Full Document Text
Extracted text from the original document for search indexing.
EVALUATION REPORT
FINAL PERFORMANCE EVALUATION OF
THE INTEGRATED FINANCIAL
MANAGEMENT SYSTEM (I FMS) ACTIVITY
Haiti Evaluation and Survey Services Project
MARCH 5, 2018
This publication was produced at the request of the United States Agency for International Development. It was prepared independently for
USAID by Social Impact. The authors’ views expressed in this publication do not necessarily reflect the views of the United States Agency for
International Development or the United States Government.
DIRECTION GENERALE DES IMPOTS CENTRAL NETWORK OPERATIONS CEN TER (NOC) (LEFT), MINISTERE DE L'INTERIEUR ET DES COLLECTIVITES TERRITORIALES
KENSKOFF NOC (TOP RIGHT), OFFICE DE MANAGEMENT ET DES RESSOURCES HUMAINES’S NOC (BOTTOM RIGHT). PHOTO CREDIT: WESLY JE AN.
ABSTRACT
The United States Agency for International Development (USAID)/Haiti Integrated Financial
Management System (IFMS) activity supported the Government of Haiti (GOH) in developing a system
for transparent management of public revenues and expenditures. This final performance evaluation
focused on Phase V of the activity, implemented by Chemonics International from September 2014 to
March 2018. To answer three evaluation questions (EQs) regarding activity effectiveness (EQ 1),
utilization (EQ 2), and sustainability (EQ 3), the evaluation team conducted a document review, 20 key
informant interviews, 8 group interviews, and site observations including 12 diagnostics. For EQ 1, the
evaluation concluded that infrastructure and systems implementation remain ongoing. Because the
infrastructure is incomplete, aspects of the systems are not being used by intended beneficiaries. The
activity conducted several trainings, but participants have not had opportunities to apply acquired skills.
Connectivity and electricity issues hindered IFMS, as did lack of buy-in from GOH leadership. For EQ 2,
GOH is using IFMS hardware and infrastructure, but not using some of the software applications.
Financial reporting within the GOH remains the same as before this phase, real-time data exchange is not
occurring, and gains to improve fiscal transparency were minimal. For EQ 3, the IFMS intranet and
Network Operating Center were the activity’s most sustainable aspects, whereas non-infrastructure
investments are currently less sustainable. More training and coaching on the new systems are required.
The activity did not have a sustainability plan or exit strategy in place at the time of the evaluation.
TABLE OF CONTENTS
ACKNOWLEDGEMENTS ............................................................................................................. I
ACRONYMS .................................................................................................................................... II
EXECUTIVE SUMMARY ............................................................................................................. I
1. INTRODUCTION ................................................................................................................. 1
2. EVALUATION METHODS AND LIMITATIONS ........................................................ 7
3. FINDINGS AND CONCLUSIONS ................................................................................. 11
4. RECOMMENDATIONS ................................................................................................... 34
ANNEXES
ANNEX A: EVALUATION STATEMENT OF WORK ......................................................... 37
ANNEX B: IFMS PHASE IMPLEMENTATION ..................................................................... 43
ANNEX C: EVALUATION DESIGN MATRIX ...................................................................... 44
ANNEX D: IFMS LOGIC FRAMEWORK ................................................................................ 46
ANNEX E: DATA COLLECTION PROTOCOLS ................................................................... 48
ANNEX E.1: SEMI-STRUCTURED INTERVIEW QUESTIONS ............................ 49
ANNEX E.2: SITE OBSERVATION/HARDWARE DIAGNOSTIC SHEET ......... 54
ANNEX E.3: SITE OBERSERVATION/SOFTWARE DIAGNOSTIC SHEE T ...... 62
ANNEX F: INDICATOR & OUTPUT-LEVEL ANALYSIS TABLE ................................... 70
ANNEX G: ANALYSIS OF PROVIDED EQUIPMENT ........................................................ 76
ANNEX H: TRAINING MATERIALS AND IFMS POLICY DOCUMENTS .................... 77
ANNEX I: FULL LISTING OF REFERENCES AND REPORTS UTILIZED .................... 78
ANNEX J: EVALUATION DISSEMINATION PLAN ........................................................... 81
TABLES
TABLE 1. REQUIREMENTS FOR THE NOC UPGRADE ........................................................... 13
TABLE 2. TRAININGS PROVIDED BY THE ACTIVITY ........................................................... 23
FIGURES
FIGURE 1. OVERVIEW OF THE IFMS ACTIVITY ....................................................................... 1
FIGURE 2. IFMS THEORY OF CHANGE REVISITED ................................................................. 3
FIGURE 3. IFMS ACTIVITY TASKS .............................................................................................. 4
FIGURE 4. EVALUATION PHASES ............................................................................................... 7
FIGURE 5. EVALUATION METHODS STATISTICS .................................................................... 8
FIGURE 6. DGI CENTRAL NOC ................................................................................................... 11
FIGURE 7. MICT KENSKOFF NOC .............................................................................................. 15
FIGURE 8. OMRH'S NOC ............................................................................................................... 16
FIGURE 9. EFFECTIVENESS CONCLUSION’S SUMMARY AND OVERVIEW ..................... 20
FIGURE 10. IMPACT CONCLUSION’S SUMMARY AND OVERVIEW .................................. 28
FIGURE 11: SUSTAINABILITY CONCLUSION’S SUMMARY AND OVERVIEW ................ 33
i | IFMS EVALUATION REPORT USAID.GOV
i | IFMS EVALUATION REPORT USAID.GOV
ACKNOWLEDGEMENTS
The evaluation team would like to thank the representatives from the Government of Haiti who made time
to engage with the team for this evaluation, particularly staff at the Ministère de l’Economie et des
Finances (MEF), Direction Générale des Impôts( DGI), Administration Générale des Douanes (AGD),
Treasury, Ministère de l'Intérieur et des Collectivités Territoriales (MICT), Office de Management et des
Ressources Humaines( OMRH), Unité de Lutte Contre la Corruption(ULCC), Cour Supérieure des
Comptes et du Contentieux Administratif ( CSCCA), Ministère des Travaux Publics, Transports et
Communications (MTPTC), and many others. The team thanks Chemonics for its support during the
Integrated Financial Management System (IFMS) evaluation. We also thank representatives from
Canadian International Development Agency, European Union, World Bank, and InterAmerican
Development Bank (IDB) for participating in interviews and sharing information, as well as the Softengi
representative who made time to meet with the team and share resources. The team must also thank the
United States Agency for International Development (USAID) D emocracy and Governance
representative for his assistance and guidance during the preparation and execution of the e valuation.
ACRONYMS
AGD
Administration Générale des Douanes
ATL Assistant Team Leader
ATS Automatic Transfer System
BG Back-up Generator
COP Chief of Party
CP Commercial Power
CDCS Country Development Cooperation Strategy
CSS Cascading Style Sheets
CSCCA Cour Supérieure des Comptes et du Contentieux Administratif
DGI
Direction Générale des Impôts
DSI Direction des Services Informatiques
EQ Evaluation Question
ESS Evaluation and Survey Services
GI Group Interview
GOH Government of Haiti
HR Human Resources
HTML Hypertext Markup Language
ICT Information and Communication Technologies
IDB InterAmerican Development Bank
IFMS Integrated Financial Management System
IP Implementing Partner
IT Information Technology
KII Key Informant Interview
MAN Metropolitan Area Network
MAN/WAN Metropolitan Area Network/Wide Area Network
MEF Ministère de l’Economie et des Finances
MENFP Ministère De L’Education Nationale Et De La Formation Professionnelle
MICT Ministère de l'Intérieur et des Collectivités Territoriales
MOU Memorandum of Understanding
MPCE Ministère de Planifications et Coopération Externe
MSPP Ministère de la Planification et de la Coopération Externe
MTPTC Ministère des Travaux Publics, Transports et Communications
NOC Network Operations Center
OAVCT Office d'Assurance Vehicules Contre Tiers
OMRH Office de Management et des Ressources Humaines
PFM Public Financial Management
SI Social Impact
SIGRH Système Interministériel de Gestion des Ressources Humaines
SOW Scope of Work
USAID.GOV IFMS EVALUATION REPORT | ii
iii | IFMS EVALUATION REPORT USAID.GOV
SYSDEP Système de Gestion des Dépenses
TL Team Leader
ULCC Unité de Lutte Contre la Corruption
UPS Uninterruptible Power Supply
USAID United States Agency for International Development
UXP Universal eXchange Platform
VESDA Very Early Smoke Detection Apparatus
EXECUTIVE SUMMARY
PROJECT BACKGROUND
The United States Agency for International Development (USAID)/Haiti Integrated Financial
Management System (IFMS) activity—valued at $10,455,379 and implemented by Chemonics
International from September 2014 to March 2018
1
—aimed to support the Government of Haiti ( GOH) in
the development of a full and complete financial management system that ensures transparent
management of public revenues, expenditures, and other resources throughout the executive branch at the
national, regional, and municipal levels.
2
Implemented in five phases, the activity supported the GOH in the restoration, operation, and expansion
of the IFMS network infrastructure and financial management systems to improve financial governance
and combat corruption. The IFMS activity Phase V
3
design highlights four major activity components
that, in concert, seek to reinforce and consolidate the GOH’s IFMS, permitting it to manage financial
governance, human resources (HR), as well as auditing, reporting, and financial transactions at the
national and municipal levels. The four components are (1) hardware, (2) software, (3) capacity building,
and (4) technical support. The four components were addressed through seven tasks. For more details on
the project background, see page 1.
EVALUATION PURPOSE AND EVALUATI ON QUESTIONS
This final performance evaluation assessed Phase V of the IFMS activity’s overall effectiveness. The
evaluation findings will inform possible future programming in public finance and economic governance
in Haiti and other fragile states, s erve as a strategic document for the development of USAID/Haiti’s
Country Development Cooperation Strategy (CDCS), and identify lessons learned and best practices to
inform future governance and information and communication technologies (ICT) programing. The
audience for this evaluation is USAID/Washington, USAID/Haiti, Chemonics International, and key
GOH institutions. See Annex A for the Evaluation Scope of Work (SOW) and Annex C for the
Evaluation Design Matrix.
EVALUATION QUESTIONS
This evaluation sought to answer the following overarching evaluation questions (EQs) as determined by
USAID/Haiti. See the accompanying sub-questions on page 5.
1. To what extent was the program effectively implemented?
2. To what extent is the GOH generally, and the Ministère de l’Economie et des Finances (MEF)
specifically, at both the national and municipal levels, using the IFMS?
3. How sustainable is the IFMS?
1
The original activity was set to end in September 2017, but the activity received a six-month extension.
2
SOW Final Performance Evaluation of Integrated Financial Management System (IFMS). USAID, 2017.
3
The IFMS activity is now in its fifth phase. Phases I and II were completed by 2006, and Phases III and IV ran from 2007 until
implementation was interrupted by the 2010 earthquake.
i | IFMS EVALUATION REPORT USAID.GOV
EVALUATION DESIGN, METHODS, AND LIMITATIONS
This evaluation employed a mixed- methods evaluation design that included a combination of qualitative
data collection methods to answer the key questions listed above. Between October 25 and November 21,
2017, a four-member team collected data throughout Port -au-Prince, Haiti, with many stakeholders from
USAID and Chemonics International and representatives from across the GOH .
The evaluation team conducted a document review, 20 key informant interviews (KIIs), 8 group
interviews (GIs), and structured site observations that included 12 diagnostics for the hardware and
software components of the IFMS activity.
4
Altogether, the team collected data with over 57 individuals (48
males and 9 females) during the KIIs, GIs, and Diagnostics. See Annex G for the data collection protocols.
LIMITATIONS AND MITIGATIONS STRATEGIES
The evaluation team faced certain challenges and limitations in conducting this evaluation. Due to the
evaluation’s primarily qualitative design, respondent biases such as recall, and selection bias may have
occurred. Given the level of formality required to schedule meetings with GOH representatives and the
lack of availability of GOH ministry leadership and non-information technology ( IT) staff, the team was
unable to meet with MEF leadership (with the exception of leadership from the IT department) and with
Office d’Assurance Vehicules Contre Tiers (OAVCT) representatives. Moreover, a comprehensive list of
project stakeholders and contacts was not available until the second week in country, which made the
fieldwork preparation challenging, especially as related to defining the sample. Finally, the evaluation
team experienced two changes before and during fieldwork. The team made every effort to mitigate the
above limitations by triangulating different methods and believes that the robustness of the evaluation’s
mixed-methods design has resulted in evidence-based findings, conclusions, and recommendations. For
more detail on limitations and mitigation strategies, see page 10.
FINDINGS AND CONCLUS IONS
EVALUATION QUESTION 1: TO WHAT E XTENT WAS THE PROGRAM EFFECTIVELY IMPLEM ENTED?
1. IFMS initiated activities under all seven tasks, and IFMS infrastructure and systems implementation
remains ongoing. Substantial procurement and ICT investments have occurred that have updated,
upgraded, and expanded the IFMS infrastructure. Diagnostics tools used during the team’s four site
visits to the Network Operations Center (NOC) at MEF confirmed that Chemonics performed several
improvements to the NOC infrastructure as requested by USAID in the project solicitation. Data
shows that 254 pieces of equipment were replaced across existing NOCs; Chemonics procured and
delivered 35 pieces of equipment to support the CIVITAX activities within several municipalities and
under Ministère de l'Intérieur et des Collectivités Territoriales
(MICT) oversight; and invested in
generators, power inverters, batteries for the inverters, and almost all systems provided were coupled
with an uninterruptible power supply (UPS).
However, some of the infrastructure work that has been completed has bugs or show signs of poor
maintenance (e.g. hardware not properly configured, dust accumulation in the equipment, broken air
4
The evaluation team conducted limited software diagnostics because most of the procured software, including SIGRH, UXP,
and Business Intelligence, were only recently procured and introduced by the activity or are still in a test and installation phase.
USAID.GOV IFMS EVALUATION REPORT | ii
conditioning, inadequate cabling, etc.). Because the infrastructure is incomplete, major aspects of the
systems are not being used by intended beneficiaries.
2. IFMS provided a significant amount of trainings on all the systems developed or delivered and
developed policy and procedural documents on managing aspects of IFMS. However, the effectivenes
of these trainings is greatly reduced, as the ongoing installation of associated infrastructure and software
has not allowed GOH employees to apply skills learned. This conclusion is discussed under EQ 2.
3. IFMS helped GOH address connectivity and electricity issues in many instances, yet these issues
remain a major problem for the activity because systems such as the Universal eXchange Platform
(UXP) require dedicated internet connections for which GOH agencies often do not have budgets.
Moreover, electricity remains unstable throughout the country, and many GOH agencies do not have
stable generators or alternative power sources.
5
The support material provided by IFMS has not yet
reached all the GOH agencies.
4. IFMS focused significant attention on working with GOH IT staff because these individuals will be
the system’s caretakers. At the same time, IFMS did not successfully build buy-in from across the
highest levels of GOH leadership. For example, a trip to Estonia to build support and buy-in for the
UXP only included IT staff and not GOH leadership . This was a missed opportunity to standardize
understanding of IFMS among GOH leadership, and identify champions to own and push forward the
IFMS activity’s objectives. Chemonics also experienced communication and planning issues with
GOH counterparts. GOH stakeholders and observers from the donor community suggested that the
level of coordination and communication from Chemonics and USAID leadership was limited and
thus insufficient to obtain buy-in from the relevant stakeholders. However, it should be noted that the
activity was conducted in a very challenging context as Haiti went through a few transitions
throughout implementation, from electoral transitions to political instability, and turnover of activity
stakeholders both from Chemonics and GOH.
EVALUATION QUESTION 2: TO WHAT EXTENT IS THE GOH USING THE IFMS?
1. The hardware and infrastructure elements of the project are the most successful aspects of the IFMS
activity, but they also are still being completed. The activity struggled to implement the software and
capacity building components. Many systems are still being rolled out and are not yet functional, and
thus are not currently being used.
2. GOH agencies are currently using the Metropolitan Area Network/Wide Area Network
(MAN/WAN), NOC, and other ICT equipment, such as computers, that were purchased. However,
GOH is currently not using other systems or applications either because they are recent installations
(e.g. Système Interministériel de Gestion des Ressources Humaines (SIGRH) – no interviewees
reported using this software), are still being configured and are thus unavailable (e.g. VXRail and the
Backup), or have yet to be purcahsed (e.g. Audit software). For some of these applications , their
5
According to interviews with OMRH representatives, their office does not have a backup generator to power its system in case
of a commercial power outage.
iii | IFMS EVALUATION REPORT USAID.GOV
relevance to GOH remains uncertain due to other donors’ upcoming Public Financial Management
(PFM) efforts.
3. The improved capabilities of MAN/WAN have supported continued functionality between GOH
agencies and MEF. However MAN/WAN still faces challenges that inhibit its performance across
many of the 61 sites. The network is working, but slowdowns are occurring that are affecting the use
of software applications such as Système de Gestion des Dépenses (SYSDEP). Network serv ice
failures are quite common, and loss of service can last a long time, sometimes forcing employees to
move sites to work. Lastly, UXP is not functional, so real -time financial data exchange on
expenditures and revenue has not yet emerged outside of agencies that use the SYS application.
4. Financial reporting within the GOH remained the same as it was before this phase of IFMS. Although
some GOH entities are still using the SYS software suite, no new data is being shared in real-time as
the UXP is not yet in use for data exchange, and no data sources have been dedicated for the Business
Intelligence software, rolled out in August 2017. Audit performance remained unchanged, as software
had yet to be purchased at the time of the evaluation.
5. Although the activity established policies and procedures for the management of the MEF NOC and
network monitoring (as noted in EQ 1), the team did not find any concrete evidence of buy-in and
engagement across GOH agencies regard ing managing the IFMS-developed systems, policies , and
procedures. This was due, in part, to limited IT leadership at the MEF in the early stages of this phase
of the IFMS activity. Another possible factor was the mixed understanding of the IFMS activity and
its intended results among senior level, non -IT GOH stakeholders who were not targeted or included
in some of the capacity building efforts.
6. Chemonics conducted a few efforts to promote transparency, but the full potential of these efforts is
currently limited. Chemonics conducted an audit assessment and decided on an audit software, but the
software has yet to be purchased and rolled out. The installed UXP, if functional, could help improve
transparency by allowing the exchange of financial data among government agencies in real time.
However, the platform is not functional and much remains to be done to make it functional across
government agencies. Outside of these efforts, there was little evidence that Chemonics did much to
promote IFMS among non-IT staff.
7. The Direction Générale des Impôts( DGI) was the happiest and most satisfied IFMS beneficiary. DGI
central office was happy to share their success with the team, and several DGI offices visited clearly
associated their increased revenues with the equipment received. However, many other GOH partners
seemed unhappy with the project management and implementation approach. There is also a
fundamental difference in stakeholders’ understanding of their own needs and what the activity
promised or delivered. Some agencies expressed needs that were not, in their opinion, considered in
activity implementation. Others critiqued the quality of the collaboration and inputs they received
from IFMS.
EVALUATION QUESTION 3: HOW SUSTAINABLE IS THE IFMS?
1. The IFMS MAN/WAN and NOC upgrades are the most sustainable aspects of the activity. GOH is
currently using them to support financial transactions and offer a certain level of corruption
USAID.GOV IFMS EVALUATION REPORT | iv
deterrence because of these systems’ ability to document transaction data that is captured and housed
on the MEF servers. They are critical to GOH economic governance and financial management
oversight, and the World Bank plans on using these aspects of the IFMS activity as the foundation of
its Integrated Financial Management Information Systems (IFMIS) project.
2. Outside of the infrastructure investments, other elements of IFMS are less sustainable. UXP and
software such as Business Intelligence, SIGRH , and Audit are in a fragile introductory stage; their
integration into and utility for the relevant GOH institutions remain unproven. Moreover, more
training and coaching are required to build staff confidence and work out any issues with these new
systems.
3. Chemonics and USAID have yet to initiate exit and post -IFMS transition planning with the GOH.
Additionally, the future and continuity of IFMS investments currently rely heavily on continued
donor community funding and support , rather than a GOH-led budget .
RECOMMENDATIONS
1. USAID should ensure that its activities are more integrated with and have stronger buy-in from
the GOH. This could be achieved through the creation of a GOH-wide IFMS governance structure
with representation from across all participating GOH entities, including signed Memorandum of
Understanding (MOUs) and pledged cash or in-kind contributions for participation from each entity.
2. Local partners need early involvement in the needs identification and funded activity design.
The evaluation showed that there were disconnects between Chemonics and some GOH entities over
the technical decisions made, such as which applications to purchase. This stemmed from the fact that
those agencies felt they had no input into the decisions made. As such, future activities should
actively seek to increase the involvement and contribution of participating GOH entities —including
technical, political, and IT representatives—early in the activity conception phase to promote
acceptance of and support for the activity.
3. Future Fiscal Governance and Transparency activities should include non-IT staff and be
conditioned on specific performance goals . Learning from the challenges raised by positioning
IFMS as an IT project, future activity designs should target both IT and non-IT staff in efforts to
promote fiscal governance and transparency. Incorporating realistic targets and benchmarks for
improved fiscal governance and transparency in activity monitoring, evaluation, and learning plans
can also help in this regard.
4. Given that some, but not all aspects of IFMS are sustainable, USAID should collaborate with
other donors in the public financial reform sector for the remainder of activity implementation
to strengthen IFMS activity gains. The evaluation showed that other donor-funded PFM projects
are ongoing or in the planning stages and are looking to leverage IFMS gains. To avoid duplication
and irrelevance, USAID should collaborate with the World Bank and other donors and pool efforts
around consolidating and improving Haiti’s IFMS system. Recommended next steps are: (1) complete
and strengthen Task 1 (IFMS technological infrastructure update, upgrade, and extension), and (2)
establish a strong knowledge base among GOH staff to support the delivered systems. The latter
v | IFMS EVALUATION REPORT USAID.GOV
should include reviewing the skills and capabilities needed to support the NOC and the MAN/WAN,
align training with existing and installed systems, and provide training and mentoring until a
reasonable standard of integration, use, and functionality are achieved.
5. USAID should develop and implement an exit strategy in collaboration with GOH and other
partners, well before the end of the project. The evaluation showed the extent of the work done by
Chemonics over the last three years in upgrading sites, repairing the NOC and establishing systems
(SIGRH, Business Intelligence, etc.) to support proper GOH fiscal governance activities. The
evaluation also showed the limited involvement of the GOH overall, and the lack of ownership
exerted towards these systems. As the activity nears its end, USAID should collaborate more closely
with GOH to ensure the ownership of the activity’s results, the assets procured, and the systems
installed to ensure the survival of the systems implemented.
USAID.GOV IFMS EVALUATION REPORT | vi
1 | IFMS EVALUATION REPORT USAID.GOV
1. INTRODUCTION
PROJECT BACKGROUND
In November 2004, the United States Agency for International
Development (USAID) signed an innovative agreement with the
Government of Haiti (GOH) to support p ublic finance reform and
develop an Integrated F inancial Management S ystem (IFMS)
with the Ministère de l’Economie et des Finances (MEF) at its
core. USAID developed the IFMS activity to address a need for
increased efficiency and transparency in GOH operations. There
were many databases in use across the GOH, which limited its
capacity to use information on public financial management
(PFM) in a timely manner.
6
Among this agreement’s stated goals
were to develop the MEF’s ability to exercise control over its
financial transfers to line ministries and other government
agencies and municipalities, prevent corruption , and ensure
transparency.
7
The initial activity phases (Phases I and II) were completed by
2006 and most notably produced a network linking 40 GOH
entities in the capital region, a remotely accessible expenditure
tracking system [Système de Gestion des Dépenses (SYSDEP) ],
and strengthened the government Independent Audit entity and
Anti-Corruption Unit.
8
The initial work to establish better control
of financial transactions and fight corruption led to the creation of
a Metropolitan Area Network (MAN) of 20 GOH sites.
Phases III and IV started in 2007, but were interrupted by the 2010 earthquake. The initiative suffered a
significant setback as the GOH suffered significant loss of life (technicians working on the IFMS activity )
and materials, notably, the MAN infrastructure. To address ongoing business needs, GOH stitched
together a MAN built mostly of surviving network equipment housed in a building donated by USAID
and using radio towers to connect to the different ministries relocated throughout Port-au-Prince. The
technology used was based on Cisco 1310 and 1410 radios in the 2.4 GHz (802.11B/G) and 5.7Ghz
(802.11A) unlicensed bands configured as point-to-point and point-to-multipoint. After the emergency
resulting from the earthquake began to subside, USAID hired an independent provider, Phase One, to
assess the state of the IFMS activity .
9
Following the firm’s comprehensive report, USAID issued a new
solicitation to continue the IFMS activity, address identified weaknesses and issues, and implement the
recommendations.
6
Taken from notes from a phone meeting with Chemonics on September 13, 2017.
7
USAID Combatting Corruption through IFMIS (Brochure).
8
Integrated Financial Management Systems (IFMS) (Brochure).
TDY Report Interim Government of Haiti—Integrated Financial Management Systems: USAID/M/PMO Assessment Team—
November 29–December 3, 2004.
9
Haiti IFMS Assessment (Final Report) February 15, 2013—Report developed by Phase One.
Activity Name:
Integrated Financial Management
System (IFMS)
Implementer:
Chemonics International
Cooperative Agreement #:
AID-OAA-I-12-00035
Total Estimated Ceiling:
$10,455,379
Life of Activity:
09/26/2014 – 09/25/2017
Development Objective:
Representative and Effective
Governance
FIGURE 1. OVERVIEW OF THE
IFMS ACTIVITY
The new IFMS activity (Phase V)—valued at $ 10,455,379 and implemented by Chemonics International
from September 2014 to March 2018 (following a 6-month extension from the original September 2017
end date)—aimed to support GOH in developing a full and complete financial management system that
ensures transparent management of public revenues, expenditures, and other resources throughout the
executive branch at the national, regional, and municipal levels.
10
The activity provided support to GOH
for the restoration, operation, and expansion of the IFMS network infrastructure and financial
management systems that contribute to improved financial governance and combating corruption. In
addition to improving existing functionality, access, security, and accountability, the new IFMS activity
sought to develop and implement business continuity and contingency plans, as well as facilitate a process
optimization exercise over all functions related to the IFMS before applications were updated to ensure a
better alignment with GOH’s business processes and technology. This result was expected given the
following key outcomes :
• IFMS network infrastructure updated and improved
• GOH capacity to utilize the IFMS for financial reporting and auditing processes expanded
• The capacity of the network to support both operational support and financial auditing built
• The expenditure and revenue systems integrated, and financial management improved
• MEF information technology (IT) governance and management capabilities to properly document and
implement governance policies and procedures for each of the stakeholder GOH ministries and
municipalities enhanced
Theory of Change
The Phase V IFMS activity’s theory of change , illustrated in Figure 2, posits that if GOH and selected
municipalities are provided the appropriate support for the restoration, operation, and expansion of both
their IFMS-related network infrastructure and financial management systems, then they would be able to
manage public revenues, expenditures, and other resources more effectively and transparently.
The IFMS Phase V design highlighted four major activity components that, in concert, sought to reinforce
and consolidate the GOH’s existing IFMS, permitting it to manage financial governance, human
resources (HR), as well as auditing, reporting, and financial transactions at the national and municipal
levels. The four components can be summarized as follows:
• Component 1: Hardware, which focused on building both the physical and information and
communication technologies (ICT) infrastructure at the national and municipal levels that will serve
as the platform for Haiti’s IFMS .
• Component 2: Software, which focused on developing, updating, and installing the requisite
software and programs that serve as the user interface that GOH entities will use to securely conduct
financial, HR, reporting, and auditing functions.
• Components 3 and 4: Capacity building and technical support, which focused on promoting the
use, maintenance, and sustainability of GOH’s updated and expanded IFMS, including:
− capacity building of key staff at provincial and national levels, promoting dialogue with other
donors and strategic planning for maintaining and extending the IFMS; and
10
SOW Final Performance Evaluation of Integrated Financial Management System (IFMS). USAID, 2017.
USAID.GOV IFMS EVALUATION REPORT | 2
3 | IFMS EVALUATION REPORT USAID.GOV
− the creation of system protocols, procedures, and operational manuals for the maintenance and
utilization of the IFMS.
The IFMS activity was organized into seven tasks (see Figure 3) that address these four components.
Annex E outlines the IFMS logical framework for the detailed tasks and subtasks. Annex B provides
detailed information on the equipment utilized during each phase of IFMS.
FIGURE 2. IFMS THEORY OF CHANGE REVISITED
GOH has complete and functional IFMS
Skill building, capacity building,and appropiation for
IFMS (including reporting and auditing)
Technical Supportfor the creation of systems protocols,
procedures, and operations manuals
IFMS administration software and interface
development and security protocol
Hardware and infrastucture development, expansion,
and maintenance
USAID.GOV IFMS EVALUATION REPORT | 4
Task 1
•Replace IFMS
Information
Technology to
strengthen the
existing network
infrastructure.
Task 2
•Build the
capacity of MEF
IFMS technical
support team to
ensure
transparency and
accountability for
the IFMS.
Task 3
•Integrate IFMS software to
support GOH
PFM policies
including the
design and
installation of an
IT interface.
Task 4
•Expand the GOH capacity to utilize
the IFMS for
financial
reporting and
auditing
processes.
Task 5
•Extend the IFMS Network
Infrasturcture to
new GOH sites.
Task 6
•Coordinate USAID IFMS
contract activities
with other donors
in PFM.
Task 7
•Assess and implement a
government-wide
HR management
application with
OMRH.
Goal:
The Government of Haiti to possess a full and complete IFMS that ensures transparent management of public revenues, expenditures, and
other resources throughout the executive branch and the regional and municipal levels.
FIGURE 3. IFMS ACTIVITY TASKS
5 | IFMS EVALUATION REPORT USAID.GOV
Operating Environment
Phase V of the IFMS activity navigated a challenging political environment in the one-year period
following the 2016 presidential elections during which Haiti did not have a formal government, as well as
during the new administration’s installation. This involved working with only willing government
counterparts who did not have authority to sign Memoranda of Understanding or make data exchange
agreements, which were critical steps to ensuring GOH ownership and buy-in. Additionally, turnover at
the highest levels of GOH leadership remained a challenge throughout the life of the acti vity. New
Ministers, Director Generals, and Managers were routinely appointed, which required the activity to
continually begin anew its awareness raising and counterpart engagement work.
11
EVALUATION PURPOSE AND AUDIENCE
This purpose of this final performance evaluation was to assess the overall effectiveness of the current
IFMS activity, which started in 2014. The evaluation findings will inform future programming in public
finance and economic governance in Haiti and other fragile states, serve as a strategic document for the
development of USAID/Haiti’s Country Development Cooperation Strategy (CDCS), and identify lessons
learned and best practices to inform future programming related to governance and ICT.
The intended audience for this evaluation is USAID/Washington, USAID/Haiti ( Office of Democracy and
Governance), Chemonics International , and key GOH institutions including MEF , Direction Générale des
Impôts (DGI), Administration Générale des Douanes (AGD), Cour Supérieure des Comptes et du
Contentieux Administratif (CSCCA), Ministère de la Planification et de la Coopération Externe (MPCE),
the Office de Management et des Ressources Humaines (OMRH), Unité de Lutte contre la Corruption
(ULCC), and all members of Haiti’s Public Finance Reform Commission. Findings may also be useful for
other donors and entities seeking to develop new public finance reform projects in Haiti.
EVALUATION QUESTIONS
This evaluation sought to answer the following evaluation questions (EQs) and accompanying sub -
questions as determined by USAID/Haiti:
1. To what extent was the program effectively implemented?
12
1.1. I
1.2. Are the new IFMS infrastructure and systems updated and
improved, relative to the previous systems?
1.3. Have staff been sufficiently trained and coached in using th
IFMS systems and interfaces?
1.4. Are the IFMS interfaces and ICT systems fully functional
and without major bugs?
e
1.5. T
1.6. How effectively has the implementing partner (IP) negotiated and adapted to changing political
circumstances in the implementation of the PFM system?
11
Input from Chemonics International into the Final Performance Evaluation of the Integrated Financial Management System
(IFMS) activity (2018).
12
Definitions on the textboxes come from the USAID/Office of U.S. Foreign Disaster Assistance’s Evaluation Guidelines for
Foreign Assistance - http://pdf.usaid.gov/pdf_docs/Pnado818.pdf
.
Effectiveness
“Effectiveness refers to the
extent to which an intervention’s
objectives are achieved or are
likely to be achieved.”
USAID.GOV IFMS EVALUATION REPORT | 6
2. To what extent is the Haitian Government, generally, and the Ministry of Economy and
Finance, specifically, at both the national and municipal levels , using the IFMS?
2.1. To what extent has IFMS contributed to improving GOH
capacity to utilize IFMS for financial reporting and auditing
processes?
2.2. To what extent has the program facilitated staff to connect
the revenue and expenditure streams of the GOH financial
chain?
2.3. How is IFMS enhancing MEF IT governance and
management capabilities to properly document and implement governance policies and
procedures?
2.4. What transparency measures have been implemented, and how are the GOH agencies tasked
with combating corruption utilizing the IFMS to better do their jobs?
2.5. Are the beneficiary entities satisfied by the results of the program? Do they correspond to their
real needs?
3.
How sustainable is the IFMS?
3.1.
Are there plans and processes in place to continue providing
the training necessary to effectively use the IFMS?
3.2.
Is the necessary budget in place to maintain the IFMS
infrastructure and continue ongoing training needs?
3.3.
To what extent do internet connectivity and electricity
challenges inhibit the system’s use?
TEAM COMPOSITION
The evaluation team was comprised of four core team members and
one supplementary technical expert. Evaluation Team Leader (TL),
Dr. Brandy Jones, brought more than 10 years of experience leading mixed -methods performance
evaluations for USAID and other donors, especially with regards to governance and decentralization
project evaluations in French-speaking nations. Assistant Team Leader (ATL), Rudolph P. St. Jean, is a
Haitian information technology professional with expertise in monitoring and evaluating advanced
information management and financial solutions. PFM Technical Expert, Stephen Leeds , brought over
30 years of experience conducting evaluations of USAID and other donors’ PFM programming. IT
Technical Expert, Carl Lacrête, is a local Information System Engineer with technical skills and training
in information system management and database implementation. Mr. Lacrête served as the
supplementary technical expert on the team. Notetaker, Wesly Jean, had seven years of research
experience working throughout Haiti collecting both quantitative and qualitative data and managing
research teams of various sizes.
The evaluation team was supported by an SI management team composed of Evaluation and Survey
Services (ESS) Chief of Party (COP), Dr. Jennifer Mandel; Project Director, Jean-Camille
Kollmorgen; Project Manager, Mariana Davila; and Project Assistant, Lisa Anderberg . This team
provided technical and managerial oversight, quality assurance, and logistical support throughout the
evaluation.
Impact
“In evaluation parlance, impacts
refer to results or effects that are
caused by, or are attributable to,
a project or program or policy.”
Sustainability
“Sustainability refers to the
continuation of an intervention’s
services and benefits after
foreign assistance ends. Three
dimensions of sustainability—
financial, institutional and
environmental—can be
examined in evaluations.”
7 | IFMS EVALUATION REPORT USAID.GOV
2. EVALUATION METHODS A ND LIMITATIONS
This evaluation employed a mixed-methods evaluation design, including a combination of qualitative data
collection methods. Between October 25 and November 21, 2017, the four-member team collected data
throughout Port-au-Prince, Haiti, with stakeholders from USAID, Chemonics International, and across the
GOH. See Annex C for the evaluation design matrix.
The evaluation included a document review, key informant interviews (KIIs), group interviews (GIs), and
structured site observations that included IFMS hardware and software component diagnostics .
13
The
evaluation process consisted of three phases: (1) planning; (2) data collection ; and (3) analysis, reporting,
and presentations.
FIGU RE 4. EVALUATION PHASES
3) Analysis, Reporting,
1) Planning 2) Data Collection and Presentation
Desk Review Team Planning Meeting Data Analysis
Design Report Inbrief Report Writing
Inception Report Primary Data Collection Presentation to
USAID/Haiti
Travel Mobilization Preliminary Analysis
PHASE ONE: PLANNING
From August 2017 until the team’s arrival in Haiti on October 25 , 2017, Haiti ESS and the evaluation
team solicited all rel evant documents for the desk review and conducted teleconferences with USAID and
Chemonics to clarify the IFMS activity scope as it related to design, geographic reach, and sampling.
After these meetings and initial sharing of project documents, the team began the desk review, which
included program-specific documents that USAID and Chemonics provided, as well as secondary literature
regarding the PFM sector more broadly. See Annex K for a list of documents reviewed. The team
summarized the findings from the desk review in an Inception Report and used the background
knowledge as the basis for the designing the evaluation.
PHASE TWO: DATA COLLECTION
Upon arrival of the TL in Port-au -Prince, the team held a meeting with Chemonics on October 25 , 2017
and an in-brief with USAID on October 27,
2017. Following these meetings, the team finalized fieldwork
preparation and began data collection.
13
Limited software diagnostics were conducted because most of the procured software—including SIGRH, UXP, and Business
Intelligence—were only recently procured and introduced by the activity or were still in a test and installation phase.
KEY INFORMANT AND GR OUP INTERVIEWS
The evaluation team conducted 20 KIIs and 8
GIs
14
representing the following organizations:
• USAID
• Chemonics International;
• International Donors: World Bank,
Embassy of Canada, and InterAmerican
Development Bank (IDB)
• GOH: MEF, DGI, AGD, ULCC, CSCCA,
Ministère des Travaux Publics, Transports
et Communications (MTPTC), Ministère de
l'Intérieur et des Collectivités Territoriales
(MICT), Ministère De L’Education Nationale
Et De La Formation Professionnelle
(MENFP), and OMRH
• IFMS Service Providers
KII and GI protocols were tailored to each
informant’s role, the nature and extent of the ir
involvement in the IFMS activity, and the time
available for interviewing. All data was
collected in French. KII and GIs protocols are
in Annex G.
IFMS HARDWARE AND SOFTWARE DIAGNOSTICS
The evaluation team also conducted diagnostics using an observation checklist (see Annex G.3) to verify
the quality and content of materials, software, and infrastructure that were installed and provided at the
sampled sites. While hardware diagnostics were conducted at almost all visited sites, the software
diagnostics were not conducted at all sites because many of the software and applications were either still
being installed or developed (Network Monitoring Software, Virtualization Software, Backup System,
Business Intelligence Software, Human Resource Application), were in an initial test phase (Universal
eXchange Platform [UXP]), or had yet to be purchased (Audit Software).
The evaluation team conducted 12 d iagnostics overall at the following sites:
• MEF
• DGI headquarters and 4 Sub -Offices (Delmas, Carrefour, Kenscoff, and Pétionville )
• MICT sub-offices
• CSCCA headquarters
• ULCC headquarters
• MENFP headquarters
Altogether, the evaluation team collected data with 57 individuals (48 males and 9 females) during the
KIIs, GIs, and Diagnostics.
14
GIs are interviews where more than one person is present to participate in the key informant interview.
USAID.GOV IFMS EVALUATION REPORT | 8
The methods we used: How many people
we interviewed:
2 Women
18 Men
20 Key Informants
7 Women
18 Men
25 Informants
Key Informant
Interviews 20
12 Men
12 Informants Diagnostics 1
Group Interviews
8
FIGURE 5. EVALUATION METHODS STATISTICS
[... middle sections omitted for long document ...]
77 | IFMS EVALUATION REPORT USAID.GOV
ANNEX H: TRAINING MATERIALS A ND IFMS POLICY DOCUM ENTS
TRAINING
81
PROGRAM MANUAL NUMBER OF DAYS POWERPOINT
LIST OF
PARTICIPANTS
82
1. IT Security x x 4 -- --
2. IT Project Management x x 5 -- --
3. IT Network Administration x x 8 -- --
4. Database Administration x x 5 -- --
5. UXP x x -- X x
6. Windows Server x -- 5 -- x
7. Business Intelligence Software x -- 3 -- x
8. Cisco Network Training -- -- 4 -- x
9. VXRAIL -- -- -- -- x
10. Civitax (??VPN) -- -- -- x x
11. SIGRH x x 5 x x
12. IT Hardware Management with GLPI x x -- -- x
13. ELOGIC on NOC Equipment Training ??? -- -- 5 -- x
POLICY DOCUMENTS AND PROCEDURAL MANUA LS RECEIVED
POLICY AND PROCEDURA L DOCUMENT CONTENT
1. Policy on Maintenance of the NOC Systems and Materials • Manual covers NOC Cleaning, Software Updating, System Verification, and
Upgrading.
2. Procedure for the Inventory of MEF Hardware and Software Materials • Guidelines for inventory for IT equipment and with MEF.
3. MEF Policy for Security Against Viruses and Malware • Guidance regarding virus and malware protection protocols with in the MEF
IFMS network and systems.
4. Procedures for Accessing the MEC: NOC • Guidelines for security surrounding access to the NOC
5. Procedures for Database Maintenance and Back-up • Guidelines for database managers on maintenance and backup of MEF databases.
6. Project Proposal Package • Complete Project Design Documents
81
X signifies that the document or resource was shared.
82
Chemonics scanned the signup sheets from the various trainings; no organized training list of participants was provided to the evaluation team. The evaluation team had to go
through and scan the list to garner any and all resulting information contained in this document.
ANNEX I: FULL LISTING OF REFERENCES AND REPORT S UTILIZED
Centre de convention BRH. 2017. Aide -mémoire de la première rencontre annuelle conjointe.
Chemonics International. 2016. Annual Report Year 2: Haiti IFMS. Port-au -Prince: Chemonics
International.
Chemonics International. 2015. Ann ual Report Year 1: Haiti IFMS. Port-au -Prince: Chemonics
International.
Chemonics International. 2014. Chemonics Technical Proposal USAID Haiti IFMS 1 of 1.
Chemonics International. 2014– 2017. Haiti IFMS Weekly Highlights (12.6.14-08.23.17). Port-au-
Prince: Chemonics International.
Chemonics International. 2017. IFMS Inventory Tracker. Port-au -Prince: Chemonics
International.
Chemonics International. 2016. Improving Governance Efforts and Financial Transparency in
Haiti. Web. http://www.chemonics.com/OurWork/OurProjects/Pages/Haiti-Integrated-
Financial-Management-System.aspx
Chemonics International. 2017. Quarterly Report Year 3 Quarter 3: Haiti IFMS. Port-au -Prince:
Chemonics International.
Chemonics International. 2017. Quarterly Report Year 3 Quarter 2: Haiti IFMS. Port-au -Prince:
Chemonics International.
Chemonics International. 2017. Quarterly Report Year 3 Quarter 1: Haiti IFMS. Port-au -Prince:
Chemonics International.
Chemonics International. 2016. Quarterly Report Year 2 Quarter 4: Haiti IFMS. Port-au -Prince:
Chemonics International.
Chemonics International. 2016. Quarterly Report Year 2 Quarter 3: Haiti IFMS. Port-au -Prince:
Chemonics International.
Chemonics International. 2016. Quarterly Report Year 2 Quarter 2: Haiti IFMS. Port-au -Prince:
Chemonics International.
Chemonics International. 2016. Quarterly Report Year 2 Quarter 1: Haiti IFMS. Port-au -Prince:
Chemonics International.
Chemonics International. 2015. Quarterly Report Year 1 Quarter 3: Haiti IFMS. Port-au -Prince:
Chemonics International.
Chemonics International. 2015. Quarterly Report Year 1 Quarter 2: Haiti IFMS. Port-au -Prince:
Chemonics International.
Chemonics International. 2015. Quarterly Report Year 1 Quarter 1: Haiti IFMS. Port-au -Prince:
Chemonics International.
Chemonics International and USAID Haiti. 2017. The Introduction of Transformational
Financial Management Information Systems in Haiti: SIGRH and UXP. PowerPoint.
Haiti Libre. 2016. Haiti - Technology: Pilot phase of impleme ntation of the UXP platform. Port-
au-Prince: Haiti Libre News. Web. http://www.haitilibre.com/
Haiti Libre. 2015. Haiti - Technology: The X-ROAD project making great strides. Port-au-
Prince: Haiti Libre News. Web. http://www.haitilibre.com/
IDB République d’Haïti. 2017. Evaluation de la fonctionnalité, la fiabilité et l’intégrité du compte unique
du trésor en Haïti.
IFMS. 2017. Haïti Integrate Financial Management System: Guide d’utilisation du portail UXP.
USAID.GOV IFMS EVALUATION REPORT | 78
79 | IFMS EVALUATION REPORT USAID.GOV
IFMS. 2017. Integrated Financial Management Information Systems. Fiche pédagogique: Formation sur
l’utilisation du portal UXP.
Kozeli, Frenki. 2017. Transforming Public Finance: A Proven and Scalable Information
Systems Solution in Haiti. Chemonics. http://blog.chemonics.com/transforming-public -finance-
%E2%80%94-a-proven-and -scalable-information-systems- solution-in-haiti
Ministère de l’Economie et des Finances : Projet loi de loi de finances rectificative de l’exercice
2016-2017.
Phase One. 2013. Haiti Integrated Financial Management System Assessment: Final Report.
Washington, D.C. : USAID.
Phase One. [Unknown Date]. Haiti Integrated Financial Management System Assessment. Web.
http://www.pocg.com/haiti-integrated-financial-management-system-assessment/
République d’Haïti. Ministère de l’Economie et des Finances. 2014. Commission de réforme des
finances publiques et de gouvernance économique: Stratégie de réforme des finances publiques.
République d’Haïti. Ministère de l’Economie et des Finances. 2013-2018. Schéma directeur
Informatique: réalisation d’une étude pour la modernisation des systèmes de gestion des
finances publiques en république d’Haïti.
USAID/Chemonics. Ministère de l’Economie et des Finances. 2016. Politique de Sécurité Contre les
Virus et Logiciels Malveillants.
USAID/Chemonics. Ministère de l’Economie et des Finances. 2017. Pro cédures d’accès au NOC du
MEF.
USAID. 2014. Public Financial Management Practices in Latin America and the
Caribbean: A Review of Trends, Challenges, and Opportunities for Improvement.
Washington D.C.: USAID Strengthening Public Financial Management in Latin America and the
Caribbean (PFM-LAC).
USAID. 2008. Integrated Financial Management Information Systems: A Practical Guide.
Washington D.C.: USAID.
USAID. 2008. Integrated Financial Management Information Systems: Factsheet.
Washington, D.C.: USAID.
USAID Bureau for Economic Growth and Trade, Infrastructure and Engineering, Information
Communication Technology (USAID/EGAT/I&E/ICT). 2006. Haiti IFMS: Applied Technology .
PowerPoint.
USAID Bureau for Management, Property Management Officer (USAID/M/PMO). 2004.
Integrated Financial Management System: TDY Report Interim Government of Haiti.
Washington, D.C.: USAID Bureau for Democracy, Conflict and Humanitarian Assistance,
Democracy and Governance (USAD/DCHA/DG).
USAID Haiti. [Unknown Date]. Combating Corruption through the Integrated Financial
Management System (IFMS): USAID Factsheet. Port-au -Prince: USAID Haiti.
USAID Haiti. 2015. Integrated Financial Management Information Systems: Year One
Annual Workplan: USAID Haiti.
USAID Haiti. 2015. Integrated Financial Management Information Systems: Year One
Annual Workplan: USAID Haiti.
USAID Haiti. 2015. Integrated Financial Management Information Systems: Year Two
Annual Workplan: USAID Haiti.
USAID Haiti. 2016. Integrated Financial Management Information Systems: Year Tree
Annual Workplan: USAID Haiti.
USAID. Ministère de l’Economie et des Finances. Procédures de sauvegarde des données.
USAID Haiti. 2015. Integrated Financial Management Information Systems: Administration de base de
données.
USAID.GOV IFMS EVALUATION REPORT | 80
USAID. 2015. Final Report - SIGRH Upgrade Requirements Analysis.
USAID. Ministre de l’Economie et des Finances (MEF). Infrastructure et design d’active Directory.
USAID. Ministre de l’Economie et des Finances (MEF). 2017. Politique de Maintenance et de Mise à
jour.
USAID. Ministre de l’Economie et des Finances (MEF). Procédure de Nomination Standard des
équipements du Ministère de L’Economie Et des Finances.
USAID. IFMS. 2016. Presentation UXP Data Exchange Platform . PowerPoint.
World Bank. Ministère de l’Economie et des Finances. Assistance à la maîtrise d’ouvrage:
Audit du réseau métropolitain du Ministère de l’Economie et des Finances.
World Bank. Ministère de l’Economie et des Finances. 2017. Assistance à la maîtrise d’œuvre :
DSI du MEF. Rapport mensuel intermédiaire Aout 2017.
World Bank. Ministère de l’Economie et des Finances. 2017. Assistance à la maîtrise d’œuvre :
DSI du MEF. Rapport mensuel intermédiaire Octobre 2017.
Bureau for Policy, Planning and Learning
April 2015 EVALUATION DISSEMINATION PLAN: USAID/HAITI IFMS EVALUATION -
81
ANNEX J: EVALUATION DISSEMINATION PLAN
Key Milestones Expected Dates
Statement of Work June 2017
Evaluation Design September 2017
Draft Report January 2018
Final Report February 2018
Evaluation Title: Final Performance Evaluation of the Integrated Financial Management System (IFMS) Activity
Intended
Audience
Goal Tool/Medium Forum Responsible
Party
Target Date Follow-up
USAID/Haiti,
Chemonics
Ensure that key findings and
conclusions emerging from
this evaluation are
understood and the
recommendations utilized
Findings
presentation
In-person presentation Haiti ESS January 2018 Activity completed
USAID/Haiti,
Chemonics
To provide USAID and
Chemonics with a succinct yet detailed account of the
evaluation team’s work.
Full
evaluation report
Distribution via email and
USAID’s Development Clearing House (DEC)
Haiti ESS February
2018
USAID/Haiti,
Chemonics,
Government of
Haiti (GOH)
Ministry of
Finance (MEF),
Other Donors
To inform the broader
community about the key
learnings of this evaluation
Standalone
abstract and
executive summary
document of
the final
evaluation
report
Distribution via email,
Donor Working Group,
and USAID’s Development Clearing
House (DEC)
Haiti ESS
and
USAID/Haiti
March 2018