Objective
The overall objective is to improve the capacity and quality of the transport and logistics infrastructure in Haiti, improving the accessibility from the different country's regions to internal and external markets.
As published by IDB projects dataset, in its original language.
- Sector
- Transport
- Stage
- Closed since March 2, 2023
- Approval
- November 20, 2013
- Closing
- March 2, 2023
- Instrument
- Grant, Sovereign Guaranteed
- Effectiveness
- Not reported
- Last transaction
- April 30, 2021
- Operation ID
- HA-L1079
Life cycle4 stages, 9 dates
Stage history
| Stage | From |
|---|---|
| Approved | November 20, 2013 |
| Under way | February 18, 2014 |
| Closing | March 15, 2022 |
| Closed | March 2, 2023 |
Dated events
| Event | Date | Source |
|---|---|---|
| Approval | November 20, 2013 | IDB projects dataset |
| First commitment | November 20, 2013 | Transactions |
| Signing | February 18, 2014 | IDB projects dataset |
| Planned start | June 26, 2014 | IATI |
| Actual start | July 28, 2014 | IATI |
| First disbursement | July 31, 2014 | Transactions |
| Last disbursement | April 30, 2021 | Transactions |
| Closing date | March 15, 2022 | IATI |
| Actual end | March 2, 2023 | IATI |
Financing
Table 1.Financing, US$ millions
| Financier | AmountUS$ millions | Role | Source |
|---|---|---|---|
| IDB | 50.0 | Institution | IDB projects dataset |
Table 2.Position at the data date by source (stocks), US$ millions
| This pageUS$ millions | Source | IATIUS$ millions | |
|---|---|---|---|
| Commitment | 50.0 | IDB projects dataset | 50.0 |
| Disbursed | 37.0 | IATI | 37.0 |
| Undisbursed | Not reported | ||
| Total cost | 50.0 | IDB projects dataset |
Each amount is given as the source publishes it, converted to US$. IATI column: the commitments and disbursements the partner reports to IATI, converted to US$. Amounts by source
This page uses IDB projects dataset for the commitment and IATI for disbursements.
Changes to the operationnot reported
- Original closing date
- Not reported
- Closing date extensions
- Not reported
- Restructurings
- Not reported
- Emergency component
- Not reported
New commitments and disbursements by fiscal year
Table 3.New commitments and disbursements by fiscal year (flows), US$ millions
| FY2013-14US$ millions | FY2014-15US$ millions | FY2015-16US$ millions | FY2016-17US$ millions | FY2017-18US$ millions | FY2018-19US$ millions | FY2019-20US$ millions | FY2020-21US$ millions | |
|---|---|---|---|---|---|---|---|---|
| New commitments | 50.0 | Not reported | Not reported | Not reported | Not reported | Not reported | Not reported | Not reported |
| Disbursements | 7.2 | 4.2 | 8.3 | 2.0 | 5.0 | 1.7 | 2.9 | 5.6 |
| Cumulative disbursements | 7.2 | 11.5 | 19.8 | 21.8 | 26.8 | 28.5 | 31.4 | 37.0 |
Records and documents
Transactions39 records, November 20, 2013 to April 30, 2021
Table 4.Transactions, US$ millions
| Date | Measure | AmountUS$ millions | Source | Method |
|---|---|---|---|---|
| November 20, 2013 | Commitment | 50.0 | IDB projects dataset | commitment at approval date |
| July 31, 2014 | Disbursements | 1.0 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| August 31, 2014 | Disbursements | 0.6 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| September 30, 2014 | Disbursements | 5.7 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| October 31, 2014 | Disbursements | 0.8 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| March 31, 2015 | Disbursements | 3.0 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| June 30, 2015 | Disbursements | 0.4 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| November 30, 2015 | Disbursements | 2.5 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| December 31, 2015 | Disbursements | 0.3 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| January 31, 2016 | Disbursements | 0.9 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| February 29, 2016 | Disbursements | 3.0 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| June 30, 2016 | Disbursements | 0.8 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| August 31, 2016 | Disbursements | 0.5 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| September 30, 2016 | Disbursements | 0.3 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| November 30, 2016 | Disbursements | 0.7 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| December 31, 2016 | Disbursements | <0.1 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| April 30, 2017 | Disbursements | 1.0 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| June 30, 2017 | Disbursements | 0.2 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| July 31, 2017 | Disbursements | 0.1 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| November 30, 2017 | Disbursements | 0.1 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| December 31, 2017 | Disbursements | 0.6 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| January 31, 2018 | Disbursements | 0.1 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| February 28, 2018 | Disbursements | 0.9 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| April 30, 2018 | Disbursements | 0.2 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| May 31, 2018 | Disbursements | 0.9 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| June 30, 2018 | Disbursements | 1.1 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| July 31, 2018 | Disbursements | 1.0 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| October 31, 2018 | Disbursements | 0.2 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| November 30, 2018 | Disbursements | 0.3 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| December 31, 2018 | Disbursements | 0.7 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| July 31, 2019 | Disbursements | 0.5 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| November 30, 2019 | Disbursements | 0.5 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| December 31, 2019 | Disbursements | 1.9 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| February 29, 2020 | Disbursements | 0.5 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| March 31, 2020 | Disbursements | <0.1 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| April 30, 2020 | Disbursements | <0.1 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| May 31, 2020 | Disbursements | 0.1 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| December 31, 2020 | Disbursements | 3.5 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| April 30, 2021 | Disbursements | 2.1 | IATI | IATI disbursement (transaction type 3), paid to another organization |
Terms5 of 6 reported
- Finance type
- 110 Standard grant
- Flow type
- 20 Other official flows, excluding export credits
- Aid type
- C01 Project-type interventions
- Tied status
- 5 Untied
- Collaboration type
- 4 Multilateral outflows
- Humanitarian
- Not reported
Locations1 place named
| Departments | Not reported |
| Places named by the source | Haiti, 27 RUE TOUSSAINT LOUVERTURE, DELMAS 33, DELMAS |
| Places with coordinates | 0 |
Results indicators11 indicators
| Indicator | Baseline | Target | Latest value | Date of latest value |
|---|---|---|---|---|
| Kilometres de routes entretenues | Not reported | 23.00 | 0.00 | December 31, 2018 |
| Kilometres finis de routes rehabilitatees | Not reported | 1.00 | 0.00 | December 31, 2017 |
| Ligne de base de donnees d'accidents pour la RN1 | Not reported | 1.00 | 0.00 | December 31, 2017 |
| Nombre d'ateliers et campagnes avec des leaders des communautes | Not reported | 1.00 | 2.00 | December 31, 2017 |
| Nombre d'equipements acquis pour les DD | Not reported | 3.00 | 0.00 | December 31, 2015 |
| Nombre d'etudes d'ingenierie et plans realisees | Not reported | 1.00 | 1.00 | December 31, 2015 |
| Nombre de femmes formees en travaux d'infrastructures | Not reported | 100.00 | 0.00 | December 31, 2014 |
| Nombre de kilometres de routes pavees | Not reported | 2.00 | 0.00 | December 31, 2017 |
| Nombre de personnes atteintes par le programme VIH | Not reported | 30000.00 | 1750.00 | December 31, 2015 |
| Nombre de rapports d'avancement de la supervision des travaux | Not reported | 2.00 | 12.00 | December 31, 2018 |
| Nombre de villes avec projet de controle de poussiere realise | Not reported | 5.00 | 0.00 | December 31, 2017 |
Funds passed on58 transactions
| Receiver | Transaction | Date | US$ millions |
|---|---|---|---|
| Techniplan S.R.L. | Disbursement | April 30, 2021 | 0.1 |
| Wenling Hongyuan Traffic Engineering | Disbursement | April 30, 2021 | 1.9 |
| CECOM Consultants S.A. | Disbursement | April 30, 2021 | <0.1 |
| Ministere de Travaux Publics Transports | Disbursement | December 31, 2020 | 3.5 |
| Techniplan S.R.L. | Disbursement | December 31, 2020 | <0.1 |
| Techniplan | Disbursement | May 31, 2020 | 0.1 |
| Techniplan | Disbursement | April 30, 2020 | <0.1 |
| Techniplan | Disbursement | March 31, 2020 | <0.1 |
| Name not shown | Disbursement | February 29, 2020 | 0.5 |
| Techniplan | Disbursement | December 31, 2019 | <0.1 |
| Fasgel S.A. | Disbursement | December 31, 2019 | 0.1 |
| Fasgel S.A. | Disbursement | December 31, 2019 | 0.1 |
| Techniplan | Disbursement | December 31, 2019 | <0.1 |
| Name not shown | Disbursement | December 31, 2019 | 0.6 |
| CECOM Consultants S.A. | Disbursement | December 31, 2019 | <0.1 |
| MTPTC Prog. Appui au Secteur Transports | Disbursement | December 31, 2019 | 1.1 |
| Fasgel S.A. | Disbursement | November 30, 2019 | 0.4 |
| CECOM Consultants S.A. | Disbursement | November 30, 2019 | 0.1 |
| Techniplan | Disbursement | November 30, 2019 | <0.1 |
| Name not shown | Disbursement | July 31, 2019 | 0.5 |
| Wenling Hongyuan Traffic Engineering | Disbursement | December 31, 2018 | 0.7 |
| Fasgel S.A | Disbursement | November 30, 2018 | 0.3 |
| Wenling Hongyuan Traffic Engineering | Disbursement | October 31, 2018 | 0.2 |
| Fasgel S.A | Disbursement | July 31, 2018 | 0.1 |
| Wenling Hongyuan Traffic Engineering | Disbursement | July 31, 2018 | 0.9 |
| MTPTC Prog. Appui au Secteur Transports | Disbursement | June 30, 2018 | 1.0 |
| Fasgel S.A. | Disbursement | June 30, 2018 | 0.1 |
| Fasgel S.A | Disbursement | May 31, 2018 | 0.2 |
| Wenling Hongyuan Traffic Engineering | Disbursement | May 31, 2018 | 0.8 |
| Name not shown | Disbursement | April 30, 2018 | <0.1 |
| Fasgel S.A | Disbursement | April 30, 2018 | 0.2 |
| Wenling Hongyuan Traffic Engineering | Disbursement | February 28, 2018 | 0.6 |
| Wenling Hongyuan Traffic Engineering | Disbursement | February 28, 2018 | 0.3 |
| Insuco Intl Limited | Disbursement | January 31, 2018 | 0.1 |
| Insuco Intl Limited | Disbursement | December 31, 2017 | 0.1 |
| MTPTC Prog. Appui au Secteur Transports | Disbursement | December 31, 2017 | 0.5 |
| Fasgel S.A. | Disbursement | November 30, 2017 | <0.1 |
| Fasgel S.A. | Disbursement | November 30, 2017 | 0.1 |
| Fasgel S.A. | Disbursement | July 31, 2017 | 0.1 |
| Fasgel S.A | Disbursement | June 30, 2017 | 0.2 |
| MTPTC Prog. Appui au Secteur Transports | Disbursement | April 30, 2017 | 1.0 |
| Fasgel S.A. | Disbursement | December 31, 2016 | <0.1 |
| Fasgel S.A. | Disbursement | November 30, 2016 | 0.1 |
| Fasgel S.A. | Disbursement | November 30, 2016 | 0.1 |
| Wenling Hongyuan Traffic Engineering | Disbursement | November 30, 2016 | 0.5 |
| Wenling Hongyuan Traffic Engineering | Disbursement | September 30, 2016 | 0.3 |
| Wenling Hongyuan Traffic Engineering | Disbursement | August 31, 2016 | 0.5 |
| Wenling Hongyuan Traffic Engineering | Disbursement | June 30, 2016 | 0.8 |
| MTPTC Prog. Appui au Secteur Transports | Disbursement | February 29, 2016 | 3.0 |
| Wenling Hongyuan Traffic Engineering | Disbursement | January 31, 2016 | 0.9 |
| WSP Canada Inc | Disbursement | December 31, 2015 | 0.3 |
| MTPTC Prog. Appui au Secteur Transports | Disbursement | November 30, 2015 | 2.5 |
| Wenling Hongyuan Traffic Engineering | Disbursement | June 30, 2015 | 0.4 |
| MTPTC Prog. Appui au Secteur Transports | Disbursement | March 31, 2015 | 3.0 |
| UNOPS | Disbursement | October 31, 2014 | 0.8 |
| Wenling Hongyuan Traffic Engineering | Disbursement | September 30, 2014 | 5.7 |
| MTPTC | Disbursement | August 31, 2014 | 0.6 |
| MTPTC Prog. Appui au Secteur Transports | Disbursement | July 31, 2014 | 1.0 |
Identifiers3 identifiers
| System | Identifier | Source |
|---|---|---|
| IATI identifier | XI-IATI-IADB-HA-L1079 | IATI |
| IDB operation | HA-L1079 | Operation record |
| Public investment program line | 1114-1-12-53-57 | Public investment program |
Partner documents39 documents
- Analysis of Construction Costs in Haiti 38020282.PPT, iadb.org
- Economic Feasibility Study 38015729.DOCX, iadb.org
- Engineering Designs 38022825.PDF, iadb.org
- Enlace electronico Opcional 8Evaluacion de impacto acumulativo HA-L1076 36838525.PDF, iadb.org
- Environmental and Social Analysis 37955457.DOCX, iadb.org
- Institutional Strengthening Plan for the MTPTC 38020293.DOCX, iadb.org
- Monitoring Evaluation Arrangements 37950826.DOCX, iadb.org
- Plan of Activities POA 38020064.XLSX, iadb.org
- Procurement Plan 38020079.XLSX, iadb.org
- Proposal for a nonreimbursable financing for the project Support for HaitisTransportation Sector III 38234402.PDF, iadb.org
- Report Workshop Institutional Strengthening Informe de Relatora Workshop Institutional Strengthening Road Sect 38020313.DOCX, iadb.org
- Road Safety Audit in Haiti 38020225.DOC, iadb.org
- Propuesta de financiamiento no reembolsable para el proyecto Apoyo al SectorTransporte de Hait-III 38234445.PDF, iadb.org
- Mapa Haiti tramo Ennery Plaisance 38005592.docx, iadb.org
- Raport d action de Reinstalation ENNERY-PLAISANCE 38236693.PDF, iadb.org
- Safeguards Policy Filter and thSafeguards Policy Filter and the Safeguard Screening Form for Classification of 38019387.DOCX, iadb.org
- IDB-PCR-Production-Timeline.pdf, iadb.org
- PCR aprobado - HA-L1079 - Support for Haitis Transportation Sector III - Informe de Terminacion de Proyecto PCR.msg, iadb.org
- PCRHA-L1079CI-TSP-sep23.pdf, iadb.org
- PCRHA-L1079FRA-Final.pdf, iadb.org
- HA-L1079 First period Jan-Jun 2014-Public Report 40181532.PDF, iadb.org
- HA-L1079 First period Jan-Jun 2015-Public Report 40194399.PDF, iadb.org
- HA-L1079 First period Jan-Jun 2016-Public Report 40799068.PDF, iadb.org
- HA-L1079 First period Jan-Jun 2017-Public Report.pdf, iadb.org
- HA-L1079 First period Jan-Jun 2018-Public Report.pdf, iadb.org
- HA-L1079 First period Jan-Jun 2019-Public Report.pdf, iadb.org
- HA-L1079 First period Jan-Jun 2020 - Public Report.pdf, iadb.org
- HA-L1079 First period Jan-Jun 2021 - Public Report.pdf, iadb.org
- HA-L1079 First period Jan-Jun 2022 - Public Report.PDF, iadb.org
- HA-L1079 Second period Jan-Dec 2013-Public Report 40172111.PDF, iadb.org
- HA-L1079 Second period Jan-Dec 2014-Public Report 40185530.PDF, iadb.org
- HA-L1079 Second period Jan-Dec 2015-Public Report 40377342.PDF, iadb.org
- HA-L1079 Second period Jan-Dec 2016-Public Report.pdf, iadb.org
- HA-L1079 Second period Jan-Dec 2017-Public Report.pdf, iadb.org
- HA-L1079 Second period Jan-Dec 2018-Public Report.pdf, iadb.org
- HA-L1079 Second period Jan-Dec 2019-Public Report.pdf, iadb.org
- HA-L1079 Second period Jan-Dec 2020 - Public Report.pdf, iadb.org
- HA-L1079 Second period Jan-Dec 2021 - Public Report.PDF, iadb.org
- HA-L1079 Second period Jan-Dec 2022 - Public Report.PDF, iadb.org
Procurement notices (5)
- IDB_Procurement_Notices.xlsx, iadb.org
- HA-L1079 1250.pdf, iadb.org
- HA-L1079 2085.pdf, iadb.org
- HA-L1079P543703SP.pdf, iadb.org
- IDB_Project_Procurement_Contract_Awards_Data.xlsx, iadb.org
Sources
- IATI record (d-portal): terms of use set by the publisher
- IATI: terms of use set by the publisher
- IDB project page: terms of use set by the publisher
- Transactions: terms of use set by the publisher
- Operation record: terms of use set by the publisher
- Public investment program: terms of use set by the publisher
Data as of October 18, 2026
| Source | Read on |
|---|---|
| IATI | October 18, 2026 |
| IATI | October 18, 2026 |
| IDB projects dataset | October 18, 2026 |
| Public investment program | October 18, 2026 |
Cite this page
HaitiDocs. Support for Haiti's Transportation Sector III. Partner portfolio, data as of October 18, 2026. https://www.haitidocs.org/portfolio/projects/IDB%3AHA-L1079