Data / Partner portfolio / IDB Group / IDB
Urban Rehabilitation Program
US$ millions unless stated. Haitian fiscal year, October to September. FY2026-27 began October 1, 2026.
Objective
The Program aims at improving the living conditions of the inhabitants of Cité Soleil, one of the poorest urban settlements in the country by: increasing their access to basic urban and social services, consolidating and strengthening participatory planning at the neighborhood level, and promoting income generation activities.
As published by IDB projects dataset, in its original language.
- Sector
- Social protection
- Stage
- Closed since December 11, 2019
- Approval
- July 6, 2005
- Closing
- December 11, 2019
- Instrument
- Grant, Sovereign Guaranteed
- Effectiveness
- Not reported
- Last transaction
- December 31, 2015
- Operation ID
- HA-L1002
Life cycle4 stages, 9 dates
Stage history
| Stage | From |
|---|---|
| Approved | July 6, 2005 |
| Under way | July 21, 2005 |
| Closing | December 31, 2015 |
| Closed | December 11, 2019 |
Dated events
| Event | Date | Source |
|---|---|---|
| Approval | July 6, 2005 | IDB projects dataset |
| First commitment | July 6, 2005 | Transactions |
| Signing | July 21, 2005 | IDB projects dataset |
| Planned start | September 2, 2005 | IATI |
| Actual start | September 12, 2005 | IATI |
| First disbursement | November 30, 2010 | Transactions |
| Last disbursement | December 31, 2015 | Transactions |
| Closing date | December 31, 2015 | IATI |
| Actual end | December 11, 2019 | IATI |
Financing
Table 1.Financing, US$ millions
| Financier | AmountUS$ millions | Role | Source |
|---|---|---|---|
| Local counterpart | −7.7 | Counterpart | IDB projects dataset |
| IDB | 62.6 | Institution | IDB projects dataset |
Table 2.Position at the data date by source (stocks), US$ millions
| This pageUS$ millions | Source | IATIUS$ millions | |
|---|---|---|---|
| Commitment | 62.6 | IDB projects dataset | 62.6 |
| Disbursed | 12.4 | IATI | 12.4 |
| Undisbursed | Not reported | ||
| Total cost | 62.9 | IDB projects dataset |
Each amount is given as the source publishes it, converted to US$. IATI column: the commitments and disbursements the partner reports to IATI, converted to US$. Amounts by source
This page uses IDB projects dataset for the commitment and IATI for disbursements.
Changes to the operationnot reported
- Original closing date
- Not reported
- Closing date extensions
- Not reported
- Restructurings
- Not reported
- Emergency component
- Not reported
New commitments and disbursements by fiscal year
Table 3.New commitments and disbursements by fiscal year (flows), US$ millions
| FY2004-05US$ millions | FY2010-11US$ millions | FY2011-12US$ millions | FY2012-13US$ millions | FY2013-14US$ millions | FY2014-15US$ millions | FY2015-16US$ millions | |
|---|---|---|---|---|---|---|---|
| New commitments | 62.6 | Not reported | Not reported | Not reported | Not reported | Not reported | Not reported |
| Disbursements | Not reported | 5.0 | 1.0 | 3.7 | 2.1 | 0.6 | 0.1 |
| Cumulative disbursements | Not reported | 5.0 | 5.9 | 9.7 | 11.8 | 12.3 | 12.4 |
Records and documents
Transactions43 records, July 6, 2005 to December 31, 2015
Table 4.Transactions, US$ millions
| Date | Measure | AmountUS$ millions | Source | Method |
|---|---|---|---|---|
| July 6, 2005 | Commitment | 62.6 | IDB projects dataset | commitment at approval date |
| November 30, 2010 | Disbursements | 0.8 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| December 31, 2010 | Disbursements | 1.3 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| May 31, 2011 | Disbursements | 1.9 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| July 31, 2011 | Disbursements | 0.2 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| August 31, 2011 | Disbursements | 0.5 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| September 30, 2011 | Disbursements | 0.2 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| November 30, 2011 | Disbursements | 0.2 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| December 31, 2011 | Disbursements | 0.1 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| January 31, 2012 | Disbursements | <0.1 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| February 29, 2012 | Disbursements | 0.2 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| March 31, 2012 | Disbursements | 0.2 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| July 31, 2012 | Disbursements | <0.1 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| September 30, 2012 | Disbursements | 0.3 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| October 31, 2012 | Disbursements | 0.9 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| December 31, 2012 | Disbursements | 0.7 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| January 31, 2013 | Disbursements | 0.2 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| February 28, 2013 | Disbursements | 0.3 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| March 31, 2013 | Disbursements | 0.3 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| April 30, 2013 | Disbursements | 0.3 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| May 31, 2013 | Disbursements | 0.3 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| June 30, 2013 | Disbursements | 0.1 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| July 31, 2013 | Disbursements | 0.4 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| September 30, 2013 | Disbursements | 0.2 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| October 31, 2013 | Disbursements | 0.4 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| November 30, 2013 | Disbursements | 0.6 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| December 31, 2013 | Disbursements | 0.5 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| February 28, 2014 | Disbursements | 0.1 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| March 31, 2014 | Disbursements | 0.1 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| June 30, 2014 | Disbursements | <0.1 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| July 31, 2014 | Disbursements | 0.1 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| August 31, 2014 | Disbursements | 0.2 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| September 30, 2014 | Disbursements | <0.1 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| November 30, 2014 | Disbursements | <0.1 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| December 31, 2014 | Disbursements | 0.2 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| January 31, 2015 | Disbursements | 0.1 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| February 28, 2015 | Disbursements | <0.1 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| March 31, 2015 | Disbursements | 0.1 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| April 30, 2015 | Disbursements | 0.1 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| May 31, 2015 | Disbursements | 0.1 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| July 31, 2015 | Disbursements | <0.1 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| November 30, 2015 | Disbursements | <0.1 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| December 31, 2015 | Disbursements | 0.1 | IATI | IATI disbursement (transaction type 3), paid to another organization |
Terms5 of 6 reported
- Finance type
- 110 Standard grant
- Flow type
- 20 Other official flows, excluding export credits
- Aid type
- C01 Project-type interventions
- Tied status
- 5 Untied
- Collaboration type
- 4 Multilateral outflows
- Humanitarian
- Not reported
Results indicators15 indicators
| Indicator | Baseline | Target | Latest value | Date of latest value |
|---|---|---|---|---|
| Access road to Truitier landfill built. | Not reported | 1.30 | 1.30 | December 31, 2009 |
| Centre d'accueil à carrefour réhabilité | Not reported | 1.00 | 1.00 | December 31, 2008 |
| Complexes Administratifs et Socioculturel (CASC) construits dans 9 Chefs-lieux de Département. | Not reported | 1.00 | 1.00 | December 31, 2009 |
| Direct beneficiaries satisfied by travel time. | Not reported | 30.00 | 0.00 | December 31, 2010 |
| Six rues à Carrefour se sont réhabilité | Not reported | 6550.00 | 6550.00 | December 31, 2008 |
| Strategic investements in Carrefours and each Department done. | Not reported | 2.00 | 2.00 | December 31, 2010 |
| Trois marchés à Carrefour inauguré | Not reported | 1.00 | 1.00 | December 31, 2009 |
| Access road to Truitier landfill built. | Not reported | 1.30 | 1.30 | December 31, 2009 |
| Centre d'accueil à carrefour réhabilité | Not reported | 1.00 | 1.00 | December 31, 2008 |
| Complexes Administratifs et Socioculturel (CASC) construits dans 9 Chefs-lieux de Département. | Not reported | 1.00 | 1.00 | December 31, 2009 |
| Department Centres Administratifs et Socio-Culturels (CASCs) operated and maintained. | Not reported | 15.00 | 0.00 | December 31, 2012 |
| Direct beneficiaries satisfied by travel time. | Not reported | 30.00 | 0.00 | December 31, 2010 |
| Six rues à Carrefour se sont réhabilité | Not reported | 6550.00 | 6550.00 | December 31, 2008 |
| Strategic investements in Carrefours and each Department done. | Not reported | 2.00 | 2.00 | December 31, 2010 |
| Trois marchés à Carrefour inauguré | Not reported | 1.00 | 1.00 | December 31, 2009 |
Funds passed on139 transactions
| Receiver | Transaction | Date | US$ millions |
|---|---|---|---|
| AMF Experts Corp | Disbursement | December 31, 2015 | <0.1 |
| AMF Experts Corp | Disbursement | December 31, 2015 | <0.1 |
| Consultora Knowledge Works Limitada | Disbursement | December 31, 2015 | <0.1 |
| Consultora Knowledge Works Limitada | Disbursement | November 30, 2015 | <0.1 |
| Name not shown | Disbursement | July 31, 2015 | <0.1 |
| Merove-Pierre and Associates | Disbursement | May 31, 2015 | 0.1 |
| Name not shown | Disbursement | April 30, 2015 | <0.1 |
| Plurimats | Disbursement | April 30, 2015 | 0.1 |
| UTE PRU-1639SF-HA | Disbursement | April 30, 2015 | <0.1 |
| Plurimats | Disbursement | March 31, 2015 | 0.1 |
| Name not shown | Disbursement | February 28, 2015 | <0.1 |
| STUDIO A | Disbursement | February 28, 2015 | <0.1 |
| PISACO | Disbursement | January 31, 2015 | 0.1 |
| Plurimats | Disbursement | December 31, 2014 | 0.1 |
| UTE PRU-1639SF-HA | Disbursement | December 31, 2014 | 0.1 |
| Name not shown | Disbursement | November 30, 2014 | <0.1 |
| Name not shown | Disbursement | September 30, 2014 | <0.1 |
| Plurimats | Disbursement | August 31, 2014 | 0.2 |
| Merove-Pierre and Associates | Disbursement | August 31, 2014 | <0.1 |
| Name not shown | Disbursement | July 31, 2014 | <0.1 |
| UTE PRU-1639SF-HA | Disbursement | July 31, 2014 | 0.1 |
| Name not shown | Disbursement | June 30, 2014 | <0.1 |
| BESUL | Disbursement | March 31, 2014 | <0.1 |
| BESUL | Disbursement | March 31, 2014 | 0.1 |
| STUDIO A | Disbursement | February 28, 2014 | <0.1 |
| UTE PRU-1639SF-HA | Disbursement | February 28, 2014 | 0.1 |
| Name not shown | Disbursement | February 28, 2014 | <0.1 |
| BESUL | Disbursement | December 31, 2013 | <0.1 |
| Groupementsoheco-Plurimat-Gitech | Disbursement | December 31, 2013 | 0.1 |
| Name not shown | Disbursement | December 31, 2013 | <0.1 |
| Plurimats | Disbursement | December 31, 2013 | 0.1 |
| Les Chantiers Modernes d'Haiti | Disbursement | December 31, 2013 | 0.1 |
| BESUL | Disbursement | December 31, 2013 | 0.1 |
| BESUL | Disbursement | December 31, 2013 | 0.1 |
| PISACO | Disbursement | November 30, 2013 | 0.5 |
| Plurimats | Disbursement | November 30, 2013 | 0.2 |
| Groupement Soheco-Plurimats-Gitech | Disbursement | October 31, 2013 | 0.2 |
| Les Chantiers Modernes d'Haiti | Disbursement | October 31, 2013 | 0.1 |
| UTE PRU-1639SF-HA | Disbursement | October 31, 2013 | 0.1 |
| Plurimats | Disbursement | September 30, 2013 | 0.2 |
| Name not shown | Disbursement | July 31, 2013 | <0.1 |
| SOPEC Plus | Disbursement | July 31, 2013 | 0.1 |
| Name not shown | Disbursement | July 31, 2013 | <0.1 |
| Merove-Pierre and Associates | Disbursement | July 31, 2013 | <0.1 |
| Name not shown | Disbursement | July 31, 2013 | <0.1 |
| Plurimats | Disbursement | July 31, 2013 | 0.3 |
| Atelier d'Architecture et d'Urbanisme | Disbursement | July 31, 2013 | <0.1 |
| LOPAS S.A. | Disbursement | June 30, 2013 | <0.1 |
| Name not shown | Disbursement | June 30, 2013 | <0.1 |
| Name not shown | Disbursement | June 30, 2013 | <0.1 |
| UTE PRU-1639SF-HA | Disbursement | June 30, 2013 | 0.1 |
| BESUL | Disbursement | May 31, 2013 | <0.1 |
| BESUL | Disbursement | May 31, 2013 | <0.1 |
| Plurimats | Disbursement | May 31, 2013 | 0.2 |
| SOPEC Plus | Disbursement | May 31, 2013 | <0.1 |
| STUDIO A | Disbursement | May 31, 2013 | <0.1 |
| Name not shown | Disbursement | May 31, 2013 | <0.1 |
| SOPEC Plus | Disbursement | April 30, 2013 | 0.1 |
| Name not shown | Disbursement | April 30, 2013 | <0.1 |
| Name not shown | Disbursement | April 30, 2013 | <0.1 |
| Les Chantiers Modernes d'Haiti | Disbursement | April 30, 2013 | 0.1 |
| TRUXTON | Disbursement | April 30, 2013 | 0.1 |
| UTE PRU-1639SF-HA | Disbursement | March 31, 2013 | 0.1 |
| Name not shown | Disbursement | March 31, 2013 | <0.1 |
| Plurimats | Disbursement | March 31, 2013 | 0.1 |
| Name not shown | Disbursement | February 28, 2013 | <0.1 |
| Muleng S.A. | Disbursement | February 28, 2013 | 0.1 |
| Les Chantiers Modernes d'Haiti | Disbursement | February 28, 2013 | 0.2 |
| Name not shown | Disbursement | February 28, 2013 | <0.1 |
| BESUL | Disbursement | January 31, 2013 | <0.1 |
| CASCOMP | Disbursement | January 31, 2013 | <0.1 |
| Merove-Pierre Cabinet d'Experts-Comptabl | Disbursement | January 31, 2013 | 0.1 |
| BESUL | Disbursement | January 31, 2013 | 0.1 |
| Name not shown | Disbursement | January 31, 2013 | <0.1 |
| BESUL | Disbursement | January 31, 2013 | <0.1 |
| BESUL | Disbursement | December 31, 2012 | 0.1 |
| BESUL | Disbursement | December 31, 2012 | 0.1 |
| Truxton SA | Disbursement | December 31, 2012 | 0.1 |
| Merove-Pierre and Associates | Disbursement | December 31, 2012 | 0.1 |
| BESUL | Disbursement | December 31, 2012 | 0.1 |
| CASCOMP | Disbursement | December 31, 2012 | <0.1 |
| Labranche et Associes | Disbursement | December 31, 2012 | <0.1 |
| Plurimats | Disbursement | December 31, 2012 | 0.2 |
| Name not shown | Disbursement | October 31, 2012 | <0.1 |
| Muleng S.A. | Disbursement | October 31, 2012 | <0.1 |
| UTE PRU-1639SF-HA | Disbursement | October 31, 2012 | 0.3 |
| IBC | Disbursement | October 31, 2012 | <0.1 |
| Name not shown | Disbursement | October 31, 2012 | <0.1 |
| IBC | Disbursement | October 31, 2012 | <0.1 |
| BESUL | Disbursement | October 31, 2012 | 0.2 |
| ENCOTRA | Disbursement | October 31, 2012 | <0.1 |
| EXECO S.A. | Disbursement | October 31, 2012 | 0.1 |
| Muleng S.A. | Disbursement | October 31, 2012 | 0.1 |
| ENCOTRA | Disbursement | October 31, 2012 | <0.1 |
| Name not shown | Disbursement | October 31, 2012 | <0.1 |
| Les Chantiers Modernes d'Haiti | Disbursement | October 31, 2012 | 0.2 |
| Plurimats | Disbursement | September 30, 2012 | 0.1 |
| EXECO S.A. | Disbursement | September 30, 2012 | <0.1 |
| SOPEC Plus | Disbursement | September 30, 2012 | 0.1 |
| SOPEC Plus | Disbursement | September 30, 2012 | <0.1 |
| Name not shown | Disbursement | July 31, 2012 | <0.1 |
| Name not shown | Disbursement | July 31, 2012 | <0.1 |
| UTE PRU-1639SF-HA | Disbursement | March 31, 2012 | <0.1 |
| Plurimats | Disbursement | March 31, 2012 | 0.1 |
| Name not shown | Disbursement | March 31, 2012 | <0.1 |
| Name not shown | Disbursement | March 31, 2012 | <0.1 |
| UTE PRU-1639SF-HA | Disbursement | March 31, 2012 | <0.1 |
| Name not shown | Disbursement | March 31, 2012 | <0.1 |
| Plurimats | Disbursement | February 29, 2012 | 0.1 |
| Name not shown | Disbursement | February 29, 2012 | <0.1 |
| Name not shown | Disbursement | February 29, 2012 | <0.1 |
| Name not shown | Disbursement | February 29, 2012 | <0.1 |
| Name not shown | Disbursement | February 29, 2012 | <0.1 |
| Muleng S.A | Disbursement | February 29, 2012 | 0.1 |
| Name not shown | Disbursement | January 31, 2012 | <0.1 |
| UTE PRU-1639SF-HA | Disbursement | December 31, 2011 | <0.1 |
| EXECO | Disbursement | December 31, 2011 | <0.1 |
| Plurimats | Disbursement | December 31, 2011 | 0.1 |
| BESUL | Disbursement | December 31, 2011 | <0.1 |
| UTE PRU-1639SF-HA | Disbursement | November 30, 2011 | <0.1 |
| Plurimats | Disbursement | November 30, 2011 | 0.1 |
| ENCOTRA | Disbursement | November 30, 2011 | <0.1 |
| EXECO S.A | Disbursement | September 30, 2011 | 0.1 |
| BESUL | Disbursement | September 30, 2011 | <0.1 |
| Name not shown | Disbursement | September 30, 2011 | <0.1 |
| Name not shown | Disbursement | September 30, 2011 | <0.1 |
| Plurimats | Disbursement | August 31, 2011 | 0.3 |
| BESUL | Disbursement | August 31, 2011 | <0.1 |
| Atelier d'Architecture et d'Urbanisme | Disbursement | August 31, 2011 | <0.1 |
| Experco International Limitee | Disbursement | August 31, 2011 | 0.2 |
| Atelier d'Architecture et d'Urbanisme | Disbursement | August 31, 2011 | <0.1 |
| Merove-Pierre | Disbursement | July 31, 2011 | <0.1 |
| UTE PRU-1639SF-HA | Disbursement | July 31, 2011 | 0.1 |
| Experco International Limitee | Disbursement | July 31, 2011 | 0.1 |
| UTE PRU-1639SF-HA | Disbursement | May 31, 2011 | 1.0 |
| UTE PRU-1639SF-HA | Disbursement | May 31, 2011 | 1.0 |
| UTE PRU-1639SF-HA | Disbursement | December 31, 2010 | 0.6 |
| UTE PRU-1639SF-HA | Disbursement | December 31, 2010 | 0.6 |
| UTE PRU-1639SF-HA | Disbursement | November 30, 2010 | 0.8 |
Identifiers2 identifiers
| System | Identifier | Source |
|---|---|---|
| IATI identifier | XI-IATI-IADB-HA-L1002 | IATI |
| IDB operation | HA-L1002 | Operation record |
Partner documents18 documents
- Urban Rehabilitation Program 565358.PDF, iadb.org
- Programa de Rehabilitacin Urbana 565359.PDF, iadb.org
- Contrat Modificatif - Programme de Rhabilitation Urbaine.pdf, iadb.org
- Contrat sign Programme de rehabilitation Urbaine 541805.DOC, iadb.org
- Programme de Rhabilitation Urbaine 542452.DOC, iadb.org
- Programme de Rhabilitation Urbaine 543391.DOC, iadb.org
- Programme de Rhabilitation Urbaine 543392.DOC, iadb.org
- IDB-PCR-Production-Timeline.pdf, iadb.org
- HA-L1002 First period Jan-Jun 2014-Public Report 40181476.PDF, iadb.org
- HA-L1002 First period Jan-Jun 2016-Public Report 40796926.PDF, iadb.org
- HA-L1002 First period Jan-Jun 2017-Public Report.pdf, iadb.org
- HA-L1002 First period Jan-Jun 2018-Public Report.pdf, iadb.org
- HA-L1002 First period Jan-Jun 2019-Public Report.pdf, iadb.org
- HA-L1002 Second period Jan-Dec 2013-Public Report 40172110.PDF, iadb.org
- HA-L1002 Second period Jan-Dec 2014-Public Report 40185500.PDF, iadb.org
- HA-L1002 Second period Jan-Dec 2016-Public Report.pdf, iadb.org
- HA-L1002 Second period Jan-Dec 2017-Public Report.pdf, iadb.org
- HA-L1002 Second period Jan-Dec 2018-Public Report.pdf, iadb.org
Procurement notices (2)
- IDB_Procurement_Notices.xlsx, iadb.org
- IDB_Project_Procurement_Contract_Awards_Data.xlsx, iadb.org
Sources
- IATI record (d-portal): terms of use set by the publisher
- IATI: terms of use set by the publisher
- IDB project page: terms of use set by the publisher
- Transactions: terms of use set by the publisher
- Operation record: terms of use set by the publisher
Data as of October 18, 2026
| Source | Read on |
|---|---|
| IATI | October 18, 2026 |
| IATI | October 18, 2026 |
| IDB projects dataset | October 18, 2026 |
Cite this page
HaitiDocs. Urban Rehabilitation Program. Partner portfolio, data as of October 18, 2026. https://www.haitidocs.org/portfolio/projects/IDB%3AHA-L1002