Environmental and Social Commitment Plan, Haiti COVID-19 Response Project, additional financing (draft)
- Commits the MSPP to update the labour management procedures within 60 days of project effectiveness, the one deadline in the plan expressed in days.
- Records ESS 5 on land acquisition and resettlement, ESS 6 on biodiversity, ESS 7 on indigenous peoples and ESS 9 on financial intermediaries as not relevant to the additional financing.
- Names MSPP-UGP as the responsible entity on every commitment row, so accountability sits with the project management unit throughout.
- Carries a footnote saying the date is to be updated to the negotiation date, marking the text as a draft.
The plan is a table of commitments running against the World Bank's Environmental and Social Standards. ESS 1 requires the MSPP to set up and keep a project organisational structure with environment and social staff, to update and disclose the environmental and social management framework, and to prepare plans and instruments through the assessment process; it also lists the activity types excluded from financing. ESS 2 requires the labour management procedures to be updated within 60 days of project effectiveness. ESS 3, ESS 4 and ESS 8 carry commitments on pollution prevention, community health and safety and cultural heritage. ESS 5, ESS 6, ESS 7 and ESS 9 are recorded as not relevant. Every row names MSPP-UGP as the responsible entity. A footnote marks the date as one to be updated to the negotiation date in due course, which is why the document is labelled a draft.