Productive Infrastructure Program II

US$ millions unless stated. Haitian fiscal year, October to September. FY2026-27 began October 1, 2026.

Objective

The program will contribute to the socioeconomic development of Northern Haiti by creating conditions for the establishment of manufacturing firms in the Caracol Industrial Park (Parc Industriel de Caracol PIC) and thus generating employment opportunities for the Haitian population.

As published by IDB projects dataset, in its original language.

Partner
IDB Group, IDB
Sector
Social protection
Stage
Closed since October 31, 2018
Approval
December 16, 2013
Closing
October 31, 2018
Instrument
Grant, Sovereign Guaranteed
Effectiveness
Not reported
Last transaction
November 30, 2018
Operation ID
HA-L1081
Life cycle4 stages, 8 dates

Stage history

StageFrom
ApprovedDecember 16, 2013
Under wayFebruary 18, 2014
ClosingOctober 31, 2018
ClosedOctober 31, 2018

Dated events

EventDateSource
ApprovalDecember 16, 2013IDB projects dataset
First commitmentDecember 16, 2013Transactions
SigningFebruary 18, 2014IDB projects dataset
Planned startMay 20, 2014IATI
Actual startJune 16, 2014IATI
First disbursementJune 30, 2014Transactions
Closing dateOctober 31, 2018IATI
Last disbursementNovember 30, 2018Transactions

Financing

Table 1.Financing, US$ millions

FinancierAmountUS$ millionsRoleSource
IDB40.5InstitutionIDB projects dataset

Table 2.Position at the data date by source (stocks), US$ millions

This pageUS$ millionsSourceIATIUS$ millions
Commitment40.5IDB projects dataset40.5
Disbursed39.6IATI39.6
UndisbursedNot reported
Total cost40.5IDB projects dataset

Each amount is given as the source publishes it, converted to US$. IATI column: the commitments and disbursements the partner reports to IATI, converted to US$. Amounts by source

This page uses IDB projects dataset for the commitment and IATI for disbursements.

Changes to the operationnot reported
Original closing date
Not reported
Closing date extensions
Not reported
Restructurings
Not reported
Emergency component
Not reported

New commitments and disbursements by fiscal year

Disbursements, US$ millions
FY2013-14, US$9.2 million913-14FY2014-15, US$25.2 million2514-15FY2015-16, US$1.5 million215-16FY2016-17, US$1.5 million216-17FY2017-18, US$1.7 million217-18FY2018-19, US$0.5 million0.518-19FY2013-14, US$9.2 million913-14FY2014-15, US$25.2 million2514-15FY2015-16, US$1.5 million215-16FY2016-17, US$1.5 million216-17FY2017-18, US$1.7 million217-18FY2018-19, US$0.5 million0.518-19

Table 3.New commitments and disbursements by fiscal year (flows), US$ millions

FY2013-14US$ millionsFY2014-15US$ millionsFY2015-16US$ millionsFY2016-17US$ millionsFY2017-18US$ millionsFY2018-19US$ millions
New commitments40.5Not reportedNot reportedNot reportedNot reportedNot reported
Disbursements9.225.21.51.51.70.5
Cumulative disbursements9.234.435.937.439.139.6

Records and documents

Transactions14 records, December 16, 2013 to November 30, 2018

Table 4.Transactions, US$ millions

DateMeasureAmountUS$ millionsSourceMethod
December 16, 2013Commitment40.5IDB projects datasetcommitment at approval date
June 30, 2014Disbursements7.2IATIIATI disbursement (transaction type 3), paid to another organization
July 31, 2014Disbursements2.0IATIIATI disbursement (transaction type 3), paid to another organization
December 31, 2014Disbursements10.0IATIIATI disbursement (transaction type 3), paid to another organization
February 28, 2015Disbursements0.9IATIIATI disbursement (transaction type 3), paid to another organization
April 30, 2015Disbursements2.0IATIIATI disbursement (transaction type 3), paid to another organization
June 30, 2015Disbursements3.2IATIIATI disbursement (transaction type 3), paid to another organization
July 31, 2015Disbursements4.1IATIIATI disbursement (transaction type 3), paid to another organization
August 31, 2015Disbursements2.4IATIIATI disbursement (transaction type 3), paid to another organization
September 30, 2015Disbursements2.7IATIIATI disbursement (transaction type 3), paid to another organization
April 30, 2016Disbursements1.5IATIIATI disbursement (transaction type 3), paid to another organization
October 31, 2016Disbursements1.5IATIIATI disbursement (transaction type 3), paid to another organization
December 31, 2017Disbursements1.7IATIIATI disbursement (transaction type 3), paid to another organization
November 30, 2018Disbursements0.5IATIIATI disbursement (transaction type 3), paid to another organization
Terms5 of 6 reported
Finance type
110 Standard grant
Flow type
20 Other official flows, excluding export credits
Aid type
C01 Project-type interventions
Tied status
5 Untied
Collaboration type
4 Multilateral outflows
Humanitarian
Not reported
Results indicators82 indicators
IndicatorBaselineTargetLatest valueDate of latest value
Access road built (10m wide)Not reported260.00184.00December 31, 2016
Annex buildings (200 s.q.m) builtNot reported2.001.00December 31, 2016
Bicycle lane from PIC to Caracol builtNot reported1.000.00December 31, 2016
Bicycles using the bicycle lane per dayNot reported250.000.00December 31, 2016
Biodiversity Baseline study completedNot reported1.000.00December 31, 2014
Bus depot for PIC builtNot reported1.000.00December 31, 2016
Caracol bay preservation projects for site protection, fishermen, and another livelihood type are implementedNot reported1.000.00December 31, 2016
Cumulative Impact Assessment study completedNot reported1.000.00December 31, 2014
Domestic waste water treatment plant constructedNot reported1.000.00December 31, 2014
Environmental, health and safety system implementedNot reported1.000.00December 31, 2016
Firms operating at the PICNot reported7.006.00December 31, 2016
Garbage from PIC and four surrounding cities is landfilled or recycled in Solid Waste FacilityNot reported50.000.00December 31, 2016
Gender Plan ImplementedNot reported1.000.00December 31, 2016
General use buildings built (dormitories, canteens, and sanitary facilities)Not reported4.002.00December 31, 2016
Haitian women employed by firms operating in the PICNot reported8930.007667.00December 31, 2018
Hydrology, aquifer capacity and flood risk assessment studies completedNot reported1.001.00December 31, 2014
Industrial Warehouses (11,700 and 5,000 s.q.m) builtNot reported6.002.00December 31, 2016
Interior roads built (8m wide)Not reported2315.002391.00December 31, 2016
Jobs filled by Haitians employed by firms operating in the PICNot reported13750.0012569.00December 31, 2018
Minor transportation infrastructure works completed (Container Yard)Not reported1.000.00December 31, 2015
Multipurpose community infrastructure builtNot reported1.000.00December 31, 2014
PIC monitoring and evaluation system implementedNot reported1.000.00December 31, 2014
Passengers utilizing the transfer station/depotNot reported9550.000.00December 31, 2018
Priority urban development projects in the eight municipalities surrounding the PIC finishedNot reported6.000.00December 31, 2014
Rental payments by international PIC tenant firmsNot reported4200000.00978816.40December 31, 2016
SONAPI staff trained in management of the PICNot reported10.000.00December 31, 2016
Services (transportation, water, sanitation) payments by international PIC tenants firmsNot reported490000.00890658.56December 31, 2016
Social security payments made by PIC firms for Haitian workersNot reported890000.00834618.15December 31, 2015
Solid Waste Management Facility constructedNot reported1.000.00December 31, 2014
Technical assistance and office and IT equipment delivered to eight MunicipalitiesNot reported6.000.00December 31, 2014
Three bays National Park management unit establishedNot reported1.000.00December 31, 2016
Total salaries paid to Haitian workers in PICNot reported19525000.029457379.0December 31, 2018
Total taxes paid by PIC tenants for goods coming in/out of HaitiNot reported10000.000.00December 31, 2016
Urban streets pavedNot reported500.000.00December 31, 2016
Urban transportation study completedNot reported1.001.00December 31, 2014
Wastewater collection network expanded, with 300mm-a 42" diameter pipesNot reported2178.002860.00December 31, 2014
Water distribution networks expanded with 50mm a 150 mm-diameter pipes installedNot reported3598.002860.00December 31, 2014
Women and children who obtain social services provided by the community centerNot reported9000.000.00December 31, 2016
Women using lactation rooms in PICNot reported1900.000.00December 31, 2018
Workshops conducted to train SONAPI staff in management of the PICNot reported2.000.00December 31, 2016
Access road built (10m wide)Not reported260.00184.00December 31, 2016
Annex buildings (200 s.q.m) builtNot reported2.001.00December 31, 2016
Batiments construits du PICNot reported1.001.00December 31, 2013
Bicycle lane from PIC to Caracol builtNot reported1.000.00December 31, 2016
Bicycles using the bicycle lane per dayNot reported250.000.00December 31, 2016
Biodiversity Baseline study completedNot reported1.000.00December 31, 2014
Bus depot for PIC builtNot reported1.000.00December 31, 2016
Caracol bay preservation projects for site protection, fishermen, and another livelihood type are implementedNot reported1.000.00December 31, 2016
Compensation de desplace pour el Parc IndustrielleNot reported300.00411.00December 31, 2013
Cumulative Impact Assessment study completedNot reported1.000.00December 31, 2014
Domestic waste water treatment plant constructedNot reported1.000.00December 31, 2014
Environmental, health and safety system implementedNot reported1.000.00December 31, 2016
Firms operating at the PICNot reported7.006.00December 31, 2016
Garbage from PIC and four surrounding cities is landfilled or recycled in Solid Waste FacilityNot reported50.000.00December 31, 2016
Gender Plan ImplementedNot reported1.000.00December 31, 2016
General use buildings built (dormitories, canteens, and sanitary facilities)Not reported4.002.00December 31, 2016
Haitian women employed by firms operating in the PICNot reported8930.007667.00December 31, 2018
Hydrology, aquifer capacity and flood risk assessment studies completedNot reported1.001.00December 31, 2014
Industrial Warehouses (11,700 and 5,000 s.q.m) builtNot reported6.002.00December 31, 2016
Interior roads built (8m wide)Not reported2315.002391.00December 31, 2016
Jobs filled by Haitians employed by firms operating in the PICNot reported13750.0012569.00December 31, 2018
Minor transportation infrastructure works completed (Container Yard)Not reported1.000.00December 31, 2015
Multipurpose community infrastructure builtNot reported1.000.00December 31, 2014
PIC monitoring and evaluation system implementedNot reported1.000.00December 31, 2014
Passengers utilizing the transfer station/depotNot reported9550.000.00December 31, 2018
Priority urban development projects in the eight municipalities surrounding the PIC finishedNot reported6.000.00December 31, 2014
Rental payments by international PIC tenant firmsNot reported4200000.00978816.40December 31, 2016
SONAPI staff trained in management of the PICNot reported10.000.00December 31, 2016
Services (transportation, water, sanitation) payments by international PIC tenants firmsNot reported490000.00890658.56December 31, 2016
Social security payments made by PIC firms for Haitian workersNot reported890000.00834618.15December 31, 2015
Solid Waste Management Facility constructedNot reported1.000.00December 31, 2014
Technical assistance and office and IT equipment delivered to eight MunicipalitiesNot reported6.000.00December 31, 2014
Three bays National Park management unit establishedNot reported1.000.00December 31, 2016
Total salaries paid to Haitian workers in PICNot reported19525000.029457379.0December 31, 2018
Total taxes paid by PIC tenants for goods coming in/out of HaitiNot reported10000.000.00December 31, 2016
Urban streets pavedNot reported500.000.00December 31, 2016
Urban transportation study completedNot reported1.001.00December 31, 2014
Wastewater collection network expanded, with 300mm-a 42" diameter pipesNot reported2178.002860.00December 31, 2014
Water distribution networks expanded with 50mm a 150 mm-diameter pipes installedNot reported3598.002860.00December 31, 2014
Women and children who obtain social services provided by the community centerNot reported9000.000.00December 31, 2016
Women using lactation rooms in PICNot reported1900.000.00December 31, 2018
Workshops conducted to train SONAPI staff in management of the PICNot reported2.000.00December 31, 2016
Funds passed on22 transactions
ReceiverTransactionDateUS$ millions
Utemefprojet 3132GR-HA. ProgrammeDisbursementNovember 30, 20180.5
Ingenieria Estrella S.ADisbursementDecember 31, 20170.8
Ingenieria Estrella S.ADisbursementDecember 31, 20170.9
Utemefprojet 3132GR-HA. ProgrammeDisbursementOctober 31, 20161.5
Ingenieria Estrella S.ADisbursementApril 30, 20161.5
Ingenieria Estrella S.ADisbursementSeptember 30, 20152.7
Ingenieria Estrella S.ADisbursementAugust 31, 20152.4
Utemefprojet 3132GR-HA. ProgrammeDisbursementJuly 31, 20152.0
Ingenieria Estrella S.A.DisbursementJuly 31, 20152.1
Ingenieria Estrella S.A.DisbursementJune 30, 20150.8
Ingenieria Estrella S.A.DisbursementJune 30, 20151.3
Ingenieria Estrella S.ADisbursementJune 30, 20151.1
Ingenieria Estrella S.A.DisbursementApril 30, 20152.0
Ingenieria Estrella S.A.DisbursementFebruary 28, 20150.9
Ingenieria Estrella S.A.DisbursementDecember 31, 20141.3
Ingenieria Estrella S.A.DisbursementDecember 31, 20140.6
Ingenieria Estrella S.A.DisbursementDecember 31, 20141.1
Ingenieria Estrella S.A.DisbursementDecember 31, 20142.3
Ingenieria Estrella S.A.DisbursementDecember 31, 20141.1
Ingenieria Estrella S.A.DisbursementDecember 31, 20143.5
Utemefprojet 3132GR-HA. ProgrammeDisbursementJuly 31, 20142.0
Ingenieria Estrella S.ADisbursementJune 30, 20147.2
Identifiers2 identifiers
SystemIdentifierSource
IATI identifierXI-IATI-IADB-HA-L1081IATI
IDB operationHA-L1081Operation record
Partner documents30 documents
Procurement notices (3)

Sources

Data as of October 18, 2026
SourceRead on
IATIOctober 18, 2026
IATIOctober 18, 2026
IDB projects datasetOctober 18, 2026
Cite this page

HaitiDocs. Productive Infrastructure Program II. Partner portfolio, data as of October 18, 2026. https://www.haitidocs.org/portfolio/projects/IDB%3AHA-L1081