Data / Partner portfolio / World Bank Group / IDA
Haiti Strengthening Public Financial Management Project
US$ millions unless stated. Haitian fiscal year, October to September. FY2026-27 began October 1, 2026.
Objective
To strengthen inclusive access to and delivery of selected public services
As published by World Bank Projects, in its original language.
Description
The development objective of Strengthening Public Financial Management Project for Haiti is to strengthen government capacity and transparency in public revenue mobilization and financial management. This project has five components. 1) The first component, Improving Domestic Revenue Mobilization, has the following sub-components: (i) Strengthening Customs presence and control; and (ii) Improving the efficiency of Customs Administration. 2) The second component, Consolidating PFM reforms, has the following sub-components: (i) Operationalizing the budget reform; and (ii) Consolidating the IFMIS and strengthening its use for improved accrual-based financial reporting. 3) The third component, Improving implementation capacity, strengthening evidence-based policy making and citizen engagement, has the following components: (i) Leadership and change management for results; and (ii) Platforms and mechanisms for coalition building, citizen
more
engagement and external communications; and (iii) Promoting evidence-based policy making. 4) The fourth component, Contingent Emergency Response Component (CERC), aims to provide for an immediate response to eligible emergencies at the government’s request.5) Project coordination, aims to strengthen the GoH’s capacity for coordination and management of the project.
- Partner
- World Bank Group, IDA
- Sector
- Governance and security
- Stage
- Under way since March 4, 2025
- Approval
- March 4, 2025
- Closing
- February 28, 2030
- Instrument
- IBRD/IDA financing, IDA
- Undisbursed gap
- −2.7: the IDA statement values undisbursed credits in special drawing rights at the current exchange rate
- Borrower
- Republic of Haiti
- Implementing agency
- Ministry of Economy and Finance
- Effectiveness
- June 18, 2025
- Departments
- Ouest
- Last transaction
- July 31, 2026
- Operation ID
- P180384
Life cycle3 stages, 13 dates
Stage history
| Stage | From |
|---|---|
| Planned | November 20, 2023 |
| Approved | March 4, 2025 |
| Under way | March 4, 2025 |
Dated events
| Event | Date | Source |
|---|---|---|
| Concept review | November 20, 2023 | World Bank Projects |
| Disclosure | December 5, 2023 | World Bank Projects |
| Appraisal | November 5, 2024 | World Bank Projects |
| Negotiation | January 22, 2025 | World Bank Projects |
| Actual start | March 4, 2025 | IATI |
| Approval | March 4, 2025 | World Bank Projects |
| First commitment | March 4, 2025 | Transactions |
| Planned start | March 4, 2025 | IATI |
| Effectiveness | June 18, 2025 | World Bank Projects |
| First disbursement | September 30, 2025 | Transactions |
| Last disbursement | July 31, 2026 | Transactions |
| Closing date | February 28, 2030 | IATI |
| Completion report due | August 28, 2030 | World Bank Projects |
Undisbursed: US$60.7 million on September 30, 2026, with closing on February 28, 2030. Disbursed in FY2025-26: US$1.0 million.
Financing
Table 1.Financing, US$ millions
| Financier | AmountUS$ millions | Role | Source |
|---|---|---|---|
| IDA Grant | 60.0 | Institution | World Bank Projects |
Table 2.Position at the data date by source (stocks), US$ millions
| This pageUS$ millions | Source | IATIUS$ millions | |
|---|---|---|---|
| Commitment | 60.0 | IDA Statement of Credits and Grants | 60.0 |
| Disbursed | 2.0 | IDA Statement of Credits and Grants | 1.6 |
| Undisbursed | 60.7 | IDA Statement of Credits and Grants | |
| Total cost | 50.0 | World Bank Projects |
World Bank amounts. Approved: Net commitment, the amount approved less cancellations, in US$ at the data date. Disbursed to date: The disbursements of the IDA statement and the Projects API to date, in US$. Undisbursed: The undisbursed balance the IDA statement publishes, in US$ at the data date. IATI column: the commitments and disbursements the partner reports to IATI, converted to US$. Amounts by source
Changes to the operation0 extensions, emergency component included
- Original closing date
- February 28, 2030
- Closing date extensions
- 0
- Restructurings
- Not reported
- Emergency component
- Contingent emergency response component included (document of June 4, 2025) document
New commitments and disbursements by fiscal year
Table 3.New commitments and disbursements by fiscal year (flows), US$ millions
| FY2024-25US$ millions | FY2025-26US$ millions | |
|---|---|---|
| New commitments | 60.0 | Not reported |
| Disbursements | 1.0 | 1.0 |
| Cumulative disbursements | 1.0 | 2.0 |
Records and documents
Transactions5 records, March 4, 2025 to July 31, 2026
Table 4.Transactions, US$ millions
| Date | Measure | AmountUS$ millions | Source | Method |
|---|---|---|---|---|
| March 4, 2025 | Commitment | 60.0 | IDA Statement of Credits and Grants | credit original principal at board approval |
| September 30, 2025 | Disbursements | 1.0 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| February 28, 2026 | Disbursements | 0.3 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| June 30, 2026 | Disbursements | 0.3 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| July 31, 2026 | Disbursements | 0.4 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
Terms4 of 6 reported
- Finance type
- 110 Standard grant
- Flow type
- Not reported
- Aid type
- C01 Project-type interventions
- Tied status
- 5 Untied
- Collaboration type
- 2 Multilateral inflows
- Humanitarian
- Not reported
Locations1 department, 2 places named, 2 places with coordinates
| Departments | Ouest |
| Places named by the source | Port-au-Prince, Republic of Haiti |
| Places with coordinates | 2 |
Results indicators14 indicators
| Indicator | Baseline | Target | Latest value | Date of latest value |
|---|---|---|---|---|
| Number of ministries for which 100% of budget expenditure is executed in program mode in the IFMIS | 0 | 12 | 0 | Not reported |
| On-time submission of annual financial statements produced through the IFMIS to the SAI (without extra budgetary expenses) | Not reported | 2027-2028 financial statement | Not reported | Not reported |
| Preparation and publication of quantitative reports on customs performance based on ASYCUDA data | Not reported | Quarterly reports published | Not reported | Not reported |
| Reduced customs clearance processing times for high-risks goods | 7 | 2 | 7 | Not reported |
| Citizens providing feedback in budget dissemination and accountability sessions | 0 | 50 | 0 | Not reported |
| Climate and gender budget tagging introduced in budgetary practices | Not reported | 10% increase each in climate and gender related expenditure in approved budget | Not reported | Not reported |
| Customs duties that are paid through the online payment platform | 0 | 30 | 0 | Not reported |
| First program budgets prepared in Ministries in accordance with the approved program structure | 0 | Not reported | 0 | January 1, 1900 |
| Innovative tools for data collection introduced | No | Yes | No | Not reported |
| Interfaces between IFMIS and key platforms established for data exchange (cumulative) | Not reported | 3 targeted interfaces | Not reported | Not reported |
| Public accounts audited by the SAI using its audit software | 0 | 12 | 0 | Not reported |
| Public officials trained in the use of select PFM platforms and budget practices | 0 | 40% increase | 0 | Not reported |
| Public servants and stakeholders trained and engaged through coalitions to support the reforms | 0 | 30% increase | 0 | Not reported |
| Select customs offices rehabilitated | 0 | 3 | 0 | Not reported |
Ratings6 ratings
| Rating | Value | Date |
|---|---|---|
| ISR Financial Management | Moderately Satisfactory | July 10, 2026 |
| ISR Monitoring and Evaluation | Satisfactory | July 10, 2026 |
| ISR Overall Implementation Progress (IP) | Moderately Satisfactory | July 10, 2026 |
| ISR Procurement | Satisfactory | July 10, 2026 |
| ISR Progress towards achievement of PDO | Satisfactory | July 10, 2026 |
| ISR Project Management | Moderately Satisfactory | July 10, 2026 |
Contract awards15 awards
| Supplier | Date | Method | Amount |
|---|---|---|---|
| Name not shown | June 26, 2026 | CDS | 29,176.47 USD |
| ZAMOR Services | June 16, 2026 | RFQ | 59,400 USD |
| Name not shown | May 28, 2026 | CDS | 68,850 USD |
| Name not shown | May 22, 2026 | DIR | 69,454 USD |
| Name not shown | May 9, 2026 | CDS | 90,000 USD |
| Freebalance Inc. | April 24, 2026 | CDS | 1,388,779 USD |
| OCPAH | March 10, 2026 | CDS | 654,094 USD |
| Name not shown | February 10, 2026 | CDS | 26,000 USD |
| Name not shown | December 17, 2025 | CDS | 50,000 USD |
| Name not shown | November 20, 2025 | CDS | 5,895,000 HTG |
| Name not shown | October 29, 2025 | DIR | 50,000 USD |
| Name not shown | June 27, 2025 | CDS | 38,823 USD |
| Name not shown | June 27, 2025 | CDS | 590,000 HTG |
| Name not shown | June 20, 2025 | CDS | 3,587,760 HTG |
| Name not shown | June 20, 2025 | CDS | 11,640,552 HTG |
Funds passed on4 transactions
Identifiers5 identifiers
| System | Identifier | Source |
|---|---|---|
| IATI identifier | 44000-P180384 | IATI |
| IDA credit or grant | IDAE4170 | IDA Statement of Credits and Grants |
| Public investment program line | 1112-1-12-52-35 | Public investment program |
| World Bank loan | IDA-E4170 | World Bank Projects |
| World Bank project | P180384 | Operation record |
Partner documents36 documents
- Record on projects.worldbank.org, projects.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P180384- Haiti Strengthening Public Financial Management Project - Procurement Plan, October 7, 2026, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P180384- Haiti Strengthening Public Financial Management Project - Procurement Plan, July 23, 2026, documents.worldbank.org
- Environmental and Social Management Framework (ESMF) Haiti Strengthening Public Financial Management Project (P180384), July 22, 2026, documents.worldbank.org
- Disclosable Version of the ISR - Haiti Strengthening Public Financial Management Project - P180384 - Sequence No : 3, July 10, 2026, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P180384- Haiti Strengthening Public Financial Management Project - Procurement Plan, May 28, 2026, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P180384- Haiti Strengthening Public Financial Management Project - Procurement Plan, May 12, 2026, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P180384- Haiti Strengthening Public Financial Management Project - Procurement Plan, May 6, 2026, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P180384- Haiti Strengthening Public Financial Management Project - Procurement Plan, April 21, 2026, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P180384- Haiti Strengthening Public Financial Management Project - Procurement Plan, April 1, 2026, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P180384- Haiti Strengthening Public Financial Management Project - Procurement Plan, March 25, 2026, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P180384- Haiti Strengthening Public Financial Management Project - Procurement Plan, March 17, 2026, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P180384- Haiti Strengthening Public Financial Management Project - Procurement Plan, March 2, 2026, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P180384- Haiti Strengthening Public Financial Management Project - Procurement Plan, February 18, 2026, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P180384- Haiti Strengthening Public Financial Management Project - Procurement Plan, January 16, 2026, documents.worldbank.org
- Disclosable Version of the ISR - Haiti Strengthening Public Financial Management Project - P180384 - Sequence No : 2, December 24, 2025, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P180384- Haiti Strengthening Public Financial Management Project - Procurement Plan, December 12, 2025, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P180384- Haiti Strengthening Public Financial Management Project - Procurement Plan, December 5, 2025, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P180384- Haiti Strengthening Public Financial Management Project - Procurement Plan, October 7, 2025, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P180384- Haiti Strengthening Public Financial Management Project - Procurement Plan, September 23, 2025, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P180384- Haiti Strengthening Public Financial Management Project - Procurement Plan, August 1, 2025, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P180384- Haiti Strengthening Public Financial Management Project - Procurement Plan, July 22, 2025, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P180384- Haiti Strengthening Public Financial Management Project - Procurement Plan, July 14, 2025, documents.worldbank.org
- Disclosable Version of the ISR - Haiti Strengthening Public Financial Management Project - P180384 - Sequence No : 1, June 4, 2025, documents.worldbank.org
- Official Documents- Financing Agreement for Grant E417-HT.pdf, March 28, 2025, documents.worldbank.org
- Official Documents- Disbursement and Financial Information Letter for Grant E417-HT.pdf, March 26, 2025, documents.worldbank.org
- Environmental and Social Commitment Plan (ESCP) Haiti Strengthening Public Financial Management Project (P180384), March 17, 2025, documents.worldbank.org
- Minutes of a Meeting of the Executive Directors of IBRD, IDA and the Board of Directors of IFC and MIGA on March 4, 2025, and Record of Approval on an Absence of Objection Basis between February 21, 2025, and March 4, 2025 , March 4, 2025, documents.worldbank.org
- Haiti - Strengthening Public Financial Management Project , February 7, 2025, documents.worldbank.org
- Environmental and Social Commitment Plan (ESCP) Haiti Strengthening Public Financial Management Project (P180384), January 27, 2025, documents.worldbank.org
- Appraisal Environmental and Social Review Summary (ESRS) - Haiti Strengthening Public Financial Management Project - P180384, March 8, 2024, documents.worldbank.org
- Appraisal Project Information Document (PID), March 8, 2024, documents.worldbank.org
- Environmental and Social Commitment Plan (ESCP) - Haiti Strengthening Public Financial Management Project - P180384, March 8, 2024, documents.worldbank.org
- Stakeholder Engagement Plan (SEP) - Haiti Strengthening Public Financial Management Project - P180384, March 8, 2024, documents.worldbank.org
- Concept Environmental and Social Review Summary (ESRS) - Strengthening Public Financial Management Project - P180384, December 12, 2023, documents.worldbank.org
- Concept Project Information Document (PID), December 5, 2023, documents.worldbank.org
Procurement notices (2)
- Contract Awards, projects.worldbank.org
- Procurement Notices, projects.worldbank.org
Sources
- Partner documents: terms of use set by the publisher
- IATI record (d-portal): terms of use set by the publisher
- IATI: terms of use set by the publisher
- IDA statement of credits and grants (dataset): World Bank data, CC BY 4.0 (https://datacatalog.worldbank.org/public-licenses).
- Transactions: terms of use set by the publisher
- Operation record: terms of use set by the publisher
- Public investment program: terms of use set by the publisher
- World Bank procurement notices: terms of use set by the publisher
- World Bank project page: terms of use set by the publisher
- World Bank documents: terms of use set by the publisher
Data as of October 18, 2026
| Source | Read on |
|---|---|
| IATI | October 18, 2026 |
| IATI | October 18, 2026 |
| IDA Statement of Credits and Grants | October 18, 2026 |
| Public investment program | October 18, 2026 |
| World Bank procurement notices | October 11, 2026 |
| World Bank Projects | October 18, 2026 |
| World Bank documents | October 18, 2026 |
Cite this page
HaitiDocs. Haiti Strengthening Public Financial Management Project. Partner portfolio, data as of October 18, 2026. https://www.haitidocs.org/portfolio/projects/WB%3AP180384