Data / Partner portfolio / IDB Group / IDB
Increasing Access to Quality Education
Published title: Increasing Access to Quality Education in Haiti
US$ millions unless stated. Haitian fiscal year, October to September. FY2026-27 began October 1, 2026.
Objective
The overall objectives of the project are to support the following objectives of the Operational Plan for Education 2010-2015: (i) improving access to education; (ii) improving the quality of education; (iii) strengthening the institutional capacity of MENFP
As published by IDB projects dataset, in its original language.
- Sector
- Education
- Stage
- Closed since February 27, 2023
- Approval
- November 28, 2012
- Closing
- February 27, 2023
- Instrument
- Grant, Sovereign Guaranteed
- Effectiveness
- Not reported
- Last transaction
- June 30, 2023
- Operation ID
- HA-L1077
Life cycle4 stages, 9 dates
Stage history
| Stage | From |
|---|---|
| Approved | November 28, 2012 |
| Under way | January 25, 2013 |
| Closing | December 31, 2022 |
| Closed | February 27, 2023 |
Dated events
| Event | Date | Source |
|---|---|---|
| Approval | November 28, 2012 | IDB projects dataset |
| First commitment | November 28, 2012 | Transactions |
| Signing | January 25, 2013 | IDB projects dataset |
| Planned start | May 15, 2013 | IATI |
| First disbursement | May 31, 2013 | Transactions |
| Actual start | May 12, 2014 | IATI |
| Last disbursement | December 31, 2021 | Transactions |
| Closing date | December 31, 2022 | IATI |
| Actual end | February 27, 2023 | IATI |
Financing
Table 1.Financing, US$ millions
| Financier | AmountUS$ millions | Role | Source |
|---|---|---|---|
| IDB | 50.0 | Institution | IDB projects dataset |
Table 2.Position at the data date by source (stocks), US$ millions
| This pageUS$ millions | Source | IATIUS$ millions | |
|---|---|---|---|
| Commitment | 50.0 | IDB projects dataset | 57.0 |
| Disbursed | 79.3 | IATI | 79.3 |
| Undisbursed | Not reported | ||
| Total cost | 50.0 | IDB projects dataset |
Each amount is given as the source publishes it, converted to US$. IATI column: the commitments and disbursements the partner reports to IATI, converted to US$. Amounts by source
This page uses IDB projects dataset for the commitment and IATI for disbursements.
Changes to the operationnot reported
- Original closing date
- Not reported
- Closing date extensions
- Not reported
- Restructurings
- Not reported
- Emergency component
- Not reported
New commitments and disbursements by fiscal year
Table 3.New commitments and disbursements by fiscal year (flows), US$ millions
| FY2012-13US$ millions | FY2013-14US$ millions | FY2014-15US$ millions | FY2015-16US$ millions | FY2016-17US$ millions | FY2017-18US$ millions | FY2018-19US$ millions | FY2019-20US$ millions | FY2020-21US$ millions | FY2021-22US$ millions | FY2022-23US$ millions | |
|---|---|---|---|---|---|---|---|---|---|---|---|
| New commitments | 50.0 | Not reported | Not reported | Not reported | Not reported | Not reported | Not reported | Not reported | Not reported | Not reported | Not reported |
| Disbursements | 0.5 | 0.6 | 15.5 | 19.9 | 11.0 | 14.8 | 2.5 | 4.5 | 6.5 | 3.6 | −0.1 |
| Cumulative disbursements | 0.5 | 1.1 | 16.6 | 36.4 | 47.4 | 62.2 | 64.7 | 69.2 | 75.8 | 79.4 | 79.3 |
Records and documents
Transactions30 records, November 28, 2012 to June 30, 2023
Table 4.Transactions, US$ millions
| Date | Measure | AmountUS$ millions | Source | Method |
|---|---|---|---|---|
| November 28, 2012 | Commitment | 50.0 | IDB projects dataset | commitment at approval date |
| May 31, 2013 | Disbursements | 0.5 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| May 31, 2014 | Disbursements | 0.6 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| October 31, 2014 | Disbursements | 6.0 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| December 31, 2014 | Disbursements | 7.1 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| September 30, 2015 | Disbursements | 2.4 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| December 31, 2015 | Disbursements | 16.0 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| January 31, 2016 | Disbursements | 0.3 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| February 29, 2016 | Disbursements | 1.7 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| June 30, 2016 | Disbursements | 1.4 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| July 31, 2016 | Disbursements | 0.5 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| October 31, 2016 | Disbursements | 1.2 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| November 30, 2016 | Disbursements | 0.2 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| December 31, 2016 | Disbursements | 9.1 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| April 30, 2017 | Disbursements | 0.4 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| July 31, 2017 | Disbursements | <0.1 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| October 31, 2017 | Disbursements | <0.1 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| November 30, 2017 | Disbursements | 13.4 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| January 31, 2018 | Disbursements | <0.1 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| June 30, 2018 | Disbursements | 1.3 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| August 31, 2019 | Disbursements | 2.5 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| August 31, 2020 | Disbursements | 4.5 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| December 31, 2020 | Disbursements | 2.9 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| June 30, 2021 | Disbursements | 3.7 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| November 30, 2021 | Disbursements | −0.4 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| December 31, 2021 | Disbursements | 4.0 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| October 31, 2022 | Disbursements | −0.0 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| December 31, 2022 | Disbursements | −0.0 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| May 31, 2023 | Disbursements | −0.0 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| June 30, 2023 | Disbursements | −0.0 | IATI | IATI disbursement (transaction type 3), paid to another organization |
Terms5 of 6 reported
- Finance type
- 110 Standard grant
- Flow type
- 20 Other official flows, excluding export credits
- Aid type
- C01 Project-type interventions
- Tied status
- 5 Untied
- Collaboration type
- 4 Multilateral outflows
- Humanitarian
- Not reported
Locations4 places named
| Departments | Not reported |
| Places named by the source | Haiti, 1, DELMAS 75, PORT-AU-PRINCE, Haiti, 3, RUE VILLEVALLEIX, PEGUYVILLE, PETION-VILLE, Haiti, 5, AVENUE CHARLES SUMMER, PORT-AU-PRINCE, Haiti, 8,RUE ANTOINE SIMON, DELMAS 83, PORT-AU-PRINCE |
| Places with coordinates | 0 |
Results indicators30 indicators
| Indicator | Baseline | Target | Latest value | Date of latest value |
|---|---|---|---|---|
| Deworming campaigns carried out in selected schools | Not reported | 2.00 | 0.00 | December 31, 2015 |
| Financial transfers per beneficiary schools done during the school year. | Not reported | 1.00 | 1.00 | December 31, 2015 |
| Grade 1-6 students benefitting from tuition-free education | Not reported | 35000.00 | 20328.00 | December 31, 2015 |
| Impact evaluation of the tuition waiver program completed | Not reported | 1.00 | 0.00 | December 31, 2015 |
| Institutionalized information system operational and providing updated and timely data | Not reported | 1.00 | 1.00 | December 31, 2016 |
| National program to improve the quality of education, and primarily literacy, designed | Not reported | 1.00 | 0.00 | December 31, 2015 |
| New infrastructure to host the Ministry of Education is under construction | Not reported | 1.00 | 0.00 | December 31, 2015 |
| New preschool-to-grade 9 schools open for enrollment | Not reported | 20.00 | 0.00 | December 31, 2016 |
| Percentage of non-public schools accredited | Not reported | 20.00 | 0.00 | December 31, 2016 |
| Preschool to grade 9 students benefitting from additional learning space | Not reported | 8200.00 | 0.00 | December 31, 2016 |
| School map used in decision making regarding the localization of schools to be built in coming years | Not reported | 1.00 | 0.00 | December 31, 2015 |
| Schools accredited by the MENFP | Not reported | 200.00 | 0.00 | December 31, 2016 |
| Schools certified Hygiene Friendly | Not reported | 50.00 | 152.00 | December 31, 2017 |
| Set of norms, standardized plans and execution manuals for the construction of secondary schools designed and published. | Not reported | 1.00 | 0.00 | December 31, 2015 |
| Students from preschool to grade 9 with improved readiness to learn | Not reported | 315000.00 | 867730.00 | December 31, 2016 |
| Deworming campaigns carried out in selected schools | Not reported | 2.00 | 0.00 | December 31, 2015 |
| Financial transfers per beneficiary schools done during the school year. | Not reported | 1.00 | 1.00 | December 31, 2015 |
| Grade 1-6 students benefitting from tuition-free education | Not reported | 35000.00 | 20328.00 | December 31, 2015 |
| Impact evaluation of the tuition waiver program completed | Not reported | 1.00 | 0.00 | December 31, 2015 |
| Institutionalized information system operational and providing updated and timely data | Not reported | 1.00 | 1.00 | December 31, 2016 |
| National program to improve the quality of education, and primarily literacy, designed | Not reported | 1.00 | 0.00 | December 31, 2015 |
| New infrastructure to host the Ministry of Education is under construction | Not reported | 1.00 | 0.00 | December 31, 2015 |
| New preschool-to-grade 9 schools open for enrollment | Not reported | 20.00 | 0.00 | December 31, 2016 |
| Percentage of non-public schools accredited | Not reported | 20.00 | 0.00 | December 31, 2016 |
| Preschool to grade 9 students benefitting from additional learning space | Not reported | 8200.00 | 0.00 | December 31, 2016 |
| School map used in decision making regarding the localization of schools to be built in coming years | Not reported | 1.00 | 0.00 | December 31, 2015 |
| Schools accredited by the MENFP | Not reported | 200.00 | 0.00 | December 31, 2016 |
| Schools certified Hygiene Friendly | Not reported | 50.00 | 152.00 | December 31, 2017 |
| Set of norms, standardized plans and execution manuals for the construction of secondary schools designed and published. | Not reported | 1.00 | 0.00 | December 31, 2015 |
| Students from preschool to grade 9 with improved readiness to learn | Not reported | 315000.00 | 867730.00 | December 31, 2016 |
Funds passed on29 transactions
| Receiver | Transaction | Date | US$ millions |
|---|---|---|---|
| Ministere de L Economie et des Finances | Disbursement | December 31, 2021 | 4.0 |
| Ministere de L Economie et des Finances | Disbursement | June 30, 2021 | 3.7 |
| Ministere de L Economie et des Finances | Disbursement | December 31, 2020 | 2.9 |
| Name not shown | Disbursement | August 31, 2020 | 4.5 |
| Name not shown | Disbursement | August 31, 2019 | 2.5 |
| FAES-ACEQH-Dollars | Disbursement | June 30, 2018 | 1.3 |
| GF Consulting Group Corp. | Disbursement | January 31, 2018 | <0.1 |
| MENFP-ACEQH-USD | Disbursement | November 30, 2017 | 0.7 |
| Utemef 2863GR-HA - Programme Aumenter | Disbursement | November 30, 2017 | 6.0 |
| GF Consulting Group Corp. | Disbursement | October 31, 2017 | <0.1 |
| GF Consulting Group Corp. | Disbursement | July 31, 2017 | <0.1 |
| MENFP-ACEQH-USD | Disbursement | April 30, 2017 | 0.4 |
| FAES-ACEQH-Dollars | Disbursement | December 31, 2016 | 4.3 |
| MENFP-ACEQH-USD | Disbursement | December 31, 2016 | 0.2 |
| MENFP-ACEQH-USD | Disbursement | November 30, 2016 | 0.2 |
| Fond des Bailleursmspp | Disbursement | October 31, 2016 | 0.6 |
| FAES-ACEQH-Dollars | Disbursement | July 31, 2016 | 0.5 |
| Banque Nationale de Credit | Disbursement | June 30, 2016 | 0.6 |
| Banque Nationale de Credit | Disbursement | June 30, 2016 | 0.9 |
| Banque Nationale de Credit | Disbursement | February 29, 2016 | 1.7 |
| Banque Nationale de Credit | Disbursement | January 31, 2016 | 0.2 |
| Utemef 2863GR-HA - Programme Aumenter | Disbursement | December 31, 2015 | 8.0 |
| Banque Nationale de Credit | Disbursement | September 30, 2015 | 1.2 |
| FAES-ACEQH-Dollars | Disbursement | December 31, 2014 | 1.5 |
| Fond des Bailleursmspp | Disbursement | December 31, 2014 | 0.8 |
| Banque Nationale de Credit | Disbursement | December 31, 2014 | 1.7 |
| Utemef 2863GR-HA - Programme Aumenter | Disbursement | October 31, 2014 | 3.0 |
| Utemef 2863GR-HA - Programme Aumenter | Disbursement | May 31, 2014 | 0.3 |
| Utemef 2863GR-HA - Programme Aumenter | Disbursement | May 31, 2013 | 0.5 |
Identifiers3 identifiers
| System | Identifier | Source |
|---|---|---|
| IATI identifier | XI-IATI-IADB-HA-L1077 | IATI |
| IDB operation | HA-L1077 | Operation record |
| Public investment program line | 1311-1-12-51-14 | Public investment program |
Where sources differ1 field
| Field | Source | Value | Used |
|---|---|---|---|
| Commitment | IDB projects dataset | US$50.0 million | ✓ |
| Commitment | IATI | US$57.0 million |
Partner documents33 documents
- Increasing Access to Quality Education in Haiti Grant Proposal 37302335.PDF, iadb.org
- Increasing Access to Quality Education in Haiti LINK ESMR 37092943.docx, iadb.org
- Aumento del Acceso a Educacin de Calidad en Hait Propuesta de Financiamiento no Reembolsable 37302379.PDF, iadb.org
- Contrat - Augmenter lAccs une Education de Qualit en Hati.pdf, iadb.org
- HA-L1077 First period Jan-Jun 2017-Public Report.pdf, iadb.org
- IDB-PCR-Production-Timeline.pdf, iadb.org
- PCR HA-L1077 PCR aprobado.pdf, iadb.org
- PCR HA-L1077 Education - French.pdf, iadb.org
- HA-L1077 First period Jan-Jun 2014-Public Report 40181528.PDF, iadb.org
- HA-L1077 First period Jan-Jun 2015-Public Report 40194398.PDF, iadb.org
- HA-L1077 First period Jan-Jun 2016-Public Report 40799066.PDF, iadb.org
- HA-L1077 Second period Jan-Dec 2014-Public Report 40185529.PDF, iadb.org
- HA-L1077 Second period Jan-Dec 2015-Public Report 40377338.PDF, iadb.org
- HA-L1077 Second period Jan-Dec 2016-Public Report.pdf, iadb.org
- HA-L1077 Second period Jan-Dec 2017-Public Report.pdf, iadb.org
- HA-L1077 Second period Jan-Dec 2018-Public Report.pdf, iadb.org
- HA-L1077 Second period Jan-Dec 2019-Public Report.pdf, iadb.org
- HA-L1077 Second period Jan-Dec 2020 - Public Report.pdf, iadb.org
- HA-L1077 Second period Jan-Dec 2021 - Public Report.PDF, iadb.org
- HA-L1077 Second period Jan-Dec 2022 - Public Report.PDF, iadb.org
- Report for PublicationPMR-HA-L1077-2013-1-Period 38267499.PDF, iadb.org
- Informe para PublicacinPMR-HA-L1077-2013-1-Periodo 38266826.PDF, iadb.org
- HA-L1077 First period Jan-Jun 2018-Public Report.pdf, iadb.org
- HA-L1077 First period Jan-Jun 2019-Public Report.pdf, iadb.org
- HA-L1077 First period Jan-Jun 2020 - Public Report.pdf, iadb.org
- HA-L1077 First period Jan-Jun 2021 - Public Report.pdf, iadb.org
- HA-L1077 First period Jan-Jun 2022 - Public Report.PDF, iadb.org
- HA-L1077 First period Jan-Jun 2023 - Public Report.PDF, iadb.org
- HA-L1077 Second period Jan-Dec 2013-Public Report 40172064.PDF, iadb.org
- Rapport pour PublicationPMR-HA-L1077-2012-2-Perodo 37873943.PDF, iadb.org
- Rapport pour PublicationPMR-HA-L1077-2013-1-Perodo 38266161.PDF, iadb.org
- Relatrio para publicaoPMR-HA-L1077-2012-2-Perodo 37873275.PDF, iadb.org
- Relatrio para publicaoPMR-HA-L1077-2013-1-Perodo 38265496.PDF, iadb.org
Procurement notices (11)
- IDB_Procurement_Notices.xlsx, iadb.org
- HA-L1077 1009.pdf, iadb.org
- HA-L1077 38784769.PDF, iadb.org
- HA-L1077 39430767.PDF, iadb.org
- HA-L1077 39992777.PDF, iadb.org
- HA-L1077 40316856.PDF, iadb.org
- HA-L1077 40319796.PDF, iadb.org
- HA-L1077P565612SP.pdf, iadb.org
- PPM PAO2863- UCP-MENFP actualis au 19 novembre 2019 version 1.xlsx, iadb.org
- HA-L1077 39356082.PDF, iadb.org
- IDB_Project_Procurement_Contract_Awards_Data.xlsx, iadb.org
Sources
- IATI record (d-portal): terms of use set by the publisher
- IATI: terms of use set by the publisher
- IDB project page: terms of use set by the publisher
- Transactions: terms of use set by the publisher
- Operation record: terms of use set by the publisher
- Public investment program: terms of use set by the publisher
Data as of October 18, 2026
| Source | Read on |
|---|---|
| IATI | October 18, 2026 |
| IATI | October 18, 2026 |
| IDB projects dataset | October 18, 2026 |
| Public investment program | October 18, 2026 |
Cite this page
HaitiDocs. Increasing Access to Quality Education. Partner portfolio, data as of October 18, 2026. https://www.haitidocs.org/portfolio/projects/IDB%3AHA-L1077