Data / Partner portfolio / Sectors
Energy
15 active operations of funding partners. US$ millions unless stated. Haitian fiscal year, October to September. FY2026-27 began October 1, 2026.
Browse this sector's operations
Disbursed in FY2025-26
As each source records them; 2 of the 11 funding partners on record report them
New commitments in FY2025-26
Approved or obligated, net of reductions; 2 of the 11 funding partners on record report them
Active portfolio at October 18, 2026
15 of 15 active operations report an approved amount
Portfolio at October 18, 2026
A position at the data date: approved is every commitment to date on the operations, cancellations deducted; disbursed to date and undisbursed are as each partner publishes them.
Table 1.Portfolio of active operations at October 18, 2026, US$ millions
| Operations | ApprovedUS$ millions | Disbursed to dateUS$ millions | Undisbursed | |
|---|---|---|---|---|
| Active operations | 15 | 207.9 | 53.98 of 15 reported | No total12.3, 1 of 15 ops |
Active operations by partner
Table 2.Active energy operations by funding partner, US$ millions
| Portfolio of active operations at October 18, 2026 | ||||
|---|---|---|---|---|
| Partner | Active operations | ApprovedUS$ millions | Disbursed to dateUS$ millions | Undisbursed |
| World Bank Group | 6 | 98.4 | 15.32 of 6 reported | No total12.3 for 1 of 6 |
| Green Climate Fund | 3 | 64.2 | 1.52 of 3 reported | Not reported |
| IDB Group | 4 | 37.2 | 31.02 of 4 reported | Not reported |
| United States | 1 | 8.1 | 6.0 | Not reported |
| Switzerland | 1 | <0.1 | <0.1 | Not reported |
| All funding partners | 15 | 207.9 | 53.9 | No total12.3 for 1 of 15 |
UN agency spending
Money UN agencies spend in Haiti. Most of it comes from the funding partners above, so it is not added to them. Incomplete data: the agency's latest disbursement is dated more than six months before the data date, or its IATI disbursements in 2025 are below half the humanitarian funding OCHA FTS records it received that year. Its figures are then the sums of what it reports.
Table 3.UN agencies, energy, US$ millions
| Agency | Disbursed FY2025-26US$ millions | Disbursed FY2026-27to Oct 18US$ millions |
|---|---|---|
| United Nations Development Programmedata to October 2026 | 0.1 | None to date |
| UN agencies, sum of those reporting | 0.1 | None to date |
New commitments and disbursements, FY2016-17 to FY2025-26
Sums of the funding partners that report each year, out of 11. A blank cell: nothing recorded for the partner that year.
Table 4.Disbursements for energy by funding partner, US$ millions
| Partner | FY2016-17US$ millions | FY2017-18US$ millions | FY2018-19US$ millions | FY2019-20US$ millions | FY2020-21US$ millions | FY2021-22US$ millions | FY2022-23US$ millions | FY2023-24US$ millions | FY2024-25US$ millions | FY2025-26US$ millions | Ten years |
|---|---|---|---|---|---|---|---|---|---|---|---|
| World Bank Group | 5.6 | 7.6 | 6.1 | 4.5 | 2.4 | 0.8 | 0.5 | 0.4 | 4.5 | 8.4 | |
| IDB Group | 18.9 | 6.8 | 8.7 | 5.2 | 7.4 | 1.1 | Not reported | 6.5 | 18.4 | 7.8 | |
| Canada | 0.2 | Not reported | Not reported | 0.2 | 0.6 | 0.2 | 0.3 | 0.1 | Not reported | Not reported | |
| France | Not reported | Not reported | Not reported | Not reported | Not reported | 0.1 | 0.1 | Not reported | Not reported | Not reported | |
| Germany | 6.8 | 1.7 | 1.9 | 0.8 | 0.7 | Not reported | 0.1 | Not reported | Not reported | Not reported | |
| Green Climate Fund | Not reported | Not reported | Not reported | Not reported | 0.1 | Not reported | 0.2 | 1.2 | 0.1 | Not reported | |
| Switzerland | Not reported | Not reported | Not reported | Not reported | Not reported | Not reported | Not reported | <0.1 | <0.1 | Not reported | |
| United Arab Emirates | Not reported | Not reported | Not reported | Not reported | Not reported | 0.8 | 2.0 | Not reported | Not reported | Not reported | |
| United Kingdom | <0.1 | Not reported | Not reported | Not reported | Not reported | Not reported | Not reported | Not reported | Not reported | Not reported | |
| United States | 8.1 | 6.1 | 2.7 | 2.6 | 8.7 | 1.9 | 1.9 | 3.1 | 0.9 | Not reported | |
| Sum of partners reporting | 39.5 | 22.2 | 19.3 | 13.3 | 19.8 | 4.8 | 5.1 | 11.2 | 24.0 | 16.3 | |
| Partners reporting, of 11 on record | 6 | 4 | 4 | 5 | 6 | 6 | 7 | 6 | 5 | 2 |
New commitments by partnerFY2016-17 to FY2025-26
Table 5.New commitments for energy by funding partner, US$ millions
| Partner | FY2016-17US$ millions | FY2017-18US$ millions | FY2018-19US$ millions | FY2019-20US$ millions | FY2020-21US$ millions | FY2021-22US$ millions | FY2022-23US$ millions | FY2023-24US$ millions | FY2024-25US$ millions | FY2025-26US$ millions | Ten years |
|---|---|---|---|---|---|---|---|---|---|---|---|
| World Bank Group | Not reported | 14.9 | −15.3 | 4.8 | Not reported | −0.0 | Not reported | Not reported | 42.6 | 7.1 | |
| Canada | Not reported | Not reported | Not reported | 1.3 | Not reported | Not reported | Not reported | Not reported | Not reported | Not reported | |
| France | Not reported | Not reported | Not reported | Not reported | 0.2 | Not reported | Not reported | Not reported | Not reported | Not reported | |
| Germany | Not reported | <0.1 | Not reported | Not reported | Not reported | <0.1 | <0.1 | Not reported | Not reported | Not reported | |
| Green Climate Fund | Not reported | Not reported | Not reported | 45.7 | 18.5 | Not reported | Not reported | Not reported | Not reported | Not reported | |
| IDB Group | Not reported | Not reported | 1.9 | 42.5 | 5.9 | 4.3 | 3.0 | 5.7 | 5.7 | Not reported | |
| Switzerland | Not reported | Not reported | Not reported | Not reported | Not reported | Not reported | Not reported | Not reported | <0.1 | Not reported | |
| United Arab Emirates | Not reported | Not reported | Not reported | Not reported | 3.0 | Not reported | Not reported | Not reported | Not reported | Not reported | |
| United States | 3.3 | 3.6 | 1.5 | 9.2 | 3.5 | 1.6 | 1.9 | 2.3 | 0.2 | −0.3 | |
| Sum of partners reporting | 3.3 | 18.5 | −11.9 | 103.6 | 31.1 | 6.0 | 4.9 | 8.0 | 48.6 | 6.8 | |
| Partners reporting, of 11 on record | 1 | 3 | 3 | 5 | 5 | 4 | 3 | 2 | 4 | 2 |
Operations
Active operations (19)
19 operations, 15 of them of funding partners. Funding partners, approved to date (stock): US$207.9 million. Disbursed in FY2025-26 (flow): US$16.3 million, reported for 2 of 15.
Table 6.Active operations, largest commitment first, US$ millions
Renewable Energy for AllJun 202750.112.312.3
- Partner
- World Bank Group, World Bank
- Sector
- Energy
- Stage
- Under way
- Instrument
- Recipient-executed trust fund grant
- Lending window
- Grants
- Approval
- October 25, 2017
- Effectiveness
- July 23, 2018
- Closing
- June 30, 2027
- Disbursed as of
- September 30, 2026
- Implementing agency
- MTPTC Energy Cell,Ministry of Public Works, Transportation and Communication
- Commitment
- 50.1
- Disbursed
- 12.3
- Undisbursed
- 12.3
- Undisbursed gap
- 25.4: trust funds are not in the IDA statement, which gives undisbursed amounts for IDA money only; the IDA statement values undisbursed credits in special drawing rights at the current exchange rate
- Records at the source
- Partner documents
IATI record (d-portal)
IATI
IDA statement of credits and grants (dataset)
World Bank procurement notices
World Bank project page - Last transaction
- June 30, 2026
- Operation ID
- P156719
Scaling Smart, Solar, Energy Access MicrogridsSep 202845.7Not reportedNot reported
- Partner
- Green Climate Fund
- Sector
- Energy
- Stage
- Approved
- Instrument
- Not reported
- Planned start
- March 12, 2020
- Effectiveness
- Not reported
- Closing
- September 12, 2028
- Disbursed as of
- Not reported
- Implementing agency
- Not reported
- Commitment
- 45.7
- Disbursed
- Not reported
- Undisbursed
- Not reported
- Records at the source
- IATI record (d-portal)
IATI - Last transaction
- March 12, 2020
- IATI identifier
Additional Financing: Haiti Renewable Energy For AllJun 202719.6Not reportedNot reported
- Partner
- World Bank Group, World Bank
- Sector
- Energy
- Stage
- Under way
- Instrument
- IBRD/IDA financing
- Lending window
- Grants
- Approval
- October 18, 2024
- Effectiveness
- April 22, 2025
- Closing
- June 30, 2027
- Disbursed as of
- Not reported
- Implementing agency
- MTPTC Energy Cell,Ministry of Public Works, Transportation and Communication
- Commitment
- 39.6
- Disbursed
- Not reported
- Undisbursed
- Not reported
- Records at the source
- World Bank project page
- Operation ID
- P181584
Improving Electricity AccessDec 202631.528.0Not reported
- Sector
- Energy
- Stage
- Under way
- Instrument
- Grant
- Lending window
- Sovereign Guaranteed
- Approval
- November 13, 2019
- Effectiveness
- Not reported
- Closing
- December 10, 2026
- Disbursed as of
- May 31, 2026
- Implementing agency
- Not reported
- Commitment
- 31.5
- Disbursed
- 28.0
- Undisbursed
- Not reported
- Records at the source
- Partner documents
IATI record (d-portal)
IATI
IDB project page - Last transaction
- May 31, 2026
- Operation ID
- HA-L1140
Global Subnational Climate Fund (SnCF Global) – EquityApr 204017.91.2Not reported
- Partner
- Green Climate Fund
- Sector
- Energy
- Stage
- Under way
- Instrument
- Not reported
- Haiti share
- 2% of a 750.0 multi-country award
- Planned start
- November 13, 2020
- Effectiveness
- Not reported
- Closing
- April 20, 2040
- Disbursed as of
- November 23, 2023
- Implementing agency
- Not reported
- Commitment
- 17.9
- Disbursed
- 1.2
- Undisbursed
- Not reported
- Records at the source
- IATI record (d-portal)
IATI - Last transaction
- November 23, 2023
- IATI identifier
Haiti Modern Energy Services For AllApr 202815.7Not reportedNot reported
- Partner
- World Bank Group, World Bank
- Sector
- Energy
- Stage
- Under way
- Instrument
- Recipient-executed trust fund grant
- Lending window
- Grants
- Approval
- October 25, 2017
- Effectiveness
- February 5, 2018
- Closing
- April 30, 2028
- Disbursed as of
- Not reported
- Implementing agency
- MTPTC - Ministry of Public Works, Transport and Communications
- Commitment
- 15.7
- Disbursed
- Not reported
- Undisbursed
- Not reported
- Records at the source
- Partner documents
World Bank procurement notices
World Bank project page - Operation ID
- P154351
Reduce the cases of malariaDec 202515.215.2Not reported
- Sector
- Energy
- Stage
- Closing
- Instrument
- Not reported
- Start
- January 1, 2021
- Effectiveness
- Not reported
- Closing
- December 31, 2025
- Disbursed as of
- December 31, 2025
- Implementing agency
- Not reported
- Commitment
- 15.2
- Disbursed
- 15.2
- Undisbursed
- Not reported
- Records at the source
- IATI record (d-portal)
- Last transaction
- September 30, 2026
- IATI identifier
Technical, Operational and Programmatic Support (TOPS)Jul 20268.16.0Not reported
- Partner
- United States, USAID
- Sector
- Energy
- Stage
- Closing
- Instrument
- Not reported
- Haiti share
- 71% of a 11.4 multi-country award
- Start
- July 15, 2021
- Effectiveness
- Not reported
- Closing
- July 14, 2026
- Disbursed as of
- June 30, 2025
- Implementing agency
- Not reported
- Commitment
- 8.1
- Disbursed
- 6.0
- Undisbursed
- Not reported
- Records at the source
- IATI record (d-portal)
- Last transaction
- June 30, 2025
- Operation ID
- 7200AA21N00001
- Last changed
- October 16, 2026
Renewable Energy for AllNot reported7.1Not reportedNot reported
- Partner
- World Bank Group, World Bank
- Sector
- Energy
- Stage
- Approved
- Instrument
- Recipient-executed trust fund grant
- Lending window
- Grants
- Approval
- October 30, 2025
- Effectiveness
- Not reported
- Closing
- Not reported
- Disbursed as of
- Not reported
- Implementing agency
- Not reported
- Commitment
- 7.1
- Disbursed
- Not reported
- Undisbursed
- Not reported
- Records at the source
- World Bank project page
- Operation ID
- P510191
Access to electricityJun 20256.97.0Not reported
- Sector
- Energy
- Stage
- Closing
- Instrument
- Not reported
- Start
- January 3, 2018
- Effectiveness
- Not reported
- Closing
- June 30, 2025
- Disbursed as of
- September 30, 2026
- Implementing agency
- Not reported
- Commitment
- 6.9
- Disbursed
- 7.0
- Undisbursed
- Not reported
- Records at the source
- IATI record (d-portal)
IATI - Last transaction
- September 30, 2026
- IATI identifier
Additional Financing Haiti Renewable Energy for AllJun 20272.9Not reportedNot reported
- Partner
- World Bank Group, World Bank
- Sector
- Energy
- Stage
- Under way
- Instrument
- IBRD/IDA financing
- Lending window
- Grants
- Approval
- September 30, 2020
- Effectiveness
- December 10, 2020
- Closing
- June 30, 2027
- Disbursed as of
- Not reported
- Implementing agency
- MTPTC Energy Cell,Ministry of Public Works, Transportation and Communication
- Commitment
- 6.9
- Disbursed
- Not reported
- Undisbursed
- Not reported
- Records at the source
- World Bank project page
- Operation ID
- P174736
Solengy Haiti: Co-Loan for Solar PV SolutionsNot reported3.03.0Not reported
- Partner
- IDB Group, IDB Invest
- Sector
- Energy
- Stage
- Under way
- Instrument
- Not reported
- Start
- December 13, 2024
- Effectiveness
- Not reported
- Closing
- Not reported
- Disbursed as of
- December 13, 2024
- Implementing agency
- Not reported
- Commitment
- 3.0
- Disbursed
- 3.0
- Undisbursed
- Not reported
- Records at the source
- IATI record (d-portal)
IATI - Last transaction
- December 13, 2024
- Operation ID
- 14715-01
Solengy HaitiNot reported3.03.0Not reported
- Partner
- World Bank Group, IFC
- Sector
- Energy
- Stage
- Under way
- Instrument
- Loan
- Lending window
- Loan
- Approval
- December 5, 2024
- Effectiveness
- March 14, 2025
- Closing
- Not reported
- Disbursed as of
- December 20, 2024
- Implementing agency
- Not reported
- Commitment
- 3.0
- Disbursed
- 3.0
- Undisbursed
- Not reported
- Records at the source
- IATI record (d-portal)
IATI
IFC project page - Last transaction
- December 20, 2024
- Operation ID
- 49360
Additional solar photovoltaic capacity to replace fossil fuelNot reported2.5Not reportedNot reported
- Sector
- Energy
- Stage
- Under way
- Instrument
- Investment grant
- Lending window
- Sovereign Guaranteed
- Approval
- November 6, 2024
- Effectiveness
- Not reported
- Closing
- Not reported
- Disbursed as of
- Not reported
- Implementing agency
- Not reported
- Commitment
- 2.5
- Disbursed
- Not reported
- Undisbursed
- Not reported
- Records at the source
- IDB project page
- Operation ID
- HA-G1060
Global Subnational Climate Fund, technical assistance facilityApr 20280.60.3Not reported
- Partner
- Green Climate Fund
- Sector
- Energy
- Stage
- Under way
- Instrument
- Not reported
- Haiti share
- 2% of a 26.6 multi-country award
- Planned start
- November 13, 2020
- Effectiveness
- Not reported
- Closing
- April 20, 2028
- Disbursed as of
- July 23, 2025
- Implementing agency
- Not reported
- Commitment
- 0.6
- Disbursed
- 0.3
- Undisbursed
- Not reported
- Records at the source
- IATI record (d-portal)
IATI - Last transaction
- July 23, 2025
- IATI identifier
- Last changed
- October 16, 2026
Capitalization of ERAF achievementsDec 20260.20.2Not reported
- Sector
- Energy
- Stage
- Under way
- Instrument
- Not reported
- Start
- January 1, 2024
- Effectiveness
- Not reported
- Closing
- December 31, 2026
- Disbursed as of
- January 31, 2026
- Implementing agency
- Not reported
- Commitment
- 0.2
- Disbursed
- 0.2
- Undisbursed
- Not reported
- Records at the source
- IATI record (d-portal)
- Last transaction
- September 30, 2026
- IATI identifier
3 more active operations
Support to the execution and preparation of rural electrification projectsNot reported0.2Not reportedNot reported
- Sector
- Energy
- Stage
- Under way
- Instrument
- Technical cooperation
- Lending window
- Sovereign Guaranteed
- Approval
- July 29, 2025
- Effectiveness
- Not reported
- Closing
- Not reported
- Disbursed as of
- Not reported
- Implementing agency
- Not reported
- Commitment
- 0.2
- Disbursed
- Not reported
- Undisbursed
- Not reported
- Records at the source
- IDB project page
- Operation ID
- HA-T1348
HT:Kako's Kids_Football tournament - small action creditDec 2025<0.1<0.1Not reported
- Sector
- Energy
- Stage
- Closing
- Instrument
- Not reported
- Start
- January 1, 2025
- Effectiveness
- Not reported
- Closing
- December 31, 2025
- Disbursed as of
- December 31, 2024
- Implementing agency
- Not reported
- Commitment
- <0.1
- Disbursed
- <0.1
- Undisbursed
- Not reported
- Records at the source
- IATI record (d-portal)
- Last transaction
- December 31, 2024
- IATI identifier
Capitalization of ERAF achievementsDec 2026Not reportedNot reportedNot reported
- Sector
- Energy
- Stage
- Under way
- Instrument
- Not reported
- Start
- January 1, 2024
- Effectiveness
- Not reported
- Closing
- December 31, 2026
- Disbursed as of
- Not reported
- Implementing agency
- Not reported
- Commitment
- Not reported
- Disbursed
- Not reported
- Undisbursed
- Not reported
- Records at the source
- Partner documents
IATI record (d-portal) - IATI identifier
Closed and stopped operations (120)
120 operations, 112 of them of funding partners. Funding partners, approved to date (stock): US$620.1 million, reported for 107 of 112. Disbursed in FY2025-26 (flow): none. 1 operation counted with its parent operation.
Sources
- OCHA FTS: terms of use set by the publisher
- Partner documents: terms of use set by the publisher
- IATI: terms of use set by the publisher
- IATI: terms of use set by the publisher
- IDA Statement of Credits and Grants: World Bank data, CC BY 4.0 (https://datacatalog.worldbank.org/public-licenses).
- IDB projects dataset: terms of use set by the publisher
- IFC Finances One: terms of use set by the publisher
- USAspending: terms of use set by the publisher
- World Bank procurement notices: terms of use set by the publisher
- World Bank Projects: terms of use set by the publisher
Data as of October 18, 2026
| Source | Read on |
|---|---|
| fts:2021:summary_gap | October 18, 2026 |
| Exchange rates (Federal Reserve, IMF) | October 18, 2026 |
| IATI | October 18, 2026 |
| IATI | October 18, 2026 |
| IDA Statement of Credits and Grants | October 18, 2026 |
| IDB projects dataset | October 18, 2026 |
| IFC Finances One | October 18, 2026 |
| Public investment program | October 18, 2026 |
| USAspending | October 18, 2026 |
| World Bank procurement notices | October 18, 2026 |
| World Bank Projects | October 18, 2026 |
| OCHA FTS, 2010 to 2026 | October 18, 2026 |
Cite this page
HaitiDocs. Energy. Partner portfolio, data as of October 18, 2026. https://www.haitidocs.org/portfolio/sectors/energy