Operations of funding partners in Haiti, as each partner reports them. Data as of October 18, 2026.
| Stock at October 18, 2026, US$ millions | Flow, US$ millions | |||||||||
|---|---|---|---|---|---|---|---|---|---|---|
| Stock at October 18, 2026, US$ millions | ||||||||||
| Operation | Stage | Sector | Departments | Approval or start | Closing | Approved (net commitment, US$ at the data date) definition | Disbursed to date definition | Undisbursed definition | Disbursed in FY2026-27 definition | |
| Total, funding partners (767 operations) | 3,625.4sum of those reporting, 764 of 767 | 2,150.0sum of those reporting, 95 of 767 | Not reported | Not reported | ||||||
| Expansion of safety nets for vulnerable populations affected by Coronavirus | Closed | Social protection | Not reported | Jun 2021 | Aug 2024 | 70.0 | 70.0 | Not reported | None to date | |
| Program for Rehabilitation of Basic Economic Infrastructure | Closed | Finance and private sector | Not reported | Nov 2003 | Not reported | 70.0 | Not reported | Not reported | Not reported | |
| Support for Haiti's Transport Sector V | Closed | Transport | Not reported | Oct 2015 | Feb 2022 | 65.0 | 52.5 | Not reported | None to date | |
| Local Development Program | Closed | Social protection | Not reported | Nov 2003 | Not reported | 65.0 | Not reported | Not reported | Not reported | |
| Urban Rehabilitation Program | Closed | Social protection | Not reported | Jul 2005 | Dec 2019 | 62.6 | 12.4 | Not reported | None to date | |
| Safety Nets for Vulnerable People Affected by Coronavirus | Closed | Social protection | Not reported | Jul 2020 | Aug 2022 | 60.0 | 60.0 | Not reported | None to date | |
| Support for Transport Sector | Closed | Transport | Not reported | Dec 2011 | Nov 2019 | 55.0 | 55.3 | Not reported | None to date | |
| Infrastructure Program | Closed | Transport | Not reported | Jul 2011 | Aug 2017 | 55.0 | 55.7 | Not reported | None to date | |
| Productive Infrastructure Program III | Closed | Social protection | Not reported | Dec 2014 | Sep 2019 | 55.0 | 78.8 | Not reported | None to date | |
| Agricultural and Agroforestry Technological Innovation Program - PITAG | Closed | Agriculture and food security | Not reported | Nov 2017 | Jun 2025 | 55.0 | 54.4 | Not reported | None to date | |
| Drinking Water and Sanitation Sector Reform | Closed | Water and sanitation | Not reported | Aug 1998 | Not reported | 54.0 | Not reported | Not reported | Not reported | |
| Support for Transport Sector II | Closed | Transport | Not reported | Oct 2012 | Jul 2020 | 53.0 | 55.7 | Not reported | None to date | |
| Drainage Port-Au-Prince II | Closed | Water and sanitation | Not reported | Nov 1986 | Not reported | 51.8 | Not reported | Not reported | Not reported | |
| Fiscal Sustainability II | Closed | Governance and security | Not reported | Apr 2010 | Jul 2010 | 50.0 | 50.0 | Not reported | None to date | |
| Support for Haiti's Reconfiguration of the Education Sector | Closed | Education | Not reported | Nov 2010 | Aug 2019 | 50.0 | 81.6 | Not reported | None to date | |
| Support to the Implementation of the Education Plan and Reform | Closed | Education | Not reported | Nov 2011 | Jan 2020 | 50.0 | 68.5 | Not reported | None to date | |
| Productive Infrastructure Program | Closed | Social protection | Not reported | Sep 2012 | Dec 2020 | 50.0 | 50.6 | Not reported | None to date | |
| Increasing Access to Quality Education | Closed | Education | Not reported | Nov 2012 | Feb 2023 | 50.0 | 79.3 | Not reported | None to date | |
| Support for Haiti's Transportation Sector III | Closed | Transport | Not reported | Nov 2013 | Mar 2023 | 50.0 | 37.0 | Not reported | None to date | |
| Support for Transport Sector IV | Closed | Transport | Not reported | Jun 2014 | Feb 2023 | 50.0 | 50.3 | Not reported | None to date | |
| Investment Sector Loan | Closed | Governance and security | Not reported | Dec 1996 | Not reported | 50.0 | Not reported | Not reported | Not reported | |
| Emergency & Economic Recovery Program II | Closed | Social protection | Not reported | Nov 1995 | Not reported | 50.0 | Not reported | Not reported | Not reported | |
| Rural and Secondary Roads | Closed | Transport | Not reported | Mar 1997 | Not reported | 50.0 | Not reported | Not reported | Not reported | |
| Transport Infrastructure Rehabilitation Program | Closed | Transport | Not reported | Jun 2005 | Mar 2013 | 50.0 | 76.9 | Not reported | None to date | |
| Pont-Sonde-Mirebalais Highways and Access Roads | Closed | Transport | Not reported | Feb 1990 | Not reported | 48.5 | Not reported | Not reported | Not reported | |
| Road Maintenance & Rehab. National Program | Closed | Transport | Not reported | Feb 1995 | Not reported | 45.0 | Not reported | Not reported | Not reported | |
| Agricultural Intensification | Closed | Agriculture and food security | Not reported | Nov 2003 | Not reported | 41.9 | Not reported | Not reported | Not reported | |
| Productive Infrastructure Program II | Closed | Social protection | Not reported | Dec 2013 | Oct 2018 | 40.5 | 39.6 | Not reported | None to date | |
| Temporary Social Safety Net and Skills for Youth | Closed | Social protection | Not reported | Nov 2018 | Jun 2024 | 40.0 | 40.8 | Not reported | None to date | |
| Emergency and Economic Recuperation Program (EERP) | Closed | Social protection | Not reported | Jan 1995 | Not reported | 40.0 | Not reported | Not reported | Not reported | |
| Sewer System Port-Au-Prince | Closed | Water and sanitation | Not reported | Dec 1978 | Not reported | 38.8 | Not reported | Not reported | Not reported | |
| Sustainable Coastal Tourism Program | Closed | Industry, trade and tourism | Not reported | Dec 2014 | Apr 2024 | 36.0 | 36.2 | Not reported | None to date | |
| Port-au-Prince Water and Sanitation Project II | Closed | Water and sanitation | Not reported | Jun 2013 | Feb 2022 | 35.5 | 36.6 | Not reported | None to date | |
| Institutional Transformation and Modernization Program of the Energy Sector I | Closed | Energy | Not reported | Jul 2011 | Aug 2011 | 35.0 | 35.0 | Not reported | None to date | |
| Port Au Prince Water and Sanitation Project | Closed | Water and sanitation | Not reported | Jul 2010 | Not reported | 35.0 | Not reported | Not reported | Not reported | |
| Natural Disaster Mitigation Program in Priority Watersheds I | Closed | Environment and disaster risk | Not reported | Sep 2009 | Dec 2016 | 30.0 | 29.7 | Not reported | None to date | |
| Support to the Shelter Sector Response Plan | Closed | Social protection | Not reported | Apr 2010 | Jul 2020 | 30.0 | 29.9 | Not reported | None to date | |
| Program to Support Transportation Sector Development | Closed | Transport | Not reported | Jul 2010 | Feb 2013 | 29.0 | 29.0 | Not reported | None to date | |
| Emergency and Economic Recuperation Program (EERP) | Closed | Sector not identified | Not reported | Jan 1995 | Not reported | 28.5 | Not reported | Not reported | Not reported | |
| Ennery-Quinte Agricultural Intensification Project | Closed | Agriculture and food security | Not reported | Jul 2005 | Nov 2014 | 27.1 | 27.0 | Not reported | None to date | |
| Land tenure security program in rural areas | Closed | Agriculture and food security | Not reported | Apr 2012 | Apr 2019 | 27.0 | 27.6 | Not reported | None to date | |
| Institutional Strengthening and Reform of the Transport Sector II | Closed | Transport | Not reported | May 2015 | Sep 2015 | 27.0 | 27.0 | Not reported | None to date | |
| Social Investment Help Fund | Closed | Social protection | Not reported | Nov 1996 | Not reported | 27.0 | Not reported | Not reported | Not reported | |
| Technology Transfer to Small Farmers Program | Closed | Agriculture and food security | Not reported | Aug 2011 | Not reported | 25.0 | Not reported | Not reported | Not reported | |
| Fiscal Reform and Governance | Closed | Governance and security | Not reported | Jul 2005 | Apr 2008 | 25.0 | 25.0 | Not reported | None to date | |
| Financial Sector Reform Support Program | Closed | Governance and security | Not reported | Dec 2006 | Sep 2012 | 25.0 | 24.5 | Not reported | None to date | |
| Rehabilitation of Road Infrastructure for Integration of the Territory | Closed | Transport | Not reported | Nov 2007 | Mar 2017 | 25.0 | 100.0 | Not reported | None to date | |
| Fiscal Sustainability I | Closed | Governance and security | Not reported | Aug 2009 | Nov 2009 | 25.0 | 25.0 | Not reported | None to date | |
| Water Management Program in the Artibonite Basin | Closed | Agriculture and food security | Not reported | Nov 2013 | Feb 2021 | 25.0 | 24.8 | Not reported | None to date | |
| Southern Roads Construction Leogane Cayes | Closed | Transport | Not reported | Oct 1975 | Not reported | 25.0 | Not reported | Not reported | Not reported | |
Page 1 of 16 Next
Sources
- IATI: terms of use set by the publisher
- IDB projects dataset: terms of use set by the publisher
Data as of October 18, 2026. Sources and methodology
Cite this page
HaitiDocs. Operations. Partner portfolio, data as of October 18, 2026. https://www.haitidocs.org/portfolio/projects?partner=idb-group&stage=closed