Haiti Community Driven Development (CDD) Project / PRODEP

US$ millions unless stated. Haitian fiscal year, October to September. FY2026-27 began October 1, 2026.

Objective

Building on the successful experience of the PCF-funded CDD pilot, the proposed project would scale-up the direct transfer of public resources to local community organizations in poor rural and peri-urban communities, by: (i) improving their access to basic social and economic infrastructure and support income-generating activities by financing small-scale investments proposed, implemented and managed by community organizations; and (ii) improving governance and building social capital of communities by increasing citizen participation and transparency in open decision-making processes. Key indicators for the project would be (i) total resources transferred to OCBs over the life of the project; (ii) change in access to basic services as a function of subprojects implemented by OCBs; (iii) cost-effectiveness of infrastructure investments, compared with traditional service delivery mechanisms, and (iv) cost-benefit of productive subprojects.

As published by World Bank Projects, in its original language.

Description

The Community Driven Development Project for Haiti will scale-up the direct transfer of public resources to local community organizations in poor rural and peri-urban communities. The project consists of the following components: Component 1) will finance, in some 55-65 targeted communes of rural and peri-urban Haiti. It will also earmark resources for the hiring of technical assistance service providers to mobilize community organizations (OCBs) in the targeted communes and train them in preparation and subsequent execution for subproject investments. Component 2) will finance: (i) training-of trainers events in basic management, administration, accounting and financial management; (ii) periodic regional and national exchanges; (iii) workshops for MDODs and their associated field offices; (iv) training for staff in order to effectively supervise overall

more

project implementation; (v) various consultant services including possible preparation of future operation and assessment of ways in which the Haitian Diaspora might be mobilized; and (vi) policy dialogue to engage the Government of Haiti and other stakeholders on a medium to long-term national strategy to facilitate the mainstreaming of community-driven development. Component 3) finance incremental costs associated with project implementation.

Partner
World Bank Group, IDA
Sector
Agriculture and food security
Stage
Closed since June 30, 2013
Approval
July 28, 2005
Closing
June 30, 2013
Instrument
IBRD/IDA financing, IDA
Undisbursed gap
−2.0: the IDA statement values undisbursed credits in special drawing rights at the current exchange rate
Effectiveness
December 8, 2005
Departments
Nord-Est, Sud, Centre, Ouest, Sud-Est, Grande Anse, Nord, Nippes, Artibonite, Nord-Ouest
Last transaction
November 30, 2013
Operation ID
P093640
Life cycle5 stages, 14 dates

Stage history

StageFrom
PlannedFebruary 3, 2005
ApprovedJuly 28, 2005
Under wayJuly 28, 2005
ClosingJune 30, 2013
ClosedJune 30, 2013

Dated events

EventDateSource
Concept reviewFebruary 3, 2005World Bank Projects
DisclosureFebruary 8, 2005World Bank Projects
AppraisalMay 23, 2005World Bank Projects
NegotiationJune 14, 2005World Bank Projects
Planned startJuly 21, 2005IATI
Actual startJuly 28, 2005IATI
ApprovalJuly 28, 2005World Bank Projects
First commitmentJuly 28, 2005Transactions
EffectivenessDecember 8, 2005World Bank Projects
First disbursementJune 30, 2011Transactions
Actual endJune 30, 2013IATI
Closing dateJune 30, 2013IATI
Last disbursementSeptember 30, 2013Transactions
Completion report dueDecember 30, 2013World Bank Projects

Undisbursed: US$0.0 million on September 30, 2026, with closing on June 30, 2013.

Financing

Table 1.Financing, US$ millions

FinancierAmountUS$ millionsRoleSource
Borrower/Recipient2.3CounterpartWorld Bank Projects
IDA Grant38.0InstitutionWorld Bank Projects

Table 2.Related operations, US$ millions

OperationRelationPartnerStageCommitmentUS$ millions
Community-Driven Development (CDD) Additional FinancingAdditional financing or child operationWorld Bank GroupClosed8.0
Rural Community Driven Development - Additional Financing IIAdditional financing or child operationWorld Bank GroupClosed15.0

Table 3.Position at the data date by source (stocks), US$ millions

This pageUS$ millionsSource
Commitment60.8IDA Statement of Credits and Grants
Disbursed62.8IDA Statement of Credits and Grants
Undisbursed0.0IDA Statement of Credits and Grants
Total cost40.3World Bank Projects

World Bank amounts. Approved: Net commitment, the amount approved less cancellations, in US$ at the data date. Disbursed to date: The disbursements of the IDA statement and the Projects API to date, in US$. Undisbursed: The undisbursed balance the IDA statement publishes, in US$ at the data date. Amounts by source

Changes to the operationnot reported
Original closing date
Not reported
Closing date extensions
Not reported
Restructurings
Not reported
Emergency component
Not reported

New commitments and disbursements by fiscal year

Disbursements, US$ millions
FY2004-05, not reportedn.r.04-05FY2008-09, not reportedn.r.08-09FY2009-10, not reportedn.r.09-10FY2010-11, US$1.5 million210-11FY2011-12, US$9.2 million911-12FY2012-13, US$4.1 million412-13FY2013-14, US$−0.0 million−0.013-14FY2004-05, not reportedn.r.04-05FY2008-09, not reportedn.r.08-09FY2009-10, not reportedn.r.09-10FY2010-11, US$1.5 million210-11FY2011-12, US$9.2 million911-12FY2012-13, US$4.1 million412-13FY2013-14, US$−0.0 million−0.013-14

Table 4.New commitments and disbursements by fiscal year (flows), US$ millions

FY2004-05US$ millionsFY2008-09US$ millionsFY2009-10US$ millionsFY2010-11US$ millionsFY2011-12US$ millionsFY2012-13US$ millionsFY2013-14US$ millions
New commitments38.08.015.0Not reportedNot reportedNot reported−0.2
DisbursementsNot reportedNot reportedNot reported1.59.24.1−0.0
Cumulative disbursementsNot reportedNot reportedNot reported49.558.762.862.8

The running total starts at the opening balance of US$48.0 million.

Records and documents

Transactions26 records, July 28, 2005 to November 30, 2013

Table 5.Transactions, US$ millions

DateMeasureAmountUS$ millionsSourceMethod
July 28, 2005Commitment38.0IDA Statement of Credits and Grantscredit original principal at board approval
January 29, 2009Commitment8.0IDA Statement of Credits and Grantscredit original principal at board approval
May 27, 2010Commitment15.0IDA Statement of Credits and Grantscredit original principal at board approval
November 30, 2013Commitment−0.1IDA Statement of Credits and Grantscancellation: increase in cumulative cancelled amount between snapshots (non-USD credit: includes exchange revaluation)
November 30, 2013Commitment−0.1IDA Statement of Credits and Grantscancellation: increase in cumulative cancelled amount between snapshots (non-USD credit: includes exchange revaluation)
April 30, 2011Disbursements8.0IDA Statement of Credits and Grantscumulative at first snapshot (opening balance)
April 30, 2011Disbursements37.7IDA Statement of Credits and Grantscumulative at first snapshot (opening balance)
April 30, 2011Disbursements2.2IDA Statement of Credits and Grantscumulative at first snapshot (opening balance)
June 30, 2011Disbursements0.1IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
September 30, 2011Disbursements1.4IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
December 31, 2011Disbursements2.6IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
February 29, 2012Disbursements2.7IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
May 31, 2012Disbursements1.4IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
June 30, 2012Disbursements1.6IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
July 31, 2012Disbursements0.6IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
August 31, 2012Disbursements0.3IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
October 31, 2012Disbursements0.1IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
November 30, 2012Disbursements0.1IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
December 31, 2012Disbursements1.2IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
January 31, 2013Disbursements0.6IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
February 28, 2013Disbursements0.1IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
March 31, 2013Disbursements0.9IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
March 31, 2013Disbursements0.9IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
August 31, 2013Disbursements0.1IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
September 30, 2013Disbursements0.1IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
October 31, 2013Disbursements−0.0IDA Statement of Credits and Grantsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
Terms4 of 6 reported
Finance type
110 Standard grant
Flow type
Not reported
Aid type
C01 Project-type interventions
Tied status
5 Untied
Collaboration type
2 Multilateral inflows
Humanitarian
Not reported
Locations10 departments, 57 places named, 114 places with coordinates
DepartmentsNord-Est, Sud, Centre, Ouest, Sud-Est, Grande Anse, Nord, Nippes, Artibonite, Nord-Ouest
Places named by the sourceAnse Rouge, Anse-a-Pitres, Anse-a-Veau, Aquin, Bahon, Baie de Henne, Bainet, Baraderes, Bassin Bleu, Belladere, Belle-Anse, Boucan Carre, Capotille, Carice, Carrefour Saut d'Eau, Cavaillon, Cerca la Source, Chantal, Corail, Cornillon, Cote de Fer, Desdunes, Dessalines, Ennery, Fond Verrettes, Grand Gosier, Grande Saline, Gros Morne, Jean-Rabel, L'Asile, La Chapelle, La Vallee de Jacmel, Lascahobas, Maissade, Maniche, Marigot, Marmelade, Mirebalais, Mont Organise, Ouanaminthe and 17 more
Places with coordinates114
Results indicators22 indicators
IndicatorBaselineTargetLatest valueDate of latest value
10 CADECs allocating funds from other development programs.010Not YetJune 30, 2013
75% of CBO members have attended at least one training event.075%87%June 30, 2013
80% of subprojects are implemented within 6 months.080%87June 30, 2013
90% of CADEC members have attended at least two training events.090%100%June 30, 2013
Amount of Project funds disbursed within the Project timeframe.0US$61 millionUS$ 58.7 millionJune 30, 2013
Component 1- # of subprojects: (a) 4050 proposed, (b) 2900 approved, (c) 2020 start implementation, and (d) 2010 completed.(a): 0 (b): 0 (c): 0 (d): 0# of subprojects: (a) 4050 (b) 2900 (c) 2020 d) 2010(a) 10,202 (b) 1685 (c) 11 (d) 1668June 30, 2013
Component 1- 100 new CBOs created as a result of the Project.0100238June 30, 2013
Component 1- 59 CADECs following democratic and open meeting procedures as detailed in the Project Operational Manual.(a): 0 (b): 0 (c): 0 (d): 05959June 30, 2013
Component 1--30% of CBO and 15% of CADEC members of the executive committee are women.0/030/1543% CBOs, 26% CADECsJune 30, 2013
Component 1-75% of subprojects with adequate O&M arrangements implemented.075%45%June 30, 2013
Component 2 - 460 training events for CBOs, CADECs.03604030June 30, 2013
Component 3 MIS provides complete quarterly reports within 30 days after the end of the quarter.Not reportedYesNot yet, and data from first two years of implementation is incomplete.June 30, 2013
Health facilities constructed, renovated, and/or equipped (number)0.000.0028.00June 30, 2013
Improved community water points constructed or rehabilitated under the project0.000.00444.00June 30, 2013
Number of additional classrooms built or rehabilitated at the primary level resulting from project interventions.0.000.00294.00June 30, 2013
Roads rehabilitated, Rural0.000.00892.00June 30, 2013
1.2 million residents in 59 Municipalities of the Project area improved their access to basic social and economic infrastructure and/or benefits of productive subprojects.41% of residents have access to potable water less than 15 minutes away from their homes (Baseline Dec 08).1.2 million residents in 59 Municipalities1.2 million residents in 59 MunicipalitiesJune 30, 2013
20-point change in Social Capital Index, reflecting greater citizen participation in resource allocation decisions.Not reported20%Not yet availableJune 30, 2013
3500 CBOs in the 59 Municipalities are officially constituted and participating in CADECs.139 (as of end of LICUS pilot Grant)3,5003819June 30, 2013
60% of the adult population in the 59 Municipalities expresses to be aware of PRODEP and its objectives/activities/ means of access.20.6 (per Dec 2008 baseline survey).60%55%June 30, 2013
75% of productive/ income-generating subprojects within the 59 Municipalities are operational and are being maintained 12 months after completion.075%82%June 30, 2013
In 59 Municipalities CBO have successfully managed the direct transfers for community subprojects3 (at the end of the PCF and LICUS-funded pilot grants)59 communes with 59 CADECs fully operational59June 30, 2013
Ratings27 ratings
RatingValueDate
IEG bankqualityofsupervisionSatisfactoryOctober 16, 2014
IEG borrowcomplianceModerately UnsatisfactoryOctober 16, 2014
IEG borrowimplementationModerately SatisfactoryOctober 16, 2014
IEG evaltypeESOctober 16, 2014
IEG evaluation_riskdoHighOctober 16, 2014
IEG icrqualitySatisfactoryOctober 16, 2014
IEG mequalitySubstantialOctober 16, 2014
IEG outcomeModerately SatisfactoryOctober 16, 2014
IEG overallbankperfSatisfactoryOctober 16, 2014
IEG overallborrowperfModerately SatisfactoryOctober 16, 2014
ICR bankqualityentryNot RatedDecember 30, 2013
ICR banksupervisionNot RatedDecember 30, 2013
ICR banksupervisionSubstantialDecember 30, 2013
ICR banksupervisionModerately SatisfactoryDecember 30, 2013
ICR borrgovtModerately SatisfactoryDecember 30, 2013
ICR borrimplegencyModerately SatisfactoryDecember 30, 2013
ICR borroverallModerately SatisfactoryDecember 30, 2013
ICR completion_riskdoSubstantialDecember 30, 2013
ICR outratingindModerately SatisfactoryDecember 30, 2013
ICR overallratingModerately SatisfactoryDecember 30, 2013
ISR Counterpart FundingSatisfactoryJune 26, 2013
ISR Financial ManagementModerately UnsatisfactoryJune 26, 2013
ISR Monitoring and EvaluationModerately UnsatisfactoryJune 26, 2013
ISR Overall Implementation Progress (IP)SatisfactoryJune 26, 2013
ISR ProcurementSatisfactoryJune 26, 2013
ISR Progress towards achievement of PDOModerately SatisfactoryJune 26, 2013
ISR Project ManagementModerately UnsatisfactoryJune 26, 2013
Identifiers8 identifiers
SystemIdentifierSource
IATI identifier44000-P093640IATI
IDA credit or grantIDAH1810IDA Statement of Credits and Grants
IDA credit or grantIDAH4450IDA Statement of Credits and Grants
IDA credit or grantIDAH5850IDA Statement of Credits and Grants
World Bank loanIDA-H1810World Bank Projects
World Bank loanIDA-H4450World Bank Projects
World Bank loanIDA-H5850World Bank Projects
World Bank projectP093640Operation record
Where sources differ2 fields
FieldSourceValueUsed
CommitmentIDA Statement of Credits and GrantsUS$60.8 million✓
CommitmentWorld Bank ProjectsUS$38.0 million
StatusWorld Bank ProjectsClosed✓
StatusIATIActive
Partner documents27 documents
Procurement notices (2)

Sources

Data as of October 18, 2026
SourceRead on
IATIOctober 18, 2026
IDA Statement of Credits and GrantsOctober 18, 2026
World Bank ProjectsOctober 18, 2026
World Bank documentsOctober 18, 2026
Cite this page

HaitiDocs. Haiti Community Driven Development (CDD) Project / PRODEP. Partner portfolio, data as of October 18, 2026. https://www.haitidocs.org/portfolio/projects/WB%3AP093640