Water Management Program in the Artibonite Basin
US$ millions unless stated. Haitian fiscal year, October to September. FY2026-27 began October 1, 2026.
Objective
(1) Increase agricultural production in a sustainable and climate change resilient way (2) Decrease losses due to natural desasters in the Artibonite watershed
As published by IDB projects dataset, in its original language.
- Stage
- Closed since February 4, 2021
- Approval
- November 27, 2013
- Closing
- February 4, 2021
- Instrument
- Grant, Sovereign Guaranteed
- Effectiveness
- Not reported
- Last transaction
- July 31, 2021
- Operation ID
- HA-L1087
Life cycle4 stages, 8 dates
Stage history
| Stage | From |
|---|---|
| Approved | November 27, 2013 |
| Under way | February 5, 2014 |
| Closing | February 4, 2021 |
| Closed | February 4, 2021 |
Dated events
| Event | Date | Source |
|---|---|---|
| Approval | November 27, 2013 | IDB projects dataset |
| First commitment | November 27, 2013 | Transactions |
| Signing | February 5, 2014 | IDB projects dataset |
| Planned start | February 13, 2014 | IATI |
| Actual start | June 2, 2014 | IATI |
| First disbursement | June 30, 2014 | Transactions |
| Closing date | February 4, 2021 | IATI |
| Last disbursement | February 28, 2021 | Transactions |
Financing
Table 1.Financing, US$ millions
| Financier | AmountUS$ millions | Role | Source |
|---|---|---|---|
| Local counterpart | 2.5 | Counterpart | IDB projects dataset |
| IDB | 25.0 | Institution | IDB projects dataset |
Table 2.Position at the data date by source (stocks), US$ millions
| This pageUS$ millions | Source | IATIUS$ millions | |
|---|---|---|---|
| Commitment | 25.0 | IDB projects dataset | 25.0 |
| Disbursed | 24.8 | IATI | 24.8 |
| Undisbursed | Not reported | ||
| Total cost | 27.5 | IDB projects dataset |
Each amount is given as the source publishes it, converted to US$. IATI column: the commitments and disbursements the partner reports to IATI, converted to US$. Amounts by source
This page uses IDB projects dataset for the commitment and IATI for disbursements.
Changes to the operationnot reported
- Original closing date
- Not reported
- Closing date extensions
- Not reported
- Restructurings
- Not reported
- Emergency component
- Not reported
New commitments and disbursements by fiscal year
Table 3.New commitments and disbursements by fiscal year (flows), US$ millions
| FY2013-14US$ millions | FY2015-16US$ millions | FY2016-17US$ millions | FY2017-18US$ millions | FY2018-19US$ millions | FY2019-20US$ millions | FY2020-21US$ millions | |
|---|---|---|---|---|---|---|---|
| New commitments | 25.0 | Not reported | Not reported | Not reported | Not reported | Not reported | Not reported |
| Disbursements | 4.7 | 4.7 | 2.2 | 3.6 | 3.6 | 4.7 | 1.3 |
| Cumulative disbursements | 4.7 | 9.3 | 11.6 | 15.2 | 18.8 | 23.6 | 24.8 |
Records and documents
Transactions13 records, November 27, 2013 to July 31, 2021
Table 4.Transactions, US$ millions
| Date | Measure | AmountUS$ millions | Source | Method |
|---|---|---|---|---|
| November 27, 2013 | Commitment | 25.0 | IDB projects dataset | commitment at approval date |
| June 30, 2014 | Disbursements | 0.1 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| July 31, 2014 | Disbursements | 4.6 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| March 31, 2016 | Disbursements | 4.7 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| February 28, 2017 | Disbursements | 2.2 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| December 31, 2017 | Disbursements | 3.4 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| August 31, 2018 | Disbursements | 0.1 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| September 30, 2018 | Disbursements | 0.1 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| October 31, 2018 | Disbursements | 3.6 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| August 31, 2020 | Disbursements | 4.7 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| January 31, 2021 | Disbursements | 0.7 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| February 28, 2021 | Disbursements | 0.7 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| July 31, 2021 | Disbursements | −0.1 | IATI | IATI disbursement (transaction type 3), paid to another organization |
Terms5 of 6 reported
- Finance type
- 110 Standard grant
- Flow type
- 20 Other official flows, excluding export credits
- Aid type
- C01 Project-type interventions
- Tied status
- 5 Untied
- Collaboration type
- 4 Multilateral outflows
- Humanitarian
- Not reported
Results indicators48 indicators
| Indicator | Baseline | Target | Latest value | Date of latest value |
|---|---|---|---|---|
| Indicator 4.1: Days with water level at Péligre dam above the maximum limit for flood management | Not reported | 75.00 | 0.00 | December 31, 2014 |
| Indicator 4.2: Days with water flows released by Péligre dam above 400 m3/sec | Not reported | 18.00 | 0.00 | December 31, 2014 |
| Indicator 6.1: Secondary and tertiary canals and drains dredged (manually) by the 3 WUAs in the pilot area | Not reported | 108.00 | 40.60 | December 31, 2016 |
| Indicator 6.2: Rate of cost recovery in the 3 WUAs of the pilot area | Not reported | 75.00 | 0.00 | December 31, 2016 |
| Output 10: ODVA?s procedures manual for operation and maintenance of infrastructure and equipment prepared | Not reported | 1.00 | 0.00 | December 31, 2015 |
| Output 11: CIA-ODVA's staff trained | Not reported | 20.00 | 24.00 | December 31, 2017 |
| Output 12: Annual technical and financial plan and annual technical and financial report of operation and maintenance of primary infrastructures under ODVA?s responsibility prepared | Not reported | 2.00 | 0.00 | December 31, 2018 |
| Output 13: CIA-ODVA equipped with a package of operating equipment | Not reported | 1.00 | 0.00 | December 31, 2014 |
| Output 14: ODVA?s administrative and financial staff trained | Not reported | 10.00 | 10.00 | December 31, 2016 |
| Output 15: Accounting software installed at the ODVA?s administrative and financial service | Not reported | 1.00 | 0.00 | December 31, 2014 |
| Output 16: ODVA�s administrative and financial service equipped with a package of operating equipment | Not reported | 1.00 | 0.00 | December 31, 2014 |
| Output 17: DGSE-ODVA equipped with a package of operating equipment | Not reported | 1.00 | 0.00 | December 31, 2014 |
| Output 18: Water Users Associations (WUAs) equipped with office, IT equipment and motorcycles | Not reported | 4.00 | 0.00 | December 31, 2017 |
| Output 19: DGSE and WUA staff trained | Not reported | 170.00 | 93.00 | December 31, 2018 |
| Output 1: Water and sediment containment infrastructures built in gullies in the pilot area of the upper watershed | Not reported | 225.00 | 180.00 | December 31, 2018 |
| Output 20: Annual technical and financial plan and annual technical and financial report of operation and maintenance of infrastructures under WUAs? responsibility: prepared | Not reported | 6.00 | 0.00 | December 31, 2018 |
| Output 2: Electromechanical system (gates and automatic control) at Canneau dam rehabilitated | Not reported | 1.00 | 0.00 | December 31, 2015 |
| Output 3: Protection walls preventing the Left and Right Banks Master Canals from collapsing downstream Canneau dam: built | Not reported | 2.00 | 0.00 | December 31, 2015 |
| Output 4: Secondary and tertiary irrigation and drainage canals built or rehabilitated, and equipped, in the pilot area of the irrigation district | Not reported | 28.40 | 35.90 | December 31, 2016 |
| Output 5: Primary irrigation and drainage canals dredged in the irrigation district | Not reported | 30000.00 | 1954.00 | December 31, 2018 |
| Output 6: Equipment to regulate and measure water flow built/installed on the main canals of the irrigation district | Not reported | 50.00 | 0.00 | December 31, 2016 |
| Output 7: Meetings of the Péligre Commission taking place | Not reported | 6.00 | 4.00 | December 31, 2018 |
| Output 8: Flood management system (composed of water level gauges, flood management software and one computer per dam) operating at the Péligre and Canneau dams | Not reported | 1.00 | 0.00 | December 31, 2015 |
| Output 9: Artibonite Watershed Binational Commission created | Not reported | 1.00 | 0.00 | December 31, 2018 |
| Indicator 4.1: Days with water level at Péligre dam above the maximum limit for flood management | Not reported | 75.00 | 0.00 | December 31, 2014 |
| Indicator 4.2: Days with water flows released by Péligre dam above 400 m3/sec | Not reported | 18.00 | 0.00 | December 31, 2014 |
| Indicator 6.1: Secondary and tertiary canals and drains dredged (manually) by the 3 WUAs in the pilot area | Not reported | 108.00 | 40.60 | December 31, 2016 |
| Indicator 6.2: Rate of cost recovery in the 3 WUAs of the pilot area | Not reported | 75.00 | 0.00 | December 31, 2016 |
| Output 10: ODVA?s procedures manual for operation and maintenance of infrastructure and equipment prepared | Not reported | 1.00 | 0.00 | December 31, 2015 |
| Output 11: CIA-ODVA's staff trained | Not reported | 20.00 | 24.00 | December 31, 2017 |
| Output 12: Annual technical and financial plan and annual technical and financial report of operation and maintenance of primary infrastructures under ODVA?s responsibility prepared | Not reported | 2.00 | 0.00 | December 31, 2018 |
| Output 13: CIA-ODVA equipped with a package of operating equipment | Not reported | 1.00 | 0.00 | December 31, 2014 |
| Output 14: ODVA?s administrative and financial staff trained | Not reported | 10.00 | 10.00 | December 31, 2016 |
| Output 15: Accounting software installed at the ODVA?s administrative and financial service | Not reported | 1.00 | 0.00 | December 31, 2014 |
| Output 16: ODVA�s administrative and financial service equipped with a package of operating equipment | Not reported | 1.00 | 0.00 | December 31, 2014 |
| Output 17: DGSE-ODVA equipped with a package of operating equipment | Not reported | 1.00 | 0.00 | December 31, 2014 |
| Output 18: Water Users Associations (WUAs) equipped with office, IT equipment and motorcycles | Not reported | 4.00 | 0.00 | December 31, 2017 |
| Output 19: DGSE and WUA staff trained | Not reported | 170.00 | 93.00 | December 31, 2018 |
| Output 1: Water and sediment containment infrastructures built in gullies in the pilot area of the upper watershed | Not reported | 225.00 | 180.00 | December 31, 2018 |
| Output 20: Annual technical and financial plan and annual technical and financial report of operation and maintenance of infrastructures under WUAs? responsibility: prepared | Not reported | 6.00 | 0.00 | December 31, 2018 |
| Output 2: Electromechanical system (gates and automatic control) at Canneau dam rehabilitated | Not reported | 1.00 | 0.00 | December 31, 2015 |
| Output 3: Protection walls preventing the Left and Right Banks Master Canals from collapsing downstream Canneau dam: built | Not reported | 2.00 | 0.00 | December 31, 2015 |
| Output 4: Secondary and tertiary irrigation and drainage canals built or rehabilitated, and equipped, in the pilot area of the irrigation district | Not reported | 28.40 | 35.90 | December 31, 2016 |
| Output 5: Primary irrigation and drainage canals dredged in the irrigation district | Not reported | 30000.00 | 1954.00 | December 31, 2018 |
| Output 6: Equipment to regulate and measure water flow built/installed on the main canals of the irrigation district | Not reported | 50.00 | 0.00 | December 31, 2016 |
| Output 7: Meetings of the Péligre Commission taking place | Not reported | 6.00 | 4.00 | December 31, 2018 |
| Output 8: Flood management system (composed of water level gauges, flood management software and one computer per dam) operating at the Péligre and Canneau dams | Not reported | 1.00 | 0.00 | December 31, 2015 |
| Output 9: Artibonite Watershed Binational Commission created | Not reported | 1.00 | 0.00 | December 31, 2018 |
Funds passed on13 transactions
| Receiver | Transaction | Date | US$ millions |
|---|---|---|---|
| Southport Dredging Inc | Disbursement | February 28, 2021 | 0.1 |
| Aecom Consultants Inc. | Disbursement | February 28, 2021 | 0.1 |
| Southport Dredging Inc | Disbursement | February 28, 2021 | 0.4 |
| Southport Dredging Inc | Disbursement | January 31, 2021 | 0.7 |
| Ressources Financement Non Rembousable | Disbursement | August 31, 2020 | 4.7 |
| Ressources Financement Non Rembousable | Disbursement | October 31, 2018 | 3.6 |
| Direction du Centre d'ETUDE et | Disbursement | September 30, 2018 | 0.1 |
| Societe du Canal de Province (SCP) | Disbursement | August 31, 2018 | 0.1 |
| Ressources Financement Non Rembousable | Disbursement | December 31, 2017 | 3.4 |
| Ressources Financement Non Rembousable | Disbursement | February 28, 2017 | 2.2 |
| Ressources Financement Non Rembousable | Disbursement | March 31, 2016 | 4.7 |
| Ressources Financement Non Rembousable | Disbursement | July 31, 2014 | 4.6 |
| Ressources Financement Non Rembousable | Disbursement | June 30, 2014 | 0.1 |
Identifiers2 identifiers
| System | Identifier | Source |
|---|---|---|
| IATI identifier | XI-IATI-IADB-HA-L1087 | IATI |
| IDB operation | HA-L1087 | Operation record |
Partner documents37 documents
- Link - Annual Operating Plan HA-L087 38110838.xlsx, iadb.org
- Link - Detailed Budget HA-L1087 38107888.xls, iadb.org
- Link - Economic Analysis HA-L1087 38136444.docx, iadb.org
- Link - Monitoring and Evaluation Plan HA-L1087 38133821.docx, iadb.org
- Analyse EIESPGESARTIBONITEdocx 38689059.DOCX, iadb.org
- Base de donnes Thomonde par Alex Bellande Sept2013 38082849.xls, iadb.org
- Development of a Binational Technical Cooperation Structure in the Artibonite Watershed OXFAM-Qubec 2013 38129348.DOCX, iadb.org
- Devis estimatif - Rhabilitation Berges gauche et droite en aval de Canneau COB 2013 38133483.XLSX, iadb.org
- Estimation des bnfices technico-conomiques esprs du programme dinvestissement et de maintenance - Rapport 38154933.DOCX, iadb.org
- Etude Prliminaire Bassin Versant Artibonite par Alex Bellande - Sept2013 38082840.doc, iadb.org
- Etude de curage des drains critiques - SCP 2013 38092249.PDF, iadb.org
- Etudes dinstrumentation des barrages de Pligre et de Canneau - Besoin dinvestissement - Coyne et Bellier 38111468.PDF, iadb.org
- Evaluation des contreparties de lODVA dans le cadre du projet dassistance technique en vue du transfert de ges 38094218.PDF, iadb.org
- Finalisation de la trame hydraulique du secteur pilote- Rapport 1a i Provisioire SCP 2013 38094164.PDF, iadb.org
- Implmentation dun systme de rgulation des canaux primaires - rapport 1a ii Provisioire - SCP 2013 38094109.PDF, iadb.org
- Mthodologie dassistance technique lODVA - Rapport 2b Provisioire v-2 38094096.PDF, iadb.org
- Projet de protection de la berge gauche du fleuve Artibonite et des canaux maitres rive gauche et rive droite en 38133702.doc, iadb.org
- Rforme du schma institutionnel de la gestion de leau et des infrastructures du primtre irrigu de la valle 38156741.PDF, iadb.org
- TDR de lassistance technique - Accompagnement de la DGSE de lODVA et des AI pour la mise en oeuvre de la rfor 38094139.PDF, iadb.org
- HA-L1087 First period Jan-Jun 2017-Public Report.pdf, iadb.org
- HA-L1087 First period Jan-Jun 2018-Public Report.pdf, iadb.org
- HA-L1087 First period Jan-Jun 2019-Public Report.pdf, iadb.org
- HA-L1087 First period Jan-Jun 2020 - Public Report.pdf, iadb.org
- IDB-PCR-Production-Timeline.pdf, iadb.org
- Water Management Program in the Artibonite Basin - HA-L1087.pdf, iadb.org
- Programme de Gestion de lEau dans le Bassin de lArtibonite - HA-L1087.pdf, iadb.org
- HA-L1087 First period Jan-Jun 2014-Public Report 40181536.PDF, iadb.org
- HA-L1087 First period Jan-Jun 2016-Public Report 40799074.PDF, iadb.org
- HA-L1087 First period Jan-Jun 2021 - Public Report.pdf, iadb.org
- HA-L1087 Second period Jan-Dec 2013-Public Report 40172068.PDF, iadb.org
- HA-L1087 Second period Jan-Dec 2014-Public Report 40185526.PDF, iadb.org
- HA-L1087 Second period Jan-Dec 2015-Public Report 40377348.PDF, iadb.org
- HA-L1087 Second period Jan-Dec 2016-Public Report.pdf, iadb.org
- HA-L1087 Second period Jan-Dec 2017-Public Report.pdf, iadb.org
- HA-L1087 Second period Jan-Dec 2018-Public Report.pdf, iadb.org
- HA-L1087 Second period Jan-Dec 2019-Public Report.pdf, iadb.org
- HA-L1087 Second period Jan-Dec 2020 - Public Report.pdf, iadb.org
Procurement notices (16)
- IDB_Procurement_Notices.xlsx, iadb.org
- HA-L1087 38857517.PDF, iadb.org
- HA-L1087 38990344.PDF, iadb.org
- HA-L1087 38990346.PDF, iadb.org
- HA-L1087 39045392.PDF, iadb.org
- HA-L1087 39115924.PDF, iadb.org
- HA-L1087 39345122.PDF, iadb.org
- HA-L1087 39454120.PDF, iadb.org
- HA-L1087 39519127.PDF, iadb.org
- HA-L1087 39598399.PDF, iadb.org
- HA-L108793882SP.pdf, iadb.org
- HA-L1087P523046SP.pdf, iadb.org
- HA-L1087P534366SP.pdf, iadb.org
- HA-L1087P534566SP.pdf, iadb.org
- HA-L1087P549388SP.pdf, iadb.org
- IDB_Project_Procurement_Contract_Awards_Data.xlsx, iadb.org
Sources
- IATI record (d-portal): terms of use set by the publisher
- IATI: terms of use set by the publisher
- IDB project page: terms of use set by the publisher
- Transactions: terms of use set by the publisher
- Operation record: terms of use set by the publisher
Data as of October 18, 2026
| Source | Read on |
|---|---|
| IATI | October 18, 2026 |
| IATI | October 18, 2026 |
| IDB projects dataset | October 18, 2026 |