Caribbean Regional Air Transport Connectivity Project - Haiti

US$ millions unless stated. Haitian fiscal year, October to September. FY2026-27 began October 1, 2026.

Objective

The objectives of the Project (PDO) are to: (i) improve operational safety and navigation efficiency of air transport in the Recipient’s territory; and (ii) increase the climate and disaster resilience of associated infrastructure at the Recipient’s international airports.

As published by World Bank Projects, in its original language.

Description

The objectives of the Caribbean Regional Air Transport Connectivity Project for Haiti are to: (i) improve operational safety and navigation efficiency of air transport in the Recipient’s territory; and (ii) increase the climate and disaster resilience of associated infrastructure at the Recipient’s international airports. The Project has four components. 1. PAP (IATA 3-letter code for Port-au-Prince Toussaint Louverture Airport) and CAP (IATA three-letter code for Cap-Haïtien Airport) operational safety and navigation efficiency investments component will finance infrastructure and equipment at Haiti’s two international airports—PAP and CAP. It will finance, inter alia: (i) Civil works; (ii) Purchase and installation of equipment; (iii) Consulting and non-consulting services. 2. PAP and CAP airfield drainage system improvements component will reduce the risk of airfield

more

flooding associated with the annual rainy season, hurricanes, and climate change at PAP and CAP by increasing the drainage capacity at both airfields and thus improving their climate/disaster resilience. This component would finance inter alia: (i) Civil works; (ii) Consulting and non-consulting services. 3. Institutional strengthening and project management component will: (i) strengthen the institutional capacity of the Ministry of Public Works, Transportation, and Communication (MTPTC), National Airport Authority (AAN), and National Office of Civil Aviation (OFNAC) to manage, operate, and oversee airport operations and their development through a combination of TA activities and training; (ii) provide technical assistance (TA) to assess the capabilities, needs, and opportunities for the use of Unmanned Aircraft Systems (UAS) in Haiti; ; and (iii) finance project implementation support. 4. Contingent Emergency Response component is included for rapid response in the event of an eligible emergency, subject to the request of the Government of Haiti (GoH).

Partner
World Bank Group, IDA
Sector
Transport
Stage
Under way since May 28, 2020
Approval
May 28, 2020
Closing
December 31, 2027
Instrument
IBRD/IDA financing, IDA
Undisbursed gap
0.4: the IDA statement values undisbursed credits in special drawing rights at the current exchange rate
Borrower
Republic of Haiti
Implementing agency
Central Execution Unit of the Ministry of Public Works (UCE)
Effectiveness
August 27, 2020
Last transaction
September 30, 2026
Operation ID
P170907
Life cycle3 stages, 13 dates

Stage history

StageFrom
PlannedMay 30, 2019
ApprovedMay 28, 2020
Under wayMay 28, 2020

Dated events

EventDateSource
Concept reviewMay 30, 2019World Bank Projects
DisclosureJune 6, 2019World Bank Projects
Planned startJanuary 15, 2020IATI
AppraisalFebruary 11, 2020World Bank Projects
NegotiationMarch 14, 2020World Bank Projects
Actual startMay 28, 2020IATI
ApprovalMay 28, 2020World Bank Projects
First commitmentMay 28, 2020Transactions
EffectivenessAugust 27, 2020World Bank Projects
First disbursementFebruary 28, 2021Transactions
Last disbursementSeptember 30, 2026Transactions
Closing dateDecember 31, 2027IATI
Completion report dueJune 30, 2028World Bank Projects

Undisbursed: US$71.1 million on September 30, 2026, with closing on December 31, 2027. Disbursed in FY2025-26: US$11.2 million.

Financing

Table 1.Financing, US$ millions

FinancierAmountUS$ millionsRoleSource
IDA Grant84.0InstitutionWorld Bank Projects

Table 2.Related operations, US$ millions

OperationRelationPartnerStageCommitmentUS$ millions
Additional Financing - Haiti Caribbean Air Transport Connectivity ProjectAdditional financing or child operationWorld Bank GroupUnder way12.0

Table 3.Position at the data date by source (stocks), US$ millions

This pageUS$ millionsSourceIATIUS$ millions
Commitment96.0IDA Statement of Credits and Grants96.0
Disbursed24.4IDA Statement of Credits and Grants16.9
Undisbursed71.1IDA Statement of Credits and Grants
Total cost84.0World Bank Projects

World Bank amounts. Approved: Net commitment, the amount approved less cancellations, in US$ at the data date. Disbursed to date: The disbursements of the IDA statement and the Projects API to date, in US$. Undisbursed: The undisbursed balance the IDA statement publishes, in US$ at the data date. IATI column: the commitments and disbursements the partner reports to IATI, converted to US$. Amounts by source

Changes to the operation1 extension, 1 restructuring, emergency component included
Original closing date
June 30, 2026
Closing date extensions
1
  • Extended from June 30, 2026 to December 31, 2027 (document of August 31, 2025)
Restructurings
1
Emergency component
Contingent emergency response component included (document of June 27, 2025) restructuring paper

New commitments and disbursements by fiscal year

Disbursements, US$ millions
FY2019-20, not reportedn.r.19-20FY2020-21, US$3.0 million320-21FY2021-22, US$0.5 million0.521-22FY2022-23, US$1.2 million122-23FY2023-24, US$4.3 million423-24FY2024-25, US$4.2 million424-25FY2025-26, US$11.2 million1125-26FY2019-20, not reportedn.r.19-20FY2020-21, US$3.0 million320-21FY2021-22, US$0.5 million0.521-22FY2022-23, US$1.2 million122-23FY2023-24, US$4.3 million423-24FY2024-25, US$4.2 million424-25FY2025-26, US$11.2 million1125-26

Table 4.New commitments and disbursements by fiscal year (flows), US$ millions

FY2019-20US$ millionsFY2020-21US$ millionsFY2021-22US$ millionsFY2022-23US$ millionsFY2023-24US$ millionsFY2024-25US$ millionsFY2025-26US$ millions
New commitments84.0Not reportedNot reported12.0Not reportedNot reportedNot reported
DisbursementsNot reported3.00.51.24.34.211.2
Cumulative disbursementsNot reported3.03.54.79.013.224.4

Records and documents

Transactions39 records, May 28, 2020 to September 30, 2026

Table 5.Transactions, US$ millions

DateMeasureAmountUS$ millionsSourceMethod
May 28, 2020Commitment84.0IDA Statement of Credits and Grantscredit original principal at board approval
July 5, 2023Commitment12.0IDA Statement of Credits and Grantscredit original principal at board approval
February 28, 2021Disbursements3.0IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
July 31, 2021Disbursements<0.1IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
January 31, 2022Disbursements0.1IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
March 31, 2022Disbursements0.4IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
May 31, 2022Disbursements<0.1IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
October 31, 2022Disbursements<0.1IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
November 30, 2022Disbursements0.4IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
December 31, 2022Disbursements<0.1IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
March 31, 2023Disbursements0.2IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
May 31, 2023Disbursements0.1IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
August 31, 2023Disbursements0.3IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
November 30, 2023Disbursements1.8IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
January 31, 2024Disbursements0.2IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
February 29, 2024Disbursements0.3IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
April 30, 2024Disbursements<0.1IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
May 31, 2024Disbursements0.1IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
June 30, 2024Disbursements0.4IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
July 31, 2024Disbursements0.9IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
August 31, 2024Disbursements0.2IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
September 30, 2024Disbursements0.4IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
October 31, 2024Disbursements0.3IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
November 30, 2024Disbursements0.1IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
December 31, 2024Disbursements0.1IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
January 31, 2025Disbursements<0.1IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
April 30, 2025Disbursements0.3IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
May 31, 2025Disbursements0.4IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
June 30, 2025Disbursements0.8IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
July 31, 2025Disbursements0.4IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
September 30, 2025Disbursements1.8IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
October 31, 2025Disbursements0.4IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
December 31, 2025Disbursements0.5IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
February 28, 2026Disbursements1.5IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
March 31, 2026Disbursements<0.1IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
May 31, 2026Disbursements1.0IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
June 30, 2026Disbursements0.2IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
July 31, 2026Disbursements0.9IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
September 30, 2026Disbursements6.7IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
Terms4 of 6 reported
Finance type
110 Standard grant
Flow type
Not reported
Aid type
C01 Project-type interventions
Tied status
5 Untied
Collaboration type
2 Multilateral inflows
Humanitarian
Not reported
Locations1 place named, 2 places with coordinates
DepartmentsNot reported
Places named by the sourceRepublic of Haiti
Places with coordinates2
Results indicators27 indicators
IndicatorBaselineTargetLatest valueDate of latest value
ADS-B for CAP and PAP installed and operationalNoYesNoFebruary 13, 2024
Additional aircraft parking apron built at PAP0.0026100.000.00February 13, 2024
Airfield Ground Lighting (AGL) for the CAP runway is installed and operationalNoYesNoFebruary 13, 2024
Aviation sector strategy preparedNoYesNoFebruary 13, 2024
Constructed CAP Air Traffic Control Tower (ATCT) in compliance with ICAO SARPsNoYesNoFebruary 13, 2024
Grievances adequately responded to and/or resolved within the stipulated service standards0.00100.000.00February 13, 2024
Length of CAP runway rehabilitated0.002450.000.00February 13, 2024
Length of PAP drainage system3850.002450.003850.00February 13, 2024
Length of PAP taxiway system built0.001460.000.00February 13, 2024
New culverts built at CAP0.004.000.00February 13, 2024
OFNAC safety inspectors trained by a certified agency0.0050.000.00February 13, 2024
PAP RESAs implemented and consistent with ICAO SARPsNoYesNoFebruary 13, 2024
People with Enhanced Access to Transportation Services0.001900000.000.00February 13, 2024
Regional training programs attended by AAN and OFNAC0.005.001.00February 13, 2024
Rescue Coordination Center staff trained by a certified agency0.0050.000.00February 13, 2024
Semi-annual meetings held with stakeholders to discuss their suggestions and related actions taken by the Project0.0012.003.00February 13, 2024
Share of infrastructure activities identified as climate resilient0.00100.000.00February 13, 2024
Share of women hired in medium-skill jobs by UCE-MTPC, OFNAC and AAN0.0015.000.00February 13, 2024
Share of women included in the medium-skills training0.0030.0033.00February 13, 2024
Wildlife management plan prepared and implemented for PAP and CAP airportsNoYesNoFebruary 13, 2024
Average Runway Occupancy Time (ROT) of airplanes at PAP7.505.007.50February 13, 2024
Average number of days per year the discharge exceeds the capacity of the airport drainage system at PAP and CAP20.000.0020.00February 13, 2024
PAP and CAP runways in compliance with ICAO SARPsNoYesNoFebruary 13, 2024
Targeted upgrade of air navigation systems achieved at CAP and PAPNon-precision navigation system: No VSAT or ADS-BElectronic navigation system in place (ADS-B impleNon-precision navigation system: No VSAT or ADS-BFebruary 13, 2024
Direct users that benefit from improved access to sustainable transport infrastructure and services0190,00000Not reported
Average number of days per year the discharge exceeds the capacity of the airport drainage system at CAP10.000.0010.00February 13, 2024
Average number of days per year the discharge exceeds the capacity of the airport drainage system at PAP10.000.0010.00February 13, 2024
Ratings6 ratings
RatingValueDate
ISR Financial ManagementModerately SatisfactoryJune 19, 2026
ISR Monitoring and EvaluationSatisfactoryJune 19, 2026
ISR Overall Implementation Progress (IP)Moderately SatisfactoryJune 19, 2026
ISR ProcurementModerately SatisfactoryJune 19, 2026
ISR Progress towards achievement of PDOModerately SatisfactoryJune 19, 2026
ISR Project ManagementModerately SatisfactoryJune 19, 2026
Contract awards21 awards
SupplierDateMethodAmount
V&F ConstructionJuly 17, 2026RFB31,546,341.58 USD
REMIX S. A.July 17, 2026RFBNot reported
V&F ConstructionJuly 17, 2026RFBNot reported
VINCI Construction Grands ProjetsMay 7, 2026CDS1,700,000 USD
Artelia Passion and SolutionsMay 8, 2025CQS529,117.11 USD
Societe de GENIE Conseil S. A.May 8, 2025CQSNot reported
Artelia Passion and SolutionsApril 7, 2025CDS480,608.8 USD
SETEC InternationalJanuary 29, 2025QCBS829,801.5 USD
BETA Ingénieurs-ConseilsJanuary 29, 2025QCBSNot reported
SETEC InternationalJanuary 13, 2025QCBS939,677.2 USD
BETA Ingénieurs-ConseilsJanuary 13, 2025QCBSNot reported
Coamco Haïti S. A.June 24, 2024RFB4,725,442.26 USD
Name not shownJuly 27, 2023INDV6,642 USD
Name not shownJune 1, 2023INDV20,000 USD
Instituto Dominicano de Aviacin Civil (IDAC)April 28, 2023DIR1,387,337.87 USD
Firme TurnierDecember 13, 2022LCS4,161,000 HTG
Unite Caribbean SASNovember 22, 2022CQS96,275 USD
CECOM Consultants S. A.November 8, 2022QCBS1,177,697 USD
CECOM Consultants S. A.November 8, 2022QCBS11,914,000 HTG
Techniplan SRLNovember 8, 2022QCBSNot reported
France Aviation Civile Services (FRACS)October 8, 2021CDS2,030,600 EUR
Funds passed on37 transactions
ReceiverTransactionDateUS$ millions
Central Execution Unit of the Ministry of Public Works (UCE)DisbursementJune 30, 20260.2
Central Execution Unit of the Ministry of Public Works (UCE)DisbursementMay 31, 20261.0
Central Execution Unit of the Ministry of Public Works (UCE)DisbursementMarch 31, 2026<0.1
Central Execution Unit of the Ministry of Public Works (UCE)DisbursementFebruary 28, 20261.5
Central Execution Unit of the Ministry of Public Works (UCE)DisbursementDecember 31, 20250.5
Central Execution Unit of the Ministry of Public Works (UCE)DisbursementOctober 31, 20250.4
Central Execution Unit of the Ministry of Public Works (UCE)DisbursementSeptember 30, 20251.8
Central Execution Unit of the Ministry of Public Works (UCE)DisbursementJuly 31, 20250.4
Central Execution Unit of the Ministry of Public Works (UCE)DisbursementJune 30, 20250.8
Central Execution Unit of the Ministry of Public Works (UCE)DisbursementMay 31, 20250.4
Central Execution Unit of the Ministry of Public Works (UCE)DisbursementApril 30, 20250.3
Central Execution Unit of the Ministry of Public Works (UCE)DisbursementJanuary 31, 2025<0.1
Central Execution Unit of the Ministry of Public Works (UCE)DisbursementDecember 31, 20240.1
Central Execution Unit of the Ministry of Public Works (UCE)DisbursementNovember 30, 20240.1
Central Execution Unit of the Ministry of Public Works (UCE)DisbursementOctober 31, 20240.3
Central Execution Unit of the Ministry of Public Works (UCE)DisbursementSeptember 30, 20240.4
Central Execution Unit of the Ministry of Public Works (UCE)DisbursementAugust 31, 20240.2
Central Execution Unit of the Ministry of Public Works (UCE)DisbursementJuly 31, 20240.9
Central Execution Unit of the Ministry of Public Works (UCE)DisbursementJune 30, 20240.4
Central Execution Unit of the Ministry of Public Works (UCE)DisbursementMay 31, 20240.1
Central Execution Unit of the Ministry of Public Works (UCE)DisbursementApril 30, 2024<0.1
Central Execution Unit of the Ministry of Public Works (UCE)DisbursementFebruary 29, 20240.3
Central Execution Unit of the Ministry of Public Works (UCE)DisbursementJanuary 31, 20240.2
Central Execution Unit of the Ministry of Public Works (UCE)DisbursementNovember 30, 20231.8
Central Execution Unit of the Ministry of Public Works (UCE)DisbursementAugust 31, 20230.3
Central Execution Unit of the Ministry of Public Works (UCE)CommitmentJuly 31, 202312.0
Central Execution Unit of the Ministry of Public Works (UCE)DisbursementMay 31, 20230.1
Central Execution Unit of the Ministry of Public Works (UCE)DisbursementMarch 31, 20230.2
Central Execution Unit of the Ministry of Public Works (UCE)DisbursementDecember 31, 2022<0.1
Central Execution Unit of the Ministry of Public Works (UCE)DisbursementNovember 30, 20220.4
Central Execution Unit of the Ministry of Public Works (UCE)DisbursementOctober 31, 2022<0.1
Central Execution Unit of the Ministry of Public Works (UCE)DisbursementMay 31, 2022<0.1
Central Execution Unit of the Ministry of Public Works (UCE)DisbursementMarch 31, 20220.4
Central Execution Unit of the Ministry of Public Works (UCE)DisbursementJanuary 31, 20220.1
Central Execution Unit of the Ministry of Public Works (UCE)DisbursementJuly 31, 2021<0.1
Central Execution Unit of the Ministry of Public Works (UCE)DisbursementFebruary 28, 20213.0
Central Execution Unit of the Ministry of Public Works (UCE)CommitmentMay 31, 202084.0
Identifiers7 identifiers
SystemIdentifierSource
IATI identifier44000-P170907IATI
IDA credit or grantIDAD6290IDA Statement of Credits and Grants
IDA credit or grantIDAE2030IDA Statement of Credits and Grants
Public investment program line11141-1-25-31-86Public investment program
World Bank loanIDA-D6290World Bank Projects
World Bank loanIDA-E2030World Bank Projects
World Bank projectP170907Operation record
Where sources differ1 field
FieldSourceValueUsed
CommitmentIDA Statement of Credits and GrantsUS$96.0 million✓
CommitmentWorld Bank ProjectsUS$84.0 million
Partner documents62 documents
Procurement notices (2)

Sources

Data as of October 18, 2026
SourceRead on
IATIOctober 18, 2026
IATIOctober 18, 2026
IDA Statement of Credits and GrantsOctober 18, 2026
Public investment programOctober 18, 2026
World Bank procurement noticesOctober 18, 2026
World Bank ProjectsOctober 18, 2026
World Bank documentsOctober 18, 2026
Cite this page

HaitiDocs. Caribbean Regional Air Transport Connectivity Project - Haiti. Partner portfolio, data as of October 18, 2026. https://www.haitidocs.org/portfolio/projects/WB%3AP170907