Objective

The Project Development Objective is to support the Recipient in improving disaster response capacity and enhancing the resiliency of critical transport infrastructure.

As published by World Bank Projects, in its original language.

Partner
World Bank Group, IDA
Sector
Transport
Stage
Closed since June 30, 2020
Approval
June 8, 2017
Closing
June 30, 2020
Instrument
IBRD/IDA financing, IDA
Effectiveness
November 6, 2017
Departments
Sud-Est, Sud, Ouest, Nord, Grande Anse, Centre, Artibonite, Nippes
Operation ID
P163199
Life cycle4 stages, 6 dates

Stage history

StageFrom
ApprovedJune 8, 2017
Under wayNovember 6, 2017
ClosingJune 30, 2020
ClosedJune 30, 2020

Dated events

EventDateSource
AppraisalApril 24, 2017World Bank Projects
NegotiationMay 1, 2017World Bank Projects
ApprovalJune 8, 2017World Bank Projects
EffectivenessNovember 6, 2017IDA Statement of Credits and Grants
Closing dateJune 30, 2020World Bank Projects
Completion report dueJanuary 29, 2021World Bank Projects

Financing

Table 1.Financing, US$ millions

FinancierAmountUS$ millionsRoleSource
IDA Grant from CRW20.0InstitutionWorld Bank Projects

Table 2.Related operations, US$ millions

OperationRelationPartnerStageCommitmentUS$ millions
Disaster Risk Management and ReconstructionParent operationWorld Bank GroupClosed71.8

Table 3.Position at the data date by source (stocks), US$ millions

This pageUS$ millionsSource
Commitment20.0World Bank Projects
DisbursedNot reported
UndisbursedNot reported
Total cost20.0World Bank Projects

World Bank amounts. Approved: Net commitment, the amount approved less cancellations, in US$ at the data date. Disbursed to date: The disbursements of the IDA statement and the Projects API to date, in US$. Undisbursed: The undisbursed balance the IDA statement publishes, in US$ at the data date. Amounts by source

Changes to the operation0 extensions
Original closing date
June 30, 2020
Closing date extensions
0
Restructurings
Not reported
Emergency component
Not reported

Records and documents

Locations8 departments, 9 places named, 9 places with coordinates
DepartmentsSud-Est, Sud, Ouest, Nord, Grande Anse, Centre, Artibonite, Nippes
Places named by the sourceCentre, Departement de Nippes, Departement de l'Artibonite, Grandans, Nord, Port-au-Prince, Riviere des Cotes de Fer, Sud, Sud-Est
Places with coordinates9
Results indicators24 indicators
IndicatorBaselineTargetLatest valueDate of latest value
A draft road map with a score card for a disaster risk management system is developedNoYesNoAugust 5, 2016
A first pilot detailed hydrological risk modelling is developed using the Digital Elevation ModelNoYesNoMarch 15, 2017
A national radio communication system has been initiated and at least four pilot departments have been connected to the national level0.004.004.00August 5, 2016
Actions are taken in a timely manner in response to feedback received during consultation sessions with beneficiaries/project affected people(Feedback, Responses and Action are monitored and reported)NoYesNoMay 21, 2017
Female Beneficiaries0.0030.000.00March 15, 2017
Number of CCPC Staff trained and level 2-certified (Office Management and Emergency Operation Center Management), disaggregated bysex0.003500.001400.00August 5, 2016
Number of beneficiaries from a training in disaster risk management, disaggregated by sex0.00400.00330.00August 5, 2016
Number of bridges and road sections damaged by hurricane Matthew that have been repaired or consolidatedwith satisfactory technical standards0.0015.000.00March 15, 2017
Number of bridges built or rehabilitated with satisfactory technical standards0.006.003.00August 5, 2016
Number of bridges damaged by hurricane Matthew that have been rebuiltwith satisfactory technical standards0.003.000.00March 15, 2017
Number of departments with investment plan to improve all weather rural accessibility based on the Rural Index Access methodology0.003.000.00August 5, 2016
Number of level 2-certified operational Municipal Civil Protection Committees (CCPCs)0.00140.00140.00August 5, 2016
Number of man/days of LIW generated by project activities0.00300000.000.00March 15, 2017
Number of ministry officials benefitting from a training program in risk management, disaggregated by sex0.0075.000.00August 5, 2016
Number of risk maps are produced, disseminated and available in an open-data online platform0.0035.000.00May 25, 2017
Number of spot interventions to protect the local access executed with satisfactory technical standards0.0020.0020.00August 5, 2016
Percentage of the national territory covered by a high resolution Digital Elevation Model and high resolution aero-photography0.00100.0090.00August 5, 2016
Pilot evacuation shelters have been rehabilitated or reconstructed with multi-hazard resilient measures0.0025.005.00March 15, 2017
Pilot evacuation shelters tool to evaluate and prioritize shelters needs is developed and used in the affected area by MatthewNoYesNoMarch 15, 2017
Roads rehabilitated, Non-rural0.00100.0072.00August 5, 2016
Line ministries developing an action plan for vulnerability reduction0.002.000.00August 5, 2016
Number of beneficiaries from an improved and resilient investments on the road network0.0070000.0060000.00August 5, 2016
Percentate of Female Beneficiaries from an improved and resilient investments on the primary and secondary road network0.0050.0050.00August 5, 2016
Share of population living in a municipality with a CCPC (Comite Communal de Protection Civile - Municipal Civil Protection Staff) of category 2 or higher45.0075.0045.00August 5, 2016
Identifiers1 identifier
SystemIdentifierSource
World Bank projectP163199Operation record

Partner documents

Sources

Data as of October 18, 2026
SourceRead on
IDA Statement of Credits and GrantsOctober 18, 2026
World Bank ProjectsOctober 18, 2026
World Bank documentsOctober 18, 2026
Cite this page

HaitiDocs. Disaster Risk Management and Reconstruction Additional Financing. Partner portfolio, data as of October 18, 2026. https://www.haitidocs.org/portfolio/projects/WB%3AP163199