Support for Transport Sector IV
Published title: Support for Transport Sector in Haiti IV
US$ millions unless stated. Haitian fiscal year, October to September. FY2026-27 began October 1, 2026.
Objective
The general objective of the project is to increase the competitiveness and connectivity in Haiti by reducing transportation costs and providing safer services. Specific objectives include the rehabilitation of the Toussaint Louverture International Airport (TLIA) and the rehabilitation of a road segment on Route Nationale 1 (RN-1) between Plaisance and Camp Coq. The project will promote the country's regional and international integration potential and will support institutional strengthening for the transport sector in Haiti.
As published by IDB projects dataset, in its original language.
- Sector
- Transport
- Stage
- Closed since February 1, 2023
- Approval
- June 12, 2014
- Closing
- February 1, 2023
- Instrument
- Grant, Sovereign Guaranteed
- Effectiveness
- Not reported
- Last transaction
- December 31, 2021
- Operation ID
- HA-L1089
Life cycle4 stages, 8 dates
Stage history
| Stage | From |
|---|---|
| Approved | June 12, 2014 |
| Under way | August 4, 2014 |
| Closing | February 1, 2023 |
| Closed | February 1, 2023 |
Dated events
| Event | Date | Source |
|---|---|---|
| Approval | June 12, 2014 | IDB projects dataset |
| First commitment | June 12, 2014 | Transactions |
| Signing | August 4, 2014 | IDB projects dataset |
| Planned start | March 5, 2015 | IATI |
| Actual start | June 29, 2015 | IATI |
| First disbursement | June 30, 2015 | Transactions |
| Last disbursement | December 31, 2021 | Transactions |
| Closing date | February 1, 2023 | IATI |
Financing
Table 1.Financing, US$ millions
| Financier | AmountUS$ millions | Role | Source |
|---|---|---|---|
| IDB | 50.0 | Institution | IDB projects dataset |
Table 2.Position at the data date by source (stocks), US$ millions
| This pageUS$ millions | Source | IATIUS$ millions | |
|---|---|---|---|
| Commitment | 50.0 | IDB projects dataset | 50.0 |
| Disbursed | 50.3 | IATI | 50.3 |
| Undisbursed | Not reported | ||
| Total cost | 50.0 | IDB projects dataset |
Each amount is given as the source publishes it, converted to US$. IATI column: the commitments and disbursements the partner reports to IATI, converted to US$. Amounts by source
This page uses IDB projects dataset for the commitment and IATI for disbursements.
Changes to the operationnot reported
- Original closing date
- Not reported
- Closing date extensions
- Not reported
- Restructurings
- Not reported
- Emergency component
- Not reported
New commitments and disbursements by fiscal year
Table 3.New commitments and disbursements by fiscal year (flows), US$ millions
| FY2013-14US$ millions | FY2014-15US$ millions | FY2015-16US$ millions | FY2016-17US$ millions | FY2017-18US$ millions | FY2018-19US$ millions | FY2019-20US$ millions | FY2020-21US$ millions | FY2021-22US$ millions | |
|---|---|---|---|---|---|---|---|---|---|
| New commitments | 50.0 | Not reported | Not reported | Not reported | Not reported | Not reported | Not reported | Not reported | Not reported |
| Disbursements | Not reported | 8.9 | 0.2 | 5.0 | 13.6 | 6.3 | 5.3 | 3.1 | 7.9 |
| Cumulative disbursements | Not reported | 8.9 | 9.1 | 14.1 | 27.7 | 34.0 | 39.3 | 42.4 | 50.3 |
Records and documents
Transactions41 records, June 12, 2014 to December 31, 2021
Table 4.Transactions, US$ millions
| Date | Measure | AmountUS$ millions | Source | Method |
|---|---|---|---|---|
| June 12, 2014 | Commitment | 50.0 | IDB projects dataset | commitment at approval date |
| June 30, 2015 | Disbursements | 7.0 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| July 31, 2015 | Disbursements | 1.9 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| June 30, 2016 | Disbursements | 0.2 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| October 31, 2016 | Disbursements | 0.4 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| December 31, 2016 | Disbursements | 0.3 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| February 28, 2017 | Disbursements | 0.2 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| March 31, 2017 | Disbursements | 0.6 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| April 30, 2017 | Disbursements | 0.2 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| May 31, 2017 | Disbursements | 0.1 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| June 30, 2017 | Disbursements | 3.1 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| July 31, 2017 | Disbursements | 0.2 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| October 31, 2017 | Disbursements | 1.3 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| November 30, 2017 | Disbursements | 1.2 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| December 31, 2017 | Disbursements | 1.0 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| January 31, 2018 | Disbursements | 0.2 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| February 28, 2018 | Disbursements | 1.2 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| March 31, 2018 | Disbursements | 0.5 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| April 30, 2018 | Disbursements | 1.8 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| May 31, 2018 | Disbursements | 2.9 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| June 30, 2018 | Disbursements | 1.3 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| July 31, 2018 | Disbursements | 0.4 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| August 31, 2018 | Disbursements | 1.0 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| September 30, 2018 | Disbursements | 0.8 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| October 31, 2018 | Disbursements | 3.9 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| November 30, 2018 | Disbursements | 0.2 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| December 31, 2018 | Disbursements | 1.0 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| January 31, 2019 | Disbursements | <0.1 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| March 31, 2019 | Disbursements | 1.2 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| December 31, 2019 | Disbursements | 2.7 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| February 29, 2020 | Disbursements | 0.5 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| March 31, 2020 | Disbursements | 0.4 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| April 30, 2020 | Disbursements | 0.7 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| May 31, 2020 | Disbursements | 1.0 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| October 31, 2020 | Disbursements | 0.2 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| November 30, 2020 | Disbursements | 0.9 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| December 31, 2020 | Disbursements | 0.2 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| February 28, 2021 | Disbursements | 0.5 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| April 30, 2021 | Disbursements | 1.0 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| July 31, 2021 | Disbursements | 0.3 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| December 31, 2021 | Disbursements | 7.9 | IATI | IATI disbursement (transaction type 3), paid to another organization |
Terms5 of 6 reported
- Finance type
- 110 Standard grant
- Flow type
- 20 Other official flows, excluding export credits
- Aid type
- C01 Project-type interventions
- Tied status
- 5 Untied
- Collaboration type
- 4 Multilateral outflows
- Humanitarian
- Not reported
Locations1 place named
| Departments | Not reported |
| Places named by the source | Haiti, 27 RUE TOUSSAINT LOUVERTURE, DELMAS 33, DELMAS |
| Places with coordinates | 0 |
Results indicators16 indicators
| Indicator | Baseline | Target | Latest value | Date of latest value |
|---|---|---|---|---|
| Ateliers et de séances de sécurité routière | Not reported | 1.00 | 1.00 | December 31, 2017 |
| Conception et etudes développés | Not reported | 1.00 | 1.00 | December 31, 2017 |
| Femmes formées en activités de travaux d'infrastructures | Not reported | 25.00 | 0.00 | December 31, 2017 |
| Personnes formées en transport aérien | Not reported | 20.00 | 10.00 | December 31, 2017 |
| Piste de l'aéroport réhabilitée | Not reported | 130003.00 | 15600.00 | December 31, 2016 |
| Plan de gestion environnementale et sociale de l'aéroport élaboré | Not reported | 2.00 | 2.00 | December 31, 2017 |
| Rapport d'audit financier | Not reported | 1.00 | 1.00 | December 31, 2019 |
| Rapport d'avancement des travaux préparé par la supervision | Not reported | 6.00 | 6.00 | December 31, 2017 |
| Rapport d'avancement préparé par l'UCE | Not reported | 1.00 | 1.00 | December 31, 2018 |
| Rapport d'évaluation du projet préparé par l'UCE | Not reported | 1.00 | 0.00 | December 31, 2018 |
| Rapport de gestion environnementale, sociale, santé et sécurité de l'aéroport élaboré | Not reported | 2.00 | 2.00 | December 31, 2017 |
| Rapport préparé par l'expert en infrastuctures de transport aérien | Not reported | 1.00 | 1.00 | December 31, 2017 |
| Rapport péparé par le consultant d'archivage | Not reported | 1.00 | 0.00 | December 31, 2016 |
| Route primaire entretenue | Not reported | 10.60 | 0.00 | December 31, 2019 |
| Route primaire réhabilitée | Not reported | 10.60 | 0.00 | December 31, 2017 |
| Tour de control et bloc technique construit | Not reported | 1.00 | 0.00 | December 31, 2016 |
Funds passed on84 transactions
| Receiver | Transaction | Date | US$ millions |
|---|---|---|---|
| Ingenieria Estrella SRL | Disbursement | December 31, 2021 | 2.5 |
| Ministere de Travaux Publics Transports | Disbursement | December 31, 2021 | 5.4 |
| Ministere de Travaux Publics Transports | Disbursement | July 31, 2021 | 0.3 |
| Ingenieria Estrella SRL | Disbursement | April 30, 2021 | 0.5 |
| ACA (Fasgel S.A.)-CSI Ingenieros | Disbursement | April 30, 2021 | 0.5 |
| Ingenieria Estrella SRL | Disbursement | February 28, 2021 | 0.5 |
| ACA (Fasgel S.A.)-CSI Ingenieros | Disbursement | December 31, 2020 | 0.2 |
| Ingenieria Estrella SRL | Disbursement | November 30, 2020 | 0.3 |
| Ingenieria Estrella SRL | Disbursement | November 30, 2020 | 0.6 |
| ACA (Fasgel S.A.)-CSI Ingenieros | Disbursement | October 31, 2020 | 0.2 |
| Consortium RAZEL BEC V et F Co | Disbursement | May 31, 2020 | 0.9 |
| Fasgel S.A | Disbursement | May 31, 2020 | 0.1 |
| Fasgel S.A | Disbursement | May 31, 2020 | 0.1 |
| Ingenieria Estrella | Disbursement | April 30, 2020 | 0.7 |
| Name not shown | Disbursement | March 31, 2020 | 0.4 |
| Fasgel S.A. | Disbursement | February 29, 2020 | 0.2 |
| Fasgel S.A. | Disbursement | February 29, 2020 | 0.3 |
| Fasgel S.A. | Disbursement | December 31, 2019 | 0.4 |
| Groupement Adpidsna Services | Disbursement | December 31, 2019 | 0.3 |
| Consortium RAZEL BEC V et F Co | Disbursement | December 31, 2019 | 0.9 |
| Appui au Secteur des Transports IV | Disbursement | December 31, 2019 | 1.0 |
| France Aviation Civile Service | Disbursement | December 31, 2019 | 0.2 |
| Fasgel S.A | Disbursement | March 31, 2019 | 0.1 |
| Fasgel S.A | Disbursement | March 31, 2019 | 0.1 |
| Consortium RAZEL BEC V et F Construction | Disbursement | March 31, 2019 | 0.8 |
| Name not shown | Disbursement | March 31, 2019 | 0.2 |
| Groupement Adpidsna Services | Disbursement | January 31, 2019 | <0.1 |
| Ingenieria Estrella | Disbursement | December 31, 2018 | 0.2 |
| Fasgel S.A | Disbursement | December 31, 2018 | 0.1 |
| Fasgel S.A | Disbursement | December 31, 2018 | 0.1 |
| Ingenieria Estrella | Disbursement | December 31, 2018 | 0.6 |
| Groupement Adpidsna Services | Disbursement | November 30, 2018 | <0.1 |
| Fasgel S.A | Disbursement | November 30, 2018 | 0.2 |
| Consortium RAZEL BEC V et F Construction | Disbursement | October 31, 2018 | 0.9 |
| Appui au Secteur des Transports IV | Disbursement | October 31, 2018 | 3.0 |
| Consortium RAZEL.BEC-V et F Construction | Disbursement | September 30, 2018 | 0.6 |
| Ingeniera Estrella | Disbursement | September 30, 2018 | 0.2 |
| Fasgel S.A | Disbursement | August 31, 2018 | <0.1 |
| Groupement Adpidsna Services | Disbursement | August 31, 2018 | <0.1 |
| Consortium RAZEL.BEC-V et F Construction | Disbursement | August 31, 2018 | 0.9 |
| Groupement Adpidsna Services | Disbursement | August 31, 2018 | <0.1 |
| Groupement Adpidsna Services | Disbursement | July 31, 2018 | 0.3 |
| Fasgel S.A | Disbursement | July 31, 2018 | 0.1 |
| Ingenieria Estrella | Disbursement | June 30, 2018 | 0.2 |
| Fasgel S.A. | Disbursement | June 30, 2018 | <0.1 |
| Groupement Adpidsna Services | Disbursement | June 30, 2018 | 0.1 |
| Consortium RAZEL.BEC-V et F Construction | Disbursement | June 30, 2018 | 1.0 |
| Fasgel S.A | Disbursement | May 31, 2018 | 0.1 |
| Ingeniera Estrella | Disbursement | May 31, 2018 | 0.2 |
| Consortium RAZEL-BECV et F Construction | Disbursement | May 31, 2018 | 0.9 |
| Consortium RAZEL.BECV et F Construction | Disbursement | May 31, 2018 | 1.4 |
| Ingenieria Estrella | Disbursement | May 31, 2018 | 0.3 |
| Fasgel S.A | Disbursement | April 30, 2018 | 0.1 |
| ADP Ingenierie | Disbursement | April 30, 2018 | 0.2 |
| Appui au Secteur des Transports IV | Disbursement | April 30, 2018 | 1.5 |
| Ingenieria Estrella | Disbursement | March 31, 2018 | 0.3 |
| Ingenieria Estrella | Disbursement | March 31, 2018 | 0.2 |
| Consortium RAZEL.BEC - V F | Disbursement | February 28, 2018 | 1.2 |
| Esptisa Servicios de Ingeniera S.L | Disbursement | January 31, 2018 | 0.1 |
| Esptisa Servicios de Ingeniera S.L | Disbursement | January 31, 2018 | 0.1 |
| Eptisa Servicios de Ingeniera S.L | Disbursement | December 31, 2017 | 0.1 |
| Consortium RAZEL.BEC - V F | Disbursement | December 31, 2017 | 0.9 |
| Fasgel S.A | Disbursement | November 30, 2017 | 0.1 |
| Ingeniera Estrella | Disbursement | November 30, 2017 | 1.0 |
| Ingeniera Estrella | Disbursement | November 30, 2017 | 0.1 |
| Consortium RAZEL.BEC - V F | Disbursement | October 31, 2017 | 0.7 |
| Ingeniera Estrella | Disbursement | October 31, 2017 | 0.6 |
| PTISA Servicios de Ingeniera S.L | Disbursement | July 31, 2017 | 0.1 |
| Fasgel S.A. | Disbursement | July 31, 2017 | 0.1 |
| Eptisa Servicios de Ingeniera S.L | Disbursement | June 30, 2017 | 0.1 |
| Appui au Secteur des Transports IV | Disbursement | June 30, 2017 | 3.0 |
| Fasgel S.A | Disbursement | May 31, 2017 | 0.1 |
| Ingenieria Estrella | Disbursement | April 30, 2017 | 0.2 |
| RAZEL.BEC-VF | Disbursement | March 31, 2017 | 0.3 |
| RAZEL.BEC-VF | Disbursement | March 31, 2017 | 0.3 |
| Fasgel S.A. | Disbursement | February 28, 2017 | 0.2 |
| Ingenieria Estrella | Disbursement | December 31, 2016 | 0.2 |
| Eptisa Servicios de Ingeniera S.L | Disbursement | December 31, 2016 | <0.1 |
| Eptisa Servicios de Ingeniera S.L | Disbursement | December 31, 2016 | 0.1 |
| RAZEL.BEC-VF | Disbursement | October 31, 2016 | 0.2 |
| RAZEL.BEC-VF | Disbursement | October 31, 2016 | 0.1 |
| RAZEL.BEC-VF | Disbursement | June 30, 2016 | 0.2 |
| RAZEL.BEC-VF | Disbursement | July 31, 2015 | 1.9 |
| Appui au Secteur des Transports IV | Disbursement | June 30, 2015 | 7.0 |
Identifiers2 identifiers
| System | Identifier | Source |
|---|---|---|
| IATI identifier | XI-IATI-IADB-HA-L1089 | IATI |
| IDB operation | HA-L1089 | Operation record |
Partner documents43 documents
- OEL15 HA-L1089 TLIA Master Plan Demand Projections 38691885.PDF, iadb.org
- OEL16 HA-L1089 accorddecoopintituionnelle-MTPMTC-AAN-APN 38691886.PDF, iadb.org
- OEL17 HA-L1089 OACIAnexo 11 - Servicios de Transito Aereo 38691887.PDF, iadb.org
- OEL18 HA-L1089 OACIAnexo14Vol1-Aerdromos 1 38691888.PDF, iadb.org
- Plan d Action de Reinstallation RAP RN1 Plaisance-Camp Coq-Vaudreuil WSP - 39774201.PDF, iadb.org
- OEL Haitis Air Transport Sector Review Feb27 2014 38689754.DOC, iadb.org
- OEL10 Regional integration considerations 38689744.DOCX, iadb.org
- OEL12 Estimation of the Pavement Condition Index for the TLIA runway 38689746.PDF, iadb.org
- OEL2 Preliminary design Tousaint Louverture International Airport control tower 38689749.PPT, iadb.org
- OEL3 Preliminary design Route Nationale 1 Plaisance Camp Coq section 38689751.PDF, iadb.org
- OEL4 4Economic Evaluation Component 1 38689752.DOCX, iadb.org
- OEL5 Economic Evaluation Component 2 38689753.DOCX, iadb.org
- OEL7 Tousaint Louverture International Airport environmental audit 38689756.DOCX, iadb.org
- OEL8 REHABILITATION OF THE PLAISANCE CAMP COQ ROAD 38691095.docx, iadb.org
- REL3ME - Monitoring Evaluation Arrangements 38687505.DOCX, iadb.org
- REL4ESMR - 4- Environmental and Social Management Report ESMR 38687506.pdf, iadb.org
- REL5PP -5 - Procurement Plan 38687507.XLSX, iadb.org
- IDB-PCR-Production-Timeline.pdf, iadb.org
- PCR aprobado - HA-L1089 -Support for Haitis Transport Sector IV- Informe de Terminacion de Proyecto PCR.msg, iadb.org
- PCRHA-L1089.pdf, iadb.org
- PCRHA-L1089-french.pdf, iadb.org
- HA-L1089 First period Jan-Jun 2014-Public Report 40181539.PDF, iadb.org
- HA-L1089 First period Jan-Jun 2015-Public Report 40194405.PDF, iadb.org
- HA-L1089 First period Jan-Jun 2017-Public Report.pdf, iadb.org
- HA-L1089 First period Jan-Jun 2018-Public Report.pdf, iadb.org
- HA-L1089 First period Jan-Jun 2019-Public Report.pdf, iadb.org
- HA-L1089 First period Jan-Jun 2020 - Public Report.pdf, iadb.org
- HA-L1089 First period Jan-Jun 2021 - Public Report.pdf, iadb.org
- HA-L1089 First period Jan-Jun 2022 - Public Report.PDF, iadb.org
- HA-L1089 First period Jan-Jun 2023 - Public Report.PDF, iadb.org
- HA-L1089 First period Jan-Jun 2024 - Public Report.PDF, iadb.org
- HA-L1089 Second period Jan-Dec 2014-Public Report 40185524.PDF, iadb.org
- HA-L1089 Second period Jan-Dec 2015-Public Report 40377350.PDF, iadb.org
- HA-L1089 Second period Jan-Dec 2016-Public Report.pdf, iadb.org
- HA-L1089 Second period Jan-Dec 2017-Public Report.pdf, iadb.org
- HA-L1089 Second period Jan-Dec 2018-Public Report.pdf, iadb.org
- HA-L1089 Second period Jan-Dec 2019-Public Report.pdf, iadb.org
- HA-L1089 Second period Jan-Dec 2020 - Public Report.pdf, iadb.org
- HA-L1089 Second period Jan-Dec 2021 - Public Report.PDF, iadb.org
- HA-L1089 Second period Jan-Dec 2022 - Public Report.PDF, iadb.org
- HA-L1089 Second period Jan-Dec 2023 - Public Report.PDF, iadb.org
- HA-L1089 Second period Jan-Dec 2024 - Public Report.PDF, iadb.org
- HA-L1089 Second period Jan-Dec 2024 - Public Report.PDF, iadb.org
Procurement notices (11)
- IDB_Procurement_Notices.xlsx, iadb.org
- HA-L1089 38930393.PDF, iadb.org
- HA-L1089 39605169.PDF, iadb.org
- HA-L1089 39632161.PDF, iadb.org
- HA-L1089 39654133.PDF, iadb.org
- HA-L1089 39693290.PDF, iadb.org
- HA-L1089 39701128.PDF, iadb.org
- HA-L1089 39856373.PDF, iadb.org
- HA-L1089 39856374.PDF, iadb.org
- HA-L1089 40845411.PDF, iadb.org
- IDB_Project_Procurement_Contract_Awards_Data.xlsx, iadb.org
Sources
- IATI record (d-portal): terms of use set by the publisher
- IATI: terms of use set by the publisher
- IDB project page: terms of use set by the publisher
- Transactions: terms of use set by the publisher
- Operation record: terms of use set by the publisher
Data as of October 18, 2026
| Source | Read on |
|---|---|
| IATI | October 18, 2026 |
| IATI | October 18, 2026 |
| IDB projects dataset | October 18, 2026 |
Cite this page