(2024-01) Simplified Budget Execution and Achievements Report, FY 2023-2024 (DINEPA)
Summary — This report presents DINEPA's simplified budget execution for the 2023-2024 fiscal year, detailing disbursements and achievements in the drinking water and sanitation sectors. It highlights progress made despite a challenging sociopolitical context, emphasizing investments and encountered difficulties. The document covers the period from October 2023 to September 2024 and includes planning for the 2024-2025 fiscal year.
Key Findings
- The total budget for 2023-2024 was USD 69,172,113.40, with a net execution rate of 49.09% (USD 33,954,352.24) due to sociopolitical instability and delays.
- Drinking water projects accounted for 67.6% of expenditures, institutional strengthening for 30.1%, and sanitation/hygiene for 2.3%.
- Significant delays were observed in projects like HA-L 1103 P-au-P III and HTI-003B AECID due to insecurity and procurement issues, leading to project extensions.
- The EPARRDD project (IDA Grant E 170 HT) showed an over-disbursement of 16.5% for the 2023-2024 period, primarily through contracts with UNICEF and UNOPS.
- Future plans for 2024-2025 include continuing ongoing works, launching new rehabilitation/construction projects for SAEPs, solarizing water points, and establishing a water quality laboratory.
Full Description
This DINEPA report provides a simplified overview of budget execution and achievements for the 2023-2024 fiscal year, covering the period from October 2023 to September 2024. It details efforts to increase coverage of drinking water and sanitation services in Haiti, aligning with DINEPA's ten-year strategy and SDG 6. The total adopted budget amounts to USD 69,172,113.40, with a net execution rate of 49.09% of expenditures, totaling USD 33,954,352.24, primarily due to the precarious security environment and delays in activity execution.
Achievements are grouped into three main components: Drinking Water (67.6% of expenditures), Access to Sanitation and Hygiene (2.3%), and Institutional Strengthening (30.1%). The report highlights disbursements by funding partners (IDB, World Bank, AECID, UNICEF, CDC, etc.) and progress on the nine public sector projects, particularly in the Port-au-Prince Metropolitan Region and the Grand Nord. Despite challenges, infrastructure has been built or rehabilitated, awareness campaigns conducted, and institutional capacities strengthened. Planning for 2024-2025 aims to continue these efforts and improve service coverage.
Notes
Series: DINEPA sectoral budget-execution report (annual, WSS sector). PDF's own embedded metadata title confirms 'Rapport simplifié exécution budgétaire 2023-2024 et les réalisations'; cover page dated '1/1/2024' (report content covers FY2023-2024, Oct 2023-Sep 2024, per WB fiscal-year convention used throughout the PFR corpus). Covers disbursements by financing source (Trésor Public/domestic resources, HA-L1103 PAPIII, Programme de Réforme Secteur EPA HTI-003-B, HA-L1135 Grand Nord, IDA Grant E170 EPARRDD, REGLEAU/UNICEF/CDC) plus results-framework execution status and next-exercise budget outlook. Found via WP REST API (wp-json/wp/v2/media?parent=6489) attached to the article at dinepa.gouv.ht/rapport-simplifie-execution-budgetaire-2023-2024-et-les-realisations/; the article page itself only renders a 36-image page gallery on a static fetch (no visible download link), consistent with the recon note that this category is widget/JS-driven. Verified real PDF (36 pages, text-extractable via pdftotext, not a scan).