Objective

The objectives of the Project are to: (a) support the development of the Centre Artibonite Loop region, primarily by enhancing all-weather connectivity and logistics for producers, and the region’s resilience to climate change; and (b) support the Recipient’s capacity to respond promptly and effectively to an Eligible Emergency, as needed.

As published by World Bank Projects, in its original language.

Description

The development objectives of the Center and Artibonite Regional Development Project for Haiti are to: (a) support the development of the Centre Artibonite Loop (CAL) region, primarily by enhancing all-weather connectivity and logistics for producers, and the region's resilience to climate change; and (b) support the recipient's capacity to respond promptly and effectively to an eligible emergency, as needed. The project comprises of five components. The first component, enhancing logistics, transport connectivity, and climate resilience aims to link the CAL region to economic growth poles outside the region, and to improve the internal connectivity of the CAL, by increasing all-weather access to agricultural production areas, markets and services, and by increasing the rural access index and the macro-resilience of the

more

road network to natural events and effects of climate change. It has following four sub-components: (i) improving the structuring road network; (ii) improving the rural road network; (iii) strengthening road maintenance capacity and mechanisms at the local level; and (iv) supporting the application of best practices addressing the issue of climate resilience. The second component will improve the infrastructure and management capacity of key selected urban markets (2 to 4) and rural markets (4 to 8) to link agricultural producers with the roads provided under first component. It comprises of following two sub-components: (i) urban markets and associated facilities; and (ii) rural markets. The third component, supporting the development of regional knowledge, planning capacity, and local participation aims to support the Government of Haiti (GoH), municipalities, and local stakeholders to effectively plan and make consensual decisions. It has following two sub-components: (i) improving regional knowledge; and (ii) supporting the development of regional planning capacity and local participation. The fourth component, contingent emergency response include triggers and conditions for the use of funds, included in most investment projects in Haiti in keeping with the recommendations of the 2011 World Development Report (WDR) on conflict, security and development, and with the operational experience acquired in Haiti since the 2010 earthquake. The fifth component, project implementation, monitoring and evaluation will finance the activities of the implementing agency for the project: the unite technique d'execution (UTE), an existing project implementation unit (PIU) under the responsibility of Ministry of Economy and Finance (MEF).

Partner
World Bank Group, World Bank
Sector
Transport
Stage
Closed since August 31, 2020
Approval
May 19, 2014
Closing
August 31, 2020
Instrument
IBRD/IDA financing, Grants
Undisbursed gap
9.8: trust funds are not in the IDA statement, which gives undisbursed amounts for IDA money only; the IDA statement values undisbursed credits in special drawing rights at the current exchange rate
Borrower
Ministry of Economy and Finance
Implementing agency
Unite Centale d'Execution (UCE),Unite Technique d'Execution (UTE)
Effectiveness
October 6, 2014
Departments
Ouest, Nord, Centre, Artibonite
Last transaction
June 30, 2021
Operation ID
P133352
Life cycle4 stages, 12 dates

Stage history

StageFrom
ApprovedMay 19, 2014
Under wayMay 19, 2014
ClosingAugust 31, 2020
ClosedAugust 31, 2020

Dated events

EventDateSource
Planned startDecember 26, 2013IATI
AppraisalJanuary 13, 2014World Bank Projects
NegotiationApril 2, 2014World Bank Projects
Actual startMay 19, 2014IATI
ApprovalMay 19, 2014World Bank Projects
First commitmentMay 19, 2014Transactions
EffectivenessOctober 6, 2014World Bank Projects
First disbursementOctober 31, 2014Transactions
Actual endAugust 31, 2020IATI
Closing dateAugust 31, 2020IATI
Last disbursementDecember 31, 2020Transactions
Completion report dueFebruary 27, 2021World Bank Projects

Undisbursed: US$0.0 million on September 30, 2026, with closing on August 31, 2020.

Financing

Table 1.Financing, US$ millions

FinancierAmountUS$ millionsRoleSource
IDA Grant50.0InstitutionWorld Bank Projects
Strategic Climate Fund Grant8.0Trust fundWorld Bank Projects

Table 2.Position at the data date by source (stocks), US$ millions

This pageUS$ millionsSourceIATIUS$ millions
Commitment25.3IDA Statement of Credits and Grants20.8
Disbursed15.5IDA Statement of Credits and Grants15.5
Undisbursed0.0IDA Statement of Credits and Grants
Total cost58.0World Bank Projects

World Bank amounts. Approved: Net commitment, the amount approved less cancellations, in US$ at the data date. Disbursed to date: The disbursements of the IDA statement and the Projects API to date, in US$. Undisbursed: The undisbursed balance the IDA statement publishes, in US$ at the data date. IATI column: the commitments and disbursements the partner reports to IATI, converted to US$. Amounts by source

Changes to the operation1 extension, at least 2 restructurings
Original closing date
February 28, 2020
Closing date extensions
1
  • Extended from February 28, 2020 to August 31, 2020 (document of March 31, 2020)
Restructurings
at least 2
Emergency component
Not reported

New commitments and disbursements by fiscal year

Disbursements, US$ millions
FY2013-14, not reportedn.r.13-14FY2014-15, US$2.5 million314-15FY2016-17, US$2.0 million216-17FY2017-18, US$2.0 million217-18FY2018-19, US$13.8 million1418-19FY2019-20, US$−3.0 million-319-20FY2020-21, US$−1.9 million-220-21FY2013-14, not reportedn.r.13-14FY2014-15, US$2.5 million314-15FY2016-17, US$2.0 million216-17FY2017-18, US$2.0 million217-18FY2018-19, US$13.8 million1418-19FY2019-20, US$−3.0 million-319-20FY2020-21, US$−1.9 million-220-21

Table 3.New commitments and disbursements by fiscal year (flows), US$ millions

FY2013-14US$ millionsFY2014-15US$ millionsFY2016-17US$ millionsFY2017-18US$ millionsFY2018-19US$ millionsFY2019-20US$ millionsFY2020-21US$ millions
New commitments58.0Not reportedNot reportedNot reportedNot reported−26.2−6.5
DisbursementsNot reported2.52.02.013.8−3.0−1.9
Cumulative disbursementsNot reported2.54.56.520.317.315.5

Records and documents

Transactions19 records, May 19, 2014 to June 30, 2021

Table 4.Transactions, US$ millions

DateMeasureAmountUS$ millionsSourceMethod
May 19, 2014Commitment50.0IDA Statement of Credits and Grantscredit original principal at board approval
May 19, 2014Commitment8.0World Bank Projectstrust funds in the Projects API financier list, not in the IDA statement, at the board approval date
March 31, 2020Commitment−26.2IDA Statement of Credits and Grantscancellation: increase in cumulative cancelled amount between snapshots (non-USD credit: includes exchange revaluation)
June 30, 2021Commitment−6.5IDA Statement of Credits and Grantscancellation: increase in cumulative cancelled amount between snapshots (non-USD credit: includes exchange revaluation)
October 31, 2014Disbursements0.5IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
January 31, 2015Disbursements1.0IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
July 31, 2015Disbursements1.0IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
October 31, 2016Disbursements1.0IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
May 31, 2017Disbursements1.0IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
July 31, 2018Disbursements2.0IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
October 31, 2018Disbursements3.0IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
November 30, 2018Disbursements8.5IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
July 31, 2019Disbursements2.3IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
March 31, 2020Disbursements0.9IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
August 31, 2020Disbursements−3.9IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
December 31, 2020Disbursements0.8IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
February 28, 2021Disbursements−1.9IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
March 31, 2021Disbursements−0.7IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
April 30, 2021Disbursements−0.0IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
Terms4 of 6 reported
Finance type
110 Standard grant
Flow type
Not reported
Aid type
C01 Project-type interventions
Tied status
5 Untied
Collaboration type
2 Multilateral inflows
Humanitarian
Not reported
Locations4 departments, 4 places named, 8 places with coordinates
DepartmentsOuest, Nord, Centre, Artibonite
Places named by the sourceCentre, Departement de l'Artibonite, Departement de l'Ouest, Nord
Places with coordinates8
Results indicators13 indicators
IndicatorBaselineTargetLatest valueDate of latest value
Number of Road Maintenance Centers build or rehabilitated0.001.000.00August 31, 2020
Number of events/activities dedicated for knowledge dissemination and consultation0.000.0012.00August 31, 2020
Number of people trained within selected communities on basic Rural Road Maintenance (disaggregated by gender)0.00300.00284.00February 28, 2020
Roads rehabilitated, Non-rural0.0060.0055.87August 31, 2020
Roads rehabilitated, Rural0.0040.0030.00August 31, 2020
Spot interventions to enhance all-weather and resilient connectivity0.0044.0064.00August 31, 2020
Urban plans developed and consulted with Local officials and local stakeholders0.003.002.00August 31, 2020
disaggregated by gender, in % of women0.000.00Not reportedNot reported
Number of producers and users serviced by an all-weather-road accessing urban and rural markets.0.000.00123500.00August 31, 2020
Share of rural population with access to an all-season road39.0045.0044.00August 28, 2020
Share of the population in the Project area satisfied with the quality and impact of infrastructure financed by the Project0.000.0097.50June 30, 2020
Female beneficiaries0.000.000.00July 18, 2018
Number of rural people with access to an all-season road374400.000.000.00July 18, 2018
Ratings17 ratings
RatingValueDate
IEG bankqualityofsupervisionModerately SatisfactoryJune 21, 2021
IEG borrowcomplianceNot RatedJune 21, 2021
IEG evaltypeESJune 21, 2021
IEG icrqualitySubstantialJune 21, 2021
IEG mequalityModestJune 21, 2021
IEG outcomeModerately UnsatisfactoryJune 21, 2021
IEG overallbankperfModerately SatisfactoryJune 21, 2021
ICR bankqualityentryNot RatedFebruary 27, 2021
ICR banksupervisionNot RatedFebruary 27, 2021
ICR outratingindModerately UnsatisfactoryFebruary 27, 2021
ICR overallratingModerately SatisfactoryFebruary 27, 2021
ISR Financial ManagementModerately SatisfactoryAugust 31, 2020
ISR Monitoring and EvaluationModerately SatisfactoryAugust 31, 2020
ISR Overall Implementation Progress (IP)Moderately SatisfactoryAugust 31, 2020
ISR ProcurementModerately SatisfactoryAugust 31, 2020
ISR Progress towards achievement of PDOModerately SatisfactoryAugust 31, 2020
ISR Project ManagementModerately SatisfactoryAugust 31, 2020
Contract awards10 awards
SupplierDateMethodAmount
Civil Design & ConstructionJune 8, 2020DIR894,400 HTG
Global CommunitiesNovember 6, 2019FBS3,795,000 USD
SETEC InternationalOctober 31, 2019QCBS112,348,069.39 HTG
SETEC InternationalOctober 31, 2019QCBS41,016.36 USD
BETA Ingnieurs-ConseilsOctober 31, 2019QCBSNot reported
Name not shownApril 25, 2019CDS4,143,422.11 Haitian Gourdes
Name not shownJanuary 15, 2019CDS7,648,647 Haitian Gourdes
Name not shownNovember 16, 2018RFQ16,281,998 HTG
Name not shownNovember 16, 2018RFQ14,425,950 HTG
Name not shownNovember 16, 2018RFQ15,600,000 HTG
Funds passed on18 transactions
ReceiverTransactionDateUS$ millions
Unite Centale d'Execution (UCE); Unite Technique d'Execution (UTE)CommitmentJune 30, 2021−6.0
Unite Centale d'Execution (UCE); Unite Technique d'Execution (UTE)DisbursementApril 30, 2021−0.0
Unite Centale d'Execution (UCE); Unite Technique d'Execution (UTE)DisbursementMarch 31, 2021−0.7
Unite Centale d'Execution (UCE); Unite Technique d'Execution (UTE)DisbursementFebruary 28, 2021−1.9
Unite Centale d'Execution (UCE); Unite Technique d'Execution (UTE)DisbursementDecember 31, 20200.8
Unite Centale d'Execution (UCE); Unite Technique d'Execution (UTE)DisbursementAugust 31, 2020−3.9
Unite Centale d'Execution (UCE); Unite Technique d'Execution (UTE)CommitmentMarch 31, 2020−23.2
Unite Centale d'Execution (UCE); Unite Technique d'Execution (UTE)DisbursementMarch 31, 20200.9
Unite Centale d'Execution (UCE); Unite Technique d'Execution (UTE)DisbursementJuly 31, 20192.3
Unite Centale d'Execution (UCE); Unite Technique d'Execution (UTE)DisbursementNovember 30, 20188.5
Unite Centale d'Execution (UCE); Unite Technique d'Execution (UTE)DisbursementOctober 31, 20183.0
Unite Centale d'Execution (UCE); Unite Technique d'Execution (UTE)DisbursementJuly 31, 20182.0
Unite Centale d'Execution (UCE); Unite Technique d'Execution (UTE)DisbursementMay 31, 20171.0
Unite Centale d'Execution (UCE); Unite Technique d'Execution (UTE)DisbursementOctober 31, 20161.0
Unite Centale d'Execution (UCE); Unite Technique d'Execution (UTE)DisbursementJuly 31, 20151.0
Unite Centale d'Execution (UCE); Unite Technique d'Execution (UTE)DisbursementJanuary 31, 20151.0
Unite Centale d'Execution (UCE); Unite Technique d'Execution (UTE)DisbursementOctober 31, 20140.5
Unite Centale d'Execution (UCE); Unite Technique d'Execution (UTE)CommitmentMay 31, 201450.0
Identifiers4 identifiers
SystemIdentifierSource
IATI identifier44000-P133352IATI
IDA credit or grantIDAH9500IDA Statement of Credits and Grants
World Bank loanIDA-H9500World Bank Projects
World Bank projectP133352Operation record
Where sources differ2 fields
FieldSourceValueUsed
CommitmentIDA Statement of Credits and GrantsUS$25.3 million✓
CommitmentIATIUS$20.8 million
CommitmentWorld Bank ProjectsUS$58.0 million
StatusWorld Bank ProjectsClosed✓
StatusIATIActive
Partner documents64 documents
Procurement notices (2)

Sources

Data as of October 18, 2026
SourceRead on
IATIOctober 18, 2026
IATIOctober 18, 2026
IDA Statement of Credits and GrantsOctober 18, 2026
World Bank procurement noticesOctober 18, 2026
World Bank ProjectsOctober 18, 2026
World Bank documentsOctober 18, 2026
Cite this page

HaitiDocs. HT Center and Artibonite Regional Development. Partner portfolio, data as of October 18, 2026. https://www.haitidocs.org/portfolio/projects/WB%3AP133352