Official Use Only
Report No: ICR00539
IMPLEMENTATION COMPLETION AND RESULTS REPORT
IDA-D3230, IDA-D6690 and IDA-D9810
ON GRANTS
IN THE AMOUNT OF SDR 97.4 MILLION
(US$138 MILLION EQUIVALENT)
TO THE
REPUBLIC OF HAITI
FOR THE
HAITI RURAL ACCESSIBILITY & RESILIENCE PROJECT
November 18, 2025
Transport Global Practice
Latin America And Caribbean Region
The World Bank
Haiti Rural Accessibility & Resilience Project (P163490) ICR DOCUMENT
Official Use Only
CURRENCY EQUIVALENTS
(Exchange Rate Effective {May 29, 2025})
Currency Unit = Haitian Gourde
HTG 130.74= US$1
US$1 = SDR 0.57813
FISCAL YEAR
January 1 - December 31
Regional Vice President: Susana Leite Riberio Cordeiro Guerra
Country Director: Lilia Burunciuc
Regional Director: Maria Marcela Silva
Practice Manager: Bianca Bianchi Alves
Task Team Leader (s): Ibrahim Kabore, Fabian Hinojosa Couleau
ICR Main Contributor: Ibrahim Kabore
The World Bank
Haiti Rural Accessibility & Resilience Project (P163490) ICR DOCUMENT
Official Use Only
ABBREVIATIONS AND ACRONYMS
Acronym Definition
AF Additional Financing
AF1 First Additional Financing
AF2 Second Additional Financing
AM Aide Memoire
BCA Haiti Center and Artibonite Regional Development Project (Boucle Centre-Artibonite)
CE Citizen engagement
CERC Contingent Emergency Response Component
CIAT-es Inter-Ministerial Committee for Territorial Development (Comité Interministériel
d'Aménagement du Territoire)
CPF Country Partnership Framework
EIRR Economic Internal Rate of Return
GBV Gender-Based Violence
GDP Gross Domestic Product
GoH Government of Haiti
GRM Grievance Redress Mechanism
IDA International Development Association
IPF Investment Project Financing
ISR Implementation Status and Results Report
LIW Labor-Intensive Work
M&E Monitoring and Evaluation
MEF Ministry of Economy and Finance (Ministère de l’Economie et des Finances)
MTPTC Ministry of Public Works, Transportation, and Communications (Ministère des
Travaux Publics, Transports et Communications)
NPV Net Present Value
OP/BP Operational Policy/Bank Procedure
PDO Project Development Objectives
PIU Project Implementation Unit
PSDH Strategic Development Plan (Plan Stratégique de Développement d'Haïti)
RARP Rural Accessibility and Resilience Project
RAI Rural Access Index
RUTAP Resilient Urban Transport and Accessibility Project
SDR Special Drawing Rights
SME Small and Medium Enterprise
ToC Theory of Change
UCE Central Execution Unit (Unité Central d’Exécution)
UTE Technical Execution Unit (Unité Technique d’Exécution)
USD United States Dollar
WB World Bank
The World Bank
Haiti Rural Accessibility & Resilience Project (P163490) ICR DOCUMENT
Official Use Only
TABLE OF CONTENTS
DATA SHEET ................................................................................................................................................. i
I. PROJECT CONTEXT AND DEVELOPMENT OBJECTIVES ....................................................................................1
II. OUTCOME ...................................................................................................................................................6
III. KEY FACTORS AFFECTED IMPLEMENTATION AND OUTCOME................................................................... 10
IV. BANK PERFORMANCE, COMPLIANCE ISSUES, AND RISK TO DEVELOPMENT OUTCOME ............................ 11
V. LESSONS AND RECOMMENDATIONS .......................................................................................................... 15
ANNEX 1. RESULTS FRAMEWORK AND KEY OUTPUTS ........................................................................................ 17
ANNEX 2. BANK LENDING AND IMPLEMENTATION SUPPORT/SUPERVISION ....................................................... 33
ANNEX 3. PROJECT COST BY COMPONENT ......................................................................................................... 36
ANNEX 4. EFFICIENCY ANALYSIS ........................................................................................................................ 37
ANNEX 5. BORROWER, CO-FINANCIER AND OTHER PARTNER/STAKEHOLDER COMMENTS ................................. 39
ANNEX 6. SUPPORTING DOCUMENTS (IF ANY) ................................................................................................... 39
The World Bank
Haiti Rural Accessibility & Resilience Project (P163490) ICR DOCUMENT
i
Official Use Only
DATA SHEET
@#&OPS~Doctype~OPS^dynamics@icrbasicdata#doctemplate
BASIC DATA
Product Information
Operation ID Operation Name
P163490 Haiti Rural Accessibility & Resilience Project
Product Operation Short Name
Investment Project Financing (IPF) HT Rural Accessibility & Resilience
Operation Status Approval Fiscal Year
Closed 2018
Original EA Category
Partial Assessment (B) (Approval package - 31 May 2018)
CLIENTS
Borrower/Recipient Implementing Agency
The Republic of Haiti
Unite Centrale d' Execution of the Ministry of Public
Works (UCE), Unite Technique d'Execution
DEVELOPMENT OBJECTIVE
Original Development Objective (Approved as part of Approval Package on 31-May-2018)
The original Project Development Objectives are as follows: (i) to increase all-weather road access in selected sub-
regions; and (ii) to improve the resilience of selected segments of the road network.
Current Development Objective (Approved as part of Additional Financing Package Seq No 1 on 17-Mar-2022)
The Project Development Objectives are to: (i) increase all-weather road access in selected sub-regions; (ii) improve the
resilience of selected segments of the road network; and (iii) to provide immediate and effective response to an eligible
crisis or emergency.
s
s
s
s
s
s
s
s
@#&OPS~Doctype~OPS^dynamics@icrfinancing#doctemplate
The World Bank
Haiti Rural Accessibility & Resilience Project (P163490) ICR DOCUMENT
ii
Official Use Only
FINANCING
Financing Source Original Amount (US$) Revised Amount (US$) Actual Disbursed (US$)
World Bank Financing 138,000,000.00 130,594,989.63 130,593,636.44
IDA-D9810 30,000,000.00 29,469,208.23 28,549,221.96
IDA-D3230 75,000,000.00 69,472,190.87 69,941,792.47
IDA-D6690 33,000,000.00 31,653,590.53 32,102,622.01
Total 138,000,000.00 130,594,989.63 130,593,636.44
RESTRUCTURING AND/OR ADDITIONAL FINANCING
Date(s) Type
Amount Disbursed
(US$M)
Key Revisions
30-May-2025 Portal 131.12
• Results
• Disbursement Estimates
• Loan Cancellations
• Reallocations
@#&OPS~Doctype~OPS^dynamics@icrkeydates#doctemplate
KEY DATES
Key Events Planned Date Actual Date
Concept Review 21-Jul-2017 21-Jul-2017
Decision Review 26-Mar-2018 26-Mar-2018
Authorize Negotiations 09-Apr-2018 11-Apr-2018
Approval 31-May-2018 31-May-2018
Signing 06-Jun-2018 06-Jun-2018
Effectiveness 04-Sep-2018 04-Sep-2018
Additional Financing Sequence.02 Not Applicable 18-Jun-2020
Additional Financing Sequence.01 Not Applicable 17-Mar-2022
Restructuring Sequence.01 Not Applicable 30-May-2025
ICR Sequence.01 (Interim) -- 18-Nov-2025
Mid-Term Review No. 01 25-Oct-2021 22-Nov-2021
The World Bank
Haiti Rural Accessibility & Resilience Project (P163490) ICR DOCUMENT
iii
Official Use Only
Operation Closing/Cancellation 30-May-2025
Automatically populated
from Loans System
ICR/NCO 30-Nov-2025 --
@#&OPS~Doctype~OPS^dynamics@icrratings#doctemplate
RATINGS SUMMARY
Outcome Bank Performance M&E Quality
Highly Satisfactory Highly Satisfactory Substantial
ISR RATINGS
No. Date ISR Archived DO Rating IP Rating
Actual Disbursements
(US$M)
01 24-Oct-2018 Satisfactory Satisfactory 0.00
02 22-Apr-2019 Satisfactory Satisfactory 3.00
03 01-Nov-2019 Satisfactory Satisfactory 3.00
04 21-May-2020 Satisfactory Satisfactory 12.15
05 16-Dec-2020 Satisfactory Satisfactory 14.03
06 17-Jun-2021 Satisfactory Satisfactory 26.20
07 24-Dec-2021 Satisfactory Satisfactory 51.42
08 30-Jun-2022 Satisfactory Satisfactory 91.88
09 22-Dec-2022 Satisfactory Satisfactory 100.51
10 21-Jun-2023 Satisfactory Satisfactory 111.02
11 08-Jan-2024 Satisfactory Satisfactory 125.15
12 18-Jul-2024 Satisfactory Satisfactory 130.35
13 05-Mar-2025 Satisfactory Satisfactory 130.80
@#&OPS~Doctype~OPS^dynamics@icrsectortheme#doctemplate
SECTORS AND THEMES
Sectors
The World Bank
Haiti Rural Accessibility & Resilience Project (P163490) ICR DOCUMENT
iv
Official Use Only
Major Sector Sector %
Adaptation
Co-benefits
(%)
Mitigation
Co-benefits (%)
FY17 - Transportation
FY17 - Public Administration -
Transportation
9 44 0
FY17 - Rural and Inter-Urban Roads 91 56 0
Themes
Major Theme Theme (Level 2) Theme (Level 3) %
FY17 - Environment and
Natural Resource
Management
FY17 - Climate change FY17 - Adaptation 55
FY17 - Human
Development and
Gender
FY17 - Gender
66
FY17 - Urban and Rural
Development
FY17 - Disaster Risk Management
FY17 - Flood and
Drought Risk
Management
96
FY17 - Rural Development
FY17 - Rural
Infrastructure and
service delivery
100
FY17 - Urban Development FY17 - Public Transport 9
The World Bank
Haiti Rural Accessibility & Resilience Project (P163490) ICR DOCUMENT
v
ADM STAFF
Role At Approval At ICR
Practice Manager Shomik Raj Mehndiratta Bianca Bianchi Alves
Regional Director Maria Marcela Silva
Global Director Jose Luis Irigoyen Nicolas Peltier-Thiberge
Practice Group Vice President Guangzhe Chen
Country Director Anabela Abreu Lilia Burunciuc
Regional Vice President Jorge Familiar Susana Leite Riberio Cordeiro Guerra
ADM Responsible Team Leader Pierre Xavier Bonneau Ibrahim Kabore
Co-Team Leader(s) Fabian Hinojosa Couleau
ICR Main Contributor Ibrahim Kabore
The World Bank
Haiti Rural Accessibility & Resilience Project (P163490) ICR DOCUMENT
Page 1
Official Use Only
I. PROJECT CONTEXT AND DEVELOPMENT OBJECTIVES
A. CONTEXT AT APPRAISAL
Context
1. At appraisal, Haiti had the lowest income in the Western Hemisphere, marked by widespread poverty and
inequality, but a sense of optimism after years of relative stability. In 2016, Gross Domestic Product (GDP) per capita
stood at US$739.60, and Haiti ranked 163rd of 188 countries on the Human Development Index. Although extreme
poverty declined from 31 percent to 24 percent between 2000 and 2012, inequality remained high. Most gains were
concentrated in urban areas, mainly Port-au-Prince, while the Gini coefficient reached 0.64, the highest in the Latin
America and the Caribbean region. It was also among the most hazard-prone countries globally, with 96 percent of
Haiti's population living in areas identified as at hazard-prone, and with Haiti’s economy experiencing frequent natural
disasters that impacted economic growth. Despite these challenges, backed by the United Nations Stabilization
Mission in Haiti, the decade preceding appraisal saw three presidents elected and peaceful transfer of power between
opposition parties, with the government outlining Haiti’s aspiration, in its 2013 Strategic Development Plan (PSDH),
to become an emerging economy by 2030.
2. Regional connectivity, rural accessibility and climate resilient infrastructure were key priorities for Haiti’s
development vision and World Bank (WB) support. In 2015, only 39 percent of Haitians lived within 2 km of an all-
weather road, with most rural roads in poor condition. The transport infrastructure was highly vulnerable to natural
disasters and climate events, with limited coverage and poor maintenance, especially in rural areas, that hindered
access to agricultural markets, leading to post-harvest losses of up to 30 percent. In 2016, Hurricane Matthew
demonstrated again its vulnerability by destroying roads and bridges that isolated 1.2 million people from emergency
aid. To address these issues, the Haitian government prioritized, under its PSDH, climate resilience—including all-
weather roads—aiming to construct 4,000 km of roads by 2021 to improve intercity and rural connectivity. In support
of these efforts, and aligned with both the World Bank’s (WB) Systematic Country Diagnostic (Report No. 97341) and
the Haiti Country Partnership Framework (CPF, Report No. 98132) for FY2016-2019, the Rural Accessibility and
Resilience Project was designed to assist the Government of Haiti (GoH) in enhancing rural connectivity, improving
climate resilience, and strengthening institutional capacity for road infrastructure planning and maintenance.
Theory of Change (Results Chain)
3. The project’s theory of change (TOC) is presented in Figure 1.
Figure 1: TOC at approval
The World Bank
Haiti Rural Accessibility & Resilience Project (P163490) ICR DOCUMENT
Page 2
Official Use Only
Project Development Objectives (PDO)
4. The original PDO, as stated in the Financial Agreement approved on June 6, 2018 is to: (a) increase all-weather road
access in selected sub-regions; and (b) improve the resiliency of selected segments of the road network.
1
Key Expected Outcomes and Outcome Indicators
5. The two-part PDO was measured by two outcome indicators see Table 1.
Table 1. Outcome indicators at appraisal
Outcome (PDO) Outcome indicator (PDO-level results indicator)
(a) increase all-weather road access in selected
sub-regions
(i) Share of rural population in selected sub-regions with access within 2 km of an all-
weather road (percentage)
(b) improve the resiliency of selected segments
of the road network
(ii) Total population living in areas serviced by connecting roads upgraded to a climate
resilient standard (number)
1
The PDO outlined in the Financing Agreement closely aligns with that presented in the project Appraisal Document, which states: "The project Development Objectives
are to: (i) increase all-weather road access in selected sub-regions; and (ii) improve the resilience of selected segments of the road network.”
The World Bank
Haiti Rural Accessibility & Resilience Project (P163490) ICR DOCUMENT
Page 3
Official Use Only
Components
6. Component 1: Enhancing Rural Connectivity (US$45.0 million, actual US$90.0 million) aimed to improve reliable, all-
weather road access to essential services and markets for rural populations, with a focus on the South, South-East,
and Nippes departments. The activities financed under this component included: (i) rehabilitation works of tertiary
and rural road network (400 km), (ii) the building of small complementary facilities and structures, including lighting,
bus stops, and other safety structures, in inhabited areas, near schools and around water kiosks and health centers,
(iii) technical assistance, training, and developing technical guidelines for Haiti’s national all-weather rural road access
program; (iv) the preparation and financing of local mobility plans; and (v) coastal protection and slope stabilization.
7. Component 2: Improving Resilience of Transport Connecting Infrastructure (US$22.0 million, actual US$3.2 million)
aimed to strengthen the resilience of Haiti's primary and secondary road networks against climate change and extreme
weather events. The focus was on protecting critical points to prevent disruptions in the movement of people and
goods. Key activities included: (i) protection and rehabilitation of existing bridges situated on selected segments; (ii)
reinforcement of coastal protection, hydraulic protection for bridges, and slope stabilization works; (iii) a vulnerability
study of the national primary and secondary road network and the identification of critical points (which would be
used to identify and prioritize works to be financed under the component); (iv) a National Bridge Management
Program; (v) a Roadmap to improve the resilience of the primary network by 2030; and (vi) a Planning and Bridge
Assessment and Management System.
8. Component 3: Promoting Sustainable Mobility Development (US$3.0 million, actual US$1.0 million) aimed to
strengthen the institutional capacity of the Ministry of Public Works, Transport and Communication (MTPTC), through
technical assistance, training, and the provision of goods. It was designed to enhance: (i) institutional sustainability,
through continued assistance to MTPTC on resilient transport and road asset management; and (ii) sustainable urban
transport policies and management, through improved investment strategy and planning.
9. Component 4: Contingent Emergency Response Component (US$1.0 million, actual US$30.3 million) was included
to provide immediate assistance during an eligible emergency due to the high risk of a catastrophic events in Haiti.
This component was triggered after damage from the earthquake on August 14, 2021.
10. Component 5: Project Management (US$4.0 million, actual US$6.0 million) to support the MTPTC and its Central
Execution Unit (Unité Centrale d ’Execution – UCE) through the provision of goods, consultants’ services, training and
operating costs. It financed key project staff, operation costs, and equipment for the project Implementation Unit
(PIU), and provided support for social and environmental safeguards, identification and mitigation of gender
disparities, and citizens engagement (CE).
B. SIGNIFICANT CHANGES DURING IMPLEMENTATION
Revised PDOs and Outcome Targets
11. The project’s PDO was revised in 2022 through a second Additional Financing (AF2) to account for a CERC activation
response. The new PDO was revised as follows: (a) increase all-weather road access in selected sub-regions
(unchanged); (b) improve the resilience of selected segments of the road network (unchanged); and (c) provide an
immediate and effective response to an eligible crisis or emergency (new).
Revised PDO Indicators
12. An additional PDO indicator was included to address the CERC activities related to earthquake response efforts:
“People with restored access to the road network (Number)” was introduced with an end target of 407,000 people.
Revised Components
The World Bank
Haiti Rural Accessibility & Resilience Project (P163490) ICR DOCUMENT
Page 4
Official Use Only
13. Component 1 was modified to include subcomponent 1.3 through the first Additional Financing (AF1) in 2020. This
subcomponent incorporated activities
2
from the Haiti Center and Artibonite Regional Development Project (BCA,
P133352). This integration unified similar efforts under both projects to enhance resilience and access to all-weather
roads, supporting portfolio consolidation in Haiti. The Results Framework (RF) was revised to reflect the new activities.
14. Component 4 was revised in the AF2 in 2022 to reflect the activities financed under the emergency response.
Additionally, AF2 was used to replenish the financing for Components 1 and 2 (category 1), through the Crisis Response
Window, that had been reallocated to the CERC component to finance the emergency response.
15. Component 1 was modified through the third restructuring (AF3) in May 2025, by removing the following project
activities: one market, one maintenance center, and two bridges; cancelling its respective funds and revising relevant
indicators.
16. Table 2 summarizes actual estimated costs at appraisal and total expenditures related to each component.
Table 2: Project Components and cost at approval and at closing
Component Estimated cost at
appraisal (US$ M)
AF1 (2020) AF2 (2022) 3rd
Restructuring
(Cancellation)
Revised
Estimated cost
Actual
disbursed at
closing (US$
M)
3
1 45.0 30 0 0 75 90
2 22.0 0 0 0 22 3.2
3 3.0 1 0 -2.9 1.2 1
4 1.0 -1 30 0 30 30.3
5 4.0 3 0 7 6
Total 75.0 33 30 2.9 135.2 130.6
Other Changes
17. The Additional Financings and Restructurings over the life of the project included:
Table 3. Summary of Restructurings Changes
Restructuring Date
Approved
Effective Grant Funding Revised Closing
Date
Main changes
AF-1 June 20, 2020 August
7, 2020
D669-HT SDR 24.2 million
(US$33 million)
June 28, 2024
• Expand the scope: new Subcomponent 1.3
• Reallocation of funds
• Extend closing date
• Revise RF
AF-2 March 17,
2022
June 15,
2022
D981-HT SDR 21.6 million
(US$30 million)
May 30, 2025 • Reallocation of funds
• Extend closing date
• Revise RF
Restructuring
(Level II)
May 30, 2025 Cancel SDR 2.2
million (US$2.9
million)
• Revise RF
• Cancellation
2
These activities includes: (i) construction of four climate-resilient bridges, (ii) targeted improvements on key roads such as culvert installation, slope stabilization, and
maintenance or repair of 80 km of roads, (iii) building a culvert on River Bretelle, (iv) construction or rehabilitation of two road maintenance centers, and (v) training for
200 community members in rural road maintenance, (vi) building or rehabilitating four local markets and the Saint-Michel regional market, (vii) developing climate-
informed urban plans for Saint-Raphaël and Saint-Michel, and (viii) creating a regional development dashboard.
3
Component 1 reports a higher amount than component 2 due to a shortcomings in Financial management reporting, see note in Annex 3.
The World Bank
Haiti Rural Accessibility & Resilience Project (P163490) ICR DOCUMENT
Page 5
Official Use Only
18. Implementation arrangements. AF1 revised implementation arrangements to include the Unité Technique
d’Exécution (UTE) of the Ministry of Economy and Finance (MEF) as an implementing partner and the Executive
Secretariat of the Inter-Ministerial Committee for Territorial Development (CIAT-es) as a technical partner. UCE-
MTPTC continued to oversee overall coordination and original activities, while UTE-MEF continued its responsibility
for: (i) constructing or rehabilitating four markets (Fonds Bruns, Domond, Nan Poste, and Saint-Raphaël); (ii)
constructing the Saint-Michel regional market; (iii) developing climate-informed urban plans for Saint-Raphaël and
Saint-Michel; and (iv) creating a dashboard tool to track development indicators and investments at the regional level.
19. Closing date extension. The project closing date was extended twice, for a total duration of 23 months. AF1 provided
a 12-month extension, changing the deadline from June 30, 2023, to June 28, 2024. AF2 further extended the closing
date by 11 months, resulting in a new final deadline of May 30, 2025.
20. Reallocation between categories. AF1 reallocated SDR 600,000 from Category 2, emergency expenditures, to
Category 1 for the provision of technical assistance, and AF2 reallocated SDR 21,600,000 million from Category 1 to
Category 2 to finance earthquake response support.
21. Cancellation of funds. On May 20, 2025, the GoH requested cancellation of undisbursed grant balances totaling SDR
2,155,561.06 (US$2,934,184.07), which was processed in a third restructuring on May 28, 2025. This action cancelled
funds from the three Grants (IDA-D323-HT, IDA-D669-HT, and IDA-D981-HT) and updated select RF indicators
accordingly
22. Intermediate indicators. Through its restructurings, new intermediate outcome indicators were introduced, and some
original indicators were revised to ensure a more accurate representation of project activities. AF1 introduced eight
new indicators and changed the end targets for two indicators. AF2 introduced two new intermediate indicators. The
third restructuring changed the end targets for three indicators. Further details are in Annex 1.
Rationale for Changes and Their Implication on the Original Theory of Change
23. In February 2020, the project increased its scope by absorbing activities from the BCA project. As results of
implementation constraints, the BCA project was restructured leading to a reduction in scope, with remaining
activities under implementation transferred to the Project prior to August 31, 2020, BCA’s closing date. This transfer,
rather than extending the BCA closing date, facilitated portfolio consolidation, and allowed additional time for
completion of activities under the project. Similarly, towards the end of the project implementation period, in May
2025, the execution of some planned works under Component 1 was unfeasible due to elevated security risks in the
BCA area. These activities were transferred under AF3 to the Resilient Urban Transport and Accessibility Project
(RUTAP, P177210) to ensure its completion.
24. On August 23, 2021, the government formally requested activation of the CERC to facilitate post-earthquake
emergency response efforts, reallocating US$30 million to the CERC and expanding the project scope. The August
14, 2021, earthquake damaged over 850km of roads in three southern departments, isolating more than 450,000
people and causing up to US$160 million in transport sector losses. US$30 million was reallocated from Components
1 and 2 to the CERC for emergency response. The WB approved this activation on September 21, 2021, with the
following objectives: (i) restore accessibility and rural connectivity through the repair and clearance of critical road
segments; (ii) reestablish access to Grand’Anse via the construction of an emergency bridge in Jeremie; (iii) support
building assessment activities led by the Technical Building Office (Bureau Technique du Bâtiment, BTB) of the MTPTC;
and (iv) assist in the rehabilitation of essential infrastructure, including irrigation canals and water supply systems, in
the affected regions.
25. All restructurings were aligned with the original TOC and the original outcomes. While the first two restructurings
significantly increased the overall project scope, all activities and changes were in line with the original TOC. Aside
from adding a new PDO indicator to better reflect the expanded scope, intermediate outcomes were revised to reflect
The World Bank
Haiti Rural Accessibility & Resilience Project (P163490) ICR DOCUMENT
Page 6
Official Use Only
the expanded scope of AF1, the inclusion of CERC activities in AF2, and the revisions in component 1 and partial fund
cancellation under the third restructuring.
II. OUTCOME
A. RELEVANCE OF PDO
Assessment of Relevance of PDOs and Rating
26. The relevance of the PDO is rated High. At approval the project directly contributed to CPF FY16-19, in the
achievement of its Pillars 1 “Inclusive Growth” by improving infrastructure in rural areas and its Pillar 3 “Resilience”
by reducing Haiti’s vulnerability to natural disasters and climate shocks. Furthermore, the project was aligned with
the WB’s global priorities on climate change and gender, supporting targets under the WB Climate Action Plan 2016-
2020 and the Gender Strategy 2016 – 2023, which introduced targets of 28 percent climate-related financing and
closing gender gaps as core development objectives. At closing, the PDO remained aligned with the WB’s CPF for Haiti
FY25-FY29 (Report No: 181213-HT). Specifically, the project advanced the CPF’s pillar of “Building Resilience and
Preserving Human Capital” by investing in climate-resilient rural infrastructure and improving road connectivity, which
facilitates access to essential services such as health and education for vulnerable populations. The Project also
contributed to the pillar of “Strengthening Economic Governance and Creating Job Opportunities” by enabling greater
market access and supporting local employment through infrastructure works. Additionally, the project reinforced the
CPF’s focus on “Institutional Strengthening” by enhancing the capacity of the MTPTC in disaster preparedness and
infrastructure management. These targeted interventions collectively supported the Government’s Action Plan 2017-
2020 to improve transport connectivity and its rural road network in Haiti’s most underserved regions.
B. ACHIEVEMENT OF PDOs (EFFICACY)
Assessment of Achievement of Each Objective/Outcome
27. To assess the project’s efficacy, the PDO outcomes indicators are summarized in Table 4:
Table 4. PDO outcomes indicators at Project Close versus End Targets
PDO and Indicator name Baseline End Target Actual
PDO (a): Increase all-weather road access in selected sub-regions
“Share of rural population in selected sub-regions with access within 2 km of an all-
weather road (percentage)”
36
55
63
PDO (b): Improve the resilience of selected segments of the road network
“Total population living in areas serviced by connecting roads upgraded to a climate
resilient standard (number)”
0
700,000
902,267
PDO (c): Provide an immediate and effective response to an eligible crisis or emergency
“People with restored access to the road network (Number)”
0
407,000
422,337
PDO (a): Increase all-weather road access in selected sub-regions.
28. Outcome Indicator: “Share of rural population in selected sub-regions with access within 2 km of an all-weather
road (percentage)”, which had a target of 55 percent, was successfully achieved. Physical infrastructure investments
were robust and exceeded planned outputs, directly supporting improved access. The project rehabilitated 554 km of
roads (115 percent of the target), including 499 km of rural roads (116 percent of the target), restoring access for over
900,000 people. These works were concentrated in the Grand Sud and Boucle Centre Artibonite regions, but also
extended to departmental, secondary, and national networks. The interventions were strategically distributed, with
nearly 80 percent of works on communal roads, ensuring that the benefits reached the most vulnerable and remote
populations. Complementary facilities such as bus stops, lighting, and safety structures further enhanced the utility
and safety of the improved road network. These efforts led to substantial improvements in the Rural Accessibility
Index (RAI), with 63 percent of rural population in selected sub-regions, now living within 2 km of an all-weather road.
The World Bank
Haiti Rural Accessibility & Resilience Project (P163490) ICR DOCUMENT
Page 7
Official Use Only
29. The interventions also enhanced access to essential services and markets, with over 720,000 people (target:
660,000) able to reach regional markets within 120 minutes and more than 326,000 women (target: 320,000)
gaining timely access to health facilities. These results reflect the project’s gender-responsive design and its focus on
linking rural populations to economic and social opportunities. Beneficiary surveys reinforce these findings: 97 percent
of respondents highlighted the importance of the road network for community mobility, 75 percent for commercial
exchange, and 39 percent for access to basic services. The project’s adaptability, including additional financing and
integration of activities from other regions, further expanded its impact and resilience, as evidenced by both
quantitative results and positive beneficiary feedback documented by the client evaluation reports.
30. The establishment of mobility plans and the updating of the National RAI for all departments provide a solid
foundation for future investments and policy development, directly reinforcing the achievement of PDO (a). These
mobility plans, developed through community consultation and integrating climate resilience and gender
considerations, help identify and prioritize local needs for road access. Meanwhile, the updated RAI offers
comprehensive, up-to-date data on rural connectivity across the country, enabling policymakers to target investments
where they are most needed and to monitor progress effectively. Together, these tools ensure that future
interventions are strategic, evidence-based, and sustainable, supporting ongoing improvements in all-weather road
access in selected sub-regions.
31. Achievement of PDO (a) is rated High, with clear evidence of transformative impact on rural accessibility. The
quantitative and qualitative results demonstrate that the project not only met but exceeded its objectives for
increasing all-weather road access in selected sub-regions. The improvements have led to greater social inclusion,
economic opportunity, and resilience for Haiti’s rural communities.
PDO (b): Improve the resilience of selected segments of the road network
32. Outcome Indicator: “Total population living in areas serviced by connecting roads upgraded to a climate resilient
standard (number)”, which had a target of 700,000 people, was successfully achieved. The project substantially
improved the resilience of selected segments of the road network by rehabilitating and upgrading critical road sections
and bridges to climate-resilient standards, implementing robust drainage and erosion control measures, and
developing a functional bridge management system within the MTPTC. Eight critical bridges and 124 critical
points/segments were completed. These interventions have directly contributed to stabilizing key transport corridors,
reducing interruptions in the movement of people and goods during extreme weather events, and making
approximately 80 km of roads reliably passable year-round. Beneficiary surveys reinforce these achievements, with
82 percent of respondents reporting improved preparedness for natural disasters and 87 percent noting fewer access
disruptions during the rainy season, underscoring the tangible impact of the project on community resilience. These
interventions ensured that over 900,000 people now benefit from modernized, resilient roads—far exceeding the
original target—and that key crossing points remain passable during adverse weather and natural disasters.
33. Institutional strengthening was also a notable outcome, with the development and operationalization of a Bridge
Management System within MTPTC. This system enhanced the government’s ability to monitor, maintain, and plan
for resilient infrastructure, laying the groundwork for sustained improvements beyond the project’s lifespan.
Additionally, several studies were completed including urban mobility and climate resilience in Port-au-Prince and
Cap-Haitien that support institutional strengthening in urban transport and climate resilience management and
planning. The tools associated with those studies were not completed before the closing data and its development is
transferred to RUTAP. This does not undermine the achievement of the institutional strengthening objectives.
34. Achievement of PDO (b) is rated High. The combination of robust infrastructure works, positive beneficiary feedback,
and strengthened institutional capacity has significantly enhanced Haiti’s ability to withstand and recover from climate
and disaster-related shocks.
The World Bank
Haiti Rural Accessibility & Resilience Project (P163490) ICR DOCUMENT
Page 8
Official Use Only
PDO (c): Provide an immediate and effective response to an eligible crisis or emergency
35. Outcome Indicator: “People with restored access to the road network (Number)”, which had a target of 407,000,
was successfully achieved. The project effectively achieved this objective by activating its CERC following the
devastating 7.2 magnitude earthquake in Haiti in August 2021. This rapid response was enabled by reallocating US$30
million to CERC, which funded urgent interventions such as repairing and clearing critical road segments, constructing
a temporary bridge in Jérémie to restore connectivity with Grand’Anse, supporting building assessments, and
rehabilitating essential infrastructure like irrigation canals and water systems. The project not only met but exceeded
its targets, restoring road access for over 422,337 people, repairing eight critical bridges, and treating 90 critical points
(target: 80). Beneficiary feedback confirmed that over 81 percent of respondents felt their communities were better
prepared for future disasters, underscoring the effectiveness and impact of the emergency response measures.
36. Achievement of PDO (c) is rated High.
Justification of Overall Efficacy Rating
37. The Overall Project's efficacy in achieving its PDOs is rated High. The project fully achieved its objectives, and all
three PDO targets were met or surpassed.
C. EFFICIENCY
Assessment of Efficiency and Rating
38. The efficiency of critical spot improvement, bridge repairs and other rural road improvements completed under the
project are High. The project completed improvements in 550 km of rural roads, and 222 critical spots (that include
among other box culverts, slope stabilization and embankments protection) and rehabilitation and improvement of
16 bridges with a total cost of US$110 million. The average per unit cost was US$159,000 per km of rural roads,
US$78,000 per critical spot and US$ 863,000 per bridge intervened. The rehabilitation cost of rural roads is lower than
the US$200,000 /km assumed at appraisal without accounting for the price increase and inflation since appraisal and
below the average of actual costs (US$165,000/km) found under the BCA project closed in 2021.
39. While there was not an economic evaluation done at appraisal due to the framework approach designed, the
economic analysis at closing demonstrates the positive economic return of project investment using baseline
climate and climate change projections (Table 5). The main Project benefits included are a reduction in climate
impacts (fluvial, pluvial and coastal floods) on asset damage, lower road user costs through less travel disruption,
decreasing the frequency of road crashes, and economic benefits of greenhouse gas reduction (Annex 4).
Table 5. Economic indicators at Project Close
Historical climate Under climate change (SSP 5-85)
NPV (in US$ million) 20.9 32.7
EIRR (in percent) 15.3 17.1
BCR 1.21 1.33
40. The project experienced smooth implementation, achieving its outcomes in its timeframe. Despite all events and
external factors affecting the country, the project was implemented at a steady pace with disbursement following the
original and revised estimations with US$18 million on average annual disbursement and a peak of US$64 million
disbursed in FY22. The PIU had no staff-turn over, there were no significant cost over-runs and procurement didn’t
experience significant delays that impacted project implement. The 23-month extension was not a result of delay but
to accommodate completion timeframes for new activities added to its two additional financing.
41. Therefore, the project’s efficiency is rated as High, reflecting effective use of resources, strong achievement of
objectives relative to costs and timeframe, and adaptive management in response to unforeseen challenges.
The World Bank
Haiti Rural Accessibility & Resilience Project (P163490) ICR DOCUMENT
Page 9
Official Use Only
D. JUSTIFICATION OF OVERALL OUTCOME RATING
42. The overall outcome rating for the project is Highly Satisfactory, given the project’s substantial achievement of its
objectives, including significant improvements in rural accessibility, daily mobility, and access to essential services.
High beneficiary satisfaction and strong implementation performance further support this positive assessment. This
rating is consistent with a High rating for Relevance of PDO, High rating for both Efficacy and Efficiency.
Table 6. Overall Outcome Rating
Rating Dimension Rating
Relevance of PDO High
Overall efficacy
Outcome (a) High
Outcome (b) High
Outcome (c) High
Efficiency High
Outcome rating Highly Satisfactory
E. OTHER OUTCOMES AND IMPACTS (IF ANY)
43. Gender. The project significantly improved gender outcomes by increasing women’s access to health services and
economic opportunities. Pilot local mobility plans in three micro-regions incorporated women’s safety and mobility
needs, identifying specific interventions to enhance access to health services and reduce risks, including gender-based
violence (GBV), which had previously constrained women’s mobility. Post-completion surveys of over 3,200 women
showed that 88 percent reported better access to basic services, and 95 percent felt safer during their trips. The
project also promoted female participation in the transport sector, with 75 percent road maintenance trainees being
women, far exceeding the target. Improved market access and infrastructure boosted economic prospects for traders,
most of whom were women: 74 percent of survey respondents reported increased market revenues.
44. Road safety. The project improved road safety across target regions. It achieved its goal of integrating road safety
measures into 100 percent of road designs under intervention. Post-completion impact assessments confirmed this
success, with 85 percent of respondents confirming a reduction of road accidents on project roads.
45. Private sector strengthening. The project fostered a more conducive environment for private sector growth. It directly
supported the agrobusiness sector by constructing modern market facilities and improving connection between key
production areas and markets. Additionally, it provided specific training, skills development and direct economic
opportunities for construction firms, small and medium enterprises (SMEs), and local communities.
46. Institutional strengthening. Institutional capacity of Haiti’s MTPTC and UCE was significantly enhanced through
targeted training and system upgrades. Achievements included strengthened project management, fiduciary systems,
environmental and social safeguards, infrastructure management and disaster response. Activities included: training
and licensing for MS Project and AutoCAD; RAI workshops; road maintenance support; and disaster assessment
training for 390 engineers. While some systems, e.g., the climate resilience roadmap and traffic monitoring tools were
not fully implemented, adaptive management and robust structures improved effectiveness and sustainability.
47. Poverty reduction and shared prosperity. The project contributed meaningfully to poverty reduction and shared
prosperity in rural Haiti by improving access, creating jobs and promoting inclusion. Economic opportunities grew
through improved circulation of agricultural goods, better access to farmland, and upgraded local markets: 85 percent
of surveyed respondents reported better livelihoods. Labor-intensive roadwork generated 153,960 workdays for
10,264 rural residents, of which 1,096 were women. Gender-sensitive design and robust community engagement led
to high satisfaction and willingness to participate in future initiatives. Overall, key development barriers were
addressed, improving living conditions for Haiti’s most vulnerable populations.
The World Bank
Haiti Rural Accessibility & Resilience Project (P163490) ICR DOCUMENT
Page 10
Official Use Only
III. KEY FACTORS AFFECTED IMPLEMENTATION AND OUTCOME
A. KEY FACTORS DURING PREPARATION
48. Hurricane Matthew’s devastating impacts were a key factor during Project preparation. The storm struck
southwestern Haiti on October 4, 2016, as the strongest hurricane to hit the country since 1964. It affected 1.1 million
people, caused 674 fatalities, and inflicted damage equal to 32 percent of the GDP. Transport infrastructure was
severely impacted, with critical bridges and roads destroyed, isolating 1.2 million people from emergency aid. These
vulnerabilities shaped project design, prompting a resilience-focused approach, including data- driven climate
vulnerability mapping for project selection, capacity building in resilience planning, and targeted spot improvements.
49. The project areas were selected in alignment to the government strategy to close rural access gaps and to foster
synergies across the WB’s portfolio. RAI was used as the main selection criteria and as core indicator for tracking
progress and outcomes. The first RAI national survey, financed by the BCA, gained institutional momentum, becoming
the government’s tool for guiding infrastructure strategies. Coordination with other Bank-financed operations—such
as the Improving Maternal and Child Health Project (P123706), the Providing and Education of Quality in Haiti
(P155191) and the Emergency Resilient Agriculture for Food Security Project (P177072)—maximized development
impacts by improving access to services intervened by other projects in health, education and agriculture.
50. The CE strategy embedded in the project design enabled sustained performance under highly challenging national
circumstances. It included a range of measures to foster citizen involvement, including: (i) adopting a participatory
methodology for investment development; (ii) engaging local university students and organizations in data collection
and analysis; (iii) implementing a comprehensive CE plan that facilitated two-way communication and closed feedback
loops—using geolocation technologies to gather insights on aspects public transport quality, road safety, and women's
security; and (iv) establishing detailed grievance redress procedures, which clearly defined roles for government
officials, instituting mechanisms for complainant feedback, and monitoring of grievance resolutions progress.
B. KEY FACTORS DURING IMPLEMENTATION
(a) Factors subject to control of government and/or implementing entities
51. Some financial management shortcomings affected timely reporting and internal controls. Moderate deficiencies in
financial management, including delays in preparing and submitting operational budgets, interim financial reports,
and audit documents, jeopardized the project’s ability to provide reliable information for management and
monitoring. Issues such as outdated accounting records, lack of electronic backup systems, and insufficient inventory
management highlighted the need for corrective actions to strengthen internal controls.
52. Staff turnover at UTE and its main implementing partner led to delays in procuring some activities. The project faced
minor and unresolved issues in launching procurement for the regional market, the maintenance center and two
bridges due to shortcomings in the UTE and the United Nations Office for Project Services, its key implementing
agencies. Under AF1, UTE became an implementing partner for additional activities in the Artibonite region, while UCE
remained responsible for overall Project implementation. UTE, housed within the ministry of finance, faced staff
shortages and leadership turnover. Together with high security risk in the area, the commencement of the road
maintenance center, regional market and two bridges and led to the third restructuring to cancel those activities.
(b) Factors subject to World Bank control
53. Effective Supervision was essential for Project Success. The WB Task Team and the experienced UCE ensured smooth
coordination, technical exchanges, and operational guidance. Their approach allowed fast issue identification and
timely adaptation during crises, such as the 2021 earthquake, ensuring efficient resource use and continuity, even
amid Haiti’s instability. Regular field visits, prompt and candid reporting, and robust monitoring supported accurate
The World Bank
Haiti Rural Accessibility & Resilience Project (P163490) ICR DOCUMENT
Page 11
Official Use Only
progress tracking and smart decision-making. Unfinished activities were successfully shifted to other projects,
safeguarding key results despite budget and security challenges.
54. Mobilization of trust fund resources enabled effective supervision while advancing knowledge and innovation.
During implementation, the project secured five trust funds totaling US$1.7 million, which enabled effective oversight
and advance critical areas such as disaster risk reduction planning for transport infrastructure, integration of nature-
based solutions, analysis of barriers to women’s and girl’s access to education and health and delving into urban
mobility and private sector involvement in urban transport.
(c) Factors outside the control of government and/or implementing entities
55. Political instability, COVID19, and rising gang violence disrupted implementation. The assassination of President
Jovenel Moïse in July 2021, widespread protests and unrest, and “Peyi Lòk” lockdowns halted economic activity and
weakened institutions (Figure 2). Gang violence and kidnappings, especially in the Centre and Artibonite Departments,
made field operations hazardous and delayed Project execution. Additionally, the COVID19 pandemic further
challenged implementation during 2020. To overcome these challenges, the project recruited local technical staff for
on-site monitoring, restructured activities, and transferred unfinished works to other WB-financed projects.
56. Natural disasters compounded the difficulties, prompting emergency responses and project restructuring to
address urgent needs. On August 14, 2021, a magnitude 7.2 earthquake struck southern Haiti, causing over 2,000
deaths, major destruction, and isolating more than 450,000 people, with damages to over 850 km of road network
and losses estimated at US$160 million. Just three days later, Tropical Storm Grace brought flash floods and landslides,
further hampering rescue and recovery efforts. Another earthquake of magnitude 5.3 hit the Nippes region on January
24, 2022, damaging homes already affected by the previous disaster. These consecutive natural disasters (Figure 2),
alongside political, security, and COVID-19 crises, worsened the humanitarian and socio-economic situation.
Figure 2. Major Events in Haiti (2018-2025)
IV. BANK PERFORMANCE, COMPLIANCE ISSUES, AND RISK TO DEVELOPMENT OUTCOME
A. QUALITY OF MONITORING AND EVALUATION (M&E)
M&E Design
57. At appraisal, the M&E framework was robust, with clear objectives, comprehensive indicators, and explicit
responsibilities. A well-structured TOC linked activities to immediate outputs, intermediate outcomes, and long-term
The World Bank
Haiti Rural Accessibility & Resilience Project (P163490) ICR DOCUMENT
Page 12
Official Use Only
impacts, including improved accessibility, economic opportunity, and climate resilience. Gender and CE indicators,
along with a multi-criteria approach for selecting investment areas, ensured targeted and inclusive interventions.
Outcome indicators—including the rural population with access to all-weather roads, total population served by
climate-resilient roads, and people with restored road access—were specific, measurable, and directly aligned with
the PDOs, providing a solid basis for tracking progress and assessing impact. Intermediate indicators—such as
kilometers of roads rehabilitated, number of critical bridges built, territorial mobility plans developed, and citizen
satisfaction with investment designs—offered granular data for monitoring component-level progress. The inclusion
of social and environmental safeguards and the development of specialized tools (dashboard, bridge management
system) further strengthened the design. The indicators were adequate although some could have had more clarity
on the definition and methodology, these were revised through AF1 to enable teams to report more effectively and
consistently.
M&E Implementation
58. Implementation was consistent, with regular data collection and field missions, and proactive to project’s impacts.
Regular semi-annual reports and field missions enabled close monitoring, even in hard-to-reach areas. From 2018 to
2025, the project maintained consistent reporting via Implementation and Procurement Follow-up Tables, Gantt
charts, dashboards, Aide Memoires (AMs), and the Implementation Status and Results Reports (ISRs) to keep
stakeholders updated. Despite security, logistical, and data management challenges, including incomplete electronic
archiving, these issues did not hinder effective monitoring. The project adapted to security and logistical challenges
by recruiting local staff and leveraging mixed methods (quantitative surveys, qualitative interviews, focus groups).
Financial audits and a grievance redress mechanism (GRM) further promoted transparency and accountability. With
most activities concretely identify through implementation rather than at appraisal, the project proactively used its
restructuring to revise definitions, provide detailed methodologies for data collection, and revised intermediate and
final targets, demonstrating the project’s adaptability and responsiveness to external shocks. Institutional
arrangements for M&E fostered collaboration and accountability between UCE-MTPTC and UTE-MEF, with clear
responsibilities and reporting procedures detailed in the project implementation manual.
M&E Utilization
59. M&E findings were used to inform project restructurings (e.g., CERC activation after the earthquake), resource
reallocations, and future planning. M&E findings were actively used to inform project adjustments, strategic shifts,
and future recommendations. M&E data facilitated prioritization of actions, improved budget absorption, and
informed recommendations for institutionalizing participatory monitoring, integrating climate and gender
dimensions, and strengthening road information systems. The impact study provided actionable recommendations
and highlighted significant positive outcomes (improved accessibility, resilience, beneficiary satisfaction).
Justification of Overall Rating of Quality of M&E
60. The overall rating of quality of Project’s M&E system is Substantial—well-designed, effectively implemented, and
well-used for project management and learning. The system’s adaptability and comprehensive approach were notable
strengths, however minor design shortcomings, incomplete tool utilization and archiving issues prevented a “High”
rating. Continued improvements in these areas could further enhance M&E quality in future projects.
B. ENVIRONMENTAL, SOCIAL, AND FIDUCIARY COMPLIANCE
61. Overall Safeguard performance at Project closing was rated Satisfactory. At appraisal, the project was classified
“Category B” with “Moderate” risk rating, which remained consistent throughout the project’s lifetime, as activities
were small to medium in scale and posed no significant or irreversible impacts. Indeed, the rating reflects limited land
acquisition, potential economic displacement, and the need to address vulnerable groups; however, no large-scale or
irreversible social impacts were expected. The project triggered several safeguard policies, including Environmental
The World Bank
Haiti Rural Accessibility & Resilience Project (P163490) ICR DOCUMENT
Page 13
Official Use Only
Assessment (OP/BP 4.01), Natural Habitats (OP/BP 4.04), Physical Cultural Resources (OP/BP 4.11) and Involuntary
Resettlement (OP/BP 4.12), with mitigation measures detailed in an Environmental and Social Management
Framework, site-specific Environmental and Social Management Plans, a Resettlement Policy Framework, and site-
specific Resettlement Action Plans, with regular consultation and disclosure. Risk was addressed through an
Environmental and Social Management Framework and site-specific plans, with compliance rated “Satisfactory” (S)
throughout the lifespan. Moreover, social risks—e.g., labor influx and GBV—were effectively managed through
participatory planning, compensation protocols, and robust GRM, with 100 percent of registered grievances
addressed. A significant incident resulting in a fatality occurred in October 2021 when a truck engaged in loading
operations experienced brake failure and struck a nearby child. Following the incident, the client implemented a
corrective action plan, which was executed satisfactorily. Environmental compliance was rated “S” throughout
implementation, with UCE-MTPTC demonstrating strong capacity in environmental and social risk management,
including diligent monitoring, reporting, and adaptation to challenges such as COVID-19 and natural disasters. No
major environmental incidents or non-compliance issues were reported, and all required safeguards instruments were
prepared, disclosed, and implemented effectively. Social performance was rated “S” throughout implementation,
and the social risk rating remained “Moderate” for most of the project, rising to “Substantial” only at closure due to
external factors such as political instability and security constraints, rather than project-specific shortcomings. Overall,
the project maintained high standards of social safeguard compliance and stakeholder engagement despite operating
in a challenging context.
62. At closing, the project’s FM and Procurement performance were rated” Moderately Unsatisfactory” (MU) and
“Satisfactory” respectively. The project maintained strong fiduciary compliance in both procurement and financial
management throughout its lifetime, despite operating in a highly challenging environment. Procurement was
consistently rated “MS” for most of the lifespan, with an upgrade to “S” in the final stages, reflecting the successful
completion of over 100 procurement activities totaling more than US$77 million. While some procurement processes
faced delays and a limited number of valid bids, these were mitigated by experienced staff and close Bank support,
and all major contracts were completed, except for the construction of the St-Michel center. Financial management
(FM) was also rated “MS” for most of the project, with timely submission of Interim Financial Reports (IFRs) and audit
reports, and no ineligible expenditures reported. However, FM ratings were temporarily downgraded to “MU” in late
2024 and early 2025 due to unresolved issues such as delays in revising procedures manuals, incomplete asset
inventories, and missing bank account reconciliations. These issues were exacerbated by staff turnover and security
incidents, but UCE took steps to address recommendations and restore compliance including: (i) reporting FM issues
in the AM and MAL, (ii) establishing an action plan to upgrade the ratings as described in the different AM and (iii)
holding regular meetings between the Bank FM specialist and UCE FM specialist to monitor progress and propose
recommendations. Overall, fiduciary risk was rated “Substantial” at approval, reduced to “Moderate” during
implementation, and briefly returned to “High” at closure due to late-stage audit delays and persistent internal control
weaknesses. Despite these challenges, the project demonstrated resilience and adaptability, ensuring the integrity of
fiduciary processes.
C. BANK PERFORMANCE
Quality at Entry
63. The project’s design leveraged extensive lessons from previous Bank-financed transport operations in Haiti to
maximize resilience, connectivity, and resource efficiency. Drawing on a foundation established by projects like the
Transport and Territorial Development Project (P095523), the Emergency Bridge Reconstruction and Vulnerability
Reduction Project (P114292) and the other transport projects in Haiti, it incorporated proven strategies for reducing
vulnerability and improving connectivity amid resource and coordination challenges. Key technical assistance,
including surveys, road assessments, and the National Bridge Inventory, has shaped the project’s targeted spot
improvements, robust asset management, and technical support to address vulnerabilities.
The World Bank
Haiti Rural Accessibility & Resilience Project (P163490) ICR DOCUMENT
Page 14
Official Use Only
64. The project was designed as part of a continued engagement in Haiti’s transport sector, with a vision beyond project
closing. Building on the above-mentioned transport operations, it also laid the foundation for future support in critical
areas such as urban mobility and private sector participation in transport services, and bridge management. Studies
financed under Component 3 informed follow-up operations such as the RUTAP and the Resilient Corridor Project
(P510851), ensuring continuity and long-term impact.
65. Strong strategic alignment and comprehensive design enabled an effective project launch. The project’s objectives
closely matched Haiti’s development priorities, and aligned with the CPF and sectoral strategies, what ensured high
relevance and buy-in. The design integrated multiple components—including road rehabilitation, resilience-building,
sustainable mobility, emergency response, and project management—that addressed both immediate and long-term
needs. By incorporating a CERC from the start, the project was able to respond rapidly to unforeseen disasters such
as the 2021 earthquake, demonstrating foresight and adaptability.
66. Rigorous technical, social, and risk considerations enhanced project robustness. Extensive technical and social
analyses—drawing on sector diagnostics, prior lessons, and stakeholder consultations—strengthened the project
framework. The integration of gender and climate considerations through targeted indicators and activities promoted
inclusivity and resilience. Environmental and social safeguards were properly addressed with appropriate
classifications and robust frameworks, while fiduciary responsibilities were assigned to capable entities and supported
by clear financial management and procurement strategies. The design further identified and planned for substantial
risks, with mitigation strategies such as a flexible design and emergency components, reinforcing the project’s
resilience and likelihood of success.
Quality of Supervision
67. Close technical implementation support missions provided extensive technical guidance to the GoH and the PIUs.
The project benefitted from field presence of a multi-disciplinary team throughout implementation with few
turnovers, enabling regular dialogue with the GoH and close supervision. Since approval in 2018, the WB and the GoH
jointly carried out 13 official implementation support missions, both in-person and virtual, and a Mid-Term Review
mission on November 2021, that helped identify and resolve bottlenecks and prepare three restructurings.
68. Proactive and adaptive supervision enabled effective crisis response. The Bank demonstrated adaptability and
speed, notably activating the CERC and reallocating resources after the 2021 earthquake. The three restructurings
addressed evolving needs, while regular supervision missions, tracked through ISRs, aide-memoires, and impact
studies, ensured continuous engagement with the PIUs and key stakeholders. The Bank quickly introduced operational
mitigation measures to ensure smooth implementation during crisis starting during the “peyi lock”, during the COVID-
19 crisis and the most recent security crisis. It included (i) provision of equipment to PIUs for home-based working
(e.g., Internet access, batteries, and laptops); (ii) deployment of individual supervisors to strengthen field PIU’s
capacity; (iii) reorganization of work sites to promote social distancing and mechanized works wherever possible; and
(iv) the expansion of work schedules (night and day) to support appropriate social distancing practices.
69. Supportive oversight addressed implementation and safeguard challenges. The Bank provided technical and
fiduciary support to tackle financial management and procurement delays, including hiring consultants and
strengthening UCE capacity. It also reinforced the application of environmental and social safeguards through
corrective action plans, CE and GRM. Lessons learned were integrated into restructurings and additional financing,
especially for emergency response and local capacity development.
Justification of Overall Rating of Bank Performance
70. On account of all above considerations, the overall rating for WB performance is Highly Satisfactory. The project
was well tailored to Haiti’s context, drawing on lessons learned from similar operations and built in mitigation
The World Bank
Haiti Rural Accessibility & Resilience Project (P163490) ICR DOCUMENT
Page 15
Official Use Only
measures for identified risks The WB has measured its involvement and the nature of its support as required by the
emergency, expectations and difficulties of the context.
D. RISK TO DEVELOPMENT OUTCOME
71. Inadequate road maintenance and delays in timely repairs have been identified as significant risks to the
sustainability of outcomes, potentially undermining the long-term benefits of improved connectivity and resilience.
While community training on basic rural road maintenance has reached many beneficiaries, the overall system for
routine and periodic maintenance remains under-resourced and vulnerable to disruptions from security issues,
funding gaps, and institutional weaknesses. These shortcomings risk accelerating the deterioration of road assets,
especially in Haiti’s disaster-prone environment. Without robust maintenance mechanisms and rapid response
capabilities, the gains in rural accessibility and resilience achieved may not be sustained, potentially leaving
communities once again isolated and undermining broader development objectives.
72. Persisting insecurity, gang control, and climate impacts pose significant risks to the development outcomes of the
project. The spread of gang activity into project areas may further disrupt mobility, block access to key infrastructure,
and limit the safe movement of goods, people, and project teams. Additionally, Haiti’s vulnerability to climate hazards
frequently damages roads and bridges, isolates rural communities, and interrupts access to essential services. These
combined risks are especially severe for the rural poor, women, and marginalized groups, who face greater barriers
to markets, health care, and education and could undermine progress on rural connectivity and resilience,
jeopardizing the project’s ability to deliver inclusive and sustainable development benefits.
73. The disrepair of health centers threatens to reverse the project’s achievements in improving women’s access to
essential health services, undermining both health outcomes and gender equity. The project has enabled more
women, especially in rural areas, to benefit from maternal and reproductive health services. However, when facilities
deteriorate, women face renewed barriers to care, including unsafe conditions, unreliable water and sanitation, and
disrupted services such as antenatal care and screenings. This not only discourages service utilization but also risks
reversing progress in reducing maternal and child mortality. Therefore, sustained investment in health care facilities
is key to preserving the project’s development gains and ensured improvements in women’s health.
V. LESSONS AND RECOMMENDATIONS
74. The project has demonstrated that rural connectivity and transport infrastructure resilience can be improved even
amid political instability and gang violence, given targeted support and adaptative strategies. Key lessons include:
(i) prioritizing simple, low-impact investments with immediate benefits; (ii) maintaining contingency plans to ensure
continuity during crises; (iii) adopting flexible frameworks to adjust to evolving conditions; and (iv) relying on
experienced PIUs with low staff turnover and proven track records.
75. Continued sector engagement allows for a programmatic vision beyond project closing, efficient implementation
and high-quality project design. Since reengaging with Haiti in 2004, the transport sector has been a cornerstone of
the partnership between the World Bank and the Republic of Haiti, maintaining strong relationships with government
stakeholders and other development partners. This Project was the sixth IDA transport Operation since 2004 allowing
for continued engagement in the sector, proactively incorporating lessons learned, and designing project with a mid-
term vision (para. 63 and 64). Implementation has equally benefited from this continued engagement as the UCE has
implemented Bank-financed projects in the transport sector for over 18 years, becoming highly experienced in
managing World Bank financed projects in the transport sector, with extensive knowledge of the Bank’s fiduciary and
safeguard procedures (para. 53). This highlights the benefits of long-term investment in local capacity and client
engagement through a series of interventions to support a programmatic vision
76. The framework approach enabled flexibility and responsiveness, allowing interventions adapted to local needs and
evolving circumstances. Priority regions and broad intervention types were identified during preparation, while the
The World Bank
Haiti Rural Accessibility & Resilience Project (P163490) ICR DOCUMENT
Page 16
Official Use Only
specific locations and activities selection were finalized during implementation through a participatory process (para.
50). This approach ensured that investments were targeted where they would have the greatest impact and allowed
adjustments for unforeseen events like natural disasters or shifting security conditions (para. 56). Community
engagement fostered local ownership and facilitated timely identification of priority investments. The flexible
framework approach also supported efficient resource allocation and sustained progress despite Haiti’s volatile
context, ultimately contributing to the sustainability and effectiveness of project outcomes (para 42).
77. Close implementation support and supervision—backed by financial and human resources aligned with the
project’s scale and the complexity of implementation—are critical in Haiti’s fragile, low-capacity context. UCE
adapted to political instability (para. 68) by establishing regional offices in Cap Haitian and in Cayes (the latter currently
being implemented), maintaining low staff turnover, and ensuring close supervision through country-office-based
staff, including the team lead. This has been critical and allowed for faster identification and effective resolution of
fiduciary and safeguard issues (para. 61). Third-party monitoring, involving communities and local consultants,
ensured effective oversight and engagement. A procurement strategy was also developed to involve SMEs rooted in
the communities. Over the past 20 years, the PIU has also gradually built up a network of reliable regional SMEs,
facilitating smoother execution and boosting local economic participation and resilience (para 45).
78. Labor-intensive works (LIW) in transport projects have become a vehicle for social cohesion, job creation and
income generation in vulnerable communities. In Haiti, where lack of social cohesion and opportunities are primary
drivers of conflict, instability and gang violence (para. 73), transport projects have contributed to address root causes
by providing employment and fostering community engagement, which are crucial for promoting social stability (para.
47). While violence persists in some well-connected areas, as seen in Port-au-Prince, Haiti’s situation differs from
other Fragile, Conflict and Violence contexts such as the ones with active armed conflicts. Improving infrastructure
has provided better economic opportunities (para. 29) and direct employment LIW, the project strengthened
community resilience, reduced the appeal of gang involvement and promote social stability in Haiti.
The World Bank
Haiti Rural Accessibility & Resilience Project (P163490) ICR DOCUMENT
Page 17
Official Use Only
ANNEX 1. RESULTS FRAMEWORK AND KEY OUTPUTS
@#&OPS~Doctype~OPS^dynamics@icrresultframework#doctemplate
A. RESULTS FRAMEWORK
PDO Indicators by Outcomes
Increase all-weather road access in selected sub-regions
Indicator Name
Baseline Closing Period (Original) Closing Period (Current) Actual Achieved at Completion
Result Month/Year Result Month/Year Result Month/Year Result Month/Year
Share of rural population in selected
sub-regions with access within 2 km
to an all-weather road (Percentage)
36.00 Nov/2017 55.00 Jun/2024 63.00 May/2025
Comments on achieving targets This indicator is completed.
Improve the resilience of selected segments of the road network.
Indicator Name
Baseline Closing Period (Original) Closing Period (Current) Actual Achieved at Completion
Result Month/Year Result Month/Year Result Month/Year Result Month/Year
Total population living in areas
serviced by connecting roads
upgraded to a climate resilient
standard (Number)
0.00 Feb/2018 700,000.00 Jun/2023 902,267.00 May/2025
Comments on achieving targets The indicator is achieved
Provide an immediate and effective response to an eligible crisis or emergency
Indicator Name
Baseline Closing Period (Original) Closing Period (Current) Actual Achieved at Completion
Result Month/Year Result Month/Year Result Month/Year Result Month/Year
People with restored access to the
road network (Number)
0.00 Jan/2022 407,000.00 Dec/2022 422,337.00 May/2025
Comments on achieving targets This indicator is achieved
Intermediate Indicators by Components
The World Bank
Haiti Rural Accessibility & Resilience Project (P163490) ICR DOCUMENT
Page 18
Official Use Only
Enhancing Rural Connectivity
Indicator Name Baseline Closing Period (Original) Closing Period (Current) Actual Achieved at Completion
Result Month/Year Result Month/Year Result Month/Year Result Month/Year
Roads rehablitated (Kilometers)
0.00 Nov/2017 480.00 Jun/2024 554 May/2025
Comments on achieving targets This indicator is achieved
Roads rehabilitated - rural
(Kilometers)
0.00 430.00 499.00
Comments on achieving targets Indicator achieved
Roads rehabilitated - non-rural
(Kilometers)
0.00 50.00 55.00
Comments on achieving targets Indicator achieved
Number of territorial mobility plans
developed, climate informed and
incorporating women´s security
needs (Number)
0.00 Nov/2017 3.00 Dec/2021 3.00 May/2025
Comments on achieving targets Mobility plans for the three micro-regions have been completed
Share of citizens who consider that
design of investments subjected to
consultation is responsive to their
needs/views (%) (Percentage)
0.00 Feb/2018 70.00 Jun/2024 80.00 May/2025
Comments on achieving targets This indicator is achieved
Of which women, to reflect
the focus of consultations on
gender (Percentage)
0.00 90.00 95.00
Comments on achieving targets This sub-indicator is achieved
Number of people who can access
regional size markets within 120
minutes in select project areas
(Number)
525,000.00 Nov/2017 660,000.00 Jun/2024 720,620.00 May/2025
Comments on achieving targets This indicator is achieved
Number of women who can access
health services with obstetrical
facilities within 60 minutes in select
project areas (Number)
255,500.00 Nov/2017 320,000.00 Jun/2024 327,000.00 May/2025
Comments on achieving targets This indicator is achieved
0.00 Mar/2020 4.00 Feb/2022 4.00 May/2025
The World Bank
Haiti Rural Accessibility & Resilience Project (P163490) ICR DOCUMENT
Page 19
Official Use Only
Number of critical bridges built in the
CAL region (Number)
Comments on achieving targets This indicator is achieved
Spot interventions to enhance all-
weather and resilient connectivity in
the selected sub-regions of the
Center of Artibonite Loop Region
(Number)
0.00 Mar/2020 5.00 Jun/2022 5 May/2025
Comments on achieving targets This indicator is achieved
Number of Road Maintenance
Centers build or rehabilitated in the
selected sub-regions of the Center of
Artibonite Loop Region (Number)
0.00 Mar/2020 1.00 May/2025 1.00 May/2025
Comments on achieving targets This indicator is achieved
Number of people trained within
selected communities on basic Rural
Road Maintenance in the selected
sub-regions of the Center of
Artibonite Loop Region
(disaggregated by gender)
(Number)
0.00 Mar/2020 200.00 Dec/2022 166.00 May/2025
Comments on achieving targets This indicator is significantly achieved. Completion target is 83 percent of estimated at appraisal. The target at
completion was substantial enough to support the project development outcomes as originally planned.
Disaggregated by gender, in %
of women (Percentage)
0.00 35.00 75.00
Comments on achieving targets This sub-indicator was achieved
Urban and rural markets
rehabilitated/constructed in the
selected sub regions of the Center of
Artibonite Loop Region (Number)
0.00 Mar/2020 4 May/2025 4.00 May/2025
Comments on achieving targets This indicator is achieved
Urban plans developed and consulted
with Local officials and local
stakeholders in the selected sub-
regions of the Center of Artibonite
Loop Region (Number)
0.00 Mar/2020 3.00 Jun/2023 4 May/2025
Comments on achieving targets This indicator is achieved
Regional development dashboard
with open data including spatial
analysis encompassing risk and
climate data developed with Local
No Mar/2020 Yes Jun/2024 Yes May/2025
Comments on achieving targets This indicator is achieved
The World Bank
Haiti Rural Accessibility & Resilience Project (P163490) ICR DOCUMENT
Page 20
Official Use Only
officials and local stakeholders in the
CAL Region (Yes/No)
Grievances registered related to
delivery of project benefits that are
addressed (%) (Percentage)
0.00 Mar/2018 80.00 Jun/2024 100 May/2025
Comments on achieving targets 100% of registered grievances addressed
Improving Resilience of Transport Connecting Infrastructure
Indicator Name Baseline Closing Period (Original) Closing Period (Current) Actual Achieved at Completion
Result Month/Year Result Month/Year Result Month/Year Result Month/Year
Number of critical bridges
rehabilitated or protected on the
primary and secondary network
(Number)
0.00 Nov/2017 8 May/2025 8.00 May/2025
Comments on achieving targets This indicator is achieved
Number of critical spot/segments
built or rehabilitated on the primary
and secondary road network
(Number)
0.00 Jan/2018 150.00 May/2025 124.00 May/2025
Comments on achieving targets This indicator is significantly achieved. Completion target is 83 percent of estimated at appraisal. The target at
completion was substantial enough to support the project development outcomes as originally planned and
reflects the complexity of target estimations in a framework design approach.
Bridge Management System within
MTPTC developed and functional
(Yes/No)
No Feb/2018 Yes Jun/2024 Yes May/2025
Comments on achieving targets Bridge Management System is installed and functional
Promoting Sustainable Mobility Development
Indicator Name Baseline Closing Period (Original) Closing Period (Current) Actual Achieved at Completion
Result Month/Year Result Month/Year Result Month/Year Result Month/Year
Climate Resilient and Sustainable
Mobility Roadmap prepared and
associated monitoring tool developed
(Yes/No)
No Jan/2018 Yes Jun/2023 No May/2025
Comments on achieving targets This indicator is partially achieved with roadmaps completed. The indicator is marked as “NO” as the
development of the tool is not completed due to technical complexity in procurement and institutional capacity
to manage software development. While the procurement was completed by Project’s closing date, the
implementation will be taken over by the RUTAP. The partial achievement does not affect the outcome as the
studies provides substantial institutional capacity on resilient and sustainable mobility.
Establishment of a road traffic
database and monitoring tool
(Yes/No)
No Feb/2018 Yes Jun/2024 No May/2025
Comments on achieving targets This indicator is unmet due to ongoing security challenges that prevented safe data collection and
implementation. While the procurement was finalized before Project’s closing date, the implementation of the
activity has been transferred to the RUTAP project awaiting for security situation to improve.
The World Bank
Haiti Rural Accessibility & Resilience Project (P163490) ICR DOCUMENT
Page 21
Official Use Only
Road safety assessments/measures
included as part of all technical
design and feasability studies
(Yes/No)
No Mar/2018 Yes Jun/2024 Yes May/2025
Comments on achieving targets The indicator is achieved
Contingent Emergency Response
Indicator Name Baseline Closing Period (Original) Closing Period (Current) Actual Achieved at Completion
Result Month/Year Result Month/Year Result Month/Year Result Month/Year
Critical bridges repaired or
reconstructed (Number)
0.00 Jan/2022 7.00 Dec/2022 8 May/2025
Comments on achieving targets This indicator is achieved
Critical spots treated (Number)
0.00 Aug/2021 80.00 Jun/2022 90 May/2025
Comments on achieving targets This indicator is achieved
The World Bank
Haiti Rural Accessibility & Resilience Project (P163490) ICR DOCUMENT
Page 22
Official Use Only
B. KEY OUTPUTS
Increase all-weather road access in selected sub-regions
PDO Indicators
2. Share of rural population in selected sub-regions with access within 2 km to
an all-weather road
Key Outputs
(linked to the achievement of the PDO Outcome)
1. Rehabilitation of Rural Roads: 554km including 449km of rural roads and
55km of non-rural roads
2. Construction and Rehabilitation of Bridges and Culverts: 4 in the Boucle
Centre-Artibonite (BCA) region including on the Bretelle, Bonbon, Rio Frio,
Wallondry, and L’Attalaye rivers
3. Spot Interventions for All-Weather and Resilient Connectivity: 5 in
selected sub-regions of the Boucle Centre-Artibonite region. Targeted
interventions on road sections such as Aquin-Fonds-des-Blancs, Petit Trou
de Nippes-Baradères, and Titanyen-Saut d’Eau
4. Development of Territorial Mobility Plans and Capacity Building: 3,
climate-informed and incorporating women’s security needs and 200
people within selected communities trained on basic rural road
maintenance
Improve the resilience of selected segments of the road network.
PDO Indicators
3. Total population living in areas serviced by connecting roads upgraded to a
climate resilient standard
Key Outputs
(linked to the achievement of the PDO Outcome)
1. Rehabilitation and Upgrading of Rural and Connecting Roads to Climate-
Resilient Standards: 400 km of tertiary and rural road network, including
spot improvements, maintenance, and repair of 80 km of rural and non-
rural roads to ensure all-weather access. Upgrades included slope
stabilization, improved drainage, and use of weather-resistant materials.
Targeted road sections included Titanyen-Saut d’Eau, Saint Michel-Saint-
Raphaël, Dessalines-Saint-Michel, Hinche-Thomassique, and others
The World Bank
Haiti Rural Accessibility & Resilience Project (P163490) ICR DOCUMENT
Page 23
Official Use Only
2. Construction and Rehabilitation of Climate-Resilient Bridges and Culverts:
Construction of four climate-resilient bridges in the Boucle Centre–
Artibonite region and additional bridges on key road sections. Construction
of culverts on the Bretelle river and other critical points to prevent flooding
and ensure year-round connectivity. Rehabilitation and protection of
critical bridges (e.g., Trou du Nord, Bellevue, Cutis, Port-à-Piment, Rouge,
Virgile, Carrefour 44)
3. Protection and Stabilization of Road Infrastructure: Construction of
embankment walls, retaining walls, and erosion control structures to
protect roads from landslides and water damage. Protection of riverbanks
(e.g., Sucrerie Henry, Pont Boileau) and road sections (e.g., RD22 in Dupuy
and Madian). Rehabilitation of roads and urban sections (e.g., Rue générale
Marion, Chaussée in Cayes).
4. Development of Institutional Capacity and Emergency Response:
Development and operationalization of a bridge management system
within MTPTC to support ongoing maintenance and resilience. Training
of 200 people from beneficiary communities in basic rural road
maintenance. Activation of the Contingent Emergency Response
Component (CERC) post-earthquake (2021), supporting rapid
restoration of connectivity, construction of temporary bridges (e.g.,
Jérémie), and rehabilitation of critical infrastructure.
Provide an immediate and effective response to an eligible crisis or emergency
PDO Indicators 4. People with restored access to the road network
Key Outputs
(linked to the achievement of the PDO Outcome)
1. Restoration and Repair of Critical Road Network Segments: Improvement
of the Cance-Batte segment (South department). Construction and
rehabilitation of multiple culverts (dalots) in Cahoane, Les Anglais-Tiburon,
Carrefour maçon-Débouchette-Saint-Jean du Sud, Anse-à-veau–Arnault,
The World Bank
Haiti Rural Accessibility & Resilience Project (P163490) ICR DOCUMENT
Page 24
Official Use Only
and Carrefour La Colline on RN 2. Rehabilitation of General Marion Street
and hydraulic concrete road in Cayes. Protection works on riverbanks (e.g.,
Sucrerie Henry, Pont Cavaillon) and bridges (e.g., Pont de Port-à-Piment,
Pont Brash, Pont des Coteaux). Additional works in Baradères, Cascade,
Titanyen-Saut d’Eau, and Hinche-Maissade sections.
2. Construction of Temporary Bridge and Restoration of Connectivity: A
temporary bridge was constructed in Jérémie to re-establish connectivity
with Grand’Anse, a region isolated by the earthquake.
3. Repair and Reconstruction of Critical Bridges and Points: 8 critical bridges
were repaired or reconstructed, and 90 critical points were
treated/stabilized.
4. Support for Building Evaluation and Rehabilitation of Other Critical
Infrastructure: Activities supported the evaluation of buildings by the
Technical Building Office (BTB) of MTPTC. Rehabilitation of irrigation canals
and water supply systems in affected areas was also supported,
contributing to broader recovery efforts
The World Bank
Haiti Rural Accessibility & Resilience Project (P163490) ICR DOCUMENT
Page 25
Official Use Only
Project Management
Intermediate Results Indicators No indicator
Key Outputs
(linked to the achievement of the Component)
Contingent Emergency Response
Intermediate Results Indicators
25. Critical bridges repaired or reconstructed
26. Critical spots treated
Key Outputs
(linked to the achievement of the Component)
1. Construction and Rehabilitation of Bridges and Culverts:
• Construction of four bridges on the Hinche-Maïssade and Saint-
Michel-Saint-Raphaël Road sections.
• Rehabilitation of the Port-à-Piment Bridge and construction of a
large culvert at the entrance of Gelée.
• Construction of three culverts on the Maçon-Débouchette-Saint-
Jean du Sud section and three culverts on the Les Anglais-Tiburon
axis.
2. Maintenance and Repair of Critical Road Sections and Points:
• Stabilization and repair of 80 km of rural and non-rural roads.
• Improvement of critical punctual points such as culverts, bridges,
and slope stabilization on key road sections (Titanyen-Saut d’Eau,
Saint Michel-Saint-Raphaël, Dessalines-Saint-Michel, Hinche-
Thomassique).
3. Urban Infrastructure Rehabilitation
• Rehabilitation of General Marion Street in Les Cayes, addressing
critical urban connectivity.
The World Bank
Haiti Rural Accessibility & Resilience Project (P163490) ICR DOCUMENT
Page 26
Official Use Only
• Reconstruction of 1260 meters of hydraulic concrete pavement in
Les Cayes, enhancing resilience and durability of urban
infrastructure.
4. Protection of Riverbanks and Erosion Control
• Protection of riverbanks at Sucrerie Henry (Colline-Fonds-des-
Blancs), safeguarding critical infrastructure from natural hazards.
• Implementation of erosion control measures and construction of
retaining walls to protect road and bridge assets.
Promoting Sustainable Mobility Development
Intermediate Results Indicators
23. Establishment of a road traffic database and monitoring tool
22. Climate Resilient and Sustainable Mobility Roadmap prepared and
associated monitoring tool developed
24. Road safety assessments/measures included as part of all technical design
and feasability studies
Key Outputs
(linked to the achievement of the Component)
1. Integration of Road Safety Measures in Technical Studies: All technical
design and feasibility studies for project-financed works included road
safety assessments and measures, ensuring that new and rehabilitated
infrastructure meets safety standards and contributes to safer mobility.
2. Preparation of Technical Specifications and Terms of Reference: Technical
specifications and Terms of Reference for the road traffic database and
monitoring tool, as well as for the climate resilient and sustainable mobility
roadmap, were developed and finalized, laying the groundwork for future
implementation.
3. Consultant Engagement and Delivery of Preliminary Reports:
Consultants were engaged for both the road traffic database and the
mobility roadmap. Preliminary reports and databases were delivered,
providing a foundation for future activities, even though full
implementation was not achieved within the project period.
The World Bank
Haiti Rural Accessibility & Resilience Project (P163490) ICR DOCUMENT
Page 27
Official Use Only
Improving Resilience of Transport Connecting Infrastructure
Intermediate Results Indicators
19. Number of critical bridges rehabilitated or protected on the primary and
secondary network
20. Number of critical spot/segments built or rehabilitated on the primary and
secondary road network
21. Bridge Management System within MTPTC developed and functional
Key Outputs
(linked to the achievement of the Component)
1. Rehabilitation and Protection of Critical Bridges
• Eight critical bridges were rehabilitated or protected. These included
bridges in Damassin, Bash à Léogane, Milet à Roche-à-Bateau, and
Coteaux, among others.
• Works involved structural repairs, reinforcement, hydraulic
protection, and slope stabilization to ensure long-term durability
against climate hazards.
2. Construction and Rehabilitation of Critical Road Segments and Spots
• 124 critical spots/segments were built or rehabilitated, focusing on
areas prone to flooding, landslides, or other climate-related risks.
• Interventions included drainage improvements, retaining walls,
erosion control structures, and repairs to culverts and river
crossings, enhancing the resilience of the road network.
3. Development and Operationalization of the Bridge Management System
(BMS)
• The BMS was developed and made functional within MTPTC,
including the creation of a bridge inventory, assessment
protocols, and a management roadmap.
• Capacity-building activities were conducted, such as the training
workshop in Lyon, to ensure effective use and sustainability of
the system.
The World Bank
Haiti Rural Accessibility & Resilience Project (P163490) ICR DOCUMENT
Page 28
Official Use Only
Enhancing Rural Connectivity
Intermediate Results Indicators
2. Roads rehablitated
5. Number of territorial mobility plans developed, climate informed and
incorporating women´s security needs
6. Share of citizens who consider that design of investments subjected to
consultation is responsive to their needs/views ( percent)
8. Number of people who can access regional size markets within 120 minutes
in select project areas
9. Number of women who can access health services with obstetrical facilities
within 60 minutes in select project areas
10. Number of critical bridges built in the CAL region
11. Spot interventions to enhance all-weather and resilient connectivity in the
selected sub-regions of the Center of Artibonite Loop Region
12. Number of Road Maintenance Centers build or rehabilitated in the
selected sub-regions of the Center of Artibonite Loop Region
13. Number of people trained within selected communities on basic Rural
Road Maintenance in the selected sub-regions of the Center of Artibonite
Loop Region (disaggregated by gender)
15. Urban and rural markets rehabilitated/constructed in the selected sub
regions of the Center of Artibonite Loop Region
16. Urban plans developed and consulted with Local officials and local
stakeholders in the selected sub-regions of the Center of Artibonite Loop
Region
17. Regional development dashboard with open data including spatial analysis
encompassing risk and climate data developed with Local officials and local
stakeholders in the CAL Region
18. Grievances registered related to delivery of project benefits that are
addressed ( percent)
Key Outputs
(linked to the achievement of the Component)
1. Extensive Road Rehabilitation: Over 550 km of roads rehabilitated,
surpassing targets and improving year-round access for rural communities.
The World Bank
Haiti Rural Accessibility & Resilience Project (P163490) ICR DOCUMENT
Page 29
Official Use Only
2. Inclusive and Climate-Informed Mobility Planning: Three territorial
mobility plans developed, integrating climate resilience and women’s
safety, ensuring that infrastructure investments are sustainable and
inclusive.
3. Critical Infrastructure Construction: Four critical bridges and five spot
interventions completed, enhancing connectivity and resilience to climate
events.
4. Market and Health Access Improvements: Four public markets
constructed/rehabilitated, and over 326,000 women now have improved
access to health services with obstetric facilities.
5. Community Training and Capacity Building: 166 people trained in rural
road maintenance (75 percent women), building local capacity for
sustainable infrastructure upkeep.
6. Urban Planning and Data Systems: Four urban plans developed and a
regional dashboard established, supporting evidence-based planning and
monitoring.
7. Effective CE and Grievance Redress: High citizen satisfaction (80
percent), especially among women (95 percent), and 99 percent of
grievances addressed, reflecting strong participatory processes and
accountability.
C. INTERMEDIATE INDICATOR CHANGES
The World Bank
Haiti Rural Accessibility & Resilience Project (P163490) ICR DOCUMENT
Page 30
Official Use Only
Indicator Name Changes Done Rationale for Changes
ADDITIONAL FINANCING 1
INTERMEDIATE INDICATORS
Roads rehabilitated – rural (CRI, km) Moved from Component 2 to
Component 1; end target increased
by 80 km
Corrected component assignment error; target increased to
reflect additional works financed under the additional financing
(AF) in the CAL region.
Roads rehabilitated – non-rural (CRI, km) End target increased by 40 km Reflects additional works under AF in CAL.
Number of territorial mobility plans developed,
climate-informed and incorporating women’s security
needs
Definition consolidated; sub-
indicator merged
Consolidation to avoid duplication and report as a single, clearer
indicator.
Number of which are climate informed and
incorporate women’s security needs
Dropped (merged into parent
indicator above)
Redundant after consolidation into the main mobility plan
indicator.
Share of citizens who consider design of investments
responsive to their needs/views ( percent)
Intermediate targets revised Target phasing adjusted; no substantive scope change.
Of which women ( percent) Intermediate targets revised Target phasing adjusted; no substantive scope change.
Number of people who can access regional-size
markets within 120 minutes
Description updated Updated to include markets transferred from BCA.
Number of women who can access obstetrical health
services within 60 minutes
Measurement refined from “
percent change” to “number”
Improves measurability; percentage can be derived from
absolute numbers.
Number of critical bridges built in CAL Scope/wording clarified to selected
areas; activities transferred
Refined description; reflects activities transferred from BCA.
Spot interventions to enhance all-weather and
resilient connectivity (number)
Added Added to reflect BCA-transferred activities and resilience spot
treatments.
Number of Road Maintenance Centers
built/rehabilitated (CAL sub-regions)
Added Added to reflect BCA-transferred activities.
People trained on basic rural road maintenance
(disaggregated)
Added Added to capture capacity-building from transferred activities.
Disaggregated by gender: percent women among
trainees
Added Introduced to track gender inclusion in training.
The World Bank
Haiti Rural Accessibility & Resilience Project (P163490) ICR DOCUMENT
Page 31
Official Use Only
Indicator Name Changes Done Rationale for Changes
Urban and rural markets rehabilitated/constructed
(CAL)
Added Introduced to reflect activities transferred from CARDIP.
Urban plans developed and consulted (CAL sub-
regions)
Added Introduced to reflect BCA-transferred planning activities.
Regional development dashboard with open data,
including risk/climate layers
Added Introduced to strengthen evidence-based planning and risk-
informed decisions.
Grievances addressed ( percent) Description added Clarifies indicator description; no target change.
Critical bridges rehabilitated or protected
(primary/secondary network)
Wording clarified Explicitly references primary and secondary network scope.
Critical spots/segments built or rehabilitated
(primary/secondary network)
Wording clarified Explicitly references primary and secondary network scope.
Bridge Management System within MTPTC functional
(Yes/No)
Moved from Component 3 to
Component 2
Corrects component alignment; indicator pertains to
Component 2’s systems strengthening.
Climate Resilient and Sustainable Mobility Roadmap
prepared + monitoring tool
Revised (intermediate targets) Intermediate Target revised consistent with AF workplan.
Road traffic database and monitoring tool (Yes/No) Revised (intermediate targets) Intermediate targets revised consistent with AF workplan.
Road safety assessments/measures included in all
designs and feasibility studies (Yes/No)
Description updated Updated to capture BCA-transferred activities and mainstream
road safety recommendations during construction/design.
ADDITIONAL FINANCING 2
PDO INDICATOR
PDO statement Amended to add crisis response
objective (iii)
Adds “to provide immediate and effective response to an
eligible crisis or emergency” due to CERC activation following
Aug 2021 earthquake .
People with restored access to the road network
(number)
Added (PDO-level indicator) New PDO indicator to measure CERC outcomes after the
earthquake.
INTERMEDIATE INDICATORS
Critical bridges repaired or reconstructed (number) Added (Component 4 – CERC) Tracks connectivity restoration via bridge works under CERC.
Critical spots treated (number) Added (Component 4 – CERC) Tracks build-back-better rehabilitation of critical road spots .
The World Bank
Haiti Rural Accessibility & Resilience Project (P163490) ICR DOCUMENT
Page 32
Official Use Only
Indicator Name Changes Done Rationale for Changes
Roads rehabilitated (CRI, km) End target increased from 380 to
480 km
Scope expanded/updated feasibility; aligns with AF2
implementation plan.
Urban and rural markets rehabilitated/constructed
(CAL)
End target increased from 4 to 5 Scope adjustment reflecting updated AF2 program.
RESTRUCTURING FOR CANCELLATION
INTERMEDIATE INDICATORS
Urban and rural markets rehabilitated/constructed
(CAL)
End target decreased from 5 to 4 Downward revision due to cancellation of Saint Michel de
l’Attalaye Regional Market and associated funds.
Road Maintenance Centers (CAL sub-regions) End target decreased from 2 to 1 Downward revision due to cancellation of Hinche road
maintenance center and associated funs
Critical bridges rehabilitated or protected
(primary/secondary network)
End target decreased from 10 to 8 Downward revision of targets due to cancellation of two
proposed bridges (La Digue and Bethel).
The World Bank
Haiti Rural Accessibility & Resilience Project (P163490) ICR DOCUMENT
Page 33
Official Use Only
ANNEX 2. BANK LENDING AND IMPLEMENTATION SUPPORT/SUPERVISION
A. TASK TEAM MEMBERS
Name Role
Ibrahim Kabore Team Leader
Fabian Hinojosa Couleau Team Leader
Lydie Madjou Financial Management Specialist
Lucas Carrer Financial Management Specialist
Adjalou Celestin Niamien Financial Management Specialist
Vladimir Mathieu Procurement Specialist
Maurice Adoni Procurement Specialist
Khalid Anouar Environmental Specialist
Kevin McCall Environmental Specialist
Barnet Joseph Environmental Specialist
Lisbet Kugler Environmental Specialist
Bruce MacPhail Social Specialist
Felipe Jacome Social Specialist
Maria Laettitia Antoine Procurement Team
Maria Cristina Rosa Lucia Villani Procurement Team
Licette M. Moncayo Team Member
Sonia Rousseau-Lopez Team Member
Nicolas Antoine Robert Collin Dit De Montesson Team Member
Xavier Espinet Alegre Team Member
Iris Teluska Team Member
Eric Andre Christophe Jannaud Team Member
Patricia De la Caridad Marrero Team Member
Malaika Becoulet Team Member
@#&OPS~Doctype~OPS^dynamics@icrannexstafftime#doctemplate
B. STAFF TIME & COST
The World Bank
Haiti Rural Accessibility & Resilience Project (P163490) ICR DOCUMENT
Page 34
Official Use Only
Stage of Project Cycle
Staff Time & Cost
No. of Staff Weeks US$ (including travel and consultant costs)
Preparation
FY17 2.515 24,842.55
FY18 42.100 323,641.92
FY19 1.802 10,807.58
FY20 0.075 441.90
FY22 1.100 5,842.32
FY23 1.715 26,434.93
FY24 0.000 52,540.00
Total 49.31 444,551.20
Supervision/ICR
FY19 23.006 192,679.94
FY20 16.153 255,440.23
FY21 30.204 503,487.81
FY22 75.871 627,398.19
FY23 82.039 616,720.79
FY24 34.269 171,081.54
FY25 11.454 117,467.16
FY26 0.570 9,729.73
Total 273.57 2,494,005.39
The World Bank
Haiti Rural Accessibility & Resilience Project (P163490) ICR DOCUMENT
Page 35
Official Use Only
The World Bank
Haiti Rural Accessibility & Resilience Project (P163490) ICR DOCUMENT
Page 36
Official Use Only
ANNEX 3. PROJECT COST BY COMPONENT
Component Amount at Approval (US$M) Actual at Project Closing (US$M)
Enhancing Rural Connectivity 45.0 90
Improving Resilience of Transport
Connecting Infrastructure
22.0 3.2
Promoting Sustainable Mobility
Development
3.0 1.0
Contingent Emergency Response 1.0 30.3
Project Management 4.0 6.0
Note: Shortcomings in Financial management affected both the allocation and reporting of funds. When the CERC was
triggered, $30 million was shifted from components 1 and 2 for emergency activities. Although Additional Financing 2 was
meant to restore these funds, $15 million meant for component 2 was not properly reflected in the financial records and
was instead reported under component 1 in the Interim Financial Reports (IFRs). As a result, while more money was actually
used for component 2 activities, only $3 million was officially recorded. This misreporting led to an underrepresentation of
expenditures for primary and secondary roads, making the limited amount reported for component 2 primarily a result of
financial management shortcomings rather than project implementation decisions.
The World Bank
Haiti Rural Accessibility & Resilience Project (P163490) ICR DOCUMENT
Page 37
Official Use Only
ANNEX 4. EFFICIENCY ANALYSIS
1. The economic evaluation covers all interventions under Component 1, 2 and 4, with a scenario-based approach the
analysis simulated flood damages for the target regions and calculated the damage level and associated costs. In addition,
the road damage results were used to calculate the user costs. To do this, an innovative scenario based methodological
approach
4
was developed to estimate the avoided potential flood, and the associated user and emission costs, that will be
enabled by the climate resilience investment in the road network. The analysis simulates 10,000 scenarios with random
flood events occurring across the analysis period (20 years) ranging from 1 in 5 and 1 in 1,000 events. We estimated, under
current climate conditions, a baseline mean annual economic cost of US$ 52.7 million on road asset damages due to
coastal, fluvial and pluvial flooding. To account for climate change, we tested the economic evaluation using increased
precipitation intensity due to climate projections related to the 2035-64 period for the SSP 5-8.5 that account for
intermediate and pessimistic global decarbonization scenarios. Under this climate change scenario, the annual economic
cost on road asset damages without project intervention could increase by 6.5 percent up to US$ 56.16 million.
1. For each climate scenario probabilistic cash flow analysis (10,000 iterations) was implemented to evaluate the return on
investment of the $110 million climate resilience improvement projects on the road networks.
Figure A4.1 Probability Distribution of Damage Repair Cost across 10,000 scenarios for current climate condition (left) and climate
projections (right)
2. Among these impacts, attempts are made to quantify the benefits in monetary terms. These are the direct benefits
from reducing climate impacts that will accrue to beneficiaries:
• Reduction in asset damages loss. The impacts from disasters (river and coastal flooding) are included in the
economic analysis. The analysis calculates the reduction on repair and rehabilitation damages. Flooding maps and
water depths combined with scientific damage curves are used to quantify baseline infrastructure damages and
the costs of repairs (based on current construction costs) (Figure A4.1). Reduction is measure as the avoided
damages due to improved climate resilience.
• Reduction in users’ losses. The analysis include reduction on users’ economic losses as results of strengthening the
resilience of transport assets. The analysis uses a network approach to user losses by identify road disruption and
alternative road paths. The disaster scenarios equivalent to flood events that range from a 5 to 1000 year return
4
Farahmand, H., Yin, K., Hsu, C. W., Savadogo, I., Alegre, X. E., & Mostafavi, A. (2024). Integrating climate projections and probabilistic network analysis
into regional transport resilience planning. Transportation Research Part D: Transport and Environment, 104229.
The World Bank
Haiti Rural Accessibility & Resilience Project (P163490) ICR DOCUMENT
Page 38
Official Use Only
periods
5
. Time saving and vehicle operating cost. Using inputs from HDM4 calibrated for the country, the analysis
includes travel time saving and vehicle operating costs as a results of less travel diversion due to road closures.
Road accidents. Besides the human suffering generally associated with road accidents, there is economic loss in
the form of vehicle and property damage, medical costs, loss of productivity of injured persons, and, in the case of
commercial vehicles, loss of earnings. As such, accident reduction is clearly an economic benefit. Existing accident
characteristics were employed to estimate the likely accident reductions. The value of life in the case of fatalities
was included in the analysis.
• Carbon emissions. The Guidance Note on the shadow price of carbon in the economic analysis was adopted and
used in the benefits estimation of reduction in carbon emissions. The World Bank’s Shadow Price of Carbon
Guidance Note
6
recommends the use of a low and high estimate of the carbon price starting at US$40 and US$80,
respectively.
Depth (m) 0 0.5 1.0 1.5 2.0 3.0 4.0 5.0 6.0
Damage Factor 0 0.25 0.42 0.55 0.65 0.80 0.90 1.00 1.00
Road Types Primary Secondary Tertiary Others
Unit Repair Cost (US$/km) 721,300 480,800 480,800 57,700
Figure A4.2: Road Asset Damage curve (figure left, table upper right) and Local unit Repair cost (bottom right)
3. Other key assumptions considered in the economic analysis are presented below:
• Discount rate for public investments is 12 percent with horizon time for analysis is 20 years.
• Estimated traffic growth is -2 percent/year (first 5 years) and 2 percent after that (based on economic forecast).
• Value of Time is US$0.34 per hour, value of Life in Haiti is US$50,000 and of serious injury US$ 12,000
• Regarding river and coastal flood damages, 30 days is considered to restore normal service
Table A4.1: Mean Economic Analysis Indicators
1. Historical Climate 2. Under climate change
Net present value (NPV) 20.9 32.7
Benefit-cost ratio (BCR) 15.3 17.1
Economic internal rate of return (EIRR) 1.21 1.33
4. As a result, the project intervention will yield positive economic returns and can be confirmed to be economically
viable. Due to reduction of climate change impacts (river and coastal floods), the project will yield annual savings on: asset
damage loss of US$ 17.5 million, US$ 0.2 million in user economic costs, US$ 84 thousand in road safety and US$ 16
thousand in carbon cost. The economic analysis includes a stress-test of climate projections in economic results. As the
project is building climate resilience in transport assets, when accounting for projected rainfall intensity increases, the
economic evaluation results in higher positive outcomes. Under SSP 8.5, the project continues to yield a positive NPV. The
mean value of NPV is US$ 32.7 million meaning that the $110M investment will yield significant avoided average annual
loss (AAL) in terms of damage repair costs, user costs, CO2 costs, and road crash costs. The mean value of IRR for the
investment is 17.1 percent and the mean value of BCR ratio is 1.33.
5
Hazard information is obtained from the WB and Fathom collaboration
6
World Bank, “Guidance Note on Shadow Price of Carbon in Economic Analysis,” World Bank, Washington DC, 2017,
The World Bank
Haiti Rural Accessibility & Resilience Project (P163490) ICR DOCUMENT
Page 39
Official Use Only
ANNEX 5. BORROWER, CO-FINANCIER AND OTHER PARTNER/STAKEHOLDER COMMENTS
The Borrower completion report is attached.
ANNEX 6. SUPPORTING DOCUMENTS (IF ANY)
The impact assessment report is attached.