Full Document Text
Extracted text from the original document for search indexing.
Document of
The World Bank
FOR OFFICIAL USE ONLY
Report No: ICR00005447
IMPLEMENTATION COMPLETION AND RESULTS REPORT
IDA-H9500 / TF-17021
ON A
GRANT
IN THE AMOUNT OF SDR 32.4 MILLION (US$50 MILLION EQUIVALENT)
AND US$8.0 MILLION
TO THE
Republic of Haiti
FOR THE
HT Center and Artibonite Regional Development Project
February 28, 2021
Transport Global Practice
Latin America And Caribbean Region
Public Disclosure Authorized
Public Disclosure Authorized
Public Disclosure Authorized
Public Disclosure Authorized
CURRENCY EQUIVALENTS
(Exchange Rate Effective {Feb 22, 2021})
Currency Unit = Haitian Gourdes (HTG)
HTG 72.83 = US$1
US$1,44 = SDR 1
FISCAL YEAR
October 1–September 30
Regional Vice President: Carlos Felipe Jaramillo
Country Director: Tahseen Sayed Khan
Regional Director: Franz R. Drees-Gross
Practice Manager: Nicolas Peltier-Thiberge
Task Team Leader(s):
Malaika Becoulet, Marc Marie Francois Navelet
Noualhier
ICR Main Contributor(s): Fabian Hinojosa Couleau, Jordy Hinaarii Timyan Chan
ABBREVIATIONS AND ACRONYMS
AfD French Development Agency (Agence Francaise de Développement)
CAL Center-Artibonite Loop
CASEC Administrative Council of Communal Sections (Conseil Administratif des Sections
Communales)
CBO community-based organization
CERC Contingent Emergency Response Component
CIAT Ministerial Committee for Territorial Development (Comité Interministeriel
d´Aménagement du Territoire)
CIF Climate Investment Fund
CTD Departmental Technical Council (Conseil Techniques Departemental)
EIRR Economic Internal Rate of Return
EU European Union
FER Road Maintenance Fund (Fond d´Entretien Routier)
FM financial management
FY fiscal year
GoH Government of Haiti
GDP gross domestic product
ICR Implementation Completion Report
IDB Inter-American Development Bank
IP Implementation Progress
IRI Intermediate Result Indicator
ISR Implementation Status Report
M&E Monitoring and Evaluation
MARNDR Ministry of Agriculture, Natural Resources and Rural Development (Ministère de
l´Agriculture, des Ressources Naturelles et du Développement Rural)
MDOD Delegated Project Management (Maîtrise d´Ouvrage Déléguée)
MEF Ministry of Finance and Economy (Ministère de l´Economie et des Finances)
MTPTC Ministry of Public Works, Transportation, and Communications (Ministère des Travaux
Publics, Transports et Communications)
MTR Mid-term Review
NPV Net Present Value
NR3 National Road 3
PAD Project Appraisal Document
PAP Project-Affected Person
PBCA Haiti Center and Artibonite Regional Development Project (Projet de la Boucle Centre
Artibonite)
PDO Project Development Objective
PIU Project Implementation Unit
PPCR Pilot Program for Climate Resilience
PSDH Strategic Plan for the Development of Haiti (Plan Stratégique pour le Développement
d´Haïti)
R18 Restructuring dated June 27, 2018
R20 Restructuring dated February 28, 2020
RAI Rural Access Index
RAP Resettlement Action Plan
RARP Rural Accessibility and Resilience Project
RED Model Roads Economic Decision Model
SMEs Small and Medium Enterprises
SPCR Strategic Program for Climate Resilience
STEP Systematic Tracking of Exchanges in Procurement
TF Trust Fund
UCE-MTPTC Central Implementation Unit of the Ministry of Public Works, Transportation, and
Communications (Unité Centrale d´Implémentation du Ministère des Travaux Publics,
Transports et Communications)
UTE-MEF Technical Implementation Unit of the Ministry of Economy and Finance (Unité Technique
d´Exécution du Ministère de l´Economie et des Finances)
TABLE OF CONTENTS
DATA SHEET .......................................................................................................................... 1
I. PROJECT CONTEXT AND DEVELOPMENT OBJECTIVES ....................................................... 6
A. CONTEXT AT APPRAISAL .........................................................................................................6
B. SIGNIFICANT CHANGES DURING IMPLEMENTATION (IF APPLICABLE) ..................................... 13
II. OUTCOME .................................................................................................................... 20
A. RELEVANCE OF PDOs ............................................................................................................ 20
B. ACHIEVEMENT OF PDOs (EFFICACY) ...................................................................................... 21
C. EFFICIENCY ........................................................................................................................... 27
D. JUSTIFICATION OF OVERALL OUTCOME RATING .................................................................... 30
E. OTHER OUTCOMES AND IMPACTS (IF ANY) ............................................................................ 30
III. KEY FACTORS THAT AFFECTED IMPLEMENTATION AND OUTCOME ................................ 33
A. KEY FACTORS DURING PREPARATION ................................................................................... 33
B. KEY FACTORS DURING IMPLEMENTATION ............................................................................. 34
IV. BANK PERFORMANCE, COMPLIANCE ISSUES, AND RISK TO DEVELOPMENT OUTCOME .. 37
A. QUALITY OF MONITORING AND EVALUATION (M&E) ............................................................ 37
B. ENVIRONMENTAL, SOCIAL, AND FIDUCIARY COMPLIANCE ..................................................... 39
C. BANK PERFORMANCE ........................................................................................................... 40
D. RISK TO DEVELOPMENT OUTCOME ....................................................................................... 42
V. LESSONS AND RECOMMENDATIONS ............................................................................. 43
ANNEX 1. RESULTS FRAMEWORK AND KEY OUTPUTS ........................................................... 46
ANNEX 2. BANK LENDING AND IMPLEMENTATION SUPPORT/SUPERVISION ......................... 54
ANNEX 3. PROJECT COST BY COMPONENT ........................................................................... 58
ANNEX 4. RATIONALE FOR THE SELECTION OF OUTCOME INDICATORS RETAINED TO ASSESS
PROJECT EFFICACY ............................................................................................................... 59
ANNEX 5. REVISIONS TO THE RESULTS FRAMEWORK ........................................................... 63
ANNEX 6. TRANSFER OF PROJECT ACTIVITIES TO THE RARP .................................................. 68
ANNEX 7. EFFICIENCY ANALYSIS ........................................................................................... 70
ANNEX 8. PROJECT OVERALL OUTCOME RATING ASSESSMENT BASED ON RESULTS EXPECTED BY
MID-2021 ............................................................................................................................ 76
ANNEX 9. BORROWER, CO-FINANCIER, AND OTHER PARTNER/STAKEHOLDER COMMENTS .. 80
The World Bank
HT Center and Artibonite Regional Development (P133352)
Page 1 of 83
DATA SHEET
BASIC INFORMATION
Product Information
Project ID Project Name
P133352 HT Center and Artibonite Regional Development
Country Financing Instrument
Haiti Investment Project Financing
Original EA Category Revised EA Category
Partial Assessment (B) Partial Assessment (B)
Organizations
Borrower Implementing Agency
Ministry of Economy and Finance
Unite Technique d'Execution (UTE), Unite Centale
d'Execution (UCE)
Project Development Objective (PDO)
Original PDO
The objectives of the Project are to: (a) support the development of the Centre Artibonite Loop region, primarily by
enhancing all-weather connectivity and logistics for producers, and the region’s resilience to climate change; and (b)
support the Recipient’s capacity to respond promptly and effectively to an Eligible Emergency, as needed.
The World Bank
HT Center and Artibonite Regional Development (P133352)
Page 2 of 83
FINANCING
Original Amount (US$) Revised Amount (US$) Actual Disbursed (US$)
World Bank Financing
IDA-H9500
50,000,000 26,752,330 16,186,274
TF-17021
8,000,000 8,000,000 6,351,914
Total 58,000,000 34,752,330 22,538,188
Non-World Bank Financing
0 0 0
Borrower/Recipient 0 0 0
Total 0 0 0
Total Project Cost 58,000,000 34,752,330 22,538,188
KEY DATES
Approval Effectiveness MTR Review Original Closing Actual Closing
19-May-2014 06-Oct-2014 21-Feb-2018 28-Feb-2020 31-Aug-2020
RESTRUCTURING AND/OR ADDITIONAL FINANCING
Date(s) Amount Disbursed (US$M) Key Revisions
27-Jun-2018 5.60 Change in Implementing Agency
Change in Results Framework
Change in Components and Cost
Reallocation between Disbursement Categories
Change in Disbursements Arrangements
Change in Institutional Arrangements
Change in Financial Management
Change in Procurement
25-Feb-2020 21.45 Change in Results Framework
Change in Components and Cost
Change in Loan Closing Date(s)
Cancellation of Financing
Reallocation between Disbursement Categories
Change in Implementation Schedule
The World Bank
HT Center and Artibonite Regional Development (P133352)
Page 3 of 83
KEY RATINGS
Outcome Bank Performance M&E Quality
Moderately Unsatisfactory Moderately Satisfactory Modest
RATINGS OF PROJECT PERFORMANCE IN ISRs
No. Date ISR Archived DO Rating IP Rating
Actual
Disbursements
(US$M)
01 11-Oct-2014 Satisfactory Satisfactory .50
02 12-May-2015 Satisfactory Moderately Satisfactory 1.50
03 24-Nov-2015 Satisfactory Moderately Satisfactory 3.10
04 31-May-2016 Satisfactory Moderately Satisfactory 3.10
05 03-Jan-2017 Moderately Satisfactory Moderately Satisfactory 4.10
06 30-Jun-2017 Moderately Satisfactory Moderately Unsatisfactory 5.10
07 02-Jan-2018 Moderately Satisfactory Moderately Unsatisfactory 5.60
08 01-Aug-2018 Moderately Satisfactory Moderately Unsatisfactory 7.60
09 10-Jan-2019 Moderately Satisfactory Moderately Satisfactory 19.11
10 05-Jul-2019 Moderately Satisfactory Moderately Satisfactory 19.11
11 14-Jan-2020 Moderately Satisfactory Moderately Satisfactory 21.45
12 31-Aug-2020 Moderately Satisfactory Moderately Satisfactory 21.75
SECTORS AND THEMES
Sectors
Major Sector/Sector (%)
Agriculture, Fishing and Forestry 9
Agricultural Extension, Research, and Other Support
Activities
9
The World Bank
HT Center and Artibonite Regional Development (P133352)
Page 4 of 83
Public Administration 18
Sub-National Government 7
Other Public Administration 11
Transportation 64
Rural and Inter-Urban Roads 64
Industry, Trade and Services 9
Agricultural markets, commercialization and agri-
business
9
Themes
Major Theme/ Theme (Level 2)/ Theme (Level 3) (%)
Private Sector Development 100
Jobs 100
Finance 3
Finance for Development 3
Housing Finance 3
Urban and Rural Development 82
Urban Development 11
Urban Infrastructure and Service Delivery 8
Urban Planning 3
Rural Development 71
Rural Markets 9
Rural Infrastructure and service delivery 62
Environment and Natural Resource Management 15
Climate change 15
Mitigation 15
The World Bank
HT Center and Artibonite Regional Development (P133352)
Page 5 of 83
ADM STAFF
Role At Approval At ICR
Regional Vice President: Hasan A. Tuluy Carlos Felipe Jaramillo
Country Director: Mary A. Barton-Dock Tahseen Sayed Khan
Director: Ede Jorge Ijjasz-Vasquez Franz R. Drees-Gross
Practice Manager: Aurelio Menendez Nicolas Peltier-Thiberge
Task Team Leader(s): Pierre Xavier Bonneau
Malaika Becoulet, Marc Marie
Francois Navelet Noualhier
ICR Contributing Author: Fabian Hinojosa Couleau
The World Bank
HT Center and Artibonite Regional Development (P133352)
Page 6 of 83
I. PROJECT CONTEXT AND DEVELOPMENT OBJECTIVES
A. CONTEXT AT APPRAISAL
Context
1. At the time of appraisal in 2014, Haiti was pursuing an economic rebalancing process across its national territory.
Public awareness that Haiti needed to rebalance development across its territory was already growing during the
early 2000s. During this period, the country had suffered considerable damage from heavy rains and hurricanes
(Jeanne in 2004; Fay, Gustav, Hanna, and Ike during the span of one month in 2008). Rebalancing gained momentum
as a solution to reduce the country’s vulnerability to natural disasters. In 2009, to ensure better governance of
territorial planning across Haiti, the Ministerial Committee for Territorial Development (Comité Interministeriel
d´Aménagement du Territoire, CIAT) was created. The importance of rebalancing was reinforced by the devastating
earthquake of January 2010. This caused considerable damage,
1
primarily in Port-au-Prince and the western part of
the country, where most of Haiti’s economic activity is concentrated. Key strategic frameworks were developed to
set territorial rebalancing and decentralization as national priorities going forward, including the 2010 Strategic Plan
for the Development of Haiti (Plan Stratégique pour le Développement d´Haïti, PSDH) and the Haiti Tomorrow report
published by the CIAT in 2010. From 2011 to 2013, Haiti’s gross domestic product (GDP) increased by a cumulative
annual growth rate of 4.2 percent. However, the country was still striving to achieve a spatial redistribution of growth
across its national territory, with high levels of unemployment and extreme poverty prevailing, especially in the
provinces.
2. The Haiti Center and Artibonite Regional Development Project (Projet de la Boucle Centre Artibonite, PBCA) was
born out of this rebalancing process and takes its roots in the “Haiti Tomorrow—The Center-Artibonite Loop:
Territorial Goals and Strategies for Reconstruction” report published by the CIAT in 2010. The document framed a
model for territorial planning and economic development across the country, by structuring a multisectoral
development vision for the Center-Artibonite Loop (CAL) region, centered on road connectivity as a means to
improve territorial and human development. Often considered as “Haiti’s breadbasket,” the CAL region spans a
territory of 4,632 square kilometers (km
2
) and has 1.2 million inhabitants. The region was identified as strategic by
the Government of Haiti (GoH), given its substantial contribution to agricultural output, a sector accounting for 25
percent of the country’s GDP and 50 percent of total employment in Haiti at appraisal.
2
The region also displayed
still untapped agricultural potential along with high poverty rates and strong vulnerability to natural hazards and
climate change. The loop itself (see Figure 1) is a 240-km-long road system connecting 10 urban centers, which are
nearly equidistant (on average 24 km away) from one another. While the strategy envisioned for the development
of the CAL was multisectoral,
3
its central element was the development of an organized urban network (the loop)
connecting the port cities of Saint-Marc, Gonaïves, and Cap-Haïtien to the north; Port-au-Prince to the south; and
1
The earthquake caused over 200,000 deaths and inflicted massive damages and losses estimated at US$7.9 billion (120 percent of
Haiti’s GDP).
2
Project Appraisal Document, PAD767, April 2014
3
It embedded actions in areas such as transport, agriculture, energy, water, health, or education.
The World Bank
HT Center and Artibonite Regional Development (P133352)
Page 7 of 83
the Dominican Republic in the east, with improved road connectivity from these external cities to the loop, between
urban centers on the loop, and to communities within the loop.
Figure 1. Center-Artibonite Loop
Source: CIAT (Comité Interministeriel d´Aménagement du Territoire), Haiti Tomorrow—The Center-Artibonite Loop (CAL): Territorial Goals and
Strategies for Reconstruction (Port-au-Prince: CIAT).
3. To help achieve this vision, the Project was designed to complement and build on structural investments in the
region, in coordination with donors and the GoH, such as the rehabilitation of National Road 3 (NR3) between Cap-
Haïtien and Port-au-Prince, the construction of the University Hospital of Mirebalais, and overall support to
agricultural production regionally. It focused on the improvement of interloop connections not already prioritized
by other funders, as well as secondary, tertiary, and rural road sections inside the loop.
4. The Project responded to major bottlenecks observed for the development of key regional sectors, including
agricultural development, business development, transport connectivity, and climate resilience. Limited access to
markets and services, weak public institutions, and extreme vulnerability to climate change and natural hazards
posed significant challenges to agricultural productivity, along with the depletion of natural resources and land
tenure insecurity. Lack of infrastructure was also a key impediment to building a conducive business environment in
The World Bank
HT Center and Artibonite Regional Development (P133352)
Page 8 of 83
the region and to developing value chains such as food exports. Transport connectivity had to be improved to
facilitate economic and agricultural trade dynamics, including (1) a functioning all-weather structural network of
primary and secondary roads to ensure access to internal and external markets; and (2) all-weather rural roads
linking production, processing sites, and local markets. A reliable road network would also lower transportation costs
and facilitate greater accessibility to social services for rural and peri-urban communities.
Figure 2. Breakdown of Planned CAL Road Investments, by Funder, in 2010
Source: CIAT (Comité Interministeriel d´Aménagement du Territoire), Haiti Tomorrow—The Center-Artibonite Loop (CAL): Territorial Goals
and Strategies for Reconstruction (Port-au-Prince: CIAT).
5. The Project was built based on the Bank’s long-standing support in the transport sector. The Bank had been
supporting Haiti’s countrywide transport sector since 2004, with a particular focus on critical spot interventions to
ensure all-weather connectivity, and on strengthening maintenance of the national road system to improve
resilience and protection of assets.
4
Furthermore, the Bank had supported the development of the GoH’s US$25.0
4
The following projects have participated in this effort: The Transport and Territorial Development Project (PTDT—P095523), the
The World Bank
HT Center and Artibonite Regional Development (P133352)
Page 9 of 83
million Strategic Program for Climate Resilience (SPCR), as part of the Climate Investment Fund’s (CIF’s) Pilot Program
for Climate Resilience (PPCR), in response to the increasing challenges posed by climate change to Haiti’s sustainable
development. In this context, the Project was allocated a grant of US$8 million (TF-17021) to cofinance the climate
proofing of CAL’s road infrastructure. The Project was aligned with recommendations of the 2009 World
Development Report,
5
which highlighted transport connectivity as a key component of regional integration and
development.
6. The Project was in line with higher-level objectives at appraisal. With a focus on helping end extreme poverty and
promoting shared prosperity, the Project fostered the economic inclusion of the CAL with the national economy via
the improved road network. It enabled new economic and labor opportunities while strengthening the resilience of
infrastructure and communities, as a direct application of the SPCR program. Moreover, the Project was fully
consistent with the World Bank Group’s Haiti Interim Strategy Note (Report No. 71885-HT) discussed by the World
Bank’s Executive Directors on September 27, 2012. The Strategy defined the program of the second tranche of the
US$500 million allocated to Haiti in response to the 2010 earthquake from the International Development
Association’s IDA16 Crisis Response Window.
7. Due to its multisectoral and regional approach, this ambitious project required close coordination between several
institutions for its implementation. The Project’s original institutional arrangements entrusted responsibility for its
implementation to the Ministry of Economy and Finance (Ministère de l´Economie et des Finances, MEF) through its
Technical Implementation Unit (Unité Technique d’exécution, UTE). However, as Project activities involved technical
expertise from various sectors, it was established that UTE-MEF would rely on the participation of the Ministry of
Public Works, Transportation, and Communications (Ministère des Travaux Publics, Transports et Communications,
MTPTC); the CIAT executive secretariat; and the Ministry of Agriculture, Natural Resources, and Rural Development
(Ministère de l’Agriculture, des Ressources Naturelles et du Développement Rural, MARNDR) for the implementation
of the components. This coordination would be formalized through a steering committee chaired by the CIAT
executive secretariat and bringing together representatives of the four designated institutions as well as local
stakeholders. An important caveat is that these institutional arrangements required active coordination among
implementing partners to achieve progress in executing the Project.
Emergency Bridge Reconstruction and Vulnerability Reduction Project (PROReV—P114292), the Disaster Risk Management &
Reconstruction Project (DRMRP—P126346), and the Infrastructure and Institutions Emergency Recovery Project (IIERP—P120895).
5
World Bank, World Development Report 2009: Reshaping Economic Geography (Washington, DC: World Bank, 2009),
https://openknowledge.worldbank.org/handle/10986/5991.
The World Bank
HT Center and Artibonite Regional Development (P133352)
Page 10 of 83
Theory of Change (Results Chain)
Figure 3. Reconstituted Theory of Change at Appraisal
Note: CBOs = community-based organizations; PDO = Project Development Objective.
Project Development Objectives (PDOs)
8. The development objectives of the Project as stated in the financing agreement and the Project Appraisal Document
(PAD) are to: (1) support the development of the Center Artibonite Loop Region, primarily by enhancing all-weather
connectivity and logistics for producers, and the region´s resilience to climate change; and (2) support the Recipient´s
capacity to respond promptly and effectively to an Eligible Emergency, as needed.
The World Bank
HT Center and Artibonite Regional Development (P133352)
Page 11 of 83
Key Expected Outcomes and Outcome Indicators
9. The key expected outcomes
6
and outcome indicators are listed in Table 1.
Table 1. Project Development Objectives (PDOs): Key Expected Outcomes and Outcome Indicators at Appraisal
No. Key Expected Outcome Outcome Indicator
1 Support the development of the
Center-Artibonite Loop Region by
enhancing all-weather connectivity
PDO indicator 1: Share of rural population with access to an all-weather road
(disaggregated by gender)
2 Support the development of the
Center-Artibonite Loop Region by
enhancing logistics for producers
PDO indicator 3: Increase in volume of transactions in improved markets
3 Support the development of the
Center-Artibonite Loop Region by
enhancing the region’s resilience to
climate change
PDO indicator 2: Share of roads classified as vulnerable to natural events and
climate change impacts
1–3 All of the above key expected
outcomes
PDO indicator 4: Direct Project beneficiaries (disaggregated by gender)
PDO indicator 5: Share of the population in the Project area satisfied with the
quality and impact of the infrastructure financed by the Project
Components
10. The Project design consists of five components,
7
outlined below from A to E, along with the various subcomponents
of each.
11. Component A: Enhancing logistics, transport connectivity, and climate resilience (original costs estimated at US$37
million). This component was comprised of four subcomponents:
12. Subcomponent A.1: Strengthening the regional connectivity, logistics, and the climate resilience of the road network
through the rehabilitation and/or construction of: (1) vulnerable road sections, bridges, river crossings, and critical
spots along three major connecting roads: (a) outbound to the capital/south (Saut-d’Eau–Titanyen); (b) outbound to
the north (Dessalines–Saint-Michel–Saint-Raphaël); (c) internal corridor west–east across the loop (Maissade–
Hinche); (2) critical sections of primary, secondary, and tertiary roads selected on the basis of the vulnerability
assessment to be carried out under Component C; (3) tertiary roads selected based on a participatory decision-
making mechanism; and (4) basic infrastructure along such roads.
6
The PAD does not specify key outcomes. Therefore the ones proposed in the table are based on the formulation of the PDO.
7
Actual component costs are shown in table 3.
The World Bank
HT Center and Artibonite Regional Development (P133352)
Page 12 of 83
13. Subcomponent A.2: Improving the rural road network and the climate resilience thereof through: (1) the
rehabilitation or upgrading of feeder roads and rural pathways selected based on a participatory decision-making
mechanism; and (2) the rehabilitation and construction of small logistical facilities.
14. Subcomponent A.3: Strengthening the road maintenance capacity and mechanisms through: (1) the preparation and
adoption of a regional road maintenance strategy and guidelines, as well as the provision of training to MTPTC; (2)
the rehabilitation of road maintenance centers in Hinche and Mirebalais; (3) the construction of a road maintenance
center in Saint-Michel; and (4) the development of new road maintenance microenterprises and community-based
organizations (CBOs) and enhancing the capacity of existing micro-enterprises and community-based organizations.
15. Subcomponent A.4: Developing technical guidelines and training programs for the incorporation of climate resilience
in the design of road infrastructure.
16. Component B: Improving infrastructure and management capacity of markets (original costs estimated at US$10
million). This component was comprised of two subcomponents:
17. Subcomponent B.1: The rehabilitation and/or construction of selected urban markets and the associated facilities,
and the improvement of their climate resilience and management capacity.
18. Subcomponent B.2: The rehabilitation and/or construction of rural markets and the associated facilities, selected
based on a participatory decision-making mechanism, and the improvement of their management capacity.
19. Component C: Supporting the development of regional knowledge, planning capacity, and local participation
(original costs estimated at US$6 million). This component was broken down into two subcomponents:
20. Subcomponent C.1: Supporting the development of regional knowledge, including climate resilience aspects
through: (1) the carrying out of a vulnerability assessment of the road network; (2) the preparation of studies, plans,
and guidelines; (3) the development of information systems; (4) the provision of technical assistance to strengthen
the capacity of the CIAT executive secretariat; and (5) the development of a dashboard tool capturing key
development indicators and investments at the regional level.
21. Subcomponent C.2: Supporting the development of regional planning capacity, including climate resilience
mainstreaming and local participation, through: (1) the preparation of a regional programmatic development
agenda; (2) supporting the implementation of the participatory decision-making mechanism at the local level to
identify local priorities and investments; and (3) enhancing the capacity of existing local Departmental Technical
Councils (Conseils Techniques Départementaux, CTDs), the technical services of selected municipalities, the
Administrative Council of Communal Sections (Conseil Administratif des Sections Communales, CASECs), and CBOs.
22. Component D: Contingent Emergency Response Component (original costs estimated at US$1 million). Provision
of support to respond to an Eligible Emergency, as needed.
The World Bank
HT Center and Artibonite Regional Development (P133352)
Page 13 of 83
23. Component E: Project implementation, monitoring and evaluation (M&E) (original costs estimated at US$ 4
million). Provision of support to MEF, CIAT executive secretariat, MTPTC, and MARNDR for Project management,
monitoring, and evaluation.
B. SIGNIFICANT CHANGES DURING IMPLEMENTATION (IF APPLICABLE)
24. The Project was restructured twice:
1. A restructuring dated June 27, 2018 (thereafter referred to as “R18”), resulting from the Mid-Term Review
(MTR); and
2. A restructuring dated February 28, 2020 (thereafter referred to as “R20”), whose primary objective was to
cancel part of the financing (SDR 17 million) to allow the transfer to the Rural Accessibility and Resilience
Project (RARP–P163490) of Project activities that would not be completed before the Project closing date
of August 31, 2020. Details on the transferred activities are in annex 6.
Revised PDOs and Outcome Targets
25. The PDOs were not revised, but the targets for outcome indicators 1 and 4 were revised (see paragraph 26).
Revised PDO Indicators
26. The key changes made to PDO indicators, the associated date of revision, and the reason for change are described
below:
8
a. PDO indicator 1, “Share of rural population with access to an all-weather road (disaggregated by
gender)”—the end target was reduced from 60 percent to 45 percent as a result of the R20 to reflect the
transfer of activities to the RARP.
b. PDO indicator 2, “Share of roads classified as vulnerable to natural events and climate change impacts”
was dropped in the R18. The data were captured by a revised intermediate results indicator, “Change in
share of roads classified as vulnerable to natural events and climate change impacts,” which was dropped in
the R20 due to the complexity of data collection compared to client capacity, the survey methodology, and
the scattered scope of the intervention areas as stated in the restructuring paper.
c. PDO indicator 3, “Increase in volume of transaction in improved markets”
9
(end target of 25 percent) was
dropped in the R18 to simplify the results framework. The associated outcome was captured under the
revised PDO indicator 4.
d. PDO indicator 4, “Direct Project beneficiaries (disaggregated by gender)” (end target of 190,000) was
revised in the R18 to “Number of people serviced by new or improved climate-resilient markets”
10
(end
target of 190,000) and in the R20 to “Number of producers and users serviced by an all-weather road
accessing urban and rural markets” (end target of 100,000). These changes aimed to (1) take into account
8
There was no change to the “Share of the population in the Project area satisfied with the quality and impact of the infrastructure
financed by the Project.”
9
Growth in volume of total transactions taking place in improved markets, based on surveys conducted by “operators” in the rural and
urban markets benefiting from Project investments.
10
That is, people living less than 60 minutes from these markets.
The World Bank
HT Center and Artibonite Regional Development (P133352)
Page 14 of 83
the transfer of the rehabilitation of urban and rural markets to the RARP, and (2) better capture the improved
logistics and access to rural and urban markets achieved under the Project.
Revised Components
27. The revised components are described below and summarized in Table 2.
Table 2. Revisions to the Scope of Project Components
Revised Component Revised Component in the R18 Revised Component in the R20
Revised Component A.
Enhancing logistics,
transport connectivity,
and climate resilience
The activities and the estimated costs
remained unchanged in the R18, but the
implementation strategy and responsibility for
the component was changed (see Section I. B.,
“Rationale for Changes and Their Implications
for the Theory of Change”).
In the R20, the scope of Component A was reduced
by US$15 million to transfer the funds to the Rural
Accessibility and Resilience Project (RARP) for
activities related to (1) the construction of four
bridges on road sections Hinche–Maissade and
Saint-Michel–Saint-Raphaël; (2) spot improvements
on road sections Titanyen–Saut-d’Eau, Saint-
Michel–Saint-Raphaël, Dessalines–Saint-Michel,
and Hinche–Thomassique and the construction of a
culvert on River Bretelle; (3) the spot improvement,
maintenance, and repair of 40 km of rural roads; (4)
the construction and rehabilitation of two road
maintenance centers (Hinche and Saint-Michel);
and (5) the training of 200 people within selected
communities on basic rural road maintenance.
Revised Component B.
Improving selected
markets and supporting
the development of
regional knowledge and
planning tools
In the R18, the original Components B and C
were merged into a new Component B to
foster implementation synergies. The new
Component B’s financing was reduced from a
total US$16 million to a total US$14.5 million.
The scope of the new Component B was
simplified to better align Project
implementation capacity with the number of
markets expected to be rehabilitated,
constructed, and/or improved, and the
number of urban plans expected to be
elaborated. The name and numbering of
components were revised to account for the
component merger. All the original activities
under the original Subcomponents B.1 and B.2
were integrated into the new Subcomponent
B.1, “Urban and rural markets and associated
facilities.” The new Subcomponent B.2,
“Improving regional knowledge and planning
tools,” consisted of all the activities under the
original Component C, plus the operating costs
In the R20, the scope of Component B was reduced
by US$9 million to transfer the funds to the RARP
for activities related to (1) the construction,
rehabilitation, and/or improvement of five markets;
(2) the development of a regional dashboard tool
capturing key development indicators and
investments at the regional level; (3) the
elaboration of climate-informed urban plans for
Saint-Michel and Saint-Raphaël; and (4) CIF
coordination.
The World Bank
HT Center and Artibonite Regional Development (P133352)
Page 15 of 83
of supporting the monitoring and evaluation of
the Pilot Program for Climate Resilience
activities funded by the Climate Investment
Fund, which was added to the financing
agreement.
Revised Component C.
Contingent Emergency
Response Component
(CERC)
No change. The CERC was not triggered during the Project. The
component was kept in the Project in the R20, but
its financing of US$1 million was cancelled and
transferred to the RARP.
Revised Component D.
Project Implementation,
Monitoring, and
Evaluation
The component was split into two
subcomponents in the R18, Subcomponents
D.1 “Support to UTE” (Technical
Implementation Unit of the Ministry of
Economy and Finance—UTE-MEF) and D.2
“Support to UCE” (Central Implementation
Unit of the Ministry of Public Works,
Transportation, and Communications—UCE-
MTPTC). As a result of the R18, US$1.5 million
was reallocated from Component B to
Component D to accommodate for the
increased costs ensuing from changes in
implementation arrangements, and the
financing gap arising from significant
depreciation of the special drawing right (SDR)
allocation.
In the R20, the financing of the component
allocation was reduced by US$1 million, which was
transferred to the RARP.
[... middle sections omitted for long document ...]
The World Bank
HT Center and Artibonite Regional Development (P133352)
Page 79 of 83
logistics improved by
the Project
(proxy indicator)
Report (ICR). It captures the contribution of
the Project to enhancing the logistics of
existing markets. For the purpose of the
computation, it was assumed that the
results of the survey carried out at Project
closing would apply to the mid-2021
scenario.
PDO 3
4
Share of roads classified
as vulnerable to natural
events and climate
change impacts
(proxy indicator)
0% 20% 16% 80% 20% 100% A similar indicator was defined at appraisal
(“share of roads classified as vulnerable to
natural events and climate change
impacts”). It was replaced by the present
indicator in the R18. However, the
indicator was dropped at the R20. The
indicator is reintroduced for the purpose of
the ICR. The methodology for the recording
of associated results is specified in annex 4.
5
Cumulated amount (in
US$ millions) in projects
elaborated using
analytical knowledge
and tools developed by
the proposed Project
(proxy indicator)
0 18 6.5 36.1% 6.5 36.1% This indicator was defined at appraisal as
an Intermediate Results Indicator and was
dropped in the R18. The indicator is
reintroduced as a proxy outcome indicator
for the purpose of the ICR.
All PDOs
6
Share of the population
in the Project area
satisfied with the
quality and impact of
the infrastructure
financed by the Project.
0% 75% 97.5% 130% 97.5% 130%
The World Bank
HT Center and Artibonite Regional Development (P133352)
Page 80 of 83
ANNEX 9. BORROWER, CO-FINANCIER, AND OTHER PARTNER/STAKEHOLDER COMMENTS
Comments of the UTE-MEF on the ICR
Arrangement institutionnel
L’arrangement institutionnel mis en place pour la mise en œuvre de l’opération partait du postulat
qu’un projet aussi transversal devait réunir un ensemble de partenaires qui n’ont pas l’habitude de
mettre en commun leurs moyens pour atteindre des résultats tangibles pour un territoire. Ainsi le
Projet allait bénéficier de la force de l’ensemble des partenaires tout en développant la culture de
travail interinstitutionnel tant nécessaire pour s’attaquer à des problèmes complexes faisant appel
des compétences multiples. D’où l’intérêt de faire appel à une entité du Ministère de l’Economie
et des Finances, l’UTE, pour jouer le rôle de coordinateur de l’ensemble des partenaires
techniques.
Malheureusement, la pratique a montré que l’arrangement institutionnel, malgré son intérêt sur le
papier, n’a jamais été totalement accepté par les partenaires. Le ST-CIAT a très mal vécu le fait
de ne pas avoir été l’agence d’exécution du Projet alors qu’il était à l’origine de la réflexion sur
l’aménagement de la Boucle Centre Artibonite. Par ailleurs, le fait que la plus grande partie des
fonds de l’opération a été consacrée au financement de travaux routiers a été perçu comme un
dévoiement du concept BCA.
Le Ministère de l’Agriculture et des Ressources Naturelles (MARNDR) est resté pratiquement en
dehors du Projet, une fois passée la phase de préparation.
De façon générale, les partenaires techniques du Projet n’ont jamais mobilisé leurs ressources de
façon optimale pour apporter l’appui nécessaire à l’UTE pour la mise en œuvre des activités. Les
différents partenaires ont mal vécu le fait de ne pas avoir la gestion directe du financement des
activités pour lesquelles ils devaient apporter un appui technique. Cette approche allait à l’encontre
de la tradition. Il n’est donc pas surprenant que les comportements aient pu radicalement évoluer
lorsqu’à la faveur des restructurations, chaque partenaire a obtenu la gestion des fonds de son
secteur.
Enfin, l’attelage entre des institutions n’ayant pas le même niveau de rigueur et des cultures
institutionnelles très éloignées les unes des autres a obéré les résultats du Projet.
Notation du projet :
L’UTE-MEF prend acte que le projet BCA est jugé modérément satisfaisant.
Le rapport de la Banque laisse penser que l’UTE serait la structure inefficace et inefficiente
responsable en grande partie des retards du Projet. L’UTE ne partage naturellement pas cet avis et
invite à tenir compte de tous les facteurs qui ont pu limiter les chances de réussite de l’opération
et de constater la part de responsabilité de chaque partenaire. Seul un tel exercice peut permettre
The World Bank
HT Center and Artibonite Regional Development (P133352)
Page 81 of 83
de tirer des leçons utiles pour l’avenir. La notation « modérément satisfaisante » est la résultante
d’un ensemble de facteurs comme la faible coopération entre les partenaires, l’inadaptation de
l’arrangement institutionnel à la réalité et aux capacités des acteurs, l’attelage entre des institutions
de capacités trop disparates etc.
En fin de compte, l’évolution des résultats du Projet conduit à conclure que, pour le moment, la
collaboration entre plusieurs entités est efficace si les aspects techniques et fiduciaires sont pris en
charge, pour chaque type d’intervention, par l’entité la plus expérimentée dans le secteur concerné.
Leçons apprises
1. L’investissement dans la connaissance des territoires, de leurs enjeux et des acteurs
permet de mieux engager les actions publiques pour le développement ;
2. A ce stade en Haïti, pour des projets multisectoriels, il est important de doter chaque
unité de gestion de ressources (humaines, administratives, financières) nécessaires lui
permettant d’exécuter les activités dont elle a la charge ;
3. Il est important de renforcer des liens sociaux entre le projet et les communautés afin
de capturer les initiatives communautaires à mettre en œuvre parallèlement aux
activités planifiées par le projet.
Unité Technique d’Exécution
du Ministère des Finances
The World Bank
HT Center and Artibonite Regional Development (P133352)
Page 82 of 83
Comments of the UCE-MTPTC on the ICR
The World Bank
HT Center and Artibonite Regional Development (P133352)
Page 83 of 83