FY2024-2025 Annual Public Procurement Plan, FNE, revised
- The revised plan lists 21 contract lines, all financed from FNE own funds (FP), of which 17 are school construction or rehabilitation works.
- The largest line is 800,000,000.00 gourdes for four lycées in the Sud at 200,000,000.00 each.
- The Centre Culturel et Technologique (CCTN) in the Nippes is planned at 600,000,000.00 gourdes over 18 months.
- All works lines use national open tender (AOON) with CNMP a-priori control marked Yes.
- Launch dates run from May to August 2025 and signatures from June to September 2025.
The Fonds National de l'Éducation (FNE) filed this annual public procurement plan (PAPMP) for fiscal year 2024-2025, marked revised (Révisé), on the CNMP form. The table lists 21 lines, all financed from own funds (FP). Lines 01 to 04 cover a security services firm (code 2909, 8,000,000.00 gourdes, DEPS, May to June 2025, control No, 4 months), five all-terrain vehicles (code 4100, 50,000,000.00 gourdes, AORN, control Yes, 3 months), one level B7 armored all-terrain vehicle (code 4100, 24,500,000.00 gourdes, GRGR, control Yes) and a communication services firm (code 2909, 15,000,000.00 gourdes, GRGR, control Yes, 4 months). Lines 05 to 21 are works by national open tender (AOON) with CNMP control marked Yes, launched between May and August 2025 with signatures between July and September 2025. The largest are the construction of four lycées in the Sud (code 612, 800,000,000.00 gourdes, 13 months: Lycée Jean Hubert Feuille, Lycée François Dominique Toussaint, Lycée Torbeck and Lycée National de Chantal at 200,000,000.00 each), the Centre Culturel et Technologique (CCTN) in the Nippes (600,000,000.00 gourdes, 18 months), three national schools in the Sud (450,000,000.00 gourdes, 10 months: Port-à-Piment, Sainte Thérèse de Saint-Jean-du-Sud, Île-à-Vache at 150,000,000.00 each), three national schools in the Nord (450,000,000.00 gourdes, 10 months: Port Français, La Victoire, La Fossette), two lycées in the Sud-Est (400,000,000.00 gourdes: Gérald Michel Mathurin and Thiotte) and two lycées in the Artibonite (400,000,000.00 gourdes: Jacques Stephen Alexis and Dellande). Single-school constructions of 200,000,000.00 gourdes each cover Lycée Jean Louis Pierrot (Nord), Lycée Technique de Limbé (Nord, 18 months), Lycée de Jean Rabel (Nord-Ouest) and Lycée Georges et Antoine Izmery (Ouest); constructions of 150,000,000.00 gourdes cover École Nationale Sainte Suzanne (Nord-Est) and École Nationale Anacaona des Filles (Ouest).
Rehabilitation lines of 40,000,000.00 gourdes each, 6 months, cover Lycée National de l'Azile (Nippes), Lycée National d'Aquin and Lycée Technique Agricole de Cance (Sud, 80,000,000.00 together), Lycée Fabre Geffrard (Artibonite) and École Nationale République du Paraguay (Ouest), plus one lycée and two national schools in the Nord (Lycée Jean Baptiste Cinéas, École Nationale Fort Bourgeois, École Nationale Bande du Nord, 120,000,000.00 gourdes together). Execution periods for construction run 10 to 18 months.
How to cite
Fonds National de l'Éducation (FNE), FY2024-2025 Annual Public Procurement Plan, FNE, revised, https://cnmp.gouv.ht/
- Rights holder
- Fonds National de l'Éducation (FNE)