Data / Partner portfolio / World Bank Group / IDA
Strengthening the Management of Agriculture Public Services (GFRP)
US$ millions unless stated. Haitian fiscal year, October to September. FY2026-27 began October 1, 2026.
Objective
The project development objective (PDO) is to enable MARNDR to prioritize and target investments according to sector policies, and improve local agriculture support services.
As published by World Bank Projects, in its original language.
Description
The objective of the Strengthening of Agricultural Public Services Project for Haiti is to enable Ministry of Agriculture, Natural Resources and Rural Development (MARNDR) to prioritize and target investments according to sector policies, and improve local agriculture support services. There are three components to the project, the first component being strengthening MARNDR managerial functions. This component will finance (at the central and local level) two subcomponents: a) sector policies and coordination; and b) enhancing administrative, Human Resources (HR), and fiduciary management. The second component is the strengthening farmer extension and support services. This component will finance the expansion of the provision of improved agriculture support services in pilot areas, the first around the research center of Ferme Levi and the
more
second one around the research center of Thiotte-Savane Zombi. Finally, the third component is the project coordination and supervision. Project execution will be under the responsibility of the Director General (DG) of MARNDR and this component will finance incremental costs associated with project implementation. A five person team will work jointly in the various aspects of project execution. The project coordinator will be a member of the DG advisory team, while fiduciary responsibility (procurement and financial management) will be with the Directorate of Administrative and Financial Affaires (DAAF). All efforts by the DG will be made to coordinate project implementation across MARNDR units.
- Partner
- World Bank Group, IDA
- Stage
- Closed since August 31, 2014
- Approval
- June 25, 2009
- Closing
- August 31, 2014
- Instrument
- IBRD/IDA financing, IDA
- Undisbursed gap
- −0.2: the IDA statement values undisbursed credits in special drawing rights at the current exchange rate
- Effectiveness
- October 13, 2009
- Departments
- Sud-Est, Ouest, Sud
- Last transaction
- April 30, 2015
- Operation ID
- P113623
Life cycle5 stages, 14 dates
Stage history
| Stage | From |
|---|---|
| Planned | January 12, 2009 |
| Approved | June 25, 2009 |
| Under way | June 25, 2009 |
| Closing | August 31, 2014 |
| Closed | August 31, 2014 |
Dates
| Event | Date | Source |
|---|---|---|
| Concept review | January 12, 2009 | World Bank Projects |
| Disclosure | February 23, 2009 | World Bank Projects |
| Planned start | April 24, 2009 | IATI |
| Appraisal | April 27, 2009 | World Bank Projects |
| Negotiation | May 19, 2009 | World Bank Projects |
| Actual start | June 25, 2009 | IATI |
| Approval | June 25, 2009 | World Bank Projects |
| First commitment | June 25, 2009 | Transactions |
| Effectiveness | October 13, 2009 | World Bank Projects |
| First disbursement | June 30, 2011 | Transactions |
| Actual closing date | August 31, 2014 | IATI |
| Planned closing date | August 31, 2014 | IATI |
| Last disbursement | September 30, 2014 | Transactions |
| Completion report due | February 27, 2015 | World Bank Projects |
Undisbursed: US$0.0 million on September 30, 2026, with closing on August 31, 2014.
Financing
Table 1.Financing, US$ millions
| Financier | AmountUS$ millions | Role | Source |
|---|---|---|---|
| IDA Grant | 5.0 | Institution | World Bank Projects |
Table 2.Position at the data date by source (stocks), US$ millions
| This pageUS$ millions | Source | |
|---|---|---|
| Commitment | 4.9 | IDA Statement of Credits and Grants |
| Disbursed | 5.1 | IDA Statement of Credits and Grants |
| Undisbursed | 0.0 | IDA Statement of Credits and Grants |
| Total cost | 5.0 | World Bank Projects |
World Bank amounts. Approved: Net commitment, the amount approved less cancellations, in US$ at the data date. Disbursed to date: The disbursements of the IDA statement and the Projects API to date, in US$. Undisbursed: The undisbursed balance the IDA statement publishes, in US$ at the data date. Amounts by source
Changes to the operationnot reported
- Original closing date
- Not reported
- Closing date extensions
- Not reported
- Restructurings
- Not reported
- Emergency component
- Not reported
New commitments and disbursements by fiscal year
Table 3.New commitments and disbursements by fiscal year (flows), US$ millions
| FY2008-09US$ millions | FY2010-11US$ millions | FY2011-12US$ millions | FY2012-13US$ millions | FY2013-14US$ millions | FY2014-15US$ millions | |
|---|---|---|---|---|---|---|
| New commitments | 5.0 | Not reported | Not reported | Not reported | Not reported | −0.1 |
| Disbursements | Not reported | 0.3 | 0.5 | 1.8 | 2.0 | −0.1 |
| Cumulative disbursements | Not reported | 1.0 | 1.4 | 3.2 | 5.2 | 5.1 |
The running total starts at the opening balance of US$0.6 million.
Records and documents
Transactions22 transactions, June 25, 2009 to April 30, 2015
Table 4.Transactions, US$ millions
| Date | Measure | AmountUS$ millions | Source | Method |
|---|---|---|---|---|
| June 25, 2009 | Commitment | 5.0 | IDA Statement of Credits and Grants | credit original principal at board approval |
| April 30, 2015 | Commitment | −0.1 | IDA Statement of Credits and Grants | cancellation: increase in cumulative cancelled amount between snapshots (non-USD credit: includes exchange revaluation) |
| April 30, 2011 | Disbursements | 0.6 | IDA Statement of Credits and Grants | cumulative at first snapshot (opening balance) |
| June 30, 2011 | Disbursements | 0.3 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| October 31, 2011 | Disbursements | 0.1 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| March 31, 2012 | Disbursements | 0.1 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| May 31, 2012 | Disbursements | 0.1 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| August 31, 2012 | Disbursements | 0.2 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| October 31, 2012 | Disbursements | 0.1 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| December 31, 2012 | Disbursements | 0.3 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| March 31, 2013 | Disbursements | 0.3 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| June 30, 2013 | Disbursements | 0.4 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| July 31, 2013 | Disbursements | 0.2 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| August 31, 2013 | Disbursements | 0.1 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| September 30, 2013 | Disbursements | 0.4 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| December 31, 2013 | Disbursements | 0.2 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| March 31, 2014 | Disbursements | 0.4 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| May 31, 2014 | Disbursements | 0.4 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| June 30, 2014 | Disbursements | 0.4 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| August 31, 2014 | Disbursements | 0.2 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| September 30, 2014 | Disbursements | 0.2 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| January 31, 2015 | Disbursements | −0.1 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
Terms4 of 6 reported
- Finance type
- 110 Standard grant
- Flow type
- Not reported
- Aid type
- C01 Project-type interventions
- Tied status
- 5 Untied
- Collaboration type
- 2 Multilateral inflows
- Humanitarian
- Not reported
Locations3 departments, 7 places named, 14 places with coordinates
| Departments | Sud-Est, Ouest, Sud |
| Places named by the source | Arrondissement de Belle-Anse, Les Cayes, Levy, Port-au-Prince, Republic of Haiti, Savane Zombi, Thiotte |
| Places with coordinates | 14 |
Results indicators40 indicators
| Indicator | Baseline | Target | Latest value | Date of latest value |
|---|---|---|---|---|
| 100% of procurement records over US$100K and managed by MARNDR published on its website before the end of the project | 0.00 | 100.00 | 51.00 | April 25, 2014 |
| 20 agricultural agents trained and educational material on gender mainstreaming in subsistence agriculture and environmentally friendly agricultural techniques prepared and disseminated in the pilotz | 0.00 | 0.00 | 38.00 | April 25, 2014 |
| Coverage mechanism against agricultural risks designed in the pilot zones before the end of the project. | N/A | Completed | Not reported | Not reported |
| Establishment of an Environmental Unit within MARNDR | No | Yes | Yes | April 25, 2014 |
| FIOP transmitted to MPCE for 80% of projects in the PIP (Public Investment Program) before the end of the project. | 0.00 | 0.00 | 100.00 | April 25, 2014 |
| Farmer Registry established | No | Yes | Yes | April 25, 2014 |
| Increase in the commitments of the operating budget (outside of salaries) in the DDAs to 70% before | 45.00 | 70.00 | 75.00 | April 25, 2014 |
| Intranet and email system installed for 300 MARNDR staff before the end of the project | 0.00 | 300.00 | 260.00 | April 25, 2014 |
| Preparation of manuals of procedures for managing the operation and investment budgets in the MARNDR at the end of the first year of the project | N/A | Not reported | Not reported | Not reported |
| Reduction from 15 to 5 the number of days to issue checks, before the end of the project. | 15.00 | 5.00 | 5.00 | April 25, 2014 |
| Farmers receiving agriculture support services | 280.00 | 3000.00 | 4565.00 | June 30, 2014 |
| Farmers receiving agriculture support services | 280.00 | 3,000.00 | 4,565.00 | June 30, 2014 |
| Prioritization and targeting of budget | No | Yes | Yes | June 30, 2014 |
| Prioritization and targeting of budget | No | Yes | Yes | June 30, 2014 |
| Rate of commitments of the operating budget | 80.00 | 95.00 | 75.00 | June 30, 2014 |
| Rate of commitments of the operating budget | 80.00 | 95.00 | 75.00 | June 30, 2014 |
| 100% of procurement records over US$100K and managed by MARNDR published on its website before the end of the project | 0.00 | 100.00 | 51.00 | June 30, 2014 |
| 100% of procurement records over US$100K and managed by MARNDR published on its website before the end of the project | 0.00 | 100.00 | Not reported | Not reported |
| 20 agricultural agents trained and educational material on gender mainstreaming in subsistence agriculture and environmentally friendly agricultural techniques prepared and disseminated in the pilotz | 0.00 | 20.00 | 38.00 | January 1, 1900 |
| 20 agricultural agents trained and educational material on gender mainstreaming in subsistence agriculture and environmentally friendly agricultural techniques prepared and disseminated in the pilotz | 0.00 | 20.00 | 38.00 | January 1, 1900 |
| At least 2 R&D studies completed in the pilot zones before the end of the project | 0.00 | 2.00 | 1.00 | June 30, 2014 |
| Coverage mechanism against agricultural risks designed in the pilot zones before the end of the project. | Not reported | Completed | Not reported | Not reported |
| Coverage mechanism against agricultural risks designed in the pilot zones before the end of the project. | Not reported | Completed | Not reported | Not reported |
| Establishment of an Environmental Unit within MARNDR | No | Yes | Yes | June 30, 2014 |
| Establishment of an Environmental Unit within MARNDR | No | Yes | Yes | June 30, 2014 |
| FIOP transmitted to MPCE for 80% of projects in the PIP (Public Investment Program) before the end of the project. | 0.00 | 0.00 | 100.00 | January 1, 1900 |
| FIOP transmitted to MPCE for 80% of projects in the PIP (Public Investment Program) before the end of the project. | Not reported | Not reported | 100.00 | January 1, 1900 |
| Farmer Registry established | No | Yes | Yes | June 30, 2014 |
| Farmer Registry established | No | Yes | Yes | June 30, 2014 |
| Increase in the commitments of the operating budget (outside of salaries) in the DDAs to 70% before | 45.00 | 70.00 | 0.00 | June 30, 2014 |
| Increase in the commitments of the operating budget (outside of salaries) in the DDAs to 70% before | 45.00 | 70.00 | 0.00 | June 30, 2014 |
| Intranet and email system installed for 300 MARNDR staff before the end of the project | 0.00 | 300.00 | 260.00 | June 30, 2014 |
| Intranet and email system installed for 300 MARNDR staff before the end of the project | 0.00 | 300.00 | 260.00 | June 30, 2014 |
| Preparation of manuals of procedures for managing the operation and investment budgets in the MARNDR at the end of the first year of the project | Not reported | Completed | Not reported | Not reported |
| Preparation of manuals of procedures for managing the operation and investment budgets in the MARNDR at the end of the first year of the project | Not reported | Completed | Not reported | Not reported |
| Reduction from 15 to 5 the number of days to issue checks, before the end of the project. | 15.00 | 5.00 | 5.00 | June 30, 2014 |
| Reduction from 15 to 5 the number of days to issue checks, before the end of the project. | 15.00 | 5.00 | 5.00 | June 30, 2014 |
| Farmers receiving agriculture support services | 280.00 | 3000.00 | 4565.00 | April 25, 2014 |
| Prioritization and targeting of budget | No | Yes | Yes | April 25, 2014 |
| Rate of commitments of the operating budget | 80.00 | 95.00 | 75.00 | April 25, 2014 |
Ratings27 ratings
| Rating | Value | Date |
|---|---|---|
| IEG bankqualityofsupervision | Moderately Satisfactory | June 30, 2015 |
| IEG borrowcompliance | Moderately Satisfactory | June 30, 2015 |
| IEG borrowimplementation | Moderately Satisfactory | June 30, 2015 |
| IEG evaltype | ES | June 30, 2015 |
| IEG evaluation_riskdo | Significant | June 30, 2015 |
| IEG icrquality | Satisfactory | June 30, 2015 |
| IEG mequality | Modest | June 30, 2015 |
| IEG outcome | Moderately Satisfactory | June 30, 2015 |
| IEG overallbankperf | Moderately Satisfactory | June 30, 2015 |
| IEG overallborrowperf | Moderately Satisfactory | June 30, 2015 |
| ICR bankqualityentry | Not Rated | February 27, 2015 |
| ICR banksupervision | Not Rated | February 27, 2015 |
| ICR banksupervision | Substantial | February 27, 2015 |
| ICR banksupervision | Moderately Satisfactory | February 27, 2015 |
| ICR borrgovt | Moderately Satisfactory | February 27, 2015 |
| ICR borrimplegency | Substantial | February 27, 2015 |
| ICR borroverall | Moderately Satisfactory | February 27, 2015 |
| ICR completion_riskdo | Substantial | February 27, 2015 |
| ICR outratingind | Substantial | February 27, 2015 |
| ICR overallrating | Substantial | February 27, 2015 |
| ISR Counterpart Funding | Satisfactory | August 11, 2014 |
| ISR Financial Management | Moderately Unsatisfactory | August 11, 2014 |
| ISR Monitoring and Evaluation | Moderately Satisfactory | August 11, 2014 |
| ISR Overall Implementation Progress (IP) | Moderately Satisfactory | August 11, 2014 |
| ISR Procurement | Moderately Unsatisfactory | August 11, 2014 |
| ISR Progress towards achievement of PDO | Moderately Satisfactory | August 11, 2014 |
| ISR Project Management | Moderately Satisfactory | August 11, 2014 |
Contract awards1 award
| Supplier | Date | Method | Amount |
|---|---|---|---|
| Name not shown | September 7, 2011 | ICB | Not reported |
Identifiers4 identifiers
| System | Identifier | Source |
|---|---|---|
| IATI identifier | 44000-P113623 | IATI |
| IDA credit or grant | IDAH5090 | IDA Statement of Credits and Grants |
| World Bank loan | IDA-H5090 | World Bank Projects |
| World Bank project | P113623 | Operation record |
Source differences2 fields
| Field | Source | Value | Used |
|---|---|---|---|
| Commitment | IDA Statement of Credits and Grants | US$4.9 million | ✓ |
| Commitment | World Bank Projects | US$5.0 million | |
| Status | World Bank Projects | Closed | ✓ |
| Status | IATI | Active |
Partner documents18 documents
- Record on projects.worldbank.org, projects.worldbank.org
- Haiti - Strengthening the Management of Agriculture Public Services Project, June 30, 2015, documents.worldbank.org
- Haiti - Strengthening Agriculture Public Services Project, February 20, 2015, documents.worldbank.org
- Haiti - Strengthening the Management of Agriculture Public Services (GFRP) : P113623 - Implementation Status Results Report : Sequence 11, August 11, 2014, documents.worldbank.org
- Haiti - Strengthening the Management of Agriculture Public Services (GFRP) : P113623 - Implementation Status Results Report : Sequence 10, June 9, 2014, documents.worldbank.org
- Haiti - Strengthening the Management of Agriculture Public Services (GFRP) : P113623 - Implementation Status Results Report : Sequence 09, December 3, 2013, documents.worldbank.org
- Haiti - Strengthening the Management of Agriculture Public Services (GFRP) : P113623 - Implementation Status Results Report : Sequence 08, April 24, 2013, documents.worldbank.org
- Haiti - Strengthening the Management of Agriculture Public Services (GFRP) : P113623 - Implementation Status Results Report : Sequence 07, September 26, 2012, documents.worldbank.org
- Haiti - Strengthening the Management of Agriculture Public Services (GFRP) : P113623 - Implementation Status Results Report : Sequence 06, March 28, 2012, documents.worldbank.org
- Haiti - Strengthening the Management of Agriculture Public Services (GFRP) : P113623 - Implementation Status Results Report : Sequence 05, July 19, 2011, documents.worldbank.org
- Haiti - Strengthening the Management of Agriculture Public Services (GFRP) : P113623 - Implementation Status Results Report : Sequence 04, January 24, 2011, documents.worldbank.org
- Haiti - Strengthening the Management of Agriculture Public Services (GFRP) Project : restructuring, April 22, 2010, documents.worldbank.org
- Financing Agreement for Grant H509-HT Conformed, July 27, 2009, documents.worldbank.org
- Announcement of World Bank Approves Five Million US Dollars for Agriculture Development in Haiti on June 26, 2009, June 26, 2009, documents.worldbank.org
- Haiti - Strengthening of Agricultural Public Services Project, June 1, 2009, documents.worldbank.org
- Haiti - Strengthening the Management of Agriculture Public Services (GFRP) Project, May 18, 2009, documents.worldbank.org
- Haiti - Strengthening of Agricultural Public Services Project : environmental assessment : Environmental and social framework, April 24, 2009, documents.worldbank.org
- Haiti - Modernization of Agriculture Institutions Project, December 31, 2008, documents.worldbank.org
Procurement notices (2)
- Contract Awards, projects.worldbank.org
- Procurement Notices, projects.worldbank.org
Sources
- IATI record (d-portal): terms of use set by the publisher
- IDA statement of credits and grants (dataset): World Bank data, CC BY 4.0 (https://datacatalog.worldbank.org/public-licenses).
- Transactions: terms of use set by the publisher
- Operation record: terms of use set by the publisher
- World Bank project page: terms of use set by the publisher
- World Bank documents: terms of use set by the publisher
Data as of October 18, 2026
| Source | Accessed on |
|---|---|
| IATI | October 18, 2026 |
| IDA Statement of Credits and Grants | October 18, 2026 |
| World Bank Projects | October 18, 2026 |
| World Bank documents | October 18, 2026 |
Cite this page
HaitiDocs. Strengthening the Management of Agriculture Public Services (GFRP). Partner portfolio, data as of October 18, 2026. https://www.haitidocs.org/portfolio/projects/WB%3AP113623