts. Approved: Net commitment, the amount approved less cancellations, in US$ at the data date. Disbursed to date: The disbursements of the IDA statement and the Projects API to date, in US$. Undisbursed: The undisbursed balance the IDA statement publishes, in US$ at the data date. IATI column: the commitments and disbursements the partner reports to IATI, converted to US$. Amounts by source

Changes to the operation2 extensions, at least 4 restructurings
Original closing date
December 31, 2017
Closing date extensions
2
  • Extended from December 31, 2017 to November 29, 2019 (document of January 31, 2018)
  • Extended from November 29, 2019 to August 31, 2020 (document of December 31, 2019)
Restructurings
at least 4
Emergency component
Not reported

New commitments and disbursements by fiscal year

Disbursements, US$ millions
FY2011-12, not reportedn.r.11-12FY2012-13, US$0.3 million0.312-13FY2013-14, US$2.0 million213-14FY2014-15, US$6.6 million714-15FY2015-16, US$8.4 million815-16FY2016-17, US$5.6 million616-17FY2017-18, US$7.6 million817-18FY2018-19, US$6.1 million618-19FY2019-20, US$4.5 million419-20FY2020-21, US$1.7 million220-21FY2021-22, not reportedn.r.21-22FY2011-12, not reportedn.r.11-12FY2012-13, US$0.3 million0.312-13FY2013-14, US$2.0 million213-14FY2014-15, US$6.6 million714-15FY2015-16, US$8.4 million815-16FY2016-17, US$5.6 million616-17FY2017-18, US$7.6 million817-18FY2018-19, US$6.1 million618-19FY2019-20, US$4.5 million419-20FY2020-21, US$1.7 million220-21FY2021-22, not reportedn.r.21-22

Table 3.New commitments and disbursements by fiscal year (flows), US$ millions

FY2011-12US$ millionsFY2012-13US$ millionsFY2013-14US$ millionsFY2014-15US$ millionsFY2015-16US$ millionsFY2016-17US$ millionsFY2017-18US$ millionsFY2018-19US$ millionsFY2019-20US$ millionsFY2020-21US$ millionsFY2021-22US$ millions
New commitments100.0Not reportedNot reportedNot reportedNot reportedNot reported−26.9−15.3−2.1Not reported−0.0
DisbursementsNot reported0.32.06.68.45.67.66.14.51.7Not reported
Cumulative disbursementsNot reported0.32.28.817.222.830.436.540.942.6Not reported

Records and documents

Transactions74 records, September 27, 2012 to July 31, 2022

Table 4.Transactions, US$ millions

DateMeasureAmountUS$ millionsSourceMethod
September 27, 2012Commitment90.0IDA Statement of Credits and Grantscredit original principal at board approval
September 27, 2012Commitment10.0World Bank Projectstrust funds in the Projects API financier list, not in the IDA statement, at the board approval date
January 31, 2018Commitment−26.9IDA Statement of Credits and Grantscancellation: increase in cumulative cancelled amount between snapshots (non-USD credit: includes exchange revaluation)
July 31, 2019Commitment−15.3IDA Statement of Credits and Grantscancellation: increase in cumulative cancelled amount between snapshots (non-USD credit: includes exchange revaluation)
August 31, 2020Commitment−2.1IDA Statement of Credits and Grantscancellation: increase in cumulative cancelled amount between snapshots (non-USD credit: includes exchange revaluation)
July 31, 2022Commitment−0.0IDA Statement of Credits and Grantscancellation: increase in cumulative cancelled amount between snapshots (non-USD credit: includes exchange revaluation)
April 30, 2013Disbursements0.2IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
August 31, 2013Disbursements0.1IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
October 31, 2013Disbursements0.1IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
November 30, 2013Disbursements0.2IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
December 31, 2013Disbursements0.1IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
January 31, 2014Disbursements0.2IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
March 31, 2014Disbursements0.1IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
April 30, 2014Disbursements0.2IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
May 31, 2014Disbursements0.1IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
June 30, 2014Disbursements0.1IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
July 31, 2014Disbursements0.3IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
September 30, 2014Disbursements0.7IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
October 31, 2014Disbursements0.1IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
November 30, 2014Disbursements1.3IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
December 31, 2014Disbursements0.6IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
February 28, 2015Disbursements0.3IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
March 31, 2015Disbursements1.5IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
April 30, 2015Disbursements0.9IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
May 31, 2015Disbursements0.1IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
June 30, 2015Disbursements0.4IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
July 31, 2015Disbursements0.3IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
August 31, 2015Disbursements0.7IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
September 30, 2015Disbursements0.4IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
October 31, 2015Disbursements0.9IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
November 30, 2015Disbursements1.5IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
December 31, 2015Disbursements0.4IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
February 29, 2016Disbursements2.2IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
March 31, 2016Disbursements0.3IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
July 31, 2016Disbursements0.7IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
August 31, 2016Disbursements1.5IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
September 30, 2016Disbursements1.0IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
October 31, 2016Disbursements0.1IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
November 30, 2016Disbursements0.4IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
February 28, 2017Disbursements1.0IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
March 31, 2017Disbursements0.2IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
April 30, 2017Disbursements0.1IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
July 31, 2017Disbursements1.2IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
August 31, 2017Disbursements1.3IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
September 30, 2017Disbursements1.4IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
October 31, 2017Disbursements0.6IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
November 30, 2017Disbursements0.2IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
December 31, 2017Disbursements0.7IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
January 31, 2018Disbursements1.0IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
February 28, 2018Disbursements0.2IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
May 31, 2018Disbursements1.9IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
June 30, 2018Disbursements2.8IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
September 30, 2018Disbursements0.2IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
October 31, 2018Disbursements0.3IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
December 31, 2018Disbursements0.4IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
January 31, 2019Disbursements0.6IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
March 31, 2019Disbursements0.9IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
May 31, 2019Disbursements0.8IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
June 30, 2019Disbursements1.0IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
July 31, 2019Disbursements1.1IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
August 31, 2019Disbursements1.1IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
October 31, 2019Disbursements0.7IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
November 30, 2019Disbursements0.9IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
December 31, 2019Disbursements0.6IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
January 31, 2020Disbursements0.5IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
February 29, 2020Disbursements0.4IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
March 31, 2020Disbursements0.3IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
April 30, 2020Disbursements0.8IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
May 31, 2020Disbursements0.3IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
September 30, 2020Disbursements−0.1IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
November 30, 2020Disbursements1.5IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
February 28, 2021Disbursements0.1IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
March 31, 2021Disbursements0.1IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
May 31, 2021Disbursements−0.0IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
Terms5 of 6 reported
Finance type
110 Standard grant
Flow type
Not reported
Aid type
C01 Project-type interventions
Tied status
5 Untied
Collaboration type
2 Multilateral inflows
Humanitarian
Yes
Locations5 departments, 8 places named, 14 places with coordinates
DepartmentsOuest, Centre, Sud, Nord, Artibonite
Places named by the sourceCap-Haïtien, DEpartement de l'Artibonite, Drouet, Département de l'Artibonite, Grand Goâve, Mirebalais, Petit Goâve, Port-au-Prince
Places with coordinates14
Results indicators14 indicators
IndicatorBaselineTargetLatest valueDate of latest value
Capacity of Renewable Energy (including Hydropower) constructed or rehabilitated2.004.003.08August 31, 2020
Distribution lines rehabilitated0.00148.00186.00August 31, 2020
Electricity sector financial model and energy sector databaseNo model exists for the sector.Data and financial model updatedThe model is utilized to prepare budget proposal, August 31, 2020
External audits of EDH accountsNo audit conducted since 2006.External audit of accounts availableCarrying out the External Audit of EDH accounts ovAugust 31, 2020
Government entity responsible for the energy sector adequately staffedNo Government entity exists to oversee the energy Idem as original target2 permanent staff allocated to support MTPTC's EneAugust 31, 2020
Offgrid access to electricity for collective uses (street lighting, schools etc.)0.001500.002038.00August 31, 2020
Offgrid connections to electricity0.0015000.0019040.00August 31, 2020
People provided with new or improved electricity service0.0020000.002501.00August 31, 2020
Restored connections0.0033000.0016806.00August 31, 2020
Technical and non technical losses66.0050.0070.00August 31, 2020
Cash Recovery Index22.0035.0037.80August 31, 2020
Direct project beneficiaries0.00200000.00151822.00August 31, 2020
Strengthening of Government's oversight capacity and transparency in sector financial flowsOversight capacity is weak in utility EDH, non exiOversight capacity strengthened; Energy Cell with The Energy Cell is fully operational. It is supporAugust 31, 2020
Female beneficiaries28000.000.0081500.00June 15, 2018
Ratings17 ratings
RatingValueDate
IEG bankqualityofsupervisionModerately SatisfactoryFebruary 7, 2022
IEG borrowcomplianceNot RatedFebruary 7, 2022
IEG evaltypeESFebruary 7, 2022
IEG icrqualitySubstantialFebruary 7, 2022
IEG mequalityModestFebruary 7, 2022
IEG outcomeModerately UnsatisfactoryFebruary 7, 2022
IEG overallbankperfModerately SatisfactoryFebruary 7, 2022
ICR bankqualityentryNot RatedJuly 28, 2021
ICR banksupervisionNot RatedJuly 28, 2021
ICR outratingindModerately UnsatisfactoryJuly 28, 2021
ICR overallratingModerately SatisfactoryJuly 28, 2021
ISR Financial ManagementModerately SatisfactoryMarch 2, 2020
ISR Monitoring and EvaluationSatisfactoryMarch 2, 2020
ISR Overall Implementation Progress (IP)Moderately UnsatisfactoryMarch 2, 2020
ISR ProcurementModerately UnsatisfactoryMarch 2, 2020
ISR Progress towards achievement of PDOModerately UnsatisfactoryMarch 2, 2020
ISR Project ManagementModerately UnsatisfactoryMarch 2, 2020
Contract awards2 awards
SupplierDateMethodAmount
Accounting & Finance Corp. (Acfinco)February 22, 2021QCBS10,600 USD
Name not shownDecember 31, 2018INDV3,190,000 Gourde hatienne
Funds passed on73 transactions
ReceiverTransactionDateUS$ millions
EDH; MTPTC, UCP EnergieCommitmentJuly 31, 2022−0.0
EDH; MTPTC, UCP EnergieDisbursementMay 31, 2021−0.0
EDH; MTPTC, UCP EnergieDisbursementMarch 31, 20210.1
EDH; MTPTC, UCP EnergieDisbursementFebruary 28, 20210.1
EDH; MTPTC, UCP EnergieDisbursementNovember 30, 20201.5
EDH; MTPTC, UCP EnergieDisbursementSeptember 30, 2020−0.1
EDH; MTPTC, UCP EnergieCommitmentAugust 31, 2020−2.0
EDH; MTPTC, UCP EnergieDisbursementMay 31, 20200.3
EDH; MTPTC, UCP EnergieDisbursementApril 30, 20200.8
EDH; MTPTC, UCP EnergieDisbursementMarch 31, 20200.3
EDH; MTPTC, UCP EnergieDisbursementFebruary 29, 20200.4
EDH; MTPTC, UCP EnergieDisbursementJanuary 31, 20200.5
EDH; MTPTC, UCP EnergieDisbursementDecember 31, 20190.6
EDH; MTPTC, UCP EnergieDisbursementNovember 30, 20190.9
EDH; MTPTC, UCP EnergieDisbursementOctober 31, 20190.7
EDH; MTPTC, UCP EnergieDisbursementAugust 31, 20191.1
EDH; MTPTC, UCP EnergieCommitmentJuly 31, 2019−14.0
EDH; MTPTC, UCP EnergieDisbursementJuly 31, 20191.1
EDH; MTPTC, UCP EnergieDisbursementJune 30, 20191.0
EDH; MTPTC, UCP EnergieDisbursementMay 31, 20190.8
EDH; MTPTC, UCP EnergieDisbursementMarch 31, 20190.9
EDH; MTPTC, UCP EnergieDisbursementJanuary 31, 20190.6
EDH; MTPTC, UCP EnergieDisbursementDecember 31, 20180.4
EDH; MTPTC, UCP EnergieDisbursementOctober 31, 20180.3
EDH; MTPTC, UCP EnergieDisbursementSeptember 30, 20180.2
EDH; MTPTC, UCP EnergieDisbursementJune 30, 20182.8
EDH; MTPTC, UCP EnergieDisbursementMay 31, 20181.9
EDH; MTPTC, UCP EnergieDisbursementFebruary 28, 20180.2
EDH; MTPTC, UCP EnergieCommitmentJanuary 31, 2018−25.0
EDH; MTPTC, UCP EnergieDisbursementJanuary 31, 20181.0
EDH; MTPTC, UCP EnergieDisbursementDecember 31, 20170.7
EDH; MTPTC, UCP EnergieDisbursementNovember 30, 20170.2
EDH; MTPTC, UCP EnergieDisbursementOctober 31, 20170.6
EDH; MTPTC, UCP EnergieDisbursementSeptember 30, 20171.4
EDH; MTPTC, UCP EnergieDisbursementAugust 31, 20171.3
EDH; MTPTC, UCP EnergieDisbursementJuly 31, 20171.2
EDH; MTPTC, UCP EnergieDisbursementApril 30, 20170.1
EDH; MTPTC, UCP EnergieDisbursementMarch 31, 20170.2
EDH; MTPTC, UCP EnergieDisbursementFebruary 28, 20171.0
EDH; MTPTC, UCP EnergieDisbursementNovember 30, 20160.4
EDH; MTPTC, UCP EnergieDisbursementOctober 31, 20160.1
EDH; MTPTC, UCP EnergieDisbursementSeptember 30, 20161.0
EDH; MTPTC, UCP EnergieDisbursementAugust 31, 20161.5
EDH; MTPTC, UCP EnergieDisbursementJuly 31, 20160.7
EDH; MTPTC, UCP EnergieDisbursementMarch 31, 20160.3
EDH; MTPTC, UCP EnergieDisbursementFebruary 29, 20162.2
EDH; MTPTC, UCP EnergieDisbursementDecember 31, 20150.4
EDH; MTPTC, UCP EnergieDisbursementNovember 30, 20151.5
EDH; MTPTC, UCP EnergieDisbursementOctober 31, 20150.9
EDH; MTPTC, UCP EnergieDisbursementSeptember 30, 20150.4
EDH; MTPTC, UCP EnergieDisbursementAugust 31, 20150.7
EDH; MTPTC, UCP EnergieDisbursementJuly 31, 20150.3
EDH; MTPTC, UCP EnergieDisbursementJune 30, 20150.4
EDH; MTPTC, UCP EnergieDisbursementMay 31, 20150.1
EDH; MTPTC, UCP EnergieDisbursementApril 30, 20150.9
EDH; MTPTC, UCP EnergieDisbursementMarch 31, 20151.5
EDH; MTPTC, UCP EnergieDisbursementFebruary 28, 20150.3
EDH; MTPTC, UCP EnergieDisbursementDecember 31, 20140.6
EDH; MTPTC, UCP EnergieDisbursementNovember 30, 20141.3
EDH; MTPTC, UCP EnergieDisbursementOctober 31, 20140.1
EDH; MTPTC, UCP EnergieDisbursementSeptember 30, 20140.7
EDH; MTPTC, UCP EnergieDisbursementJuly 31, 20140.3
EDH; MTPTC, UCP EnergieDisbursementJune 30, 20140.1
EDH; MTPTC, UCP EnergieDisbursementMay 31, 20140.1
EDH; MTPTC, UCP EnergieDisbursementApril 30, 20140.2
EDH; MTPTC, UCP EnergieDisbursementMarch 31, 20140.1
EDH; MTPTC, UCP EnergieDisbursementJanuary 31, 20140.2
EDH; MTPTC, UCP EnergieDisbursementDecember 31, 20130.1
EDH; MTPTC, UCP EnergieDisbursementNovember 30, 20130.2
EDH; MTPTC, UCP EnergieDisbursementOctober 31, 20130.1
EDH; MTPTC, UCP EnergieDisbursementAugust 31, 20130.1
EDH; MTPTC, UCP EnergieDisbursementApril 30, 20130.2
EDH; MTPTC, UCP EnergieCommitmentSeptember 30, 201290.0
Identifiers4 identifiers
SystemIdentifierSource
IATI identifier44000-P127203IATI
IDA credit or grantIDAH8060IDA Statement of Credits and Grants
World Bank loanIDA-H8060World Bank Projects
World Bank projectP127203Operation record
Where sources differ2 fields
FieldSourceValueUsed
CommitmentIDA Statement of Credits and GrantsUS$55.7 million✓
CommitmentIATIUS$49.0 million
CommitmentWorld Bank ProjectsUS$100.0 million
StatusWorld Bank ProjectsClosed✓
StatusIATIActive
Partner documents47 documents
Procurement notices (2)

Sources

Data as of October 18, 2026
SourceRead on
IATIOctober 18, 2026
IATIOctober 18, 2026
IDA Statement of Credits and GrantsOctober 18, 2026
World Bank procurement noticesOctober 18, 2026
World Bank ProjectsOctober 18, 2026
World Bank documentsOctober 18, 2026
Cite this page

HaitiDocs. Rebuilding Energy Infrastructure and Access. Partner portfolio, data as of October 18, 2026. https://www.haitidocs.org/portfolio/projects/WB%3AP127203