HaitiDocs

Data / Partner portfolio / Sectors

Energy

15 active operations of funding partners. US$ millions unless stated. Haitian fiscal year, October to September. FY2026-27 began October 1, 2026.

Disbursed in FY2025-26

US$16.3 million

As each source records them; 2 of the 11 funding partners on record report them

New commitments in FY2025-26

US$6.8 million

Approved or obligated, net of reductions; 2 of the 11 funding partners on record report them

Active portfolio at October 18, 2026

US$207.9 million

15 of 15 active operations report an approved amount

Portfolio at October 18, 2026

A position at the data date: approved is every commitment to date on the operations, cancellations deducted; disbursed to date and undisbursed are as each partner publishes them.

Table 1.Portfolio of active operations at October 18, 2026, US$ millions

OperationsApprovedUS$ millionsDisbursed to dateUS$ millionsUndisbursed
Active operations15207.953.98 of 15 reportedNo total12.3, 1 of 15 ops

Active operations by partner

Table 2.Active energy operations by funding partner, US$ millions

Portfolio of active operations at October 18, 2026
PartnerActive operationsApprovedUS$ millionsDisbursed to dateUS$ millionsUndisbursed
World Bank Group698.415.32 of 6 reportedNo total12.3 for 1 of 6
Green Climate Fund364.21.52 of 3 reportedNot reported
IDB Group437.231.02 of 4 reportedNot reported
United States18.16.0Not reported
Switzerland1<0.1<0.1Not reported
All funding partners15207.953.9No total12.3 for 1 of 15

UN agency spending

Money UN agencies spend in Haiti. Most of it comes from the funding partners above, so it is not added to them. Incomplete data: the agency's latest disbursement is dated more than six months before the data date, or its IATI disbursements in 2025 are below half the humanitarian funding OCHA FTS records it received that year. Its figures are then the sums of what it reports.

Table 3.UN agencies, energy, US$ millions

AgencyDisbursed FY2025-26US$ millionsDisbursed FY2026-27to Oct 18US$ millions
United Nations Development Programmedata to October 20260.1None to date
UN agencies, sum of those reporting0.1None to date

New commitments and disbursements, FY2016-17 to FY2025-26

Sums of the funding partners that report each year, out of 11. A blank cell: nothing recorded for the partner that year.

New commitments reported, US$ millions
FY2016-17, US$3.3 million316-17FY2017-18, US$18.5 million1917-18FY2018-19, US$−11.9 million-1218-19FY2019-20, US$103.6 million10419-20FY2020-21, US$31.1 million3120-21FY2021-22, US$6.0 million621-22FY2022-23, US$4.9 million522-23FY2023-24, US$8.0 million823-24FY2024-25, US$48.6 million4924-25FY2025-26, US$6.8 million725-26FY2026-27, none (to Oct 18)noneto Oct 1826-27FY2016-17, US$3.3 million316-17FY2017-18, US$18.5 million1917-18FY2018-19, US$−11.9 million-1218-19FY2019-20, US$103.6 million10419-20FY2020-21, US$31.1 million3120-21FY2021-22, US$6.0 million621-22FY2022-23, US$4.9 million522-23FY2023-24, US$8.0 million823-24FY2024-25, US$48.6 million4924-25FY2025-26, US$6.8 million725-26FY2026-27, none (to Oct 18)noneto Oct 1826-27
Disbursements reported, US$ millions
FY2016-17, US$39.5 million4016-17FY2017-18, US$22.2 million2217-18FY2018-19, US$19.3 million1918-19FY2019-20, US$13.3 million1319-20FY2020-21, US$19.8 million2020-21FY2021-22, US$4.8 million521-22FY2022-23, US$5.1 million522-23FY2023-24, US$11.2 million1123-24FY2024-25, US$24.0 million2424-25FY2025-26, US$16.3 million1625-26FY2026-27, none (to Oct 18)noneto Oct 1826-27FY2016-17, US$39.5 million4016-17FY2017-18, US$22.2 million2217-18FY2018-19, US$19.3 million1918-19FY2019-20, US$13.3 million1319-20FY2020-21, US$19.8 million2020-21FY2021-22, US$4.8 million521-22FY2022-23, US$5.1 million522-23FY2023-24, US$11.2 million1123-24FY2024-25, US$24.0 million2424-25FY2025-26, US$16.3 million1625-26FY2026-27, none (to Oct 18)noneto Oct 1826-27

Table 4.Disbursements for energy by funding partner, US$ millions

PartnerFY2016-17US$ millionsFY2017-18US$ millionsFY2018-19US$ millionsFY2019-20US$ millionsFY2020-21US$ millionsFY2021-22US$ millionsFY2022-23US$ millionsFY2023-24US$ millionsFY2024-25US$ millionsFY2025-26US$ millionsTen years
World Bank Group5.67.66.14.52.40.80.50.44.58.4
IDB Group18.96.88.75.27.41.1Not reported6.518.47.8
Canada0.2Not reportedNot reported0.20.60.20.30.1Not reportedNot reported
FranceNot reportedNot reportedNot reportedNot reportedNot reported0.10.1Not reportedNot reportedNot reported
Germany6.81.71.90.80.7Not reported0.1Not reportedNot reportedNot reported
Green Climate FundNot reportedNot reportedNot reportedNot reported0.1Not reported0.21.20.1Not reported
SwitzerlandNot reportedNot reportedNot reportedNot reportedNot reportedNot reportedNot reported<0.1<0.1Not reported
United Arab EmiratesNot reportedNot reportedNot reportedNot reportedNot reported0.82.0Not reportedNot reportedNot reported
United Kingdom<0.1Not reportedNot reportedNot reportedNot reportedNot reportedNot reportedNot reportedNot reportedNot reported
United States8.16.12.72.68.71.91.93.10.9Not reported
Sum of partners reporting39.522.219.313.319.84.85.111.224.016.3
Partners reporting, of 11 on record6445667652
New commitments by partnerFY2016-17 to FY2025-26

Table 5.New commitments for energy by funding partner, US$ millions

PartnerFY2016-17US$ millionsFY2017-18US$ millionsFY2018-19US$ millionsFY2019-20US$ millionsFY2020-21US$ millionsFY2021-22US$ millionsFY2022-23US$ millionsFY2023-24US$ millionsFY2024-25US$ millionsFY2025-26US$ millionsTen years
World Bank GroupNot reported14.9−15.34.8Not reported−0.0Not reportedNot reported42.67.1
CanadaNot reportedNot reportedNot reported1.3Not reportedNot reportedNot reportedNot reportedNot reportedNot reported
FranceNot reportedNot reportedNot reportedNot reported0.2Not reportedNot reportedNot reportedNot reportedNot reported
GermanyNot reported<0.1Not reportedNot reportedNot reported<0.1<0.1Not reportedNot reportedNot reported
Green Climate FundNot reportedNot reportedNot reported45.718.5Not reportedNot reportedNot reportedNot reportedNot reported
IDB GroupNot reportedNot reported1.942.55.94.33.05.75.7Not reported
SwitzerlandNot reportedNot reportedNot reportedNot reportedNot reportedNot reportedNot reportedNot reported<0.1Not reported
United Arab EmiratesNot reportedNot reportedNot reportedNot reported3.0Not reportedNot reportedNot reportedNot reportedNot reported
United States3.33.61.59.23.51.61.92.30.2−0.3
Sum of partners reporting3.318.5−11.9103.631.16.04.98.048.66.8
Partners reporting, of 11 on record1335543242

Operations

Active operations (19)

19 operations, 15 of them of funding partners. Funding partners, approved to date (stock): US$207.9 million. Disbursed in FY2025-26 (flow): US$16.3 million, reported for 2 of 15.

List the 19 operations

Closed and stopped operations (120)

120 operations, 112 of them of funding partners. Funding partners, approved to date (stock): US$620.1 million, reported for 107 of 112. Disbursed in FY2025-26 (flow): none. 1 operation counted with its parent operation.

Table 6.Closed and stopped operations, US$ millionsAn operation marked “counted with” is an additional financing whose source books its money under the parent operation: its amounts are in the parent’s row and in the totals once.

Haiti Economic Governance Reform OperationWorld Bank Group, IDAMar 20062005Closed61.061.20.0
Sector
Energy
Stage
Closed
Instrument
IBRD/IDA financing
Lending window
IDA
Approval
January 6, 2005
Effectiveness
January 10, 2005
Closing
March 31, 2006
Disbursed as of
September 30, 2026
Implementing agency
Not reported
Commitment
61.0
Disbursed
61.2
Undisbursed
0.0
Undisbursed gap
−0.2: the IDA statement values undisbursed credits in special drawing rights at the current exchange rate
Operation ID
P089873
Last changed
October 9, 2026
Rebuilding Energy Infrastructure and AccessWorld Bank Group, World BankAug 20202012Closed55.742.60.0
Sector
Energy
Stage
Closed
Instrument
IBRD/IDA financing
Lending window
Grants
Approval
September 27, 2012
Effectiveness
February 6, 2013
Closing
August 31, 2020
Disbursed as of
September 30, 2026
Implementing agency
EDH,MTPTC, UCP Energie
Commitment
55.7
Disbursed
42.6
Undisbursed
0.0
Undisbursed gap
13.1: trust funds are not in the IDA statement, which gives undisbursed amounts for IDA money only; the IDA statement values undisbursed credits in special drawing rights at the current exchange rate
Last transaction
July 31, 2022
Operation ID
P127203
Last changed
October 9, 2026
Rehabilitation of the Péligre hydroelectric power plantGermany, Federal Ministry for Economic Cooperation and Development (BMZ)Jun 20222011Closed38.932.4Not reported
Sector
Energy
Stage
Closed
Instrument
Not reported
Start
February 24, 2011
Effectiveness
Not reported
Closing
June 30, 2022
Disbursed as of
December 31, 2022
Implementing agency
Not reported
Commitment
38.9
Disbursed
32.4
Undisbursed
Not reported
Records at the source
IATI record (d-portal)
Last transaction
December 31, 2022
IATI identifier
DE-1-200967232
Operation and management of the Caracol Power PlantUnited States, USAIDOct 20242013Closed36.236.2Not reported
Sector
Energy
Stage
Closed
Instrument
Definitive contract
Lending window
contracts
Start
May 2, 2013
Effectiveness
Not reported
Closing
October 8, 2024
Disbursed as of
Not reported
Implementing agency
Nreca International
Commitment
36.2
Disbursed
1.5
Undisbursed
Not reported
Records at the source
IATI record (d-portal)
USAspending
USAspending award page
Last transaction
October 31, 2024
Operation ID
AID521C1300007
Institutional Transformation and Modernization Program of the Energy Sector IIDB Group, IDBAug 20112011Closed35.035.0Not reported
Partner
IDB Group, IDB
Sector
Energy
Stage
Closed
Instrument
Grant
Lending window
Sovereign Guaranteed
Approval
July 25, 2011
Effectiveness
Not reported
Closing
August 30, 2011
Disbursed as of
August 31, 2011
Implementing agency
Not reported
Commitment
35.0
Disbursed
35.0
Undisbursed
Not reported
Last transaction
August 31, 2011
Operation ID
HA-L1065
Power III (SDR-23.1)World Bank Group, World BankNot reported1982Closed26.024.90.0
Sector
Energy
Stage
Closed
Instrument
IBRD/IDA financing
Approval
July 6, 1982
Effectiveness
Not reported
Closing
Not reported
Disbursed as of
September 30, 2026
Implementing agency
Not reported
Commitment
26.0
Disbursed
24.9
Undisbursed
0.0
Undisbursed gap
1.1: the IDA statement values undisbursed credits in special drawing rights at the current exchange rate
Operation ID
P007287
Last changed
October 9, 2026
POWER VWorld Bank Group, IDAJan 19991989Closed23.225.50.0
Sector
Energy
Stage
Closed
Instrument
IBRD/IDA financing
Lending window
IDA
Approval
June 27, 1989
Effectiveness
January 16, 1990
Closing
January 31, 1999
Disbursed as of
September 30, 2026
Implementing agency
Not reported
Commitment
23.2
Disbursed
25.5
Undisbursed
0.0
Undisbursed gap
−2.3: the IDA statement values undisbursed credits in special drawing rights at the current exchange rate
Operation ID
P007300
Last changed
October 9, 2026
Power IV-aWorld Bank Group, World BankNot reported1984Closed22.126.70.0
Sector
Energy
Stage
Closed
Instrument
IBRD/IDA financing
Approval
November 20, 1984
Effectiveness
Not reported
Closing
Not reported
Disbursed as of
September 30, 2026
Implementing agency
Not reported
Commitment
22.1
Disbursed
26.7
Undisbursed
0.0
Undisbursed gap
−4.6: the IDA statement values undisbursed credits in special drawing rights at the current exchange rate
Operation ID
P007291
Last changed
October 9, 2026
Institutional Transformation and Modernization Program of the Energy Sector IIIIDB Group, IDBSep 20132013Closed22.022.0Not reported
Partner
IDB Group, IDB
Sector
Energy
Stage
Closed
Instrument
Grant
Lending window
Sovereign Guaranteed
Approval
June 26, 2013
Effectiveness
Not reported
Closing
September 28, 2013
Disbursed as of
September 30, 2013
Implementing agency
Not reported
Commitment
22.0
Disbursed
22.0
Undisbursed
Not reported
Last transaction
September 30, 2013
Operation ID
HA-L1083
Supplementary Financing for the Peligre Hydroelectric PlantIDB Group, IDBApr 20192011Closed20.020.3Not reported
Partner
IDB Group, IDB
Sector
Energy
Stage
Closed
Instrument
Grant
Lending window
Sovereign Guaranteed
Approval
December 14, 2011
Effectiveness
Not reported
Closing
April 20, 2019
Disbursed as of
April 30, 2019
Implementing agency
Not reported
Commitment
20.0
Disbursed
20.3
Undisbursed
Not reported
Last transaction
April 30, 2019
Operation ID
HA-L1038
Rehabilitation of Electricity Distribution System in Port au PrinceIDB Group, IDBJun 20182006Closed18.115.8Not reported
Partner
IDB Group, IDB
Sector
Energy
Stage
Closed
Instrument
Grant
Lending window
Sovereign Guaranteed
Approval
December 6, 2006
Effectiveness
Not reported
Closing
June 19, 2018
Disbursed as of
June 30, 2017
Implementing agency
Not reported
Commitment
18.1
Disbursed
15.8
Undisbursed
Not reported
Last transaction
June 30, 2017
Operation ID
HA-L1014
Semi-autonomous Electricity SupplyCanada, Foreign Affairs, Trade and Development Canada (DFATD)Dec 20132007Closed17.5Not reportedNot reported
Sector
Energy
Stage
Closed
Instrument
Not reported
Start
December 3, 2007
Effectiveness
Not reported
Closing
December 30, 2013
Disbursed as of
Not reported
Implementing agency
Not reported
Commitment
17.5
Disbursed
Not reported
Undisbursed
Not reported
Records at the source
IATI record (d-portal)
Last transaction
December 3, 2007
IATI identifier
CA-3-A032547001
North Park power generation, transmission and distribution facilitiesUnited States, USAIDMay 20132011Closed17.53.1Not reported
Sector
Energy
Stage
Closed
Instrument
Definitive contract
Lending window
contracts
Start
September 14, 2011
Effectiveness
Not reported
Closing
May 31, 2013
Disbursed as of
June 30, 2013
Implementing agency
Esd Engineering & Service S.R.L
Commitment
17.5
Disbursed
3.1
Undisbursed
Not reported
Last transaction
March 31, 2017
Operation ID
AID521C1100001
POWER IIWorld Bank Group, World BankNot reported1979Closed16.516.50.0
Sector
Energy
Stage
Closed
Instrument
IBRD/IDA financing
Approval
April 17, 1979
Effectiveness
Not reported
Closing
Not reported
Disbursed as of
September 30, 2026
Implementing agency
Not reported
Commitment
16.5
Disbursed
16.5
Undisbursed
0.0
Operation ID
P007280
Last changed
October 9, 2026
Rehabilitation of Peligre Transmission LineIDB Group, IDBNot reported2014Closed16.0Not reportedNot reported
Partner
IDB Group, IDB
Sector
Energy
Stage
Closed
Instrument
Investment grant
Lending window
Sovereign Guaranteed
Approval
December 17, 2014
Effectiveness
Not reported
Closing
Not reported
Disbursed as of
Not reported
Implementing agency
Not reported
Commitment
16.0
Disbursed
Not reported
Undisbursed
Not reported
Records at the source
IDB project page
Operation ID
HA-G1030
POWER IWorld Bank Group, World BankNot reported1976Closed16.016.00.0
Sector
Energy
Stage
Closed
Instrument
IBRD/IDA financing
Approval
June 17, 1976
Effectiveness
Not reported
Closing
Not reported
Disbursed as of
September 30, 2026
Implementing agency
Not reported
Commitment
16.0
Disbursed
16.0
Undisbursed
0.0
Operation ID
P007275
Last changed
October 9, 2026
Rehabilitate five substations in Port au PrinceUnited States, USAIDApr 20132011Closed14.97.4Not reported
Sector
Energy
Stage
Closed
Instrument
Definitive contract
Lending window
contracts
Start
July 28, 2011
Effectiveness
Not reported
Closing
April 16, 2013
Disbursed as of
September 30, 2013
Implementing agency
Perini Management Services, Inc.
Commitment
14.9
Disbursed
7.4
Undisbursed
Not reported
Last transaction
September 30, 2013
Operation ID
AID521C001100012
Rehabilitation of the Electricity Distribution System in Port-au-PrinceIDB Group, IDBFeb 20182010Closed14.014.2Not reported
Partner
IDB Group, IDB
Sector
Energy
Stage
Closed
Instrument
Grant
Lending window
Sovereign Guaranteed
Approval
July 21, 2010
Effectiveness
Not reported
Closing
February 16, 2018
Disbursed as of
June 30, 2017
Implementing agency
Not reported
Commitment
14.0
Disbursed
14.2
Undisbursed
Not reported
Last transaction
June 30, 2017
Operation ID
HA-L1035
Reinforcement of transmission lines and road infrastructure rehabilitationIDB Group, IDBNot reported2010Closed12.5Not reportedNot reported
Partner
IDB Group, IDB
Sector
Energy
Stage
Closed
Instrument
Investment grant
Lending window
Sovereign Guaranteed
Approval
November 8, 2010
Effectiveness
Not reported
Closing
Not reported
Disbursed as of
Not reported
Implementing agency
Not reported
Commitment
12.5
Disbursed
Not reported
Undisbursed
Not reported
Records at the source
IDB project page
Operation ID
HA-G1022
Péligre Hydroelectric Plant Rehabilitation ProgramIDB Group, IDBDec 20162008Closed12.532.3Not reported
Partner
IDB Group, IDB
Sector
Energy
Stage
Closed
Instrument
Grant
Lending window
Sovereign Guaranteed
Approval
December 2, 2008
Effectiveness
Not reported
Closing
December 30, 2016
Disbursed as of
September 30, 2019
Implementing agency
Not reported
Commitment
12.5
Disbursed
32.3
Undisbursed
Not reported
Last transaction
September 30, 2019
Operation ID
HA-L1032
Institutional Transformation and Modernization Program of the Energy Sector IIIDB Group, IDBJul 20122012Closed12.012.0Not reported
Partner
IDB Group, IDB
Sector
Energy
Stage
Closed
Instrument
Grant
Lending window
Sovereign Guaranteed
Approval
June 6, 2012
Effectiveness
Not reported
Closing
July 26, 2012
Disbursed as of
July 31, 2012
Implementing agency
Not reported
Commitment
12.0
Disbursed
12.0
Undisbursed
Not reported
Last transaction
July 31, 2012
Operation ID
HA-L1073
HT Electricity ProjectWorld Bank Group, IDAAug 20132006Closed9.910.30.0
Sector
Energy
Stage
Closed
Instrument
IBRD/IDA financing
Lending window
IDA
Approval
August 3, 2006
Effectiveness
July 31, 2007
Closing
August 31, 2013
Disbursed as of
September 30, 2026
Implementing agency
Not reported
Commitment
9.9
Disbursed
10.3
Undisbursed
0.0
Undisbursed gap
−0.4: the IDA statement values undisbursed credits in special drawing rights at the current exchange rate
Operation ID
P098531
Last changed
October 9, 2026
Rehabilitation of the Peligre Transmission LineIDB Group, IDBDec 20192014Closed7.77.8Not reported
Partner
IDB Group, IDB
Sector
Energy
Stage
Closed
Instrument
Grant
Lending window
Sovereign Guaranteed
Approval
December 17, 2014
Effectiveness
Not reported
Closing
December 27, 2019
Disbursed as of
November 30, 2020
Implementing agency
Not reported
Commitment
7.7
Disbursed
7.8
Undisbursed
Not reported
Last transaction
November 30, 2020
Operation ID
HA-L1100
Improving Electricity AccessIDB Group, IDBNot reported2019Closed6.5Not reportedNot reported
Partner
IDB Group, IDB
Sector
Energy
Stage
ClosedRecorded as active with no closing date; the last transaction is dated November 13, 2019.
Instrument
Investment grant
Lending window
Sovereign Guaranteed
Approval
November 13, 2019
Effectiveness
Not reported
Closing
Not reported
Disbursed as of
Not reported
Implementing agency
Not reported
Commitment
6.5
Disbursed
Not reported
Undisbursed
Not reported
Records at the source
IDB project page
Operation ID
HA-G1045
4-MEGAWATT solar electricity generation plant at Caracol industrial parkUnited States, USAIDAug 20262020Closed6.26.2Not reported
Sector
Energy
Stage
Closed
Instrument
Other reimbursable, contingent, intangible, or indirect financial assistance
Lending window
other
Start
August 27, 2020
Effectiveness
Not reported
Closing
August 26, 2026
Disbursed as of
Not reported
Implementing agency
Inter-American Development Bank
Commitment
6.2
Disbursed
6.5
Undisbursed
Not reported
Last transaction
August 12, 2026
Operation ID
72052120IO00002
25 more operations
WINECO 2IDB Group, IDB InvestNot reported2021Closed5.75.7Not reported
Sector
Energy
Stage
Closed
Instrument
Not reported
Start
June 29, 2021
Effectiveness
Not reported
Closing
Not reported
Disbursed as of
June 29, 2021
Implementing agency
Not reported
Commitment
5.7
Disbursed
5.7
Undisbursed
Not reported
Records at the source
IATI record (d-portal)
IATI
Last transaction
June 29, 2021
Operation ID
12165-01
BarbancourtIDB Group, IDB InvestNot reported2023Closed5.05.0Not reported
Sector
Energy
Stage
ClosedRecorded as active with no closing date; the last transaction is dated November 21, 2023.
Instrument
Not reported
Start
November 21, 2023
Effectiveness
Not reported
Closing
Not reported
Disbursed as of
November 21, 2023
Implementing agency
Not reported
Commitment
5.0
Disbursed
5.0
Undisbursed
Not reported
Records at the source
IATI record (d-portal)
IATI
Last transaction
November 21, 2023
Operation ID
14545-01
HT (AF) Electricity Loss Reduction ProjectWorld Bank Group, IDAAug 20132009ClosedCounted with P098531Counted with P098531Counted with P098531
Sector
Energy
Stage
Closed
Instrument
IBRD/IDA financing
Lending window
IDA
Approval
September 8, 2009
Effectiveness
December 15, 2009
Closing
August 31, 2013
Disbursed as of
Not reported
Implementing agency
Not reported
Commitment
5.0
Disbursed
Not reported
Undisbursed
Not reported
Records at the source
World Bank project page
Operation ID
P112164
DelimartIDB Group, IDB InvestNot reported2019Stopped4.54.5Not reported
Sector
Energy
Stage
Stopped
Instrument
Not reported
Start
October 23, 2019
Effectiveness
Not reported
Closing
Not reported
Disbursed as of
October 23, 2019
Implementing agency
Not reported
Commitment
4.5
Disbursed
4.5
Undisbursed
Not reported
Records at the source
IATI record (d-portal)
IATI
Last transaction
October 23, 2019
Operation ID
12485-01
Rehabilitation of Electrical FacilitiesCanada, Foreign Affairs, Trade and Development Canada (DFATD)Dec 20122005Closed4.1Not reportedNot reported
Sector
Energy
Stage
Closed
Instrument
Not reported
Start
November 21, 2005
Effectiveness
Not reported
Closing
December 31, 2012
Disbursed as of
Not reported
Implementing agency
Not reported
Commitment
4.1
Disbursed
Not reported
Undisbursed
Not reported
Records at the source
IATI record (d-portal)
Last transaction
November 21, 2005
IATI identifier
CA-3-A032970001
Technical Assistance (Jacmel) - Phase IIICanada, Foreign Affairs, Trade and Development Canada (DFATD)Mar 20112005Closed4.0Not reportedNot reported
Sector
Energy
Stage
Closed
Instrument
Not reported
Start
March 11, 2005
Effectiveness
Not reported
Closing
March 31, 2011
Disbursed as of
Not reported
Implementing agency
Not reported
Commitment
4.0
Disbursed
Not reported
Undisbursed
Not reported
Records at the source
IATI record (d-portal)
Last transaction
March 11, 2005
IATI identifier
CA-3-A032087001
AEF-I-P10000353-002FMO NV (Nederlandse Financierings-Maatschappij voor Ontwikkelingslanden N.V.)Mar 20242009Closed4.04.0Not reported
Sector
Energy
Stage
Closed
Instrument
Not reported
Start
July 1, 2009
Effectiveness
Not reported
Closing
March 15, 2024
Disbursed as of
July 1, 2009
Implementing agency
Not reported
Commitment
4.0
Disbursed
4.0
Undisbursed
Not reported
Records at the source
IATI record (d-portal)
IATI
Last transaction
July 1, 2009
IATI identifier
NL-KVK-27078545-0000116541
SRUC task order under clean energy non-CPC IQC.United States, USAIDSep 20212012Closed3.63.6Not reported
Sector
Energy
Stage
ClosedRecorded as active; the publisher reports the activity finalised.
Instrument
Not reported
Haiti share
39% of a 9.3 multi-country award
Start
December 10, 2012
Effectiveness
Not reported
Closing
September 9, 2021
Disbursed as of
March 31, 2022
Implementing agency
Not reported
Commitment
3.6
Disbursed
3.6
Undisbursed
Not reported
Records at the source
IATI record (d-portal)
Last transaction
March 31, 2022
Operation ID
AIDOAATO1400006
Operate and maintain the 10-MW generation plant and distribution gridUnited States, USAIDSep 20242020Closed3.53.5Not reported
Sector
Energy
Stage
Closed
Instrument
Definitive contract
Lending window
contracts
Start
February 1, 2020
Effectiveness
Not reported
Closing
September 29, 2024
Disbursed as of
Not reported
Implementing agency
Nreca International
Commitment
3.5
Disbursed
3.5
Undisbursed
Not reported
Records at the source
IATI record (d-portal)
USAspending
USAspending award page
Last transaction
September 29, 2024
Operation ID
72052120C00002
Institutional Transformation and Modernization of the Energy Sector IIIIDB Group, IDBNot reported2013Closed3.0Not reportedNot reported
Partner
IDB Group, IDB
Sector
Energy
Stage
Closed
Instrument
Investment grant
Lending window
Sovereign Guaranteed
Approval
June 26, 2013
Effectiveness
Not reported
Closing
Not reported
Disbursed as of
Not reported
Implementing agency
Not reported
Commitment
3.0
Disbursed
Not reported
Undisbursed
Not reported
Records at the source
IDB project page
Operation ID
HA-G1027
Solar PV ground mount and battery storage for the rural village of DondonUnited Arab Emirates, UAE Ministry of Foreign AffairsDec 20222021Closed3.02.7Not reported
Sector
Energy
Stage
Closed
Instrument
Not reported
Start
January 20, 2021
Effectiveness
Not reported
Closing
December 31, 2022
Disbursed as of
December 31, 2022
Implementing agency
Not reported
Commitment
3.0
Disbursed
2.7
Undisbursed
Not reported
Records at the source
IATI record (d-portal)
IATI
Last transaction
December 31, 2022
IATI identifier
XM-DAC-576-4290
Energy Utility Partnership - USEAUnited States, USAIDSep 20182007Closed2.93.4Not reported
Sector
Energy
Stage
ClosedRecorded as active; the publisher reports the activity finalised.
Instrument
Not reported
Haiti share
14% of a 21.3 multi-country award
Start
September 30, 2007
Effectiveness
Not reported
Closing
September 30, 2018
Disbursed as of
December 31, 2018
Implementing agency
Not reported
Commitment
2.9
Disbursed
3.4
Undisbursed
Not reported
Records at the source
IATI record (d-portal)
Last transaction
December 31, 2018
Operation ID
AIDEPPA000700008
Last changed
October 16, 2026
Battery Energy Storage System to maximize the use of surplus energyIDB Group, IDBNot reported2021Closed2.7Not reportedNot reported
Partner
IDB Group, IDB
Sector
Energy
Stage
ClosedRecorded as active with no closing date; the last transaction is dated December 16, 2021.
Instrument
Investment grant
Lending window
Sovereign Guaranteed
Approval
December 16, 2021
Effectiveness
Not reported
Closing
Not reported
Disbursed as of
Not reported
Implementing agency
Not reported
Commitment
2.7
Disbursed
Not reported
Undisbursed
Not reported
Records at the source
IDB project page
Operation ID
HA-G1048
Sustainable energy access projects with private sector participationIDB Group, IDBNot reported2022Closed2.5Not reportedNot reported
Partner
IDB Group, IDB
Sector
Energy
Stage
ClosedRecorded as active with no closing date; the last transaction is dated December 14, 2022.
Instrument
Investment grant
Lending window
Sovereign Guaranteed
Approval
December 14, 2022
Effectiveness
Not reported
Closing
Not reported
Disbursed as of
Not reported
Implementing agency
Not reported
Commitment
2.5
Disbursed
Not reported
Undisbursed
Not reported
Records at the source
IDB project page
Operation ID
HA-G1053
Energy Sector Reform ProjectUnited States, USAIDSep 20172003Closed2.47.2Not reported
Sector
Energy
Stage
ClosedRecorded as active; the publisher reports the activity finalised.
Instrument
Not reported
Start
September 30, 2003
Effectiveness
Not reported
Closing
September 30, 2017
Disbursed as of
March 31, 2015
Implementing agency
Not reported
Commitment
2.4
Disbursed
7.2
Undisbursed
Not reported
Records at the source
IATI record (d-portal)
Last transaction
June 30, 2017
Operation ID
521EPPI090300008
North power DISTRIBUTION-PH1United States, USAIDJun 20142012Closed2.41.9Not reported
Sector
Energy
Stage
Closed
Instrument
Cooperative agreement (B)
Lending window
grants
Start
January 17, 2012
Effectiveness
Not reported
Closing
June 30, 2014
Disbursed as of
December 31, 2019
Implementing agency
Nreca International
Commitment
2.4
Disbursed
1.9
Undisbursed
Not reported
Last transaction
September 30, 2020
Operation ID
AID521A1200005
Transmission and distribution materials for PPSELD expansionUnited States, USAIDSep 20152014Closed2.32.3Not reported
Sector
Energy
Stage
Closed
Instrument
Purchase order
Lending window
contracts
Start
December 8, 2014
Effectiveness
Not reported
Closing
September 30, 2015
Disbursed as of
June 30, 2016
Implementing agency
Universal Trading & Engineering Corporation
Commitment
2.3
Disbursed
2.3
Undisbursed
Not reported
Last transaction
September 30, 2016
Operation ID
AID521O1500005
Emergency program for solar power generation and lightingGlobal Environment FacilityApr 20142010Closed2.0Not reportedNot reported
Sector
Energy
Stage
ClosedRecorded as active; the publisher reports the activity finalised.
Instrument
Not reported
Start
March 16, 2010
Effectiveness
Not reported
Closing
April 30, 2014
Disbursed as of
Not reported
Implementing agency
Not reported
Commitment
2.0
Disbursed
Not reported
Undisbursed
Not reported
Records at the source
IATI record (d-portal)
IATI
Last transaction
January 27, 2010
IATI identifier
XI-BRIDGE-6385676864-4219
Sustainable Energy for HaitiIDB Group, IDBNot reported2013Closed2.0Not reportedNot reported
Partner
IDB Group, IDB
Sector
Energy
Stage
Closed
Instrument
Technical cooperation
Lending window
Sovereign Guaranteed
Approval
May 22, 2013
Effectiveness
Not reported
Closing
Not reported
Disbursed as of
Not reported
Implementing agency
Not reported
Commitment
2.0
Disbursed
Not reported
Undisbursed
Not reported
Records at the source
IDB project page
Operation ID
HA-T1183
Feasib., Hydroelec. Project la ChapelleIDB Group, IDBNot reported1980Closed1.8Not reportedNot reported
Partner
IDB Group, IDB
Sector
Energy
Stage
Closed
Instrument
Technical cooperation
Lending window
Sovereign Guaranteed
Approval
May 29, 1980
Effectiveness
Not reported
Closing
Not reported
Disbursed as of
Not reported
Implementing agency
Not reported
Commitment
1.8
Disbursed
Not reported
Undisbursed
Not reported
Records at the source
IDB project page
Operation ID
TC8001159
Inst. Strengt., Oficina Minas y EnergiaIDB Group, IDBNot reported1984Closed1.6Not reportedNot reported
Partner
IDB Group, IDB
Sector
Energy
Stage
Closed
Instrument
Technical cooperation
Lending window
Sovereign Guaranteed
Approval
November 28, 1984
Effectiveness
Not reported
Closing
Not reported
Disbursed as of
Not reported
Implementing agency
Not reported
Commitment
1.6
Disbursed
Not reported
Undisbursed
Not reported
Records at the source
IDB project page
Operation ID
TC8308076
Artibonite 4C Hydroelectric Project - StudiesIDB Group, IDBNot reported2012Closed1.5Not reportedNot reported
Partner
IDB Group, IDB
Sector
Energy
Stage
Closed
Instrument
Technical cooperation
Lending window
Sovereign Guaranteed
Approval
May 22, 2012
Effectiveness
Not reported
Closing
Not reported
Disbursed as of
Not reported
Implementing agency
Not reported
Commitment
1.5
Disbursed
Not reported
Undisbursed
Not reported
Records at the source
IDB project page
Operation ID
HA-T1150
Sigora Haiti Microutility ProjectIDB Group, IDB InvestNot reported2019Closed1.51.5Not reported
Sector
Energy
Stage
ClosedRecorded as active with no closing date; the last transaction is dated February 5, 2019.
Instrument
Not reported
Start
February 5, 2019
Effectiveness
Not reported
Closing
Not reported
Disbursed as of
February 5, 2019
Implementing agency
Not reported
Commitment
1.5
Disbursed
1.5
Undisbursed
Not reported
Records at the source
IATI record (d-portal)
IATI
Last transaction
February 5, 2019
Operation ID
12190-01
Improving Gender Equality, Waste Management and Clean EnergyCanada, Foreign Affairs, Trade and Development Canada (DFATD)May 20232020Closed1.31.4Not reported
Sector
Energy
Stage
Closed
Instrument
Not reported
Start
February 5, 2020
Effectiveness
Not reported
Closing
May 11, 2023
Disbursed as of
December 27, 2023
Implementing agency
Not reported
Commitment
1.3
Disbursed
1.4
Undisbursed
Not reported
Records at the source
IATI record (d-portal)
IATI
Last transaction
December 27, 2023
IATI identifier
CA-3-P005985001
Support to the sustainable operation of the Peligre Electric power systemIDB Group, IDBNot reported2021Closed1.3Not reportedNot reported
Partner
IDB Group, IDB
Sector
Energy
Stage
ClosedRecorded as active with no closing date; the last transaction is dated December 10, 2021.
Instrument
Technical cooperation
Lending window
Sovereign Guaranteed
Approval
December 10, 2021
Effectiveness
Not reported
Closing
Not reported
Disbursed as of
Not reported
Implementing agency
Not reported
Commitment
1.3
Disbursed
Not reported
Undisbursed
Not reported
Records at the source
IDB project page
Operation ID
HA-T1300

Operations 1 to 50 of 120 are listed, largest commitment first. Next operations

Sources

Data as of October 18, 2026
SourceRead on
fts:2021:summary_gapOctober 18, 2026
Exchange rates (Federal Reserve, IMF)October 18, 2026
IATIOctober 18, 2026
IATIOctober 18, 2026
IDA Statement of Credits and GrantsOctober 18, 2026
IDB projects datasetOctober 18, 2026
IFC Finances OneOctober 18, 2026
Public investment programOctober 18, 2026
USAspendingOctober 11, 2026
USAspendingOctober 18, 2026
World Bank procurement noticesOctober 11, 2026
World Bank ProjectsOctober 18, 2026
OCHA FTS, 2010 to 2026October 18, 2026
Cite this page

HaitiDocs. Energy. Partner portfolio, data as of October 18, 2026. https://www.haitidocs.org/portfolio/sectors/energy