Private Sector Jobs and Economic Transformation (PSJET)
US$ millions unless stated. Haitian fiscal year, October to September. FY2026-27 began October 1, 2026.
Objective
Contribute to labor demand by supporting MSMEs and value chains resilience and growth through improved business development services and access to financial resources
As published by World Bank Projects, in its original language.
Description
The development objective of the Private Sector Jobs and Economic Transformation Project for Haiti is to contribute to labor demand by supporting micro, small, and medium enterprises (MSMEs) and value chains resilience and growth through improved business development services and access to financial resources. The project comprises of four components. The first component, investing in MSMEs and value chains resilience and growth will provide business development services (BDS) and matching grants that can be used to finance investments and working capital to individual as well as groups of viable beneficiary firms. The second component, improving access to finance for MSMEs will finance the provision of a partial credit guarantee (PCG) and a line of credit (LoC) to participating financial institutions
more
(PFIs). The third component is enhancing strategy, coordination, project management, and impact evaluation. The fourth component, contingent emergency response component (CERC) will draw from the uncommitted credit resources under the project from other project components, to cover emergency response.
- Partner
- World Bank Group, IDA
- Stage
- Under way since September 28, 2021
- Approval
- September 28, 2021
- Closing
- May 31, 2027
- Instrument
- IBRD/IDA financing, IDA
- Undisbursed gap
- 2.6: the IDA statement values undisbursed credits in special drawing rights at the current exchange rate
- Borrower
- Republic of Haiti
- Implementing agency
- Ministry of the Economy and Finance
- Effectiveness
- December 15, 2021
- Departments
- Sud-Est, Sud, Ouest, Artibonite
- Last transaction
- September 30, 2026
- Operation ID
- P173743
Life cycle3 stages, 13 dates
Stage history
| Stage | From |
|---|---|
| Planned | September 18, 2020 |
| Approved | September 28, 2021 |
| Under way | September 28, 2021 |
Dated events
| Event | Date | Source |
|---|---|---|
| Concept review | September 18, 2020 | World Bank Projects |
| Disclosure | September 18, 2020 | World Bank Projects |
| Planned start | November 30, 2020 | IATI |
| Appraisal | January 28, 2021 | World Bank Projects |
| Negotiation | April 22, 2021 | World Bank Projects |
| Actual start | September 28, 2021 | IATI |
| Approval | September 28, 2021 | World Bank Projects |
| First commitment | September 28, 2021 | Transactions |
| Effectiveness | December 15, 2021 | World Bank Projects |
| First disbursement | July 31, 2022 | Transactions |
| Last disbursement | September 30, 2026 | Transactions |
| Closing date | May 31, 2027 | IATI |
| Completion report due | November 30, 2027 | World Bank Projects |
Undisbursed: US$23.5 million on September 30, 2026, with closing on May 31, 2027. Disbursed in FY2025-26: US$4.8 million.
Financing
Table 1.Financing, US$ millions
| Financier | AmountUS$ millions | Role | Source |
|---|---|---|---|
| IDA Grant | 50.4 | Institution | World Bank Projects |
Table 2.Position at the data date by source (stocks), US$ millions
| This pageUS$ millions | Source | IATIUS$ millions | |
|---|---|---|---|
| Commitment | 51.4 | IDA Statement of Credits and Grants | 69.6 |
| Disbursed | 25.3 | IDA Statement of Credits and Grants | 24.4 |
| Undisbursed | 23.5 | IDA Statement of Credits and Grants | |
| Total cost | 105.0 | World Bank Projects |
World Bank amounts. Approved: Net commitment, the amount approved less cancellations, in US$ at the data date. Disbursed to date: The disbursements of the IDA statement and the Projects API to date, in US$. Undisbursed: The undisbursed balance the IDA statement publishes, in US$ at the data date. IATI column: the commitments and disbursements the partner reports to IATI, converted to US$. Amounts by source
Changes to the operation0 extensions, at least 1 restructuring, emergency component included
- Original closing date
- May 31, 2027
- Closing date extensions
- 0
- Restructurings
- at least 1
- March 14, 2025 (document of March 14, 2025) restructuring paper
- Emergency component
- Contingent emergency response component included (document of June 17, 2026) document
New commitments and disbursements by fiscal year
Table 3.New commitments and disbursements by fiscal year (flows), US$ millions
| FY2020-21US$ millions | FY2021-22US$ millions | FY2022-23US$ millions | FY2023-24US$ millions | FY2024-25US$ millions | FY2025-26US$ millions | |
|---|---|---|---|---|---|---|
| New commitments | 75.0 | Not reported | Not reported | Not reported | −5.8 | −17.9 |
| Disbursements | Not reported | 0.2 | 2.6 | 2.0 | 15.5 | 4.8 |
| Cumulative disbursements | Not reported | 0.2 | 2.9 | 4.9 | 20.4 | 25.3 |
Records and documents
Transactions27 records, September 28, 2021 to September 30, 2026
Table 4.Transactions, US$ millions
| Date | Measure | AmountUS$ millions | Source | Method |
|---|---|---|---|---|
| September 28, 2021 | Commitment | 75.0 | IDA Statement of Credits and Grants | credit original principal at board approval |
| April 30, 2025 | Commitment | −5.8 | IDA Statement of Credits and Grants | cancellation: increase in cumulative cancelled amount between snapshots (non-USD credit: includes exchange revaluation) |
| September 30, 2026 | Commitment | −17.9 | IDA Statement of Credits and Grants | cancellation: increase in cumulative cancelled amount between snapshots (non-USD credit: includes exchange revaluation) |
| July 31, 2022 | Disbursements | 0.2 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| October 31, 2022 | Disbursements | 0.9 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| March 31, 2023 | Disbursements | 0.6 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| April 30, 2023 | Disbursements | <0.1 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| July 31, 2023 | Disbursements | 1.1 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| December 31, 2023 | Disbursements | 0.8 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| February 29, 2024 | Disbursements | 0.5 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| May 31, 2024 | Disbursements | 0.5 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| June 30, 2024 | Disbursements | 0.2 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| August 31, 2024 | Disbursements | 0.1 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| December 31, 2024 | Disbursements | 10.2 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| January 31, 2025 | Disbursements | 0.6 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| February 28, 2025 | Disbursements | 1.3 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| March 31, 2025 | Disbursements | 0.2 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| May 31, 2025 | Disbursements | 0.2 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| June 30, 2025 | Disbursements | 0.3 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| August 31, 2025 | Disbursements | 0.7 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| September 30, 2025 | Disbursements | 2.0 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| February 28, 2026 | Disbursements | 1.5 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| March 31, 2026 | Disbursements | 0.4 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| April 30, 2026 | Disbursements | 0.6 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| June 30, 2026 | Disbursements | 1.5 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| July 31, 2026 | Disbursements | 0.6 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| September 30, 2026 | Disbursements | 0.3 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
Terms5 of 6 reported
- Finance type
- 110 Standard grant
- Flow type
- Not reported
- Aid type
- C01 Project-type interventions
- Tied status
- 5 Untied
- Collaboration type
- 2 Multilateral inflows
- Humanitarian
- Yes
Policy markers2 policy markers
| Policy marker | Significance | Source |
|---|---|---|
| EP-2020-000012-001 | Not reported | IATI |
| HCOVD20 | Not reported | IATI |
Locations4 departments, 5 places named, 10 places with coordinates
| Departments | Sud-Est, Sud, Ouest, Artibonite |
| Places named by the source | Departement de l'Artibonite, Departement de l'Ouest, Republic of Haiti, Sud, Sud-Est |
| Places with coordinates | 10 |
Results indicators23 indicators
| Indicator | Baseline | Target | Latest value | Date of latest value |
|---|---|---|---|---|
| Among which to first time borrowers | 0.00 | 5000000.00 | 0.00 | November 30, 2023 |
| Among which to first time women borrowers | 0.00 | 2500000.00 | 0.00 | November 30, 2023 |
| Anti-competitive practices and regulations removed | 0.00 | 2.00 | 0.00 | November 30, 2023 |
| Business regulations reformed | 0.00 | 3.00 | 0.00 | November 30, 2023 |
| Firms benefiting from private sector initiatives | 0.00 | 550.00 | 0.00 | November 30, 2023 |
| Modules of FDI institutional development plan fully implemented | 0.00 | 4.00 | 0.00 | November 30, 2023 |
| Of which women-owned/managed | 0.00 | 0.00 | Not reported | Not reported |
| Private capital mobilized by PFIs through the project PCG | 0.00 | 30000000.00 | 0.00 | November 30, 2023 |
| Stakeholder engagement meetings held that directly involved project beneficiaries and discussed beneficiary inputs regarding project implementation | 0.00 | 7.00 | 0.00 | November 30, 2023 |
| Value of grants to beneficiary firms used for climate change adaptation | 0.00 | 3000000.00 | 0.00 | November 30, 2023 |
| Value of loans provided by PFIs through the project LoC | 0.00 | 21000000.00 | 0.00 | November 30, 2023 |
| Value of loans provided by PFIs through the project for investment in climate change mitigation | 0.00 | 25000000.00 | 0.00 | November 30, 2023 |
| Increased investment by supported firms | 0.00 | 28,000,000 | 2454166.11 | Not reported |
| Share of supported MSMEs that increase employment | 0.00 | 25.00 | 0.00 | November 30, 2023 |
| Firms benefiting from business development services | 0.00 | 2000.00 | 900 | Not reported |
| No of cluster initiatives that are supported by the collective window | 0 | 3 | 0 | Not reported |
| Private capital mobilized by PFIs through the project PPCGs | 0.00 | 30,000,000 | 880484.15 | Not reported |
| Value of Sub-loans provided by PFIs through the project LoC | 0.00 | 13,000,000 | 782068.81 | Not reported |
| Value of grants awarded to beneficiary firms | 0.00 | 10,000,000 | 3,442,600 | Not reported |
| Value of grants received by beneficiary firms | 0 | 10,000,000 | 1101320.12 | Not reported |
| Increased investment by supported firms to improve climate change adaptation and mitigation in value chains | 0.00 | 28000000.00 | 0.00 | November 30, 2023 |
| Of which women-owned or managed | 0.00 | 30.00 | Not reported | Not reported |
| Share of MSMEs impacted by COVID-19 receiving a grant that survive at project closing | 0.00 | 50.00 | 0.00 | November 30, 2023 |
Ratings6 ratings
| Rating | Value | Date |
|---|---|---|
| ISR Financial Management | Moderately Unsatisfactory | June 17, 2026 |
| ISR Monitoring and Evaluation | Moderately Satisfactory | June 17, 2026 |
| ISR Overall Implementation Progress (IP) | Moderately Unsatisfactory | June 17, 2026 |
| ISR Procurement | Moderately Satisfactory | June 17, 2026 |
| ISR Progress towards achievement of PDO | Moderately Unsatisfactory | June 17, 2026 |
| ISR Project Management | Moderately Unsatisfactory | June 17, 2026 |
Contract awards9 awards
| Supplier | Date | Method | Amount |
|---|---|---|---|
| Name not shown | October 15, 2025 | CDS | 140,000 USD |
| Name not shown | January 21, 2025 | INDV | 875,000 HTG |
| Agriconsulting Europe S.A. (AESA) | October 24, 2024 | QBS | 1,886,500 USD |
| DID | October 18, 2024 | QCBS | 2,000,000 USD |
| ADB Standard Technology | August 5, 2024 | DIR | 50,000 USD |
| Name not shown | July 29, 2024 | INDV | 300,000 HTG |
| A2F Consulting | April 24, 2024 | QCBS | 2,275,000 USD |
| Pan American Devel. Foundation-PADF | December 18, 2023 | QCBS | 7,383,871.24 USD |
| DAVE Grace & Associates | October 24, 2023 | QCBS | 635,119 USD |
Funds passed on24 transactions
| Receiver | Transaction | Date | US$ millions |
|---|---|---|---|
| Ministry of the Economy and Finance | Disbursement | June 30, 2026 | 1.5 |
| Ministry of the Economy and Finance | Disbursement | April 30, 2026 | 0.6 |
| Ministry of the Economy and Finance | Disbursement | March 31, 2026 | 0.4 |
| Ministry of the Economy and Finance | Disbursement | February 28, 2026 | 1.5 |
| Ministry of the Economy and Finance | Disbursement | September 30, 2025 | 2.0 |
| Ministry of the Economy and Finance | Disbursement | August 31, 2025 | 0.7 |
| Ministry of the Economy and Finance | Disbursement | June 30, 2025 | 0.3 |
| Ministry of the Economy and Finance | Disbursement | May 31, 2025 | 0.2 |
| Ministry of the Economy and Finance | Commitment | April 30, 2025 | −5.4 |
| Ministry of the Economy and Finance | Disbursement | March 31, 2025 | 0.2 |
| Ministry of the Economy and Finance | Disbursement | February 28, 2025 | 1.3 |
| Ministry of the Economy and Finance | Disbursement | January 31, 2025 | 0.6 |
| Ministry of the Economy and Finance | Disbursement | December 31, 2024 | 10.2 |
| Ministry of the Economy and Finance | Disbursement | August 31, 2024 | 0.1 |
| Ministry of the Economy and Finance | Disbursement | June 30, 2024 | 0.2 |
| Ministry of the Economy and Finance | Disbursement | May 31, 2024 | 0.5 |
| Ministry of the Economy and Finance | Disbursement | February 29, 2024 | 0.5 |
| Ministry of the Economy and Finance | Disbursement | December 31, 2023 | 0.8 |
| Ministry of the Economy and Finance | Disbursement | July 31, 2023 | 1.1 |
| Ministry of the Economy and Finance | Disbursement | April 30, 2023 | <0.1 |
| Ministry of the Economy and Finance | Disbursement | March 31, 2023 | 0.6 |
| Ministry of the Economy and Finance | Disbursement | October 31, 2022 | 0.9 |
| Ministry of the Economy and Finance | Disbursement | July 31, 2022 | 0.2 |
| Ministry of the Economy and Finance | Commitment | September 30, 2021 | 75.0 |
Identifiers5 identifiers
| System | Identifier | Source |
|---|---|---|
| IATI identifier | 44000-P173743 | IATI |
| IDA credit or grant | IDAD8750 | IDA Statement of Credits and Grants |
| Public investment program line | 1112-1-12-52-32 | Public investment program |
| World Bank loan | IDA-D8750 | World Bank Projects |
| World Bank project | P173743 | Operation record |
Where sources differ1 field
| Field | Source | Value | Used |
|---|---|---|---|
| Commitment | IDA Statement of Credits and Grants | US$51.4 million | ✓ |
| Commitment | IATI | US$69.6 million | |
| Commitment | World Bank Projects | US$50.4 million |
Partner documents61 documents
- Record on projects.worldbank.org, projects.worldbank.org
- Official Documents- Agreement Providing for the Amendment and Restatement of the Financing Agreement for Grant D875-HT.pdf, September 10, 2026, documents.worldbank.org
- Disclosable Restructuring Paper - Private Sector Jobs and Economic Transformation (PSJET) - P173743, August 20, 2026, documents.worldbank.org
- Disclosable Version of the ISR - Private Sector Jobs and Economic Transformation (PSJET) - P173743 - Sequence No : 8, June 17, 2026, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN - P173743 - Private Sector Jobs and Economic Transformation (PSJET) - Audited Financial Statement, May 17, 2026, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P173743- Private Sector Jobs and Economic Transformation (PSJET) - Procurement Plan, March 24, 2026, documents.worldbank.org
- Disclosable Version of the ISR - Private Sector Jobs and Economic Transformation (PSJET) - P173743 - Sequence No : 7, November 18, 2025, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P173743- Private Sector Jobs and Economic Transformation (PSJET) - Procurement Plan, September 30, 2025, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P173743- Private Sector Jobs and Economic Transformation (PSJET) - Procurement Plan, September 24, 2025, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P173743- Private Sector Jobs and Economic Transformation (PSJET) - Procurement Plan, July 30, 2025, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN - P173743 - Private Sector Jobs and Economic Transformation (PSJET) - Audited Financial Statement, April 28, 2025, documents.worldbank.org
- Disclosable Version of the ISR - Private Sector Jobs and Economic Transformation (PSJET) - P173743 - Sequence No : 6, April 19, 2025, documents.worldbank.org
- Disclosable Version of the ISR - Private Sector Jobs and Economic Transformation (PSJET) - P173743 - Sequence No : 6, April 19, 2025, documents.worldbank.org
- Official Documents- Corrigendum Letter to the First Amendment to the Financing Agreement for Grant D875-HT.pdf, April 15, 2025, documents.worldbank.org
- Official Documents- First Amendment to the Financing Agreement for Grant D875-HT.pdf, March 28, 2025, documents.worldbank.org
- Official Documents- Second Restatement of the Disbursement and Financial Information Letter for Grant D875-HT.pdf, March 26, 2025, documents.worldbank.org
- Disclosable Restructuring Paper - Private Sector Jobs and Economic Transformation (PSJET) - P173743, March 14, 2025, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P173743- Private Sector Jobs and Economic Transformation (PSJET) - Procurement Plan, March 13, 2025, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P173743- Private Sector Jobs and Economic Transformation (PSJET) - Procurement Plan, January 27, 2025, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN - P173743 - Private Sector Jobs and Economic Transformation (PSJET) - Audited Financial Statement, January 12, 2025, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P173743- Private Sector Jobs and Economic Transformation (PSJET) - Procurement Plan, December 2, 2024, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P173743- Private Sector Jobs and Economic Transformation (PSJET) - Procurement Plan, November 20, 2024, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P173743- Private Sector Jobs and Economic Transformation (PSJET) - Procurement Plan, August 12, 2024, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P173743- Private Sector Jobs and Economic Transformation (PSJET) - Procurement Plan, July 30, 2024, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P173743- Private Sector Jobs and Economic Transformation (PSJET) - Procurement Plan, July 30, 2024, documents.worldbank.org
- Disclosable Version of the ISR - Private Sector Jobs and Economic Transformation (PSJET) - P173743 - Sequence No : 5, June 25, 2024, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P173743- Private Sector Jobs and Economic Transformation (PSJET) - Procurement Plan, March 15, 2024, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P173743- Private Sector Jobs and Economic Transformation (PSJET) - Procurement Plan, February 11, 2024, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P173743- Private Sector Jobs and Economic Transformation (PSJET) - Procurement Plan, January 30, 2024, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P173743- Private Sector Jobs and Economic Transformation (PSJET) - Procurement Plan, January 17, 2024, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P173743- Private Sector Jobs and Economic Transformation (PSJET) - Procurement Plan, January 16, 2024, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P173743- Private Sector Jobs and Economic Transformation (PSJET) - Procurement Plan, January 8, 2024, documents.worldbank.org
- Disclosable Version of the ISR - Private Sector Jobs and Economic Transformation (PSJET) - P173743 - Sequence No : 04, December 19, 2023, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P173743- Private Sector Jobs and Economic Transformation (PSJET) - Procurement Plan, December 4, 2023, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P173743- Private Sector Jobs and Economic Transformation (PSJET) - Procurement Plan, November 22, 2023, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P173743- Private Sector Jobs and Economic Transformation (PSJET) - Procurement Plan, November 22, 2023, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P173743- Private Sector Jobs and Economic Transformation (PSJET) - Procurement Plan, July 20, 2023, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P173743- Private Sector Jobs and Economic Transformation (PSJET) - Procurement Plan, June 26, 2023, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P173743- Private Sector Jobs and Economic Transformation (PSJET) - Procurement Plan, June 22, 2023, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P173743- Private Sector Jobs and Economic Transformation (PSJET) - Procurement Plan, June 20, 2023, documents.worldbank.org
- Disclosable Version of the ISR - Private Sector Jobs and Economic Transformation (PSJET) - P173743 - Sequence No : 03, June 8, 2023, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P173743- Private Sector Jobs and Economic Transformation (PSJET) - Procurement Plan, May 12, 2023, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P173743- Private Sector Jobs and Economic Transformation (PSJET) - Procurement Plan, August 12, 2022, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P173743- Private Sector Jobs and Economic Transformation (PSJET) - Procurement Plan, August 8, 2022, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P173743- Private Sector Jobs and Economic Transformation (PSJET) - Procurement Plan, May 11, 2022, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P173743- Private Sector Jobs and Economic Transformation (PSJET) - Procurement Plan, May 4, 2022, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P173743- Private Sector Jobs and Economic Transformation (PSJET) - Procurement Plan, April 4, 2022, documents.worldbank.org
- Disclosable Version of the ISR - Private Sector Jobs and Economic Transformation (PSJET) - P173743 - Sequence No : 01, February 24, 2022, documents.worldbank.org
- Official Documents- Disbursement and Financial Information Letter for Grant D875-HT, October 28, 2021, documents.worldbank.org
- Official Documents- Financing Agreement for Grant D875-HT, October 28, 2021, documents.worldbank.org
- Haiti - Private Sector Jobs and Economic Transformation Project, September 7, 2021, documents.worldbank.org
- Haiti - Private Sector Jobs and Economic Transformation Project, June 14, 2021, documents.worldbank.org
- Environmental and Social Commitment Plan (ESCP) Private Sector Jobs and Economic Transformation (PSJET) (P173743), June 14, 2021, documents.worldbank.org
- Environmental and Social Commitment Plan (ESCP) Private Sector Jobs and Economic Transformation (PSJET) (P173743), April 16, 2021, documents.worldbank.org
- Environmental and Social Management Framework (ESMF) Private Sector Jobs and Economic Transformation (PSJET) (P173743), April 15, 2021, documents.worldbank.org
- Project Information Document - Private Sector Jobs and Economic Transformation (PSJET) - P173743, January 28, 2021, documents.worldbank.org
- Appraisal Environmental and Social Review Summary (ESRS) - Private Sector Jobs and Economic Transformation (PSJET) - P173743, January 26, 2021, documents.worldbank.org
- Environmental and Social Commitment Plan (ESCP) - Private Sector Jobs and Economic Transformation (PSJET) - P173743, January 26, 2021, documents.worldbank.org
- Stakeholder Engagement Plan (SEP) - Private Sector Jobs and Economic Transformation (PSJET) - P173743, January 26, 2021, documents.worldbank.org
- Concept Project Information Document (PID) - Private Sector Jobs and Economic Transformation (PSJET) - P173743, September 18, 2020, documents.worldbank.org
- Concept Environmental and Social Review Summary (ESRS) - Private Sector Jobs and Economic Transformation (PSJET) - P173743, August 19, 2020, documents.worldbank.org
Procurement notices (2)
- Procurement Notices, projects.worldbank.org
- Contract Awards, projects.worldbank.org
Sources
- Partner documents: terms of use set by the publisher
- IATI record (d-portal): terms of use set by the publisher
- IATI: terms of use set by the publisher
- IDA statement of credits and grants (dataset): World Bank data, CC BY 4.0 (https://datacatalog.worldbank.org/public-licenses).
- Transactions: terms of use set by the publisher
- Operation record: terms of use set by the publisher
- Public investment program: terms of use set by the publisher
- World Bank procurement notices: terms of use set by the publisher
- World Bank project page: terms of use set by the publisher
- World Bank documents: terms of use set by the publisher
Data as of October 18, 2026
| Source | Read on |
|---|---|
| IATI | October 18, 2026 |
| IATI | October 18, 2026 |
| IDA Statement of Credits and Grants | October 18, 2026 |
| Public investment program | October 18, 2026 |
| World Bank procurement notices | October 18, 2026 |
| World Bank Projects | October 18, 2026 |
| World Bank documents | October 18, 2026 |
Cite this page
HaitiDocs. Private Sector Jobs and Economic Transformation (PSJET). Partner portfolio, data as of October 18, 2026. https://www.haitidocs.org/portfolio/projects/WB%3AP173743