HaitiDocs

Data / Partner portfolio / World Bank Group / IDA

Additional financing, strengthening agriculture public services II

Published title: Relaunching Agriculture: Strengthening Agriculture Public Services II Project - Additional financing

US$ millions unless stated. Haitian fiscal year, October to September. FY2026-27 began October 1, 2026.

Objective

The new proposed PDO is: to (a) reinforce the capacity of the Ministry of Agriculture, Natural Resources and Rural Development to provide or facilitate access to services in the agricultural sector; (b) increase market access to small producers and food security in Selected Areas; (c) improve livelihood in areas affected by Hurricane Matthew and (d) enable the Government to respond promptly and effectively to an eligible emergency.

As published by World Bank Projects, in its original language.

Partner
World Bank Group, IDA
Sector
Agriculture and food security
Stage
Closed since March 31, 2022
Approval
June 14, 2017
Closing
March 31, 2022
Instrument
IBRD/IDA financing, IDA
Borrower
Ministry of Economy and Finance
Implementing agency
Ministry of Agriculture, Natural Resources and Rural Development
Effectiveness
November 7, 2017
Departments
Sud, Grande Anse
Operation ID
P163081
Life cycle4 stages, 6 dates

Stage history

StageFrom
ApprovedJune 14, 2017
Under wayNovember 7, 2017
ClosingMarch 31, 2022
ClosedMarch 31, 2022

Dates

EventDateSource
AppraisalMay 8, 2017World Bank Projects
NegotiationMay 12, 2017World Bank Projects
ApprovalJune 14, 2017World Bank Projects
EffectivenessNovember 7, 2017IDA Statement of Credits and Grants
Planned closing dateMarch 31, 2022World Bank Projects
Completion report dueNovember 21, 2022World Bank Projects

Financing

Table 1.Financing, US$ millions

FinancierAmountUS$ millionsRoleSource
IDA Credit from CRW35.0InstitutionWorld Bank Projects

Table 2.Related operations, US$ millions

OperationRelationPartnerStageCommitmentUS$ millions
Relaunching agriculture, strengthening agriculture public services IIParent operationWorld Bank GroupClosed82.8

Table 3.Position at the data date by source (stocks), US$ millions

This pageUS$ millionsSource
Commitment35.0World Bank Projects
DisbursedNot reported
UndisbursedNot reported
Total cost35.0World Bank Projects

World Bank amounts. Approved: Net commitment, the amount approved less cancellations, in US$ at the data date. Disbursed to date: The disbursements of the IDA statement and the Projects API to date, in US$. Undisbursed: The undisbursed balance the IDA statement publishes, in US$ at the data date. Amounts by source

Changes to the operation2 extensions
Original closing date
December 31, 2019
Closing date extensions
2
  • Extended from December 31, 2019 to December 31, 2021 (document of June 30, 2019)
  • Extended from December 31, 2021 to March 31, 2022 (document of December 31, 2021)
Restructurings
Not reported
Emergency component
Not reported

Records and documents

Locations2 departments, 2 places named, 2 places with coordinates
DepartmentsSud, Grande Anse
Places named by the sourceGrandans, Sud
Places with coordinates2
Results indicators28 indicators
IndicatorBaselineTargetLatest valueDate of latest value
Agricultural Middle School is operational for at least 30 students.NoYesNoJanuary 13, 2017
Area provided with irrigation and drainage services (ha)0.003500.000.00January 13, 2017
Area provided with irrigation and drainage services - Improved (ha)0.000.000.00January 13, 2017
Area provided with irrigation and drainage services - New (ha)0.003500.000.00January 13, 2017
Hectares restored or converted to agroforestry productions by the project0.002500.000.00January 13, 2017
Increase in productivity of the voucher beneficiaries.0.0025.000.00January 13, 2017
Number of Departments where producers have access to market information by SMS, community radio and/or by publication at all DDA and BACs.0.004.000.00January 13, 2017
Number of accredited suppliers of inputs and services in the targeted areas.0.00200.000.00January 13, 2017
Number of agricultural producers registered in the MARDNR registry14000.00150000.0014000.00January 13, 2017
Number of cattle identified by the Project and included in the information system.0.00250000.000.00January 13, 2017
Number of client days of extension services provided to producers, members of producer organizations, different than SPS training.0.0021500.001200.00January 13, 2017
Number of client days of training linked to SPS provided to epidemiological volunteers and private veterinarians.0.006600.008986.00January 13, 2017
Number of didactical material elaborated and diffused in the Project zone, classified by themes.0.0020.000.00January 13, 2017
Number of producers adopting improved agriculture technologies promoted by the Project.0.0015000.000.00January 13, 2017
Number of producers adopting improved technologies promoted by the Project (disaggregated by gender).0.002400.000.00April 30, 2016
Number of samples analyzed for the detection of the presence of diseases.0.0096000.000.00January 13, 2017
Percentage of producer organizations having an operational investment at least 12 months after its completions.0.0075.000.00January 13, 2017
Percentage of sub-projects that are sensitive to a) gender; b) environment; or c) nutrition.0.0060.0083.00January 13, 2017
Satisfaction rate of participants of the farmer field schools.0.0075.000.00January 13, 2017
a) Central Building; b) Polyvalent centers; c) Quarantine stations; and d) Laboratories; are built / rehabilitated, equipped and operationala) 0 b) 0 c) 0 d) 0a) 1 b) 4 c) 5 d) 3a) 0 b) 0 c) 0 d) 0January 13, 2017
Direct project beneficiaries0.0060000.0019114.00January 13, 2017
Female beneficiaries0.0040.0035.00January 13, 2017
Increase in sales of the supported producer organizations (Aggregated million US$)0.0010.000.00January 13, 2017
Of which beneficiaries in the Southern region (Disaggregated by gender)11195.0050500.0011195.00January 13, 2017
Of which households affected by Hurricane Matthew that received support from the Crisis Response Window (Disaggregated by gender)7445.0041000.007445.00January 13, 2017
Performance of MARNDR in Sanitary and Phytosanitary (SPS) measures (Index Rating from gap analysis using methodology of World Organization for Animal Health30.0060.0030.00January 13, 2017
Time taken to disburse funds requested by the Government for an eligible emergency0.004.000.00January 13, 2017
Value of production generated by the farmer subsidy scheme (Aggregated million US$)0.0030.000.00January 13, 2017
Identifiers1 identifier
SystemIdentifierSource
World Bank projectP163081Operation record

Partner documents

Sources

Data as of October 18, 2026
SourceAccessed on
IDA Statement of Credits and GrantsOctober 18, 2026
World Bank ProjectsOctober 18, 2026
World Bank documentsOctober 18, 2026
Cite this page

HaitiDocs. Additional financing, strengthening agriculture public services II. Partner portfolio, data as of October 18, 2026. https://www.haitidocs.org/portfolio/projects/WB%3AP163081