Haiti Reconstruction: Factors Contributing to Delays in USAID Infrastructure Construction
Summary — The US Government Accountability Office's November 2011 report to Congressional committees on Haiti reconstruction, examining why USAID infrastructure construction was delayed.
Key Findings
- An audit rather than a programme document, so its account of delay is independent of the implementing agency.
- Examines governance and rule of law spending alongside infrastructure.
- Reported to Congressional committees in November 2011.
Full Description
The US Government Accountability Office's November 2011 report to Congressional committees on Haiti reconstruction, examining why USAID infrastructure construction was delayed. GAO reports are audits rather than programme documents, so they record what went wrong with an independence that implementing agencies' own reporting does not have.
Full Document Text
Extracted text from the original document for search indexing.
United States Government Accountability Office
GAO Report to Congressional Committees
November 2011
HAITI
RECONSTRUCTION
Factors Contributing
to Delays in USAID
Infrastructure
Construction
GAO-12-68
November 2011
HAITI RECONSTRUCTION
Factors Contributing to Delays in USAID
Infrastructure Construction
Highlights of GAO-12-68, a report to
congressional committees
Why GAO Did This Study What GAO Found
On January 12, 2010, a powerful USAID and State have obligated and expended a small amount of funds for
earthquake struck Haiti, resulting in an infrastructure construction activities in six sectors: energy, ports, shelter, health,
estimated 230,000 deaths, including food security, and governance and rule of law. As of September 30, 2011, USAID
more than 16,000 Haitian government and State had allocated almost $412 million for infrastructure construction
personnel, and the destruction of many activities, obligated approximately $48.4 million (11.8 percent), and expended
ministry buildings. In addition to approximately $3.1 million (0.8 percent). Of the almost $412 million, about 87
immediate relief efforts, in July 2010, percent was allocated from the 2010 Supplemental Appropriations Act and 13
Congress appropriated $1.14 billion in percent from regular fiscal year appropriations. USAID accounts for about 89
supplemental funds for reconstruction,
percent of the $412 million, including funds for construction in the energy, ports,
most of which was provided to the U.S.
shelter, health, and food security sectors. State activities in the governance and
Agency for International Development
(USAID) and the Department of State
rule of law sector account for the remaining 11 percent.
(State). USAID and State are USAID had difficulty staffing the Haiti mission after the earthquake, a factor that
administering about $412 million in has contributed to delays in infrastructure construction activities. Soon after the
supplemental and regular fiscal year earthquake, 10 of the 17 U.S. citizen Foreign Service Officers, known as U.S.
appropriations for infrastructure direct-hire staff, in Haiti left. USAID, lacking a process for expediting the
construction activities. In May 2011, in movement of staff to post-disaster situations, had difficulty replacing them and
response to a congressional mandate, recruiting additional staff. These staff included key technical personnel such as
GAO reported on overall U.S. plans for
engineers and contracting officers needed to plan and implement infrastructure
assistance to Haiti. This report
activities in sectors such as energy and ports, where the mission had not
addresses infrastructure construction
activities, including (1) USAID and previously worked. With limited U.S. direct-hire staff on board, the mission relied
State obligations and expenditures; (2) heavily on temporary staff, and remaining staff assumed duties outside their
USAID staffing; (3) USAID planning; normal areas of expertise. The mission plans to have all U.S. direct-hire staff on
and (4) potential sustainability board by February 2012. Since infrastructure activities will continue until at least
challenges USAID faces. GAO 2015, the mission will need to maintain sufficient staff for several years to
reviewed documents and interviewed manage the activities supported by the increase in Haiti reconstruction funds.
U.S. officials in Washington, D.C., and
USAID and State are planning activities in Haiti, but various challenges have
Haiti, and visited ongoing and planned
contributed to some of USAID’s delays. As of October 2011, USAID had drafted
construction sites in Haiti.
eight Activity Approval Documents (AADs) that include planned activities, costs,
What GAO Recommends risks, and assumptions. AADs for the education, energy, food security,
governance and rule of law, health, and shelter sectors have been approved. The
To facilitate USAID’s progress in AAD process has been more comprehensive and involved than is typical for such
planning and implementing its many efforts, according to USAID officials. Although USAID made progress in planning,
post-earthquake infrastructure
construction of some activities was delayed for various reasons, and some
construction activities in Haiti over the
activities do not yet have planned start dates. For example, the mission was
next several years, particularly those
requiring key technical staff, GAO
delayed in awarding contracts in the shelter sector due to issues such as
recommends that the USAID identifying sites for shelter and obtaining land title.
Administrator ensure that U.S. direct- The sustainability of USAID-funded infrastructure depends, in part, on
hire staff are placed at the mission improvements to the Haitian government’s long-standing economic and
within time frames that avoid future institutional weaknesses. USAID has considered various sustainability issues
staffing gaps or delays. USAID and is planning institutional strengthening activities, such as management reform
described certain actions it is currently of the power utility, but USAID planning documents acknowledge that these
taking that, if continued, could address
reforms will be challenging and that infrastructure activities face risks. These
the recommendation.
challenges are consistent with prior GAO reports that address sustainability of
View GAO-12-68. For more information, U.S. infrastructure projects in other countries.
contact David Gootnick at (202) 512-3149 or
gootnickd@gao.gov.
United States Government Accountability Office
Contents
Letter 1
Background 3
USAID and State Have Obligated and Expended Small Amounts of
the Almost $412 Million Allocated for Construction Activities 9
USAID Staffing Difficulties Were a Factor in Delaying USAID
Infrastructure Construction Activities in Haiti 13
USAID Planning Is Still Under Way; Various Factors Contributed to
Delays in Infrastructure Construction 18
Haitian Government Capacity Is a Key Challenge to Sustainability
of U.S. Government Infrastructure Reconstruction Activities 23
Conclusion 27
Recommendation for Executive Action 28
Agency Comments and Our Evaluation 28
Appendix I Scope and Methodology 31
Appendix II Sector Fact Sheets 35
Appendix III Comments from the U.S. Agency for International Development 48
Appendix IV GAO Contact and Staff Acknowledgments 52
Tables
Table 1: Supplemental Funding for Post-Earthquake
Reconstruction in Haiti 4
Table 2: USAID and State Total Funds Allocated, Obligated, and
Expended for Bilateral Post-Earthquake Infrastructure
Construction Activities in Haiti, as of September 30, 2011 9
Table 3: USAID and State Sector-Specific Funding Allocations for
Post-Earthquake Construction Activities in Haiti, as of
September 30, 2011 10
Table 4: USAID and State Total Obligations and Expenditures for
Post-Earthquake Construction Activities, as of September
30, 2011 12
Page i GAO-12-68 Haiti Reconstruction
Table 5: Status of USAID Activity Approval Documents (AADs), as
of October 2011 19
Figures
Figure 1: Timeline of Actions Taken by the Government of Haiti,
International Donors, and the U.S. Government since the
January 12, 2010, Earthquake 5
Figure 2: Development Corridors and Selected Sites Targeted by
the U.S. Post-Earthquake Assistance 7
Page ii GAO-12-68 Haiti Reconstruction
Abbreviations
AAD Activity Approval Document
Act Supplemental Appropriations Act, 2010
Action Plan Action Plan for National Recovery and Development
in Haiti
ADS Automated Directives System
CRC Civilian Response Corps
EDH Electricité d’Haiti
ESF Economic Support Fund
FY fiscal year
Haiti Strategy Post-Earthquake USG Haiti Strategy: Toward
Renewal and Economic Opportunity
HTT Haiti Task Team
HUEH State University Hospital
IHRC Interim Haiti Recovery Commission
INCLE International Narcotics Control and Law
Enforcement
MCC Millennium Challenge Corporation
Mission USAID Mission in Haiti
NSDD-38 National Security Decision Directive 38
PSC personal services contractor
State Department of State
State/INL State’s Bureau of International Narcotics and Law
Enforcement
Treasury Department of the Treasury
UN United Nations
USAID U.S. Agency for International Development
WINNER Watershed Initiative for Natural Environmental
Resources
This is a work of the U.S. government and is not subject to copyright protection in the
United States. The published product may be reproduced and distributed in its entirety
without further permission from GAO. However, because this work may contain
copyrighted images or other material, permission from the copyright holder may be
necessary if you wish to reproduce this material separately.
Page iii GAO-12-68 Haiti Reconstruction
United States Government Accountability Office
Washington, DC 20548
November 16, 2011
Congressional Committees
The January 12, 2010, earthquake centered near Port-au-Prince, Haiti,
caused physical, social, and economic devastation to the poorest country
in the Western hemisphere. The earthquake is estimated to have caused
approximately 230,000 deaths, 300,000 injuries, and displaced
approximately 2 million people from their homes. According to the United
Nations (UN), the earthquake killed more than 16,000 of Haiti’s civil
service employees and destroyed almost all ministry buildings. The World
Bank reported that the earthquake caused $7.8 billion in damage
(exceeding Haiti’s 2009 gross domestic product). The UN Office of the
Special Envoy for Haiti reported that the country received unprecedented
pledges of support from around the globe, with bilateral and multilateral
donors, including the United States, pledging more than $5.6 billion to
help Haiti recover from the earthquake through 2011. Individuals and
private companies gave an additional $3.1 billion in private donations.
In July 2010, Congress passed the Supplemental Appropriations Act of
2010 (the Act), which provided more than $1.14 billion in reconstruction
funds for Haiti. 1 In January 2011, the U.S. government issued the 5-year
Post-Earthquake USG Haiti Strategy: Toward Renewal and Economic
Opportunity, which targets the Port-au-Prince, Saint-Marc, and Cap-
Haïtien areas. The U.S. Agency for International Development (USAID) is
allocating supplemental and other funds to support the construction and
rehabilitation of infrastructure in the energy, food security, health, ports,
and shelter sectors, while the Department of State (State) is allocating
supplemental and other funds to support the construction and
rehabilitation of infrastructure in the governance and rule of law sector. As
currently planned, nearly half of USAID’s and State’s funding for post-
1
Supplemental Appropriations Act, 2010, Pub. L. No. 111-212, title I, ch. 10, 124 Stat.
2302, 2320 (July 29, 2010).
Page 1 GAO-12-68 Haiti Reconstruction
earthquake reconstruction assistance is for infrastructure construction
activities. 2
In the Act, Congress made funds available for GAO to monitor U.S. post-
earthquake assistance to Haiti. 3 In response, in May 2011, we issued a
report that described the planned uses for U.S. reconstruction assistance,
USAID’s internal controls for overseeing U.S. reconstruction funds, and
Interim Haiti Recovery Commission governance and oversight structures. 4
This report addresses, for infrastructure construction activities only,
(1) the amounts of USAID and State obligations and expenditures;
(2) USAID’s staffing; (3) USAID’s planning; and (4) potential sustainability
challenges USAID faces.
To address these objectives, we reviewed reports, documents, and data and
interviewed officials from USAID and State in Washington, D.C., and Haiti. In
Haiti, we also met with representatives from organizations involved in the
reconstruction efforts. In Port-au-Prince, we visited sites damaged by the
earthquake where USAID and State have ongoing or planned reconstruction
activities. In the Cap-Haϊtien area, we visited sites USAID is considering for
reconstruction assistance.
We conducted this performance audit from November 2010 through
November 2011 in accordance with generally accepted government
auditing standards. Those standards require that we plan and perform the
audit to obtain sufficient, appropriate evidence to provide a reasonable
basis for our findings and conclusions based on our audit objectives. We
believe that the evidence obtained provides a reasonable basis for our
findings and conclusions based on our work objectives. (App. I contains a
more detailed description of our scope and methodology. App. II contains
2
As agreed with USAID and State, for this report we used USAID’s definition of
infrastructure as the stock of fixed capital equipment in a country, including factories,
roads, schools, etc. Construction includes reconstruction, renovation, and remodeling
along with new construction. We did not include disaster response programs of a short-
term nature and programs by the Offices of Food for Peace and Transition Initiatives,
which may include longer-term infrastructure-related components.
3
The law directed that funds previously available to GAO pursuant to Title I, Chapter 4 of
Pub.L. No. 106-31 (to monitor provision of assistance to address the effects of hurricanes in
Central America and the Caribbean) also be available to GAO to monitor post-earthquake
expenses related to Haiti, including relief, rehabilitation, and reconstruction aid.
4
GAO, Haiti Reconstruction: U.S. Efforts have Begun, Expanded Oversight Still to Be
Implemented, GAO-11-415 (Washington, D.C.: May 19, 2011).
Page 2 GAO-12-68 Haiti Reconstruction
a more detailed description of each of the six sectors with infrastructure
construction we reviewed.)
Background Haiti is the poorest country in the Western Hemisphere, with more than
75 percent of the population living on less than $2 per day and the
unemployment rate estimated at 60 to 70 percent. These conditions were
exacerbated when the largest earthquake in Haiti’s recorded history
devastated parts of the country, including the capital, on January 12,
2010. Since then, Haiti has suffered from a cholera epidemic that has
affected over 450,000 persons and caused over 6,000 deaths. In addition,
Haiti has experienced political uncertainty following the earthquake. Due
to the inconclusive presidential election of November 2010, the new
President was not inaugurated until May 2011. On May 13, 2011, the U.S.
and Haitian governments signed the Haiti Reconstruction Grant
Agreement. Later, the Haitian Parliament rejected two candidates
nominated by the new President for the post of Prime Minister, who
serves as head of government. In early October 2011, the Parliament
approved the President’s third nominee.
In response to the earthquake, in the Act, Congress provided more than
$1.14 billion in reconstruction funds for Haiti, available through the end of
fiscal year 2012. Of this amount, about $918 million was directed to
USAID and State, 5 of which $770 million was provided through the
USAID-administered Economic Support Fund (ESF) account and about
$148 million through the State-administered International Narcotics
Control and Law Enforcement account (see table 1).
5
Of the $918 million, USAID and State are directly administering $796 million in bilateral
reconstruction assistance funding from the Act, excluding $120 million in ESF funding
provided to the multilateral Haiti Reconstruction Fund and $2 million provided to the
Smithsonian Institution for a bilateral cultural preservation project.
Page 3 GAO-12-68 Haiti Reconstruction
Table 1: Supplemental Funding for Post-Earthquake Reconstruction in Haiti
Dollars in millions
Recipient Reconstruction amounta
USAID and State $917.7
USAID 770.0
State 147.7
Treasuryb 219.8
USAID Inspector General 4.5
Total $1,142.0
Sources: Congressional Research Service, GAO analyses of U.S.-government fiscal year 2010 supplemental budget request, and final
appropriation in the Supplemental Appropriations Act, 2010 (Pub. L. No. 111-212).
Note: Funding amounts do not add to total due to rounding.
a
In addition to reconstruction funding, the Act provided about $1.64 billion for post-earthquake relief
activities, which were primarily implemented by the Department of Defense and USAID’s Offices of
Foreign Disaster Assistance, Transition Initiatives, and Food for Peace, as well as $144 million for
diplomatic-related expenses.
b
Funding for the Department of the Treasury includes $212 million for Haitian debt relief and $7.8
million for a Treasury attaché office in the U.S. Embassy in Port-au-Prince and technical assistance.
Of the almost $918 million in supplemental funds, as of September 30, 2011,
$356.9 million was allocated for the construction and rehabilitation of
infrastructure. In addition to these supplemental funds, USAID and State
allocated funding for reconstruction activities from other budgetary sources,
such as annual appropriations for fiscal years 2010 and 2011, of which $54.8
million was allocated for construction and rehabilitation of infrastructure. In
total, the agencies allocated almost $412 million from both supplemental and
other budgetary sources for construction and rehabilitation of infrastructure. 6
In September 2010, State and USAID, as required by the Act, issued a joint
spending plan that showed allocations of supplemental reconstruction funds
(see fig. 1 for a timeline of key government of Haiti and international donors
and U.S. government actions and events after the earthquake).
6
For more detailed information on the funding provided to assist Haiti in the Fiscal Year
2010 Supplemental Appropriations Act, as well as expanded oversight actions for the
increased level of funding, see GAO-11-415.
Page 4 GAO-12-68 Haiti Reconstruction
Figure 1: Timeline of Actions Taken by the Government of Haiti, International Donors, and the U.S. Government since the
January 12, 2010, Earthquake
Note: See GAO, Haiti Reconstruction: U.S. Efforts Have Begun, Expanded Oversight
Still to Be Implemented, GAO-11-415 (Washington, D.C.: May 19, 2011), for a
description of the Interim Haiti Recovery Commission and the Haiti Reconstruction Fund.
Page 5 GAO-12-68 Haiti Reconstruction
In January 2011, the U.S. government issued the 5-year Post-Earthquake
USG Haiti Strategy: Toward Renewal and Economic Opportunity.
Consistent with the government of Haiti’s development priorities, the U.S.
strategy seeks to, among other things, encourage reconstruction and
long-term economic development in several regions of the country—
known as “development corridors”—including a region on the northern
coast of Haiti that is not close to the earthquake epicenter, but where
some people displaced by the earthquake moved. The strategy notes that
65 percent of Haiti’s economic activity was located in greater Port-au-
Prince 7 and states the U.S. government’s intent to support new economic
opportunities in the Saint-Marc and Cap-Haïtien development corridors, in
addition to assisting with reconstruction in the Port-au-Prince corridor,
which suffered the most damage from the earthquake (see fig. 2).
7
The strategy further notes that, before the earthquake, migration toward Port-au-Prince
had concentrated Haiti’s social and economic problems; over the last 10 years, poverty
declined by more than 8 percent across Haiti while increasing by 13 percent in Port-au-
Prince.
Page 6 GAO-12-68 Haiti Reconstruction
Figure 2: Development Corridors and Selected Sites Targeted by the U.S. Post-Earthquake Assistance
Page 7 GAO-12-68 Haiti Reconstruction
The U.S. strategy identifies planned U.S. reconstruction assistance in
eight sectors. 8 Six of these sectors—energy, ports, shelter, health, food
security, and governance and rule of law—involve infrastructure
construction and rehabilitation, while two sectors—economic security and
education—do not. The strategy also encompasses some of the
objectives set forth in the Haitian government’s 10-year Action Plan for
National Recovery and Development in Haiti, issued in March 2010. The
Action Plan identified and prioritized short- and long-term reconstruction
needs in four areas: (1) territorial rebuilding in Port-au-Prince and three
targeted regions of Cap-Haïtien, Saint-Marc, and Les Cayes;
(2) economic rebuilding in sectors such as construction, agriculture, and
tourism; (3) social rebuilding in the health, education, food security, and
other sectors; and (4) institutional rebuilding focused on developing
government capacity, justice, and a legal and regulatory framework.
To advise and support U.S. earthquake reconstruction efforts in Haiti,
USAID and State created special offices in Washington, D.C.
• In February 2010, USAID created the Haiti Task Team (HTT) to help
coordinate U.S. emergency relief and reconstruction work and provide
technical and staff support. At its peak, the HTT had approximately 50
staff positions, primarily U.S. full- or part-time staff who were
temporarily reassigned from USAID’s Bureau for Latin America and
the Caribbean and other bureaus, as well as contracted staff.
• In September 2010, State created the Office of the Haiti Special
Coordinator to oversee the planning and implementation of the U.S.
strategy in Haiti in coordination with USAID and other U.S.
departments and agencies. The Haiti Special Coordinator has
approximately 20 staff positions, primarily staff temporarily reassigned
full- or part-time from other bureaus and offices within State, and other
U.S. agencies as well as contracted staff.
8
The strategy refers to these eight sectors as “priorities,” but we are using the more
common term “sector.”
Page 8 GAO-12-68 Haiti Reconstruction
USAID and State Have As of September 30, 2011, USAID and State allocated $411.6 million for
bilateral post-earthquake infrastructure construction activities in Haiti
Obligated and using $356.9 million in fiscal year (FY) 2010 supplemental funds and
Expended Small $54.8 million from regular fiscal year appropriations. 9 In addition, USAID
and State had obligated $48.4 million 10 (11.8 percent) and expended $3.1
Amounts of the million (0.8 percent) of the total allocated, as shown in table 2. 11
Almost $412 Million
Allocated for Table 2: USAID and State Total Funds Allocated, Obligated, and Expended for
Bilateral Post-Earthquake Infrastructure Construction Activities in Haiti, as of
Construction September 30, 2011
Activities Dollars in millions
USAID State Total
Total funds allocated $365.7 $45.9 $411.6
FY 2010 supplemental 311.2 45.7 356.9
Other sources 54.6 0.2 54.8
Total funds obligated 42.6 5.8 48.4
FY 2010 supplemental 41.8 5.6 47.4
Other sources 0.8 0.2 1.0
Total funds expended 1.4 1.7 3.1
FY 2010 supplemental 0.6 1.7 2.4
Other sources 0.8 0.0 0.8
Source: GAO analysis of USAID and State data.
Notes: Other sources are regular fiscal year 2010 and 2011 appropriations. For food security
infrastructure construction activities, USAID plans to provide $55.5 million during fiscal years 2011
through 2014; however, we did not include this amount because USAID did not provide the funding
data by fiscal year. Total amounts may not add due to rounding.
9
USAID defines an allocation as the identification and setting aside of resources for a
specific program action.
10
An obligation is a definite commitment that creates a legal liability of the U.S. government for
the payment of goods and services ordered or received (see GAO, A Glossary of Terms Used
in the Federal Budget Process, GAO-05-734SP (Washington, D.C.: September 2005)). This
report defines obligations as the total amount of orders placed, contracts awarded, services
received, and similar transactions during a given period that will require payments during the
same or future period. USAID labels these actions subobligations. Consistent with 31 U.S.C.
§ 1501, which defines when an agency can record an obligation, USAID generally treats as an
obligation the bilateral agreements it makes with other countries to deliver assistance.
11
In addition to the funding and activities described in this report, the USAID mission in
Haiti (mission) has 11 activities that began before the earthquake—at an estimated cost,
for infrastructure and construction components, of about $172 million—that include
planning, design, and construction of infrastructure activities.
Page 9 GAO-12-68 Haiti Reconstruction
USAID and State Allocated Combined, USAID and State allocated $411.6 million for post-earthquake
Almost $412 Million in infrastructure construction activities as of September 30, 2011 (see table
Supplemental and Other 2). USAID is responsible for implementing most of the infrastructure
construction activities. USAID activities in five sectors—shelter, energy,
Funding for Post- ports, health, and food security—account for $365.7 million (88.9 percent)
Earthquake Infrastructure of the $411.6 million in total funds allocated for infrastructure construction.
Construction Activities in State has activities in the governance and rule of law sector, which
Haiti account for $45.9 million (11.1 percent) of the total funds allocated for
infrastructure construction. See appendix II for additional detailed
information on each of the six sectors. Table 3 shows USAID and State
funding allocations by sector.
Table 3: USAID and State Sector-Specific Funding Allocations for Post-Earthquake Construction Activities in Haiti, as of
September 30, 2011
Dollars in millions
FY2010 supplemental Total (percentage of supplemental
Sector funds Other funding sources and other funds)
Energy (USAID) $85.3 $13.0 $98.3 (23.9)
Ports (USAID) 77.7 0.0 77.7 (18.9)
Shelter (USAID) 55.1 1.6 56.7 (13.8)
Health (USAID) 50.5 40.0 90.5 (22.0)
Food Security (USAID) 42.6 0a 42.6 (10.3)
Governance and Rule of Law (State) 45.7 0.2 45.9 (11.1)
Total $356.9 $54.8 $411.6
Source: GAO analysis of USAID and State data.
Note: Other sources are regular fiscal year 2010 and 2011 appropriations.
a
For food security infrastructure construction activities, USAID plans to provide $55.5 million during
fiscal years 2011 through 2014; however, we did not include this amount because USAID did not
provide the funding data by fiscal year.
Examples of post-earthquake infrastructure activities are as follows:
• The energy sector includes rehabilitating substations in the Port-au-
Prince area and in the Cap-Haïtien development corridor, providing
power to the North Industrial Park—an activity that is key to Haiti’s
economic development with donor and private-sector commitments of
about $400 million and a goal of creating about 60,000 direct and
indirect jobs, according to USAID and State officials.
• The ports sector includes the construction of a new port along the
northern coast of Haiti in the Cap-Haïtien development corridor. Upon
Page 10 GAO-12-68 Haiti Reconstruction
completion, the port could provide improved shipping access for firms
operating in the North Industrial Park and other locations in the area.
• The shelter sector includes the development of approximately 15,000
service plots, which include housing and access to essential services,
in new residential settlements in the Port-au-Prince and Cap-Haïtien
development corridors.
• The health sector includes the reconstruction of the State University
Hospital in the Port-au-Prince development corridor.
• The food security sector includes the construction of irrigation canals
and farm-to-market roads in the Cap-Haïtien, Port-au-Prince, and
Saint-Marc development corridors.
• The governance and rule of law sector includes construction activities
funded through State’s Bureau of International Narcotics and Law
Enforcement (State/INL); the activities include the rehabilitation of
facilities at the Haitian National Police Academy.
USAID and State Have As of September 30, 2011, USAID had obligated $42.6 million for
Obligated Almost 12 activities in the energy, ports, shelter, health, and food security sectors.
Percent and Expended 0.8 The majority (67 percent) of USAID’s obligations have been for two
energy activities—$15.8 million for construction of power generation at
Percent of Funds Allocated the North Industrial Park and $12.9 for rehabilitation of 5 power sub-
for Infrastructure stations in the Port-au-Prince area. State had obligated $5.8 million, as of
Construction September 30, 2011, for its activities in the governance and rule of law
sector. State officials said that designing and planning of construction
activities generally involves a more lengthy process than for other
activities, and they expect obligations to grow at a faster pace later this
year and during 2012 as USAID and State infrastructure construction
activities reach the implementation stage. See table 4 for obligation and
expenditure data.
Page 11 GAO-12-68 Haiti Reconstruction
Table 4: USAID and State Total Obligations and Expenditures for Post-Earthquake
Construction Activities, as of September 30, 2011
Dollars in millions
Obligations Expenditures
USAID Activities Total $42.6 $1.4
Energy sector: Rehabilitation of 5 Port-au-Prince electrical
substations
• architectural and engineering design services 0.2 0.2
• construction 12.7 0
Energy sector: North Industrial Park short-term power
generation
• architectural and engineering design services 0.8 0.3
• construction 15.0 0
Ports sector: Feasibility study for the design of a new port 2.8 0
in northern Haiti
Shelter sector: Residential shelter site preparation, 9.8 0.7
environmental assessment, and design (Caracol Ekam)
Shelter sector: Residential shelter environmental 0.3 0.3
assessments and design
Health sector: Environmental assessment of the State 0.4 0
University Hospital (Port-au-Prince)
Food security sector: Watershed Initiative for Natural 0.5 0
a
Environmental Resources (WINNER)
State Activities Total 5.8 1.7b
Governance and rule of law sector: Haitian National Police 5.0 1.1
Academy repairs
Governance and rule of law sector: Prison repairs—site 0.2 0.2
surveys of Petionville and Carrefour facilities
Governance and rule of law sector: Construction 0.3 0.3
supervision—oversight of construction activities
Governance and rule of law sector: National Penitentiary 0.2 0.2
repairs
Governance and rule of law sector: Police station repairs 0.2 0
Source: GAO analysis of USAID and State data.
Note: Amounts may not add due to rounding.
a
Estimated award, total obligation, and expenditure amounts are for infrastructure, planning and
design, and construction components of WINNER. The total award amount for WINNER is $127
million; total obligations and expenditures as of June 30, 2011, are $59 million and $49 million,
respectively. WINNER’s infrastructure-related activities include erosion prevention, irrigation
restoration, and rebuilding and repair of transportation infrastructure.
b
State refers to expenditures as liquidations.
Page 12 GAO-12-68 Haiti Reconstruction
USAID Staffing
Difficulties Were a
Factor in Delaying
USAID Infrastructure
Construction
Activities in Haiti
USAID Has Had Difficulty Within a month after the earthquake, 10 of the mission’s 17 U.S. direct-
Replacing Staff Since the hire staff 12 had departed Haiti, leaving the mission with 7 staff in country
Earthquake to manage a program heavily involved in massive relief operations and
anticipating an increase in reconstruction activities. According to mission
officials, U.S. direct-hire staff were permitted to leave for several reasons,
primarily because approximately 40 percent of U.S. embassy housing
was damaged or destroyed, the school for mission staff children was
damaged and not functional, and staff were experiencing emotional
challenges after the earthquake.
To fill the U.S. direct-hire vacancies, USAID posted 10 routine agency
wide job announcements in March 2010, but no U.S. direct-hire staff
applied. According to USAID officials, potential applicants did not apply
due to, among other things, the damaged school, uncertainty about the
quality of life in Haiti, and the lack of financial or other incentives in the job
announcements. In May 2010, USAID again posted the 10 job
announcements and, this time, attracted a number of applicants because
the postings included financial incentives and waived the requirement that
successful applicants bid on positions in four USAID-designated critical
priority countries—Afghanistan, Iraq, Pakistan, and Sudan—upon
completion of their tours in Haiti. 13 Having received a sufficient number of
12
For U.S. direct-hire staff, we used the workforce definition developed by USAID’s 1990
Workforce Planning Working Group: U.S. citizen direct-hire foreign service staff, most of
whom serve at overseas missions. U.S. direct-hire staff do not include U.S. personal
services contractors (PSC) and other staff such as Haitian and third-country nationals. At
the time of the earthquake, 17 of the mission’s 20 authorized U.S. direct-hire positions
were filled.
13
USAID considers these countries, as designated by the USAID Administrator, to be its
most challenging assignments.
Page 13 GAO-12-68 Haiti Reconstruction
applicants for the May 2010 posting, the mission soon selected the staff.
However, U.S. direct-hire staff did not begin to arrive in Haiti until early
2011 because, among other things, households and families had to be
moved and some staff required up to 6 months in language training. In
addition to filling existing positions, USAID received approval from the
U.S. Ambassador to Haiti in February 2011 for 15 additional U.S. direct-
hire staff to manage the surge in earthquake-related funding. 14 These
positions were announced and some candidates selected when the
approval was granted in February 2011. Eleven had arrived as of
September 2011 and, according to mission officials, all are expected to
arrive in Haiti by February 2012. However, the mission will be
implementing infrastructure construction activities until at least 2015,
according to USAID planning documentation. During the next 4 years,
U.S. direct-hire staff will have opportunities to bid for other positions at
other posts. As U.S. direct-hire staff leave Haiti, the mission will need to
replace them in order to continue the progress of infrastructure
construction activities.
Lack of Staff Created Since the earthquake, the mission has been operating with a reduced
Planning Delays number of U.S. direct-hire staff. During that time, the mission experienced
delays in planning and implementing some construction activities.
According to USAID officials, U.S. direct-hire staff are essential in
planning and establishing continuity for long-term reconstruction activities,
including infrastructure activities such as the design of power generation
facilities, which require specific skills. Delays in staffing key positions,
such as engineers, contracting officers, and sector specialists, created
particular difficulties. For example:
Engineering: Although USAID allocated more than $300 million in
supplemental funds for infrastructure activities that would require
engineering skills, the mission’s planning process was delayed due, in
part, to the lack of U.S. direct-hire engineers, according to USAID
officials. USAID was unable to reassign U.S. direct-hire engineers from
other missions around the world because USAID has few engineers
worldwide, according to mission officials. At the time of the earthquake,
the mission had two Haitian engineers on its staff, but these individuals
14
Per National Security Decision Directive 38 (NSDD-38), the Chief of Mission (the U.S.
Ambassador to Haiti) must approve any U.S. department or agency request to increase
the number of staff posted in country.
Page 14 GAO-12-68 Haiti Reconstruction
had experience in constructing and repairing roads and bridges and
rehabilitating small infrastructure—with no experience in energy and ports
construction. In anticipation of its pending involvement in infrastructure
activities, the mission created a new Office of Infrastructure, Energy, and
Engineering, but staff with specialized engineering skills did not begin to
arrive at the mission until early 2011. For example, the mission’s chief
engineer, who is responsible for overseeing construction activities in the
energy sector, arrived in April 2011, and an engineer overseeing the
construction of health facilities arrived in May 2011.
Mission officials in the health sector stated that initial delays in staffing an
engineer in the Office of Infrastructure, Energy, and Engineering
presented a planning challenge because in-country engineering expertise
is essential to rehabilitate a major hospital and numerous smaller health
clinics. According to mission officials, the lack of staff and expertise made
planning difficult for several reasons. For example, some staff who were
involved in developing certain cost and planning estimates and assessing
potential constraints had limited expertise, thus requiring more review by
others. Further, some construction activities experienced delays as a
result of staff shortages. For example, on September 22, 2011, about 3
months later than initially planned, the mission awarded a feasibility study
related to its plans to invest in port development in the Cap-Haïtien
development corridor. According to USAID officials, the delay occurred
because mission staff were focused on energy-sector issues related to
the North Industrial Park. The feasibility study is needed before the
mission can determine its specific plans for port construction and set an
award date for the construction contract that is expected to follow.
Contracting: The mission also experienced delays in awarding some
infrastructure construction contracts as originally scheduled because it
had only one U.S. direct-hire contracting officer in country with the
authority to approve contracts of more than $3 million, according to
USAID officials. 15 The mission plans to award several complex contracts
for more than $3 million each from the more than $300 million in
15
USAID requires contracting officers to be U.S. citizen direct-hire employees of the U.S.
government (see 48 CFR 701.603-70). The authority of overseas heads of contracting is
generally limited to a $100,000 threshold for most contracts (see 48 CFR 701.601). The
mission received support from USAID headquarters, which assigned temporary duty staff
with contracting experience; however, according to mission officials, temporary staff did
not have sufficient approval authority.
Page 15 GAO-12-68 Haiti Reconstruction
supplemental funding it has allocated for infrastructure activities. The
mission currently has three other contracting officers with lower
contracting authority approval limits, and as of September 2011, the
mission had requested additional contracting officers it anticipates will be
needed to keep pace with the planned time frames for the mission’s
planned infrastructure activities.
Programming: The mission also experienced delays because, for more
than 1 year following the earthquake, it did not have several sector
directors, including a program office chief and office chiefs for economic
growth and democracy and governance offices, among other
programming positions. According to mission officials, key decisions
during the design and planning of construction activities were delayed, in
part, because the mission had not been involved in such activities before
the earthquake and there was limited expertise among existing staff. In
addition, mission staff have experienced increased workloads and some
mission staff have had to take on additional responsibilities outside their
normal areas of expertise. For example, the deputy mission director
assumed the additional role of leading energy sector planning for about
15 months until the April 2011 arrival of the chief engineer. In addition to
other staffing issues, three of USAID’s Haitian employees died in the
earthquake. Further, mission officials stated that numerous surviving
Haitian employees have been unable to contribute quickly to post-
earthquake planning efforts because some had family members who died
or were injured in the earthquake and many had residences that were
damaged or destroyed.
USAID Haiti Relied Largely Based on our review of USAID policies and guidance, including its
on Temporary Staff Automated Directives System, and statements of mission officials, USAID
Following the Earthquake does not have an expedited process for placing U.S. direct-hire staff to
work on reconstruction efforts in an urgent post-disaster or post-crisis
situation such as Haiti. 16 Absent such a process, USAID Haiti used
USAID’s routine but lengthy staffing process, which involves, among
16
In 2002, we recommended that the USAID Administrator develop and implement
procedures to allow USAID to reassign quickly key personnel, particularly contracting
officers, in post-emergency and post-crisis situations. See GAO, Foreign Assistance:
Disaster Recovery Program Addressed Intended Purposes, but USAID Needs Greater
Flexibility to Improve Response Capability, GAO-02-787 (Washington, D.C.:
July 24, 2002).
Page 16 GAO-12-68 Haiti Reconstruction
other things, posting job opportunities agency-wide, receiving
applications, selecting staff, and waiting until they are released from their
current assignments.
To meet the increased need for mission staff to manage the program, the
agency temporarily hired or reassigned staff, including staff from its Haiti
Task Team in Washington, D.C., to complete more than 400 temporary
duty assignments for periods ranging from one week to several months. 17
For example, USAID used personal services contracts to hire staff to
provide financial management expertise; assigned headquarters-based
staff from its Latin America and Caribbean Bureau to manage and
oversee rubble removal and other efforts; and provided fiscal year 2010
supplemental funding to an implementing organization to manage people
who repaired roads, cleaned drainage canals, and performed other
rehabilitation activities.
According to mission officials, planning and implementation of
reconstruction activities were delayed because the few staff remaining in
Haiti were heavily involved in recruiting, placing, and training temporary
staff in Haiti. Senior mission staff stated that, for many temporary staff
positions, the mission had to develop detailed scopes of work for the
positions and then brief and train newly arrived staff on substantive
issues. In addition, mission staff noted that the continuity of efforts was
sometimes problematic as multiple staff, who turned over frequently,
managed the efforts.
17
These temporary staff included personnel from the Civilian Response Corps (CRC), a
multi-agency group of civilian federal employees who are specially trained and equipped
to deploy rapidly to countries in crisis or emerging from conflict. CRC provides the U.S.
government with a first responder effort and supports the implementation of longer-term
reconstruction activities. Also, according to USAID, some of the temporary staff assisted
with immediate earthquake relief and the subsequent cholera outbreak.
Page 17 GAO-12-68 Haiti Reconstruction
USAID Planning Is
Still Under Way;
Various Factors
Contributed to Delays
in Infrastructure
Construction
USAID Has Finalized Six USAID planning for its earthquake reconstruction activities in Haiti is still
of Eight Sector-Specific under way. 18 The USAID mission in Haiti, in coordination with other U.S.
Planning Documents government agencies and USAID in Washington, D.C., has drafted eight
Activity Approval Documents (AADs)—detailed planning documents for
each sector. 19 As of October 2011, six AADs had been approved:
education, energy, food security, governance and rule of law, health, and
shelter (see table 5). These six AADs account for 87 percent of USAID’s
available supplemental and program funds, according to USAID. The two
remaining AADs require additional work before they can be approved,
according to USAID officials. Specifically, the AAD for economic
security—which does not include any planned infrastructure
construction—requires further interagency discussion with the U.S.
Department of the Treasury (Treasury), which is the co-implementer of
economic activities in Haiti, and the AAD for ports has not been approved
because, among other things, USAID is waiting for the Haitian
government to make key decisions regarding port regulations, use of
territorial waters and the Haitian customs code.
18
Because USAID’s planned funding level for infrastructure activities is almost 8 times
larger than State’s, we focused our review on USAID’s planning efforts.
19
State/INL, which is planning infrastructure construction activities in the governance and
rule of law sector, does not develop an AAD-type document during its planning process,
according to a State official. The U.S. government strategy and supplemental spending
plan describe State/INL’s plans for infrastructure construction activities, such as the
construction of a new women’s prison, repairs to two correctional facilities damaged in the
earthquake, repairs to facilities at the Haitian National Police Academy damaged by the
earthquake, and repairs and construction of police substations and counternarcotics
outposts. For more detail, see appendix II.
Page 18 GAO-12-68 Haiti Reconstruction
Table 5: Status of USAID Activity Approval Documents (AADs), as of October 2011
AADs approved AADs not approved
Education Economic Security
Energy Ports
Food Security
Governance and Rule of Law
Health
Shelter
Source: GAO analysis of USAID data.
Notes: USAID does not plan any infrastructure construction activities in the governance and rule of
law AAD, however, the AAD includes State/INL infrastructure construction activities. USAID does not
plan any infrastructure construction activities in the economic security and education AADs.
According to USAID officials, the AADs for Haiti are more comprehensive
and have involved a more extensive review process than is typical. For
example, USAID officials stated that the AADs for USAID activities in Haiti
have included more analytical metrics, such as the results USAID plans to
achieve in return for its investment. These AADs incorporate a discussion
of how each sector will meet USAID’s agency wide procurement reform
known as USAID Forward, which has, among other objectives, the goal of
broadening the base of USAID’s implementing partners. 20 According to
USAID officials, incorporating USAID Forward has changed the
procurement plan structure in the AADs, requiring more scrutiny by
agency officials. For example, USAID indicated for activities described in
the AAD procurement plans whether those activities will be targeted at
local firms or organizations or use traditional partners.
In addition, several factors led to a more extensive review process for the
AADs for activities in Haiti. According to USAID officials, AADs are
usually drafted at the mission and approved by the mission director.
However, due to U.S. foreign policy interests in Haiti, in addition to the
review and approval of the Haiti mission director, these AADs have
undergone high-level review by USAID and State’s Office of the Haiti
Special Coordinator. Because the U.S strategy is a whole-of-government
strategy, a number of other U.S. agencies were involved in reviewing and
20
USAID Forward is the USAID Administrator’s reform agenda for the agency. It outlines
seven areas for reform: implementation and procurement reform, talent management,
rebuilding policy capacity, strengthening monitoring and evaluation, rebuilding budget
management, science and technology, and innovation.
Page 19 GAO-12-68 Haiti Reconstruction
approving the AADs. These agencies included the U.S. Department of
Agriculture for food security, Treasury for economic security, and the
Centers for Disease Control and Prevention for health. According to
USAID and State officials, the inclusion of other agencies in the process
added levels of review that have extended AAD development and
approval.
Prior to AADs being approved in Washington, D.C., the Haiti mission
continued with other planning efforts. The mission’s Office of Acquisition
and Assistance developed a procurement plan to manage contract
actions—such as the award of contracts for planning, design, and
construction services—that enable implementation of the activities. In the
shelter sector, for example, the mission has awarded contracts for the
design of the proposed residential sites; the design includes site layout
plans, environmental impact assessments, and housing-unit design
specifications. In instances where an AAD had not been approved but
where the mission deemed that sufficient planning had been completed,
the mission used activity-specific approval memoranda to initiate
procurement actions, and, in some instances where design work was
completed, award construction contracts. For example, a contract for the
construction of a 10-megawatt power plant for the North Industrial Park in
the Cap-Haïtien development corridor with a value of approximately $15
million was awarded while the energy AAD was in draft.
A Few Infrastructure As of September 15, 2011, the mission had awarded its first two
Construction Activities Are infrastructure construction contracts—rehabilitation of five electrical
Under Way; Various substations in Port-au-Prince and construction of a power plant in the
North Industrial Park—at a combined cost of $28.8 million; approximately
Factors Contributed to 7 percent of USAID’s total allocation for infrastructure construction
Delays activities. 21 These awards were slightly delayed, as described below:
• Rehabilitation of five electrical substations in Port-au-Prince: On
July 28, 2011, about 1 month later than planned, USAID Haiti
awarded a $12.7 million construction contract for work to improve
electrical service in Port-au-Prince. USAID extended the time for
contractors to submit construction proposals because USAID issued
new information in response to contractors’ questions, such as those
21
The $28.8 million includes $1 million for two engineering design contracts, one contract
each for the two activities.
Page 20 GAO-12-68 Haiti Reconstruction
concerning the length of the contract performance period—considered
by contractors to be too short—and requests for clarification of
technical documents referenced in the original proposal solicitation. 22
• Construction of a power plant in the North Industrial Park: On
September 15, 2011, about 6 weeks later than planned, the mission
awarded a $15 million contract for construction of a power-generating
facility to meet the start-up electrical needs of the North Industrial
Park. Some of the delay was to allow contractors time to respond to
USAID’s clarifications and new contract requirements that were the
result of contractor questions, changes to documents in the original
solicitation, and the addition of environmental mitigation requirements.
Some of the delay was also due to time spent by USAID mission staff
focusing on a bid protest of the Port-au-Prince substation
rehabilitation contract.
Some key USAID activities experienced delays in their original schedule
due to technical issues, and other activities do not yet have a planned
award date. These delays are in part related to issues such as the length
of time it takes contractors to submit construction proposals, difficulties
obtaining building sites, and incomplete environmental assessment
documents. In addition, some activities do not yet have dates set for
award of construction contracts because the scope and location of the
infrastructure have yet to be determined.
• North Industrial Park long-term power generation: The mission
delayed its planned award of a construction contract to increase the
power plant’s generation capacity from November 2011 to April 2013.
According to a mission official, the dates were revised because the
22
According to mission officials, after the construction contract was awarded on July 28,
2011, one of the unsuccessful bidders filed a bid protest with GAO. As a result, the
mission’s chief contracting officer suspended work for 3 months while the protest is under
consideration, per USAID standard operating procedure; as of November 15, a decision
on the protest had not been announced. Bid protests may be filed with GAO against
procurement actions by federal government agencies. A bid protest is a challenge to the
award or proposed award of a contract for procurement of goods and services or a
challenge to the terms of a solicitation for such a contract. Protests can also be filed with
the agency responsible for the procurement and the U.S. Court of Federal Claims (31
U.S.C. § 3551 et. seq.).
Page 21 GAO-12-68 Haiti Reconstruction
number of future tenants in the industrial park and their electrical
power requirements are not yet known. 23
• South Industrial Park power generation: As of October 2011, a site
for the South Industrial Park had not been established. Therefore, the
mission has not yet determined the contract award date for this
activity, which will provide power to a new South Industrial Park.
• State University Hospital in Port-au-Prince (HUEH): The mission
delayed by about 5 months its plans to enter into an agreement 24 with
the governments of France and Haiti to reconstruct, repair, and
modernize earthquake-damaged buildings on Haiti’s State University
Hospital campus. 25 The delay is due, in part, to a USAID-funded
environmental assessment of the HUEH which is taking longer than
planned. 26 Mission officials expect that the assessment will be
completed near the middle of November 2011, and estimate that the
mission will be able to execute the HUEH agreement by December
2011.
• Shelter demonstration project: The mission planned to break
ground on a “demonstration” settlement of 200 houses and other
residential infrastructure on January 12, 2011. According to USAID
officials, the mission has faced challenges in obtaining land titles for
property on which to build because the government of Haiti lacks a
comprehensive, functional system for recording land ownership—
resulting in only 40 percent of landowners possessing documentation
of title to their land and land records which may be inaccurate—as
23
According to this official, the mission is conducting two studies on the expansion, one to
determine least-cost options and one to evaluate renewable energy alternatives, which will
be completed in December 2011 and October 2012, respectively.
24
According to a USAID official, the agreement will be a fixed amount reimbursable
agreement. Under terms of the agreement, USAID will pool $25 million of its funds with
$25 million provided by the government of France and approximately $3 million from the
government of Haiti to fund construction work.
25
The construction contract under which this work will be performed will be administered
by the technical unit of the government of Haiti’s Ministry of Finance.
26
USAID guidelines require an environmental assessment for planned activities. According
to the mission’s regional legal advisor, the agreement cannot be completed until the
environmental assessment is completed and the results of the assessment can be
included in the agreement. According to USAID officials, the environmental assessment
for these planned activities is complex.
Page 22 GAO-12-68 Haiti Reconstruction
well as overarching shelter legislation to guide housing, land-use, and
urban planning.
• Development and construction of new residential settlements:
The mission’s plan to award contracts to prepare 15,000 housing plots
and build 4,000 housing units has been delayed about 7 to 10
months. Originally planned for August 2011, the awards of most of
these contracts are now expected to occur between March and June
of 2012. It has taken longer than planned to identify the sites,
negotiate agreements with the Haitian government on the selection of
beneficiaries, and negotiate agreements with nongovernmental
organizations building some of the housing.
Haitian Government The sustainability of USAID-funded infrastructure activities depends, in
part, on improvements to Haiti’s long-standing economic and institutional
Capacity Is a Key weaknesses, the Haitian government’s political will to implement change,
Challenge to as well as the success of planned capacity-building activities. Based on
data from the UN Office of the Special Envoy for Haiti, aid from bilateral
Sustainability of U.S. and multilateral donors represented approximately 57 percent of the
Government government of Haiti’s total revenue in 2009. Following the earthquake, the
percentage increased substantially, to an estimated 80 percent of total
Infrastructure government revenue in 2010. 27 Additionally, more than 16,000 civil
Reconstruction servants died in the earthquake and, including those who left the country,
the Haitian government workforce is now reduced by 33 percent,
Activities according to the United Nations Development Program. 28 Further,
according to the U.S. government strategy and USAID documents and
officials, electricity laws, the structure of the health care system, the
customs code, and housing and urban development policy, among other
areas, all need reform.
27
United Nations Office of the Special Envoy for Haiti, Has Aid Changed? Channeling
Assistance to Haiti Before and After the Earthquake (New York, N.Y.: June 2011).
28
United Nations Development Program, Haiti One Year Later (Port-au-Prince, Haiti:
December 2010).
Page 23 GAO-12-68 Haiti Reconstruction
As part of its required planning processes, USAID considered various
sustainability issues for its infrastructure activities. 29 Some activities face
sustainability challenges. In planning and assessing the sustainability of
its activities in Haiti, USAID used a variety of resources. These included
relevant provisions in the Foreign Assistance Act, 30 guidance from the
agency’s Automated Directives System (ADS), 31 the agency’s project
design guidance, and studies and assessments by USAID and other
donors such as assessments of Haitian government ministries by the
Inter-American Development Bank. In addition, for infrastructure activities,
the mission relied on general principles for estimating costs, including
projecting operations and maintenance costs and estimating basic returns
on investments.
For four activities, as of September 2011, USAID has also completed
certification required by the Foreign Assistance Act indicating that Haiti is
capable of effectively maintaining and utilizing the projects. In addition,
each AAD contains a section broadly describing the sustainability issues
of the activities planned in each sector.
The following are examples of some of the challenges identified by
USAID and its plans to address those issues.
Energy sector: The power utility, Electricité d’Haiti (EDH), faces
considerable technical and managerial challenges that have resulted in
29
USAID defines sustainability in different ways depending on the goals of the sector and
project, such as usage for infrastructure projects, financial stability for capacity-building
projects, and environmental stability for numerous other projects. USAID also states that
the four key principles of sustainable development are (1) improved quality of life for
current and future generations; (2) responsible stewardship of the natural resource base;
(3) participation in political and economic life; and (4) effective institutions that are
transparent, accountable, responsive, and capable of managing change without continued
external support.
30
Section 611(e) of the Foreign Assistance Act of 1961 requires that for capital assistance
projects of more than $1 million, the agency head receive a certification of the country's
capability to maintain and utilize the project, taking into account, among other things, the
maintenance and use of projects in the country previously financed or assisted by the
United States (22 U.S.C. § 2361(e)). As of September 2011, USAID had signed 611(e)
certification memos for four activities: the North Industrial Park power generation facility,
new residential settlements in the Cap-Haïtien and Port-au-Prince development corridors,
reconstruction of the HUEH, and construction of the Millet Bridge in Port-au-Prince.
31
For example, USAID’s ADS, Planning, 201.3.9.3 and 201.3.11.6 (Washington, D.C.: rev.
Apr. 2, 2010).
Page 24 GAO-12-68 Haiti Reconstruction
financial losses. The utility receives an annual subsidy from the Haitian
government of approximately $100 million, which, according to USAID’s
energy AAD, represents approximately 12 percent of the government of
Haiti’s national budget. To assist the EDH, in April 2011 the mission
awarded a 2-year contract to improve EDH management while long-term
modernization options are developed and evaluated. In addition, USAID
plans for the North Industrial Park power generation facility to be
managed independently of EDH through September 2016. This facility is
expected to generate enough revenue to cover operations and
maintenance costs, including the replacement of major equipment.
However, modernization of the energy sector is based, among other
things, on the assumption that the Haitian government will decide on an
appropriate modernization model and take necessary, but politically
challenging steps, to implement that model, according to the energy AAD.
Health sector: The Haitian government has made efforts to decentralize
the health care system since the 1990s, but only 12 of 63 local health
networks are currently operational. 32 To support Haitian government
efforts to decentralize the health care system, USAID is planning to
provide resources, such as repair or construction of health facilities, to 9
to 12 local health networks in the U.S. development corridors. USAID is
also requiring business plans in this sector so that USAID will no longer
need to contribute to operations and maintenance of new or renovated
health facilities within 3 to 5 years of completion. USAID acknowledges
that strengthening the Haitian Ministry of Health and a decentralized
health care system—both of which would likely enhance sustainability—
are complex undertakings that will require long-term efforts. According to
USAID, there are also shortages of community health workers, low
retention of doctors and nurses who can earn more money in private
practice or working for nongovernmental organizations, and a low skill
and knowledge base at all levels.
Ports sector: According to USAID’s draft ports AAD, the Haitian
government does not have a well-defined legal and regulatory framework
for ports, and the three Haitian government entities involved in port
operations have unclear roles and responsibilities. 33 Furthermore, the
32
Local health networks consist of five to eight community health clinics and one hospital
to which the clinics refer patients that need more specialized care.
33
These Haitian government entities are the National Port Authority, the General Customs
Administration, and the Maritime Security Service.
Page 25 GAO-12-68 Haiti Reconstruction
sector is characterized by excessively high port charges, unreliably slow
port clearance processes, inadequate human and institutional capacities,
and poor integration between international and regional ports. To assist
with port construction in the Cap-Haïtien development corridor, according
to USAID’s draft ports AAD, (1) a public-private partnership 34 will be
created and (2) USAID will provide technical assistance to Haitian officials
to help them lower port charges in the northern port and introduce
processes to expedite port clearance and tax collection. However, the
ports sector AAD notes that port construction is a “high-risk” program
whose success depends on, among other things, the political will of the
Haitian government to make improvements in a sector controlled by a few
individuals, tens of millions of dollars in additional funding from other
donors, and sufficient demand for port use.
Shelter sector: Haiti lacks a single agency for housing and urban
development policy resulting in a sector characterized by fragmented
authorities and unenforced policies, according to the shelter sector AAD.
Among other things, Haiti does not have an effective national land
register—known as a cadastre—and system to record land ownership; a
policy framework that establishes and streamlines building standards and
other controls to promote disaster-resistant housing; and has poor
capacity to support the community organizations needed for shelter
infrastructure and service delivery. USAID plans to provide assistance in
areas such as building standards and enforcement mechanisms; land
tenure, land title, and property tax records; and housing finance and
mortgage markets. The shelter AAD notes that sustainability depends on
the ability of the Haitian government to manage and maintain
infrastructure and services over the long term. Policy change requires the
political will and dedication of the Haitian government, as well as support
from other members of the donor community. Sustainability also depends
on economic growth, governance reform, and the ability of Haitians to pay
taxes. If economic opportunities at the planned new shelter sites in
locations outside of the capital are insufficient, people may return to Port-
au-Prince. The success of USAID plans will depend on new economic
opportunities that would enable municipalities to pay for road
maintenance at the new sites and for housing beneficiaries to pay fees for
water services and basic maintenance, according to U.S. officials.
34
For infrastructure, USAID defines a public-private partnership as “a long-term contract
signed by a public agency and a private party for the construction, rehabilitation, operation
and/or maintenance of an infrastructure network.”
Page 26 GAO-12-68 Haiti Reconstruction
Our past work on U.S. assistance in developing countries shows that the
U.S. government has previously encountered challenges in ensuring the
sustainability of infrastructure activities. For example, following the 2001
earthquakes in El Salvador, we reported on sustainability challenges to
USAID-funded shelter and health clinic construction, including residents
who could not afford the cost of connecting to the potable water and
electricity systems in the new houses. 35 In addition, in July 2011, we
reported that the governments of Cape Verde and Honduras faced
challenges sustaining several activities funded through the Millennium
Challenge Corporation (MCC). 36 For example, in Honduras, uncertainty
about government funding for maintenance and other construction
activities may jeopardize the sustainability of some major roads built with
MCC funds.
Conclusion The United States is providing over one billion dollars to Haiti for
reconstruction but faces an enormous task in helping the country begin to
recover from the 2010 earthquake. A number of factors have delayed
USAID’s planning and implementation of projects to rebuild infrastructure
in the energy, ports, and shelter sectors—areas where the agency has
not previously worked and that require specific skills or expertise. Haiti
has always been a challenging operating environment, and the
earthquake created additional difficulties. Further, USAID had difficulties
securing staff—particularly technical staff such as contracting officers and
engineers—who were willing to live and work in the country after the
earthquake and who could bring the expertise necessary to plan and
execute large, complex infrastructure projects. Such difficulties have
contributed to delays in U.S. efforts, with only a few contracts awarded to
date. Additional issues, such as difficulties in obtaining land title and the
time needed to conduct environmental assessments, have led to delays
in planning construction activities, and some activities do not yet have
start dates. Further, the Haitian government’s long-standing economic
and institutional weaknesses are complicating U.S. efforts and could
affect the future of this assistance, and the political will of the recently
formed Haitian government to implement reforms and undertake
35
GAO, Foreign Assistance: USAID’s Earthquake Recovery Program in El Salvador Has
Made Progress, but Key Activities Are Behind Schedule, GAO-03-656 (Washington, D.C.:
May 15, 2003).
36
GAO, Millennium Challenge Corporation: Compacts in Cape Verde and Honduras
Achieved Reduced Targets, GAO-11-728 (Washington, D.C.: July 25, 2011).
Page 27 GAO-12-68 Haiti Reconstruction
sustainability efforts is unknown. Even though USAID is taking some
steps to address the long-term future of U.S.-funded infrastructure, it is
unclear at this point in time if those projects will ultimately be sustainable.
U.S. activities in Haiti will continue for many years, and USAID staff can
be expected to turn over numerous times. It is therefore critical that
USAID do as much as possible to match the number of staff with the
demands placed on the mission to ensure that the substantial amount of
U.S. funding provided for reconstruction is used efficiently and within time
frames that address the pressing needs in the country.
Recommendation for To facilitate USAID’s progress in planning and implementing its many
post-earthquake infrastructure construction activities in Haiti over the next
Executive Action several years, particularly those requiring key technical staff such as
contracting officers, engineers, and program specialists, we recommend
that the USAID Administrator ensure that U.S. direct-hire staff are placed
at the mission within time frames that avoid future staffing gaps or delays.
Agency Comments USAID provided written comments on a draft of this report, which are
reprinted in appendix III. State did not provide written comments. USAID
and Our Evaluation agreed with our finding that staffing difficulties were a factor in delaying
USAID infrastructure constructions activities in Haiti. In addition, USAID
described certain actions it is currently taking, such as providing
accelerated one-on-one language training and special bidding incentives
for Haiti, that, if continued, could address our recommendation.
USAID also emphasized staffing actions that the agency took following
the earthquake to quickly deploy staff temporarily to Haiti. Our report
recognizes these actions and the contributions they made in helping with
the relief and recovery efforts in Haiti. However, we maintain that such
efforts did not include bringing on U.S. direct-hire staff to fill permanent
positions and provide the continuity needed to manage longer-term
reconstruction projects. In particular, USAID noted that its Civilian
Response Corps (CRC), part of an interagency initiative, was used to
provide a surge capability and quickly deploy staff with specialized
knowledge and skills to Haiti. Our report notes that CRC, whose staff are
deployed for an average of 90 days, provides the U.S. government with a
first responder effort and supports the implementation of longer-term
reconstruction activities.
Page 28 GAO-12-68 Haiti Reconstruction
State and USAID both provided technical comments. Those comments,
along with information contained in USAID's written response, were
incorporated into the report where appropriate.
We are sending copies of this report to interested congressional
committees, the Secretary of State, and the USAID Administrator. We will
also provide copies to others on request. In addition, the report will be
available at no charge on the GAO Web site at http://www.gao.gov.
If you or any of your staffs have any question about this report, please
contact me at (202) 512-3149 or gootnickd@gao.gov. Contact points for
our Offices of Congressional Relations and Public Affairs may be found
on the last page of this report. GAO staff who made major contribution to
this report are listed in appendix IV.
David Gootnick
Director, International Affairs and Trade
Page 29 GAO-12-68 Haiti Reconstruction
List of Congressional Committees
The Honorable John Kerry
Chairman
The Honorable Richard Lugar
Ranking Member
Committee on Foreign Relations
United States Senate
The Honorable Patrick Leahy
Chairman
The Honorable Lindsey Graham
Ranking Member
Subcommittee on the Department of State,
Foreign Operations, and Related Programs
Committee on Appropriations
United States Senate
The Honorable Ileana Ros-Lehtinen
Chairman
The Honorable Howard L. Berman
Ranking Member
Committee on Foreign Affairs
House of Representatives
The Honorable Kay Granger
Chairwoman
The Honorable Nita M. Lowey
Ranking Member
Subcommittee on the Department of State,
Foreign Operations, and Related Programs
Committee on Appropriations
House of Representatives
Page 30 GAO-12-68 Haiti Reconstruction
Appendix I: Scope and Methodology
Appendix I: Scope and Methodology
We reviewed the infrastructure-related post-earthquake reconstruction
efforts of the U.S. Agency for International Development (USAID) and the
Department of State (State) in Haiti. 1 This report examines, for
infrastructure construction activities only, (1) the amounts of USAID and
State obligations and expenditures; (2) USAID’s staffing; (3) USAID’s
planning; and (4) potential sustainability challenges USAID faces.
In response to a congressional mandate in the Supplemental
Appropriations Act of 2010 (the Act) that made funds available for GAO to
review U.S. efforts in Haiti, we focused our review on the $918 million in
bilateral reconstruction funding provided to USAID and State in the Act 2
as well as other funding provided to USAID and State in annual fiscal
year appropriations that support reconstruction activities, including
infrastructure construction and rehabilitation, in Haiti. Of the $918 million,
$770 million was provided through the USAID-administered Economic
Support Fund (ESF) account and $148 million through the State-
administered International Narcotics Control and Law Enforcement
(INCLE) account. USAID and State have planned to allocate $356.9
million for infrastructure construction activities from the funding
appropriated in the Act. In addition, USAID and State supported
infrastructure construction activities with almost $54.8 million from regular
fiscal year appropriations, such as, for example, fiscal year 2010 funding
for the Global Health and Child Survival account. Combined, USAID and
State have allocated almost $412 million from both supplemental and
regular fiscal year appropriations for infrastructure construction activities.
1
Supplemental Appropriations Act, 2010, Pub. L. No. 111-212, title I, ch. 10, 124 Stat.
2302, 2320 (July 29, 2010). The law mandated that funds previously available to GAO
pursuant to Title I, Chapter 4 of Pub. L. No. 106-31 (to monitor provision of assistance to
address the effects of hurricanes in Central America and the Caribbean) also be available
to GAO to monitor post-earthquake expenses related to Haiti, including relief,
rehabilitation, and reconstruction aid. In May 2011, we issued a report that described the
planned uses for U.S. reconstruction assistance, USAID’s internal controls for overseeing
U.S. reconstruction funds, and Interim Haiti Recovery Commission governance and
oversight structures. See GAO-11-415.
2
In the Act, Congress provided more than $1.14 billion in reconstruction funds for Haiti
available through the end of fiscal year 2012, including about $918 million for USAID and
State and about $220 million for the Department of the Treasury for debt relief, a Treasury
attaché office in Port-au-Prince, and technical assistance. We did not review the funding
directed to Treasury. Additionally, we did not review $1.64 billion in funding provided
primarily to reimburse U.S. agencies for their emergency and humanitarian efforts in Haiti
immediately following the January 2010 earthquake, nor did we examine the
approximately $144 million in U.S. embassy-related funding included in the law.
Page 31 GAO-12-68 Haiti Reconstruction
Appendix I: Scope and Methodology
To obtain information on the appropriations, allocations, and planned
uses of U.S. reconstruction funding for Haiti, 3 we reviewed the
Supplemental Appropriations Act of 2010, enacted by Congress in July
2010; the State and USAID FY 2010 Supplemental Appropriations
Spending Plan, issued by State in September 2010; the interagency Post-
Earthquake USG Haiti Strategy: Toward Renewal and Economic
Opportunity, issued by State in January 2011; and Congressional
Research Service reports on Haiti. We also reviewed the Action Plan for
National Recovery and Development of Haiti, issued by the government
of Haiti in March 2010. In addition, we reviewed the Haiti Reconstruction
Grant Agreement, signed by the U.S. and Haitian governments in May
2011. We met in Washington, D.C., and in Port-au-Prince, Haiti, with
officials from USAID and State and other organizations implementing U.S.
government-funded activities. USAID defines allocation as the
identification and setting aside of resources for a specific program action.
To determine the amounts of funding obligated from USAID’s
supplemental ESF funding and State’s supplemental INCLE funding, as
well as funding from other sources for infrastructure construction
activities, we analyzed data reported by USAID as of June 30, 2011, and
September 30, 2011, and by State as of September 30, 2011. The
amounts reported to us by USAID and State include both expenditures
and unexpended obligated balances. These data include information on
obligations of supplemental appropriation funding overall, as well as
amounts provided for particular activities.
To assess the reliability of the data on planned allocations, obligations,
and expenditures, we conducted follow-up correspondence and
interviews with cognizant officials from USAID and State both in
Washington, D.C., and in Haiti. We asked them standard data reliability
questions—including questions about the purposes for which funding data
were collected, the use of the data, how the data were collected and
generated, and how the agencies ensured that the data were complete
and accurate—and determined the data to be sufficiently reliable for the
purposes of this report.
3
USAID and State have changed amounts allocated for infrastructure construction
activities as plans have developed. We are reporting amounts allocated based on the
most current information we received.
Page 32 GAO-12-68 Haiti Reconstruction
Appendix I: Scope and Methodology
To assess USAID’s staffing challenges in Haiti, we reviewed bidding
opportunity notices, staffing pattern analyses produced by the mission
Executive Office, and interviewed relevant officials at the mission in Haiti
and at USAID’s headquarters in Washington, D.C.
To determine the status of USAID’s planning activities, we reviewed the
agency’s policies for planning as outlined in the Automated Directives
System. We also reviewed eight sector-specific Activity Approval
Documents (AADs), six of which had been finalized as of October 2011,
as well as more detailed planning documents for specific activities with
infrastructure components, which we obtained during our visits to the
USAID mission in Haiti. To determine challenges USAID faces in
implementing activities as planned, we reviewed USAID’s and State’s
requests for proposals, amendments, and award documents posted at the
U.S. government’s Web site www.fedbizopps.gov. We also reviewed
USAID’s AADs, award documents provided by the mission, and USAID’s
activity procurement plan. In addition we interviewed relevant officials at
the mission’s Office of Acquisition and Assistance and the mission’s
Infrastructure, Energy, and Engineering Office to discuss the procurement
plan, bid solicitation process, and activity delays. Due to the small amount
of INCLE funding allocated for infrastructure activities, we did not review
the State Bureau for International Narcotics and Law Enforcement’s
planning process.
To describe issues related to the capacity of the Haitian government, we
reviewed U.S. government documents such as the U.S. government Haiti
Strategy and the AADs, and reports from the United Nations Office of the
Special Envoy for Haiti and the United Nations Development Program. To
discuss USAID’s planning process for sustainability and potential
sustainability-related challenges, we interviewed relevant officials both at
the mission in Haiti and also at USAID’s headquarters in Washington,
D.C., about sustainability and reviewed agency guidance, documents,
and legislation. We also reviewed prior GAO reports with sections on
sustainability challenges experienced by the U.S. government in other
countries.
We traveled to Haiti in April 2011 and August 2011 and met with U.S.
officials from USAID and State, as well as representatives of some of
USAID’s international and local implementing partners for humanitarian,
development, and reconstruction programs—including the Cooperative
Housing Foundation and the American Institutes for Research. We also
met with officials from the Interim Haiti Recovery Commission. We visited
sites damaged by the earthquake where USAID and State have ongoing
Page 33 GAO-12-68 Haiti Reconstruction
Appendix I: Scope and Methodology
or planned reconstruction efforts, such as the State University Hospital,
Haitian National Police Academy, and sites in Port-au-Prince where
rubble removal was ongoing. In addition, we visited sites in the Cap-
Haïtien development corridor that USAID has targeted for reconstruction
assistance. While there, we observed and discussed with USAID officials
the preliminary results of U.S.-funded development programs, including a
planned residential settlement site, a planned port, and various planned
agricultural and watershed management activities.
We conducted this performance audit from November 2010 to November
2011 in accordance with generally accepted government audit standards.
Those standards require that we plan and perform the audit to obtain
sufficient, appropriate evidence to provide a reasonable basis for our
findings and conclusions based on our audit objectives. We believe that
the evidence obtained provides a reasonable basis for our findings and
conclusions based on our work objectives.
Page 34 GAO-12-68 Haiti Reconstruction
Appendix II: Sector Fact Sheets
Appendix II: Sector Fact Sheets
Appendix II provides information on the funding, status of activities, select
challenges, and sustainability plans for the six sectors that include
infrastructure construction activities: energy, ports, shelter, health, food
security, and governance and rule of law.
Page 35 GAO-12-68 Haiti Reconstruction
Appendix II: Sector Fact Sheets
Energy Sector
HAITI
RECONSTRUCTION Building and Rehabilitating Electrical Transmission Lines,
Generation Facilities, and Other Infrastructure
Introduction Funding for Infrastructure
Prior to the January 2010 USAID allocated $98.3 million for infrastructure activities in the energy
earthquake, less than 30 percent of sector, including an estimated $85.3 million from fiscal year 2010
Haitians had access to electricity, Economic Support Fund (ESF) supplemental appropriations and $13.0
and many of those had access to million from other sources.
less than 10 hours per day. This
situation negatively affected Funding of Energy Activities, as of September 30, 2011
economic growth because a Dollars in millions
functioning energy sector and a
Allocated Obligateda Expended
dependable supply of electricity are
key to creating jobs and supporting FY10 ESF Supplemental $85.3 $28.6 $0.3
a healthy economy in Haiti. Other funding 13.0 0.2 0.2
The earthquake compounded the Total $98.3 $28.8 $0.5
lack of access to electricity by Source: GAO analysis of USAID data.
damaging substations, distribution Note: Other funding includes USAID regular fiscal year 2010 and 2011 funds. Allocations are as of
networks, and other components of September 14, 2011 (approval date of the Activity Approval Document for energy) except for the
design and supervision of the rehabilitation of 5 electrical substations in the Port-au-Prince area,
the sector. Currently, the country’s which is as of September 30, 2011.
electrical infrastructure cannot a
Obligated funds include both unexpended obligated balances and expenditures.
meet the needs of industries,
businesses, or residents. Status
Haiti’s post-earthquake Action Plan USAID plans to rehabilitate five electrical substations in the Port-au-
for National Recovery and Prince area, provide power generation for the North Industrial Park, and
Development of Haiti (Action Plan) construct other power generation, transmission, and distribution facilities
states that its priorities are to for residential customers. Most of these activities are still in the planning
restore damaged power facilities, phase.
repair the electricity transmission
and distribution network, and Status of USAID Energy Activities, as of September 30, 2010
expand access to electricity in
Dollars in millions
regions outside Port-au-Prince.
The U.S. government’s Post- Activity Allocationa Obligation Status
Earthquake USG Haiti Strategy Five electrical substations
Toward Renewal and Economic • Design and supervise $0.2 $0.2 • Award date:
Opportunity (Haiti Strategy) rehabilitation of 5 electrical November 8, 2010
includes a goal to improve and substations in the Port-au- • Contract end date:
Prince area November 9, 2012
modernize Haiti’s electrical sector
and bring affordable, reliable power • Rehabilitate 5 electrical 12.7 12.7 • Award date:
substations in Port-au-Prince July 28, 2011
to more households and area • Contract end date:
businesses. USAID plans to target
July 27, 2012
projects that will help make the
supply of electricity more efficient Power generation for the North
Industrial Park
and the power network more
• Architect and engineering 0.8 0.8 • Award date:
viable. services for short-term power April 7, 2011
generation
• Contract end date:
April 6, 2012
• Provide 10 megawatts of 19.8 15.0 • Award date:
power generation for the North September 15, 2011
Industrial Park’s start-up • Contract end date:
electrical needs September 14, 2012
Page 36 GAO-12-68 Haiti Reconstruction
Appendix II: Sector Fact Sheets
Activity Allocationa Obligation Status
Selected Challenges • Install electrical power 0 • Estimated award
—
• Haitian government capacity: distribution system to date: December
The electricity sector in Haiti, residential customers in the 2011
which is largely government north • Estimated end date:
owned, is characterized by January 2014
dramatic power shortages and • Provide an additional 15 to 30 — 0 • Estimated award
very low coverage of megawatts of power date:
generation for industrial, April 30, 2013
electricity—with only about commercial, and residential • Estimated end date:
12.5 percent of the population uses April 1, 2014
having legal regular access to
Feasibility study to assess the — 0 • Estimated award
electricity. According to State, ability to design and install date: To be
the government of Haiti’s public renewable energy power determined
electricity utility suffers from generation • Estimated end date:
inefficiencies, is poorly To be determined
maintained due to lack of Design and installation of energy — 0 • Estimated award
resources, and relies heavily solutions for South Industrial Park date:
on subsidies and donor To be determined
funding. • Estimated end date:
To be determined
• Completing energy activities Total $98.3 $28.8
as initially scheduled: USAID
awarded a contract to construct Source: GAO analysis of USAID data.
a power plant for the new North Note: Only energy infrastructure construction activities (including feasibility and design studies)
funded with USAID fiscal year 2010 supplemental funds and fiscal years 2010 and 2011 regular
Industrial Park on September funds are included in this table. Amounts may not add to total due to rounding. Allocations are as of
15, 2011, about 6 weeks later September 14, 2011 (approval date of the Activity Approval Document for energy) except for the
than planned; however, design and supervision of the rehabilitation of 5 electrical substations in the Port-au-Prince area,
which is as of September 30, 2011.
according to a USAID official a
For activities where an award has not been made, USAID planning documents include a
the delay will not affect the "procurement sensitive" cost estimate which is not shown but is included in the table total.
opening of the park, because
site work being completed by Sustainability Plans
others has already delayed the To enhance overall sustainability, USAID awarded a $10.9 million, 2-year
opening. contract in April 2011 to help the Haiti electrical utility manage electricity
USAID awarded a contract to loss reduction. USAID plans to award a 3-year management contract in
rehabilitate five electrical early 2012 to support the operation of the North Industrial Park and other
substations in July 2011. utility operations in northern Haiti.
However, the award was However, USAID planning documents state that the sustainability of the
protested and a “stop work” electrical system as a whole, and particularly after the loss reduction
order was issued. As of management contract ends, depends on, among other things, the
November 15, 2011, work had achievement of important legal and regulatory reforms to improve the
not started. commercial viability of the system and provide necessary resources for
proper operations and maintenance of the electrical infrastructure.
USAID has delayed its initial
USAID also acknowledged that the government of Haiti must take
award of a contract for the
necessary but politically challenging steps to do so.
expansion of the North
Industrial Park power
Damaged Transformer at an Electrical Power Plant in the Port-au-Prince Corridor
generation facility from
November 2011 until April
2013 to better determine the
demand for power at the
location and the most efficient
means to provide electricity
when it is needed.
Page 37 GAO-12-68 Haiti Reconstruction
Appendix II: Sector Fact Sheets
Ports Sector
HAITI
RECONSTRUCTION Designing and Building a New Port
Introduction Funding for Infrastructure
As an island nation with depleted USAID allocated $77.7 million in fiscal year 2010 ESF supplemental
natural resources, ports are crucial appropriations to infrastructure activities in the ports sector.
to Haiti’s economic viability and
growth. However, for many years Funding of Port Activities, as of September 30, 2011 (Dollars in millions)
prior to the January 2010
earthquake, Haiti’s major Allocated Obligateda Expended
international port in Port-au-Prince FY10 ESF Supplemental $77.7 $2.8 0
had deteriorated and lacked the Other 0 0 0
capability to meet the country’s Total $77.7 $2.8 0
cargo and shipping needs. The
earthquake caused significant Source: GAO analysis of USAID data.
damage to the Port-au-Prince port, Note: No other funding such as USAID fiscal year 2010 or 2011 regular funding is currently planned
for ports activities.
further reducing its capabilities. a
Obligated funds include both unexpended obligated balances and expenditures.
Haiti’s post-earthquake Action Plan
states that, as part of its overall Status
effort to deconcentrate economic
USAID is conducting a feasibility study and, depending on the results of
activities in Port-au-Prince, new
the study, plans to construct a new port in the Cap-Haïtien development
deep water ports, including a new
large-capacity port and harbor
corridor. In addition, USAID plans smaller port rehabilitation and
facility, need to be constructed in construction in other areas. During our review, we visited an existing port
Haiti’s northern region. The U.S. facility in Cap-Haïtien and a potential site in Fort-Liberte. The new port
government’s Haiti Strategy states would be less than 20 miles from the site of the North Industrial Park—a
that the United States is post-earthquake public-private project scheduled to begin operation in
considering investing in the design April 2012.
and development of a major port
on the northern coast. Status of USAID Port Activities, as of September 30, 2011
Dollars in millions
Activity Allocationa Obligation Status
New port in northern Haiti
• Feasibility study for the $2.5 $2.8 • Award date:
design of a new port September 22, 2011
• Contract end date:
May 31, 2012
• Construction of a new port — 0 • Estimated award date:
To be determined
• Estimated end date:
To be determined
Design and oversight of a new — 0 • Estimated award date:
port and the Cap-Haïtien port To be determined
• Estimated end date:
To be determined
Rehabilitation of the Cap- — 0 • Estimated award date:
Haïtien port To be determined
• Estimated end date:
To be determined
Contribution to port — 0 • Estimated award date:
construction in the Port-au- To be determined
Prince metropolitan area • Estimated end date:
To be determined
Page 38 GAO-12-68 Haiti Reconstruction
Appendix II: Sector Fact Sheets
Activity Allocationa Obligation Status
Selected Challenges Grant to Haiti (Council for the 0 • Estimated award date:
—
• Lack of staff with relevant Modernization of State-Owned To be determined
technical expertise: USAID’s Enterprises) for port • Estimated end date:
program in Haiti has not construction To be determined
previously involved port Total $77.7 $2.8
construction activities. With no Source: GAO analysis of USAID data.
staff who have port
Note: Only infrastructure port construction activities (including feasibility and design studies) funded
construction expertise or with USAID fiscal year 2010 supplemental funds are included in this table. Allocations are as of
experience, USAID will rely on August 1, 2011 (date of the draft Activity Approval Document for ports).
(1) a private firm to conduct a a
For activities where an award has not been made, USAID planning documents include a
feasibility study and make "procurement sensitive" cost estimate which is not shown but is included in the table total.
recommendations regarding,
among other things, port Sustainability Plans
design, economic feasibility,
According to USAID’s current plans, the new port is to be constructed by a
and financial viability; and (2) a
public-private partnership and operated by private firms when completed.
public private partnership to
These plans assume that the government of Haiti, particularly Haitian port
construct a new port.
officials, will efficiently collect import duties and that sufficient port revenues
• Potential funding shortfall: will be generated to fund recurring costs for port maintenance.
USAID’s current estimated cost
When completed, the economic viability of the port will depend on the
of constructing the northern
amount of income generated. According to USAID officials, the income is
port is $105 million: Since
projected to be derived from two broad sources, the growth in cargo
USAID has allocated only
generated by business activity related to the planned North Industrial Park
about $68 million, the
and the increased cargo diverted from other ports to the new port as the
remaining $37 million must be
result of it being a modern well managed port. In addition, they stated only
obtained from other sources.
one manufacturing firm is currently committed to operating in the North
According to USAID officials,
Industrial Park, however discussions are underway with other possible
the northern port feasibility
tenants. The economic viability of the port is one of the issues being
study includes an analysis of
addressed in the feasibility study.
financing options under a
public-private partnership to Wharf at an Existing Port in Cap-Haïtien
provide the additional required
funding.
• Delayed port feasibility
study: The northern port
feasibility study, originally
planned to be awarded in June
2011, was awarded in
September 2011. The study is
expected to take approximately
8 months to complete.
Page 39 GAO-12-68 Haiti Reconstruction
Appendix II: Sector Fact Sheets
Selected Challenges
• Land tenure: According to Shelter Sector
USAID, Haiti HAITIlacks a
comprehensive, functional
RECONSTRUCTION Developing and Building New Residential Settlements
system for recording land
ownership as well as an
effective national cadastre.
Prior to the earthquake,
Introduction Funding for Infrastructure
customary arrangements and
Prior to the January 2010 USAID allocated $55.1 million in fiscal year 2010 ESF supplemental
knowledge characterized land
earthquake, a majority of Port-au- appropriations and other funding for the development and construction of
tenure with only 40 percent of
Prince’s more than 2 million new residential settlements.
landowners possessing
inhabitants lived in crowded and
documentation such as a legal
poorly constructed housing, with Funding of Shelter Activities, as of September 30, 2011
title or transaction receipt.
inadequate basic infrastructure and
Furthermore, a large proportion Dollars in millions
unclear land tenure status.
of displaced persons were Allocated Obligateda Expended
Therenting
earthquakeproperty prior to the
destroyed FY10 ESF Supplemental $55.1 $9.6 $0.4
earthquake—with
approximately 115,000the plots of
homes and b
Other 1.6 0.6 0.6
land on
severely which they
damaged morelivedthanoften
informally
208,000, settledover
displacing and2 million Total $56.7 $10.1 $0.9
haphazardly
people. delineated—and
The International Source: GAO analysis of USAID data.
many will for
Organization have difficulty
Migration Note: Amounts may not add to total due to rounding.
a
provingthat,
estimated clear, legal
as of Julytenancy
2011, Obligated funds include both unexpended obligated balances and expenditures.
b
Other funding includes regular fiscal year appropriations.
overdue to document
590,000 discrepancies
Haitians displaced by
the or lack
earthquakeof documents.
continued to live at
sites for internally displaced
• Haitian government capacity:
Status
persons. USAID is planning to develop new residential settlements in the Port-au-
The government of Haiti’s
limited
Haiti’s legislative, Action
post-earthquake regulatory, Plan Prince and Cap-Haïtien development corridors that will provide
notesand institutional
that housing is thecapacitysectorto approximately 15,000 households with plots of land, permanent housing,
mostmanage
affected by
urban thedevelopment
earthquake. and access to essential services. USAID will manage construction of
severelyPlan
The Action constrains
proposes theto 4,000 houses. Nongovernmental organizations will manage construction
establishment
establish new, of a viable
permanent of 11,000 houses using a combination of USAID and other funding.
shelter
neighborhoods sector. According
on sites to
identified
USAID,
by the Haitianthe absence
government. of a single Status of USAID Shelter Activities, as of September 30, 2011
national
Displaced entity will
persons responsible
first move for Dollars in millions
into overseeing
provisional the shelter
shelters that will be
Activity Allocationa Obligation Status
provision
replaced with process
permanent is he most
housing,
Shelter demonstration project — $0 • Estimated award
important limitation.
sustainable Currently,
infrastructure, and date: December
near Port-au-Prince
basictheservices.
entities The
involved
Action in Plan 2011
Construction of 200 houses for
managing
also states different
that the aspects of
government internally displaced persons in the • Estimated end date:
shelter
intends include
to set up a the Ministries
security fund tof Croix-des-Bouquets municipality August 2012
Economy
support and Finance,
reconstruction Public
activities in Up to 8 new settlements in the 23.6 9.8 • Award date:
neighborhoods
Works, Planning,
and Interior
communities. and Cap-Haïtien development corridor June 17, 2011b
Socialthe
Similarly, Affairs,
U.S. as well as the
government’s Development of 5,000 plots for • Estimated end date:
HaitiCentral
Strategy Bank and themoving
prioritizes inter- 25,000-30,000 people and June 15, 2013
ministerial
displaced Committee
persons to for Land
provisional construction of 2,500 core
shelters,
Use. providing permanent houses by USAID in up to 5
municipalities
housing and services, and
strengthening institutional capacity Up to 12 new settlements in the 29.6 0.3 • Award date: May 26,
Port-au-Prince development 2010c
and access to financing.
corridor • Estimated end date:
Development of 10,000 plots for September 15, 2013
50,000-60,000 people and
construction of 1,500 core
houses by USAID in the Croix-
des-Bouquets and Cabaret
municipalities
Total $56.7 $10.1
Source: GAO analysis of USAID data.
Page 40 GAO-12-68 Haiti Reconstruction
Appendix II: Sector Fact Sheets
Note: Only shelter infrastructure construction activities (including design studies) funded with USAID
fiscal year 2010 supplemental funds and fiscal year 2010 regular funds are included in this table.
Amounts may not add to total due to rounding.
a
For activities where an award has not been made, USAID planning documents include a
“procurement sensitive” cost estimate which is not shown but is included in this table total.
b
Award date for engineering and design and environmental assessment, additional contracts will be
awarded for remaining site development.
c
Award date for engineering and design, additional contracts will be awarded for remaining site
development.
Sustainability Plans
According to USAID’s plans, site locations are being selected in areas
where residents have access to jobs and/or transportation. USAID is
planning to fund technical assistance programs to improve the capacity
of the national government to improve urban management, and will seek
possible solutions to policy challenges such as the absence of legislation
to guide housing, land-use, and urban planning; lack of an independent
regulatory body for the construction sector; and lack of institutional
capacity in urban planning. At the local level, USAID plans to provide
technical assistance to municipalities in areas such as land use planning,
building standards, and enforcement mechanisms; and to establish
community management committees to guide community development.
USAID recognizes that the sustainability of the new settlements depends
on the ability of Haitians to pay taxes and the ability of the Haitian
government to manage and maintain infrastructure and services over the
long term. This, in turn, depends on whether the Haitian economy can
provide adequate job opportunities and whether the Haitian government
can effectively govern.
Neighborhood in Port-au-Prince
Page 41 GAO-12-68 Haiti Reconstruction
Appendix II: Sector Fact Sheets
Health Sector
HAITI
RECONSTRUCTION Building and Rehabilitating Health Facilities
Introduction Funding for Infrastructure
Prior to the January 2010 USAID allocated $90.5 million for construction in the health sector, of
earthquake, a significant portion of which $50.5 million is allocated from the fiscal year 2010 ESF
the Haitian population had no supplemental appropriations. An additional $40.0 million in funding from
access to basic health services. other accounts is allocated for work on the HUEH and the National
Currently, only 12 of the 63 health Campus for Health Sciences.
networks created by the Haitian
government in the 1990s are Funding of Health Activities, as of September 30, 2011
operational.
(Dollars in millions)
The earthquake destroyed Allocated Obligateda Expended
infrastructure such as hospitals, FY10 ESF Supplemental $50.5 $0.4 0
clinics, medical schools, and b
Other 40.0 0 0
Ministry of Health buildings. For
example, the State University Total $90.5 $0.4 0
Hospital (HUEH) was damaged Source: GAO analysis of USAID data.
during the earthquake and services Note: Allocations are as of March 2011 (finalized Activity Approval Document for health) and July
such as surgery, and pre- and 2011 (USAID procurement plan); obligations and expenditures are as of July 2011 (the most recent
data provided by USAID).
post-operation work are still being a
performed in temporary buildings. Obligated funds include both unexpended obligated balances and expenditures.
b
The earthquake also destroyed 90 Other funding is from the fiscal year 2010 base Global Health and Child Survival—State
appropriation.
percent of the State Faculty of
Medicine.
Status
Haiti’s post-earthquake Action Plan
emphasizes rebuilding hospitals USAID is planning five construction activities in the health sector.
and training facilities in the Although these activities are still in the planning stages, USAID began
earthquake-affected regions and needs assessments of health facilities in the Port-au-Prince, Cap-Haϊtien,
construction of new hospitals in the and Saint-Marc corridors and an environmental assessment of the HUEH
department capitals. The U.S. campus. The HUEH reconstruction is a joint activity between the U.S.,
government’s Haiti Strategy French, and Haitian governments. The three governments signed a
includes a 5-year goal to rebuild memorandum of understanding in September 2010.
and reform management of public
health infrastructure, including Status of USAID Health Activities, as of September 30, 2011
earthquake-damaged structures (Dollars in millions)
and clinics, dispensaries, and
Activity Allocationa Obligation Status
hospitals in 9 to 12 health
networks. The Haiti Strategy also State University Hospital in
Port-au-Prince (HUEH)—
specifies that the State University U.S. portion
Hospital will be rebuilt and fully • Environmental $0.4 $0.4 • Environmental
operational in 5 years and have assessment of the assessment contract
rehabilitation and award date: July 12, 2011
clearly defined responsibility for
reconstruction of the • Environmental assessment
maintenance and operational hospital estimated end date:
costs. October 28, 2011
• Rehabilitation and — 0 • Construction estimated
reconstruction of HUEH award date: November/
facilities December 2011
• Construction estimated
end date: June 30, 2013
Page 42 GAO-12-68 Haiti Reconstruction
Appendix II: Sector Fact Sheets
Activity Allocationa Obligation Status
Selected Challenges
Health facilities in St. Michel — 0 • Estimated award date:
• Haitian government capacity: de L’Attalaye November 1, 2011
According to USAID officials, all Construction of a new • Estimated end date:
health planning needs to be community reference October 31, 2013
hospital and dispensary
done in coordination with the
Haitian Ministry of Health, Health facilities: Cap-Haϊtien — 0 • Estimated award date:
and Saint-Marc March 12, 2012
which was consumed for development corridors • Estimated end date:
significant parts of 2010 and Construction and expansion April 30, 2015
2011 by the cholera epidemic of dispensaries,
and uncertainty about the refurbishment and
upgrading of hospitals
presidential election. USAID
officials are working with the National Campus for Health — 0 • Estimated award date:
Sciences in Port-au-Prince April 1, 2012
Ministry of Health to identify
Reconstruction of State • Estimated end date:
and prioritize health facilities for Faculty of Medicine March 31, 2014
repair and construction. buildings destroyed in the
earthquake
• USAID Haiti mission’s lack of
Facilities for persons with — 0 • Estimated award date:
staff: USAID’s AAD indicates disabilities To be determined
that several months following Construction and equipment • Estimated end date:
the earthquake, the health of facilities for the disable May 30, 2014
office was extremely short Total $90.5 $0.4
staffed with only 11 of 21 Source: GAO analysis of USAID data.
positions filled. USAID officials Note: Only health infrastructure construction activities funded with USAID fiscal year 2010
also said that delays in staffing supplemental funds and fiscal year 2010 base Global Health and Child Survival—State
the Haiti mission, including the appropriations are included in this table. Allocations are as of March 2011 (finalized Activity Approval
Document for health) and July 2011 (USAID procurement plan); obligations and expenditures are as
Office of Infrastructure, Energy, of July 2011 (the most recent available from USAID).
and Engineering have been
a
challenging and have resulted For activities where an award has not been made, USAID planning documents include a
"procurement sensitive" cost estimate which is not shown but is included in the table total.
in staff responding to demands
outside of their usual areas of Sustainability Plans
responsibility.
USAID plans to make infrastructure investments only where there is a
business plan agreed to with the Haitian Ministry of Health in which the
USAID portion of operations and maintenance costs is reduced to zero at
the end of 3 to 5 years. USAID’s plans state that U.S. investments in
infrastructure will likely include some support for post-construction
operation and maintenance costs.
Earthquake-damaged Building at the HUEH
Page 43 GAO-12-68 Haiti Reconstruction
Appendix II: Sector Fact Sheets
Food Security Sector
HAITI
RECONSTRUCTION Building and Rehabilitating Irrigation Canals and Farm-to-
Market Roads
Introduction Funding for Infrastructure
Before the earthquake, Haiti USAID allocated $42.6 million for activities with a construction
already had one of the heaviest component in the food security sector.
burdens of hunger and malnutrition
in the Western Hemisphere: 40 Funding of Food Security Activities, as of September 30, 2011
percent of households were
Dollars in millions
undernourished (3.8 million people)
and 30 percent of children suffered Allocated Obligateda Expended
from chronic malnutrition, FY10 ESF Supplemental $42.6 $0.5 0
according to the U.S. government’s Other b
0 0 0
Haiti Strategy. To address this Total $42.6 $0.5 0
need, USAID had several food
security activities under way in Source: GAO analysis of USAID data.
Haiti. Note: Planned allocation, obligated, and expended amounts for infrastructure and construction
components only. Allocations are as of October 2011 data provided by USAID; obligations and
Agriculture generates nearly 25 expenditures are as of June 30, 2011 (the most recent provided by USAID).
a
percent of Haiti’s gross domestic Obligated funds include both unexpended balances and expenditures.
b
product, employs approximately 65 Other funding is regular fiscal year appropriations. USAID plans to provide $55.5 million during fiscal
years 2011 through 2014 for these food security activities; however, we did not include this amount
percent of the population, and because USAID did not provide the funding data by fiscal year.
serves as the primary source of
income in rural areas. However,
the earthquake exacerbated the Status
already significant challenges in
USAID plans two new activities with construction components. USAID
the agricultural sector by damaging
has additional activities with construction projects in the food and
distribution centers, food
economic security sectors that began implementation before the
processing facilities, warehouses,
earthquake. 1 However, one of these activities, the Watershed Initiative
irrigation canals, and the Ministry of
for Natural Environmental Resources (WINNER), received fiscal year
Agriculture’s Natural Resources
2010 supplemental funding.
and Rural Development
headquarters. Haiti’s post-
Status of USAID Food Security Activities, as of September 30, 2011
earthquake Action Plan includes
five agriculture-related programs, Dollars in millions
including building irrigation Activity Allocationa Obligation Status
networks and rural roads to open Watershed Initiative for Natural $13.7 $0.5 • Award date: June
up agricultural areas. Aligned with Environmental Resources 1, 2009b
the Haitian government’s priorities, (WINNER) • Contract end date:
the U.S. government’s Haiti Erosion prevention, irrigation May 31, 2014
Strategy includes a goal of restoration, and rebuilding and
agriculture sector growth in the repair of transportation
infrastructure.
U.S. development corridors
through improvements in (1) core Production Plus — 0 • Estimated award
Erosion prevention, irrigation date: March 31,
infrastructure and management, 2012
such as rebuilding canals; (2) on- construction and repair, and
farm-to-market road construction • Estimated end
farm productivity, such as use of and maintenance. date: March 31,
commercially produced seeds; and 2015
(3) post-harvest and market access
support, such as farm-to-market
roads.
1
These activities include projects such as rehabilitation of irrigation canals and
transportation infrastructure.
Page 44 GAO-12-68 Haiti Reconstruction
Appendix II: Sector Fact Sheets
Activity Allocationa Obligation Status
Selected Challenges 0 • Estimated award:
Rural Transportation —
• Land tenure: According to Infrastructure To be determined
USAID officials, many large • Estimated end
tracts of land are owned by date: To be
landlords who rent land tracts determined
to farmers. However, many Total $42.6 $0.5
landlords cannot produce proof Source: GAO analysis of USAID data.
of ownership. Uncertainty over Note: Only infrastructure and construction activities funded with USAID fiscal year 2010
land ownership may reduce supplemental funds appropriations are included in this table. USAID plans to provide $55.5 million
agriculture investment in Haiti during fiscal years 2011 through 2014 for these food security activities; however, we did not include
this amount because USAID did not provide the funding data by fiscal year. WINNER and Production
due to the risk of losing that Plus included technical assistance activities that are not included in this table. Allocations are as of
investment. Additionally, the October 2011 data provided by USAID; obligations and expenditures are as of June 30, 2011 (the
renting of land provides little most recent available from USAID). Funding amounts may not add to total due to rounding.
a
incentive for people to invest in For activities where an award has not been made, USAID planning documents include a
"procurement sensitive" cost estimate which is not shown but is included in the table total.
their farms. b
WINNER was awarded pre-earthquake, but received fiscal year 2010 supplemental funding;
• Haitian government capacity: amounts are being obligated incrementally.
According to USAID’s food
security AAD, the role and Sustainability Plans
mission of the Haitian Ministry USAID’s plans state that the U.S. government and other donors regularly
of Agriculture, Natural meet with the Haitian government and private sector to discuss progress
Resources, and Rural and reforms needed to accelerate agriculture investments in Haiti. In
Development has not been addition, the Haitian government has demonstrated commitment and
clearly defined, causing leadership in agriculture, food security, and economic security program
confusion over the ministry’s planning and coordination, according to USAID’s planning document.
policy goals. Critical policy
questions of whether the Soil Conservation Project in Bassin Zim (Central Plateau)
ministry should be focused on
strengthening food security,
increasing farm income,
building and maintaining
infrastructure, or focusing on
another priority have not been
answered.
• Local technical capacity:
Poor infrastructure, few
technically skilled companies
and people, lack of a
maintenance culture, and
health-related issues all pose
challenges to successful
reconstruction in Haiti,
according to USAID officials.
Page 45 GAO-12-68 Haiti Reconstruction
Appendix II: Sector Fact Sheets
Governance and Rule of Law Sector
HAITI
RECONSTRUCTION Building and Rehabilitating Correctional, Police, and
Counternarcotics Facilities
Introduction Funding for Infrastructure
Prior to the January 2010 State allocated $45.7 million in fiscal year 2010 INCLE supplemental
earthquake, much of Haiti’s justice funds for governance and rule of law construction activities.
infrastructure, including police
stations, police training facilities, Funding of Governance and Rule of Law Activities, as of September 30, 2011
and prisons, were in need of repair.
Many facilities were too small to Dollars in millions
meet the needs of Haitian law Allocated Obligateda Expended
enforcement and corrections FY10 INCLE Supplemental $45.7 $5.6 $1.7
systems. The earthquake caused Other 0.2 0.2 0
additional destruction and damage,
Total $45.9 $5.8 $1.7
increasing the need to rebuild
many facilities. Source: GAO analysis of State data.
Note: Other funding is prior fiscal year appropriations. Allocations, obligations and expenditures are
Haiti’s post-earthquake Action Plan as of September 2011.
states the need to rebuild a
Obligated funds include both unexpended obligated balances and expenditures.
correctional facilities, build and
expand police stations, and Status
complete construction of the State is planning several construction activities in the governance and
National Police Academy. The rule of law sector. Some activities are under way and others are still
Department of State (State) being planned.
received fiscal year 2010
supplemental funding in the Status of State’s Governance and Rule of Law Activities, as of
International Narcotics Control and September 30, 2011
Law Enforcement (INCLE) account
to meet these reconstruction needs Dollars in millions
in Haiti. In the U.S. government’s Activity Allocation Obligation Status
Haiti Strategy, State presents plans Correctional facilities $25.5
to use some INCLE funds for post- Construction advisors 0.3 0.3 Award date: Unknown
earthquake infrastructure Estimated end date:
rehabilitation and construction Rebuild of Carrefour Unknown
activities in the democracy and
men’s and Petionville 1.4 0.2 Award date: Unknown
women’s prisons Estimated end date:
governance sector, to be managed Unknown
by State’s Bureau of International Construct a new TBD 0 Estimated award date:
Narcotics and Law Enforcement women’s prison in Unknown
(State/INL). Ganthier Estimated end date:
Unknown
Repair the National 0.2 0.2 Award date: Unknown
Penitentiary Estimated end date:
Unknown
Expand inmate capacity TBD 0 Estimated award date:
Unknown
Estimated end date:
Unknown
Police facilities $8.7
Rehabilitate facilities at 5.0 5.0 Award date: Unknown
the Haitian National Estimated end date:
Police Academy Unknown
Rehabilitate and TBD 0 Estimate award date:
construct police stations Unknown
and barracks Estimated end date:
Unknown
Page 46 GAO-12-68 Haiti Reconstruction
Appendix II: Sector Fact Sheets
Activity Allocation Obligation Status
Selected Challenges Police station repair 0.2 0.2 Award date: Unknown
Lack of staff with relevant Estimated end date:
technical expertise: State/INL Unknown
has been involved in Counternarcotics facilities $11.7
counternarcotics programs in Renovate and construct 6.7 0 Estimated award date:
counternarcotics Unknown
Haiti for decades. However, outposts Estimated end date:
during that period, it has Unknown
focused on infrastructure Refurbish a maritime $5.0 $0 Estimated award date:
activities and has had no U.S. base Unknown
direct-hire engineers or other Estimated end date:
personnel with construction Unknown
expertise on its staff. Total $45.9 $5.8
State/INL’s programs have Source: GAO analysis of State data.
focused on institutional Note: State provided funding data; State did not provide estimated award dates, award dates,
capacity building, such as estimated end dates, and end dates. Only infrastructure construction activities funded with State/INL
fiscal year 2010 supplemental funds and prior year funds are included in this table. Amounts may not
training Haiti’s law enforcement add to total due to rounding. Allocations, obligations, and expenditures are as of September 2011.
and corrections personnel. For
its post-earthquake
infrastructure activities, Sustainability Plans
State/INL plans to hire (1)
In the January 2011 5-year Haiti Strategy, State includes plans to provide
private firms to develop
infrastructure plans, designs,
training programs, introduce needed procurement and maintenance
and estimates for costs, systems, and establish an independent Haitian Directorate of Prisons in
schedules, and scopes of work; an effort to achieve sustainability.
and (2) contractors to provide However, State acknowledges that investments in construction and
construction; and (3) personal rehabilitation of infrastructure will require some degree of U.S. commitment
services contractors to monitor to support operations and maintenance costs “in the out years.”
and oversee its activities.
Land tenure: For several State-Funded Rehabilitation of a Pavilion at the Haitian National Police Academy
years before the earthquake,
State/INL had attempted to
acquire clear land title from the
Haitian government for several
proposed sites for a new
women’s prison, according to
State officials. Despite ongoing
efforts, as of October 2011,
State/INL officials noted that
State still had not obtained land
title.
Initial scope of work may be
reduced: Estimated costs,
schedules, and scopes of work
for planned infrastructure
activities were developed in
2010 by State/INL and early
2011 by private firms
contracted by the agency.
Since then, estimated costs for
materials have risen and
estimated schedules have
been extended due to land Source: GAO (April 2011).
titling issues. As a result, it is
unclear whether State/INL will
construct all planned activities
as initially scheduled.
Page 47 GAO-12-68 Haiti Reconstruction
Appendix III: Comments from the U.S.
Appendix III: Comments from the U.S. Agency
for International Development
Agency for International Development
Page GAO-12-68 Haiti Reconstruction
Appendix III: Comments from the U.S. Agency
for International Development
Page GAO-12-68 Haiti Reconstruction
Appendix III: Comments from the U.S. Agency
for International Development
Page GAO-12-68 Haiti Reconstruction
Appendix III: Comments from the U.S. Agency
for International Development
Page GAO-12-68 Haiti Reconstruction
Appendix IV: GAO Contact and Staff
Appendix IV: GAO Contact and Staff
Acknowledgments
Acknowledgments
GAO Contact David Gootnick, (202) 512-3149 or gootnickd@gao.gov
Staff In addition to the contact named above, Leslie Holen (Assistant Director),
Michael Armes (Assistant Director), Sada Aksartova, Lynn Cothern,
Acknowledgments Rachel Girshick, Leslie Locke, and George Taylor made key contributions
to this report. Ashley Alley, Douglas Cole, Martin De Alteriis, Cheron
Green, Courtney Lafountain, Jeremy Sebest, and Jena Sinkfield provided
technical assistance.
(320823)
Page GAO-12-68 Haiti Reconstruction
GAO’s Mission The Government Accountability Office, the audit, evaluation, and
investigative arm of Congress, exists to support Congress in meeting its
constitutional responsibilities and to help improve the performance and
accountability of the federal government for the American people. GAO
examines the use of public funds; evaluates federal programs and
policies; and provides analyses, recommendations, and other assistance
to help Congress make informed oversight, policy, and funding decisions.
GAO’s commitment to good government is reflected in its core values of
accountability, integrity, and reliability.
Obtaining Copies of The fastest and easiest way to obtain copies of GAO documents at no
cost is through GAO’s website (www.gao.gov). Each weekday afternoon,
GAO Reports and GAO posts on its website newly released reports, testimony, and
Testimony correspondence. To have GAO e-mail you a list of newly posted products,
go to www.gao.gov and select “E-mail Updates.”
Order by Phone The price of each GAO publication reflects GAO’s actual cost of
production and distribution and depends on the number of pages in the
publication and whether the publication is printed in color or black and
white. Pricing and ordering information is posted on GAO’s website,
http://www.gao.gov/ordering.htm.
Place orders by calling (202) 512-6000, toll free (866) 801-7077, or
TDD (202) 512-2537.
Orders may be paid for using American Express, Discover Card,
MasterCard, Visa, check, or money order. Call for additional information.
Connect with GAO Connect with GAO on Facebook, Flickr, Twitter, and YouTube.
Subscribe to our RSS Feeds or E-mail Updates. Listen to our Podcasts.
Visit GAO on the web at www.gao.gov.
To Report Fraud, Contact:
Waste, and Abuse in Website: www.gao.gov/fraudnet/fraudnet.htm
E-mail: fraudnet@gao.gov
Federal Programs Automated answering system: (800) 424-5454 or (202) 512-7470
Congressional Ralph Dawn, Managing Director, dawnr@gao.gov, (202) 512-4400
U.S. Government Accountability Office, 441 G Street NW, Room 7125
Relations Washington, DC 20548
Public Affairs Chuck Young, Managing Director, youngc1@gao.gov, (202) 512-4800
U.S. Government Accountability Office, 441 G Street NW, Room 7149
Washington, DC 20548