Operations
Operations of development partners in Haiti, as their sources publish them. Data as of October 18, 2026.
| Stock at October 18, 2026, US$ millions | Flow, US$ millions | |||||||||
|---|---|---|---|---|---|---|---|---|---|---|
| Stock at October 18, 2026, US$ millions | ||||||||||
| Operation | Stage | Sector | Departments | Approval or start | Closing | Approved (net commitment, US$ at the data date) definition | Disbursed to date definition | Undisbursed definition | Disbursed in FY2026-27 definition | |
| Total, funding partners (246 operations) | 2,387.5sum of those reporting, 227 of 240 | 1,458.2sum of those reporting, 68 of 240 | No total216.4, 16 of 240 ops | Not reported | ||||||
| Program to support the national transport policy | Under way | Transport | Not reported | Apr 2010 | Dec 2030 | 256.6 | Not reported | Not reported | Not reported | |
| Transport and Departmental Connectivity | Under way | Transport | Not reported | Oct 2018 | Jan 2027 | 225.0 | 174.1 | Not reported | None to date | |
| Haiti Rural Accessibility & Resilience Project | Closed | Transport | Nord-Est, Sud-Est, Sud, Artibonite, Nord-Ouest, Centre, Nippes | May 2018 | May 2025 | 135.0 | 130.5 | 0.6 | None to date | |
| Resilient connectivity and Urban Transport Accessibility Project | Under way | Transport | Nord-Est, Sud-Est, Nord, Grande Anse, Nippes | May 2022 | May 2028 | 120.0 | 51.6 | 66.1 | None to date | |
| Infrastructure & Institutions Emergency Recovery | Closed | Transport | Ouest | Mar 2010 | Jun 2018 | 102.3 | 100.5 | 0.0 | None to date | |
| Caribbean Regional Air Transport Connectivity Project - Haiti | Under way | Transport | Not reported | May 2020 | Dec 2027 | 96.0 | 24.4 | 71.1 | None to date | |
| Resilient Corridors Project | Under way | Transport | Sud-Est, Sud, Nord-Est, Grande Anse, Nord, Nippes, Ouest | Nov 2025 | Jan 2032 | 80.0 | 1.0 | 78.5 | None to date | |
| Disaster Risk Management and Reconstruction | Closed | Transport | Sud-Est, Sud, Ouest, Nord-Ouest, Nord-Est, Nord, Grande Anse, Centre, Artibonite, Nippes | Dec 2011 | Jun 2020 | 71.8 | 66.8 | 0.0 | None to date | |
| Les Cayes-Jérémie Road | Closed | Transport | Grande Anse | Feb 2008 | Mar 2014 | 70.4 | 70.8 | Not reported | None to date | |
| Support for Haiti's Transport Sector V | Closed | Transport | Not reported | Oct 2015 | Feb 2022 | 65.0 | 52.5 | Not reported | None to date | |
| Support for Transport Sector | Closed | Transport | Not reported | Dec 2011 | Nov 2019 | 55.0 | 55.3 | Not reported | None to date | |
| Infrastructure Program | Closed | Transport | Not reported | Jul 2011 | Aug 2017 | 55.0 | 55.7 | Not reported | None to date | |
| Support for Transport Sector II | Closed | Transport | Not reported | Oct 2012 | Jul 2020 | 53.0 | 55.7 | Not reported | None to date | |
| Support for Haiti's Transportation Sector III | Closed | Transport | Not reported | Nov 2013 | Mar 2023 | 50.0 | 37.0 | Not reported | None to date | |
| Support for Transport Sector IV | Closed | Transport | Not reported | Jun 2014 | Feb 2023 | 50.0 | 50.3 | Not reported | None to date | |
| Rural and Secondary Roads | Closed | Transport | Not reported | Mar 1997 | Not reported | 50.0 | Not reported | Not reported | Not reported | |
| Transport Infrastructure Rehabilitation Program | Closed | Transport | Not reported | Jun 2005 | Mar 2013 | 50.0 | 76.9 | Not reported | None to date | |
| Pont-Sonde-Mirebalais Highways and Access Roads | Closed | Transport | Not reported | Feb 1990 | Not reported | 48.5 | Not reported | Not reported | Not reported | |
| ASIST (Support to the Infrastructure and Transport Services Sector) | Under way | Transport | Not reported | Mar 2021 | Sep 2031 | 48.2 | Not reported | Not reported | Not reported | |
| Road Maintenance & Rehab. National Program | Closed | Transport | Not reported | Feb 1995 | Not reported | 45.0 | Not reported | Not reported | Not reported | |
| Rehabilitation of Route RN3, Saint Raphael-Dondon | Under way | Transport | Not reported | Jun 2026 | Feb 2028 | 42.6 | Not reported | Not reported | Not reported | |
| Program to Support Transportation Sector Development | Closed | Transport | Not reported | Jul 2010 | Feb 2013 | 29.0 | 29.0 | Not reported | None to date | |
| Binational cooperation in the fields of trade and the environment | Under way | Transport | Not reported | Mar 2012 | Mar 2029 | 28.7 | Not reported | Not reported | Not reported | |
| Haiti Transport and Territorial Development Project | Closed | Transport | Sud-Est, Sud, Nord | Apr 2006 | Jul 2013 | 27.2 | 28.1 | 0.0 | None to date | |
| Institutional Strengthening and Reform of the Transport Sector II | Closed | Transport | Not reported | May 2015 | Sep 2015 | 27.0 | 27.0 | Not reported | None to date | |
| RD MAINT & RHB | Closed | Transport | Not reported | Mar 1995 | Dec 2001 | 26.3 | 25.1 | 0.0 | None to date | |
| HT Center and Artibonite Regional Development | Closed | Transport | Ouest, Nord, Centre, Artibonite | May 2014 | Aug 2020 | 25.3 | 15.5 | 0.0 | None to date | |
| Rehabilitation of Road Infrastructure for Integration of the Territory | Closed | Transport | Not reported | Nov 2007 | Mar 2017 | 25.0 | 100.0 | Not reported | None to date | |
| Southern Roads Construction Leogane Cayes | Closed | Transport | Not reported | Oct 1975 | Not reported | 25.0 | Not reported | Not reported | Not reported | |
| Rehabilitation of Road Infrastructure for Integration of the Territory | Closed | Transport | Not reported | Feb 2008 | Not reported | 22.5 | Not reported | Not reported | Not reported | |
| South Road Segment Leogane-Aquuin | Closed | Transport | Not reported | Aug 1973 | Not reported | 22.2 | Not reported | Not reported | Not reported | |
| Emergency Program in Response to Hurricane Matthew | Closed | Transport | Not reported | Dec 2016 | Oct 2019 | 20.0 | 19.8 | Not reported | None to date | |
| Fourth highways | Closed | Transport | Not reported | Jun 1975 | Not reported | 20.0 | 20.0 | 0.0 | None to date | |
| HT Emergency Bridge Reconst & Vulnerab Reduction Project | Closed | Transport | Grande Anse, Sud, Ouest, Centre, Sud-Est, Artibonite, Nippes | Nov 2008 | May 2015 | 19.9 | 19.4 | 0.0 | None to date | |
| Basic Economic Infrastructure Rehabilitation I | Closed | Transport | Ouest | Feb 2007 | Apr 2013 | 18.2 | 16.7 | Not reported | None to date | |
| Construction works for the Saint Raphaël bypass | Under way | Transport | Nord | Oct 2025 | Feb 2027 | 17.9 | 1.3 | Not reported | None to date | |
| Emergency Road Rehabilitation Program in Response to Hurricane Sandy | Closed | Transport | Not reported | Dec 2012 | Aug 2016 | 17.5 | 17.5 | Not reported | None to date | |
| Governance of the infrastructure and transport services sector | Under way | Transport | Not reported | Sep 2018 | Mar 2031 | 16.6 | Not reported | Not reported | Not reported | |
| Highway V/ports | Closed | Transport | Not reported | May 1978 | Not reported | 15.0 | 15.0 | 0.0 | None to date | |
| Port Lafito, S.A. | Closed | Transport | Not reported | Jul 2014 | Not reported | 15.0 | 15.0 | Not reported | None to date | |
| Route des rails - Road Infrastructure Project I | Closed | Transport | Ouest | Mar 2008 | Aug 2013 | 14.5 | 14.3 | Not reported | None to date | |
| Highways VI | Closed | Transport | Not reported | Apr 1982 | Not reported | 14.0 | 13.5 | 0.0 | None to date | |
| Institutional Strengthening and Reform of the Transport Sector I | Closed | Transport | Not reported | May 2014 | Aug 2014 | 12.0 | 12.0 | Not reported | None to date | |
| PORTS I | Closed | Transport | Not reported | Mar 1981 | Not reported | 11.0 | 9.3 | 0.0 | None to date | |
| Enlargement Port Au Prince II Stage | Closed | Transport | Not reported | Sep 1972 | Not reported | 10.0 | Not reported | Not reported | Not reported | |
| Northern highway | Closed | Transport | Not reported | May 1974 | Not reported | 10.0 | 10.0 | 0.0 | None to date | |
| Enlargement Port Au Prince | Closed | Transport | Not reported | Sep 1975 | Not reported | 7.5 | Not reported | Not reported | Not reported | |
| Institutional Strengthening and Reform of the Transport Sector I | Closed | Transport | Not reported | May 2014 | Not reported | 7.0 | Not reported | Not reported | Not reported | |
| Reahab Road Project | Closed | Transport | Not reported | Nov 1980 | Not reported | 5.8 | Not reported | Not reported | Not reported | |
| Port-au-Prince northern extension zone community revitalization program | Closed | Transport | Not reported | Sep 2015 | Jul 2018 | 5.3 | 5.3 | Not reported | None to date | |
Page 1 of 5 Next
Sources
- IATI: terms of use set by the publisher
- IDA Statement of Credits and Grants: World Bank data, CC BY 4.0 (https://datacatalog.worldbank.org/public-licenses).
- IDB projects dataset: terms of use set by the publisher
- IFC Finances One: terms of use set by the publisher
- USAspending: terms of use set by the publisher
- World Bank Projects: terms of use set by the publisher
Data as of October 18, 2026. Sources and methodology
Cite this page
HaitiDocs. Operations. Partner portfolio, data as of October 18, 2026. https://www.haitidocs.org/portfolio/projects?stage=all§or=transport