Data / Partner portfolio / World Bank Group / IDA
Cultural Heritage Preservation and Tourism Sector Support Project
US$ millions unless stated. Haitian fiscal year, October to September. FY2026-27 began October 1, 2026.
Objective
The objectives of the Project are to: (a) increase the attractiveness of the cultural heritage sites in North of Haiti for tourists; (b) improve the living environment for the residents living in North of Haiti; and (c) support the Recipient’s capacity to respond promptly and effectively to an Eligible Emergency, as needed.
As published by World Bank Projects, in its original language.
Description
The objectives of the Cultural Heritage Preservation and Tourism Sector Support Project for Haiti are to: (a) increase the attractiveness of the cultural heritage sites in North of Haiti for tourists; (b) improve the living environment for the residents living in North of Haiti; and (c) support the recipient's capacity to respond promptly and effectively to an eligible emergency, as needed. The project has five components. (1) Physical cultural heritage sites and touristic circuits in the National History Park component will support conservation and management of cultural and natural sites that can drive and service potential tourist demand. (2) Local investments in Dondon, Milot and Cap-Haïtien component will fund investments supporting physical infrastructure of a public goods nature, in the
more
localities adjacent to the historical sites being restored under the project, to support inclusive growth out of tourism development. (3) Inclusive tourism sector development support component will support tourism sector development that leverages the cultural heritage assets in the region through community engagement, tourism planning, product development, and institutional capacity building. (4) Contingent Emergency Response (CER) component will finance a provision of support to respond to an eligible emergency, as needed. (5) Project implementation, monitoring and evaluation component will finance the support to the technical implementation unit and National Cultural Heritage Institute for the project management, monitoring and evaluation, through the provision of goods, consultants' services, training and operating costs.
- Partner
- World Bank Group, IDA
- Sector
- Social protection
- Stage
- Closed since July 29, 2022
- Approval
- May 19, 2014
- Closing
- July 29, 2022
- Instrument
- IBRD/IDA financing, IDA
- Undisbursed gap
- 1.8: the IDA statement values undisbursed credits in special drawing rights at the current exchange rate
- Borrower
- Republic of Haiti
- Implementing agency
- Unite Technique d'Execution
- Effectiveness
- October 6, 2014
- Departments
- Nord
- Last transaction
- January 31, 2024
- Operation ID
- P144614
Life cycle5 stages, 14 dates
Stage history
| Stage | From |
|---|---|
| Planned | July 19, 2012 |
| Approved | May 19, 2014 |
| Under way | May 19, 2014 |
| Closing | July 29, 2022 |
| Closed | July 29, 2022 |
Dated events
| Event | Date | Source |
|---|---|---|
| Concept review | July 19, 2012 | World Bank Projects |
| Disclosure | May 1, 2013 | World Bank Projects |
| Planned start | September 26, 2013 | IATI |
| Appraisal | January 13, 2014 | World Bank Projects |
| Negotiation | March 14, 2014 | World Bank Projects |
| Actual start | May 19, 2014 | IATI |
| Approval | May 19, 2014 | World Bank Projects |
| First commitment | May 19, 2014 | Transactions |
| Effectiveness | October 6, 2014 | World Bank Projects |
| First disbursement | October 31, 2014 | Transactions |
| Last disbursement | June 30, 2022 | Transactions |
| Actual end | July 29, 2022 | IATI |
| Closing date | July 29, 2022 | IATI |
| Completion report due | March 28, 2023 | World Bank Projects |
Undisbursed: US$0.0 million on September 30, 2026, with closing on July 29, 2022.
Financing
Table 1.Financing, US$ millions
| Financier | AmountUS$ millions | Role | Source |
|---|---|---|---|
| IDA Grant | 45.0 | Institution | World Bank Projects |
Table 2.Position at the data date by source (stocks), US$ millions
| This pageUS$ millions | Source | IATIUS$ millions | |
|---|---|---|---|
| Commitment | 19.1 | IDA Statement of Credits and Grants | 21.9 |
| Disbursed | 17.3 | IDA Statement of Credits and Grants | 17.3 |
| Undisbursed | 0.0 | IDA Statement of Credits and Grants | |
| Total cost | 45.0 | World Bank Projects |
World Bank amounts. Approved: Net commitment, the amount approved less cancellations, in US$ at the data date. Disbursed to date: The disbursements of the IDA statement and the Projects API to date, in US$. Undisbursed: The undisbursed balance the IDA statement publishes, in US$ at the data date. IATI column: the commitments and disbursements the partner reports to IATI, converted to US$. Amounts by source
Changes to the operation1 extension, at least 5 restructurings
- Original closing date
- August 31, 2020
- Closing date extensions
- 1
- Extended from August 31, 2020 to July 29, 2022 (document of September 30, 2020)
- Restructurings
- at least 5
- June 29, 2018, Level 2, approved by management (document of June 29, 2018) restructuring paper
- June 6, 2020, Level 2, approved by management (document of June 6, 2020) restructuring paper
- August 27, 2020, Level 2, approved by management (document of August 27, 2020) restructuring paper
- October 9, 2021 (document of October 9, 2021) restructuring paper
- March 4, 2022, Level 2, approved by management (document of March 4, 2022) restructuring paper
- Emergency component
- Not reported
New commitments and disbursements by fiscal year
Table 3.New commitments and disbursements by fiscal year (flows), US$ millions
| FY2013-14US$ millions | FY2014-15US$ millions | FY2015-16US$ millions | FY2016-17US$ millions | FY2017-18US$ millions | FY2018-19US$ millions | FY2019-20US$ millions | FY2020-21US$ millions | FY2021-22US$ millions | FY2022-23US$ millions | FY2023-24US$ millions | |
|---|---|---|---|---|---|---|---|---|---|---|---|
| New commitments | 45.0 | Not reported | Not reported | Not reported | Not reported | Not reported | −14.4 | Not reported | −6.4 | Not reported | −5.1 |
| Disbursements | Not reported | 2.3 | 1.5 | 2.0 | 3.0 | 3.7 | Not reported | 3.3 | 2.0 | −0.5 | −0.0 |
| Cumulative disbursements | Not reported | 2.3 | 3.9 | 5.9 | 8.9 | 12.5 | Not reported | 15.8 | 17.8 | 17.3 | 17.3 |
Records and documents
Transactions22 records, May 19, 2014 to January 31, 2024
Table 4.Transactions, US$ millions
| Date | Measure | AmountUS$ millions | Source | Method |
|---|---|---|---|---|
| May 19, 2014 | Commitment | 45.0 | IDA Statement of Credits and Grants | credit original principal at board approval |
| June 30, 2020 | Commitment | −6.0 | IDA Statement of Credits and Grants | cancellation: increase in cumulative cancelled amount between snapshots (non-USD credit: includes exchange revaluation) |
| September 30, 2020 | Commitment | −8.5 | IDA Statement of Credits and Grants | cancellation: increase in cumulative cancelled amount between snapshots (non-USD credit: includes exchange revaluation) |
| March 31, 2022 | Commitment | −6.4 | IDA Statement of Credits and Grants | cancellation: increase in cumulative cancelled amount between snapshots (non-USD credit: includes exchange revaluation) |
| January 31, 2024 | Commitment | −5.1 | IDA Statement of Credits and Grants | cancellation: increase in cumulative cancelled amount between snapshots (non-USD credit: includes exchange revaluation) |
| October 31, 2014 | Disbursements | 1.3 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| January 31, 2015 | Disbursements | 1.0 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| October 31, 2015 | Disbursements | 1.5 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| February 28, 2017 | Disbursements | 2.0 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| July 31, 2018 | Disbursements | 3.0 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| June 30, 2019 | Disbursements | 3.0 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| August 31, 2019 | Disbursements | 0.7 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| January 31, 2021 | Disbursements | 1.0 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| April 30, 2021 | Disbursements | 0.5 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| May 31, 2021 | Disbursements | 0.8 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| August 31, 2021 | Disbursements | 0.4 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| September 30, 2021 | Disbursements | 0.7 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| April 30, 2022 | Disbursements | 1.0 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| June 30, 2022 | Disbursements | 1.0 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| May 31, 2023 | Disbursements | −0.4 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| June 30, 2023 | Disbursements | −0.1 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| November 30, 2023 | Disbursements | −0.0 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
Terms4 of 6 reported
- Finance type
- 110 Standard grant
- Flow type
- Not reported
- Aid type
- C01 Project-type interventions
- Tied status
- 5 Untied
- Collaboration type
- 2 Multilateral inflows
- Humanitarian
- Not reported
Locations1 department, 3 places named, 6 places with coordinates
| Departments | Nord |
| Places named by the source | Cap-Haïtien, Dondon, Milot |
| Places with coordinates | 6 |
Results indicators16 indicators
| Indicator | Baseline | Target | Latest value | Date of latest value |
|---|---|---|---|---|
| Activities supported by the Community Event & Tourism Development Grants | 0.00 | 40.00 | 47.00 | July 27, 2022 |
| An interim authority (Autorité de Gestion Provisoire) with staffing acceptable to IDA is established in the PNH-CSSR | No | No | Yes | July 27, 2022 |
| Infrastructure properly operated and maintained following project financing | 0.00 | 3.00 | 3.00 | July 29, 2022 |
| Of which are women | 0.00 | 25.00 | 1.00 | June 19, 2018 |
| Of which are youth | 0.00 | 25.00 | 0.00 | June 19, 2018 |
| PNH Management Plan (i) finalized and (ii) under implementation | No | Yes | Yes | July 29, 2022 |
| Streetscapes upgraded in project target areas | 0.00 | 150.00 | 2670.00 | July 29, 2022 |
| Touristic routes developed and promoted through project investments/activities | 0.00 | 2.00 | 2.00 | July 29, 2022 |
| An effective Park Management system is contributing to sustainable development of the park | No | Yes | No | July 29, 2022 |
| Direct project beneficiaries | 0.00 | 13500.00 | 63450.00 | July 27, 2022 |
| Number of entities providing cultural and tourism services in the project areas | 200.00 | 288.00 | 256.00 | July 29, 2022 |
| Number of restored buildings with increased resistance to seismic events | 0.00 | 1.00 | 0.00 | July 29, 2022 |
| Population in project areas satisfied with the quality of infrastructure financed by the project | 0.00 | 75.00 | 76.00 | July 29, 2022 |
| Tickets sold annually to the PNH-CSSR | 12500.00 | 16850.00 | 10500.00 | July 29, 2022 |
| An interim authority (Autorit de Gestion Provisoire) with staffing acceptable to IDA is established in the PNH-CSSR | No | Yes | Yes | July 29, 2022 |
| Female beneficiaries | 0.00 | 35.00 | 0.00 | June 19, 2018 |
Ratings14 ratings
| Rating | Value | Date |
|---|---|---|
| IEG bankqualityofsupervision | Moderately Unsatisfactory | June 28, 2023 |
| IEG evaltype | ES | June 28, 2023 |
| IEG icrquality | Substantial | June 28, 2023 |
| IEG mequality | Modest | June 28, 2023 |
| IEG outcome | Moderately Unsatisfactory | June 28, 2023 |
| IEG overallbankperf | Moderately Unsatisfactory | June 28, 2023 |
| ICR outratingind | Moderately Unsatisfactory | March 28, 2023 |
| ICR overallrating | Moderately Satisfactory | March 28, 2023 |
| ISR Financial Management | Satisfactory | July 29, 2022 |
| ISR Monitoring and Evaluation | Moderately Satisfactory | July 29, 2022 |
| ISR Overall Implementation Progress (IP) | Moderately Unsatisfactory | July 29, 2022 |
| ISR Procurement | Moderately Satisfactory | July 29, 2022 |
| ISR Progress towards achievement of PDO | Moderately Unsatisfactory | July 29, 2022 |
| ISR Project Management | Moderately Unsatisfactory | July 29, 2022 |
Contract awards18 awards
| Supplier | Date | Method | Amount |
|---|---|---|---|
| Name not shown | February 7, 2022 | INDV | 11,833.01 USD |
| CECOM Consultants S. A. | February 7, 2022 | CQS | 4,605,074.45 Gourde haïtienne |
| CECOM Consultants S. A. | February 7, 2022 | CQS | 80,000 USD |
| Techniplan SRL | February 7, 2022 | CQS | Not reported |
| We Architects | January 17, 2022 | QCBS | 377,685.02 USD |
| Expertise en Travaux d'Amnagement et de Construction (Extraco S.A) | January 4, 2022 | DIR | 17,059,764.49 HTG |
| Office STAR | August 30, 2021 | RFQ | 573,789.17 HTG |
| Ficcas (Firme Conseils Architecture de Construction et de Suoervision) | August 30, 2021 | RFQ | 69,471,833.53 HTG |
| Digitalkap | August 11, 2021 | RFQ | 68,301.2 USD |
| Diagnostic & Development Group (DDG) | August 3, 2021 | CDS | 16,295,532 Gourde hatienne |
| Name not shown | July 29, 2021 | INDV | 27,175.59 USD |
| Universal Motors S.A. | April 7, 2021 | RFQ | 25,605,000 HTG |
| Saniclean S.A. | March 10, 2021 | RFQ | 1,125,611.3 HTG |
| Name not shown | March 1, 2021 | RFQ | 986,850 HTG |
| BARGEC | October 14, 2020 | DIR | 11,740,019.32 HTG |
| L'Atelier | October 13, 2020 | DIR | 6,997,683 HTG |
| BARGEC | August 24, 2020 | DIR | 11,286.09 USD |
| Name not shown | August 14, 2020 | INDV | 4,500 USD |
Funds passed on22 transactions
| Receiver | Transaction | Date | US$ millions |
|---|---|---|---|
| Unite Technique d'Execution | Commitment | January 31, 2024 | −4.3 |
| Unite Technique d'Execution | Disbursement | November 30, 2023 | −0.0 |
| Unite Technique d'Execution | Disbursement | June 30, 2023 | −0.1 |
| Unite Technique d'Execution | Disbursement | May 31, 2023 | −0.4 |
| Unite Technique d'Execution | Disbursement | June 30, 2022 | 1.0 |
| Unite Technique d'Execution | Disbursement | April 30, 2022 | 1.0 |
| Unite Technique d'Execution | Commitment | March 31, 2022 | −5.8 |
| Unite Technique d'Execution | Disbursement | September 30, 2021 | 0.7 |
| Unite Technique d'Execution | Disbursement | August 31, 2021 | 0.4 |
| Unite Technique d'Execution | Disbursement | May 31, 2021 | 0.8 |
| Unite Technique d'Execution | Disbursement | April 30, 2021 | 0.5 |
| Unite Technique d'Execution | Disbursement | January 31, 2021 | 1.0 |
| Unite Technique d'Execution | Commitment | September 30, 2020 | −7.8 |
| Unite Technique d'Execution | Commitment | June 30, 2020 | −5.3 |
| Unite Technique d'Execution | Disbursement | August 31, 2019 | 0.7 |
| Unite Technique d'Execution | Disbursement | June 30, 2019 | 3.0 |
| Unite Technique d'Execution | Disbursement | July 31, 2018 | 3.0 |
| Unite Technique d'Execution | Disbursement | February 28, 2017 | 2.0 |
| Unite Technique d'Execution | Disbursement | October 31, 2015 | 1.5 |
| Unite Technique d'Execution | Disbursement | January 31, 2015 | 1.0 |
| Unite Technique d'Execution | Disbursement | October 31, 2014 | 1.3 |
| Unite Technique d'Execution | Commitment | May 31, 2014 | 45.0 |
Identifiers4 identifiers
| System | Identifier | Source |
|---|---|---|
| IATI identifier | 44000-P144614 | IATI |
| IDA credit or grant | IDAH9440 | IDA Statement of Credits and Grants |
| World Bank loan | IDA-H9440 | World Bank Projects |
| World Bank project | P144614 | Operation record |
Where sources differ2 fields
| Field | Source | Value | Used |
|---|---|---|---|
| Commitment | IDA Statement of Credits and Grants | US$19.1 million | ✓ |
| Commitment | IATI | US$21.9 million | |
| Commitment | World Bank Projects | US$45.0 million | |
| Status | World Bank Projects | Closed | ✓ |
| Status | IATI | Active |
Partner documents58 documents
- Record on projects.worldbank.org, projects.worldbank.org
- Haiti - HT Cultural Heritage and Tourism Sector, June 28, 2023, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN - P144614 - Cultural Heritage Preservation and Tourism Sector Support Project - Audited Financial Statement, March 31, 2023, documents.worldbank.org
- Haiti - Cultural Heritage Preservation and Tourism Sector Support Project, March 19, 2023, documents.worldbank.org
- Disclosable Version of the ISR - Cultural Heritage Preservation and Tourism Sector Support Project - P144614 - Sequence No : 16, July 29, 2022, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P144614- Cultural Heritage Preservation and Tourism Sector Support Project - Procurement Plan, May 9, 2022, documents.worldbank.org
- Haiti - - P144614 - Cultural Heritage Preservation and Tourism Sector Support Project - Audited Financial Statement, May 2, 2022, documents.worldbank.org
- Disclosable Restructuring Paper - Cultural Heritage Preservation and Tourism Sector Support Project - P144614, March 4, 2022, documents.worldbank.org
- Disclosable Version of the ISR - Cultural Heritage Preservation and Tourism Sector Support Project - P144614 - Sequence No : 15, December 20, 2021, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P144614- Cultural Heritage Preservation and Tourism Sector Support Project - Procurement Plan, December 9, 2021, documents.worldbank.org
- Official Documents- Amendment to the Financing Agreement for Grant H944-HT, October 18, 2021, documents.worldbank.org
- Disclosable Restructuring Paper - Cultural Heritage Preservation and Tourism Sector Support Project - P144614, October 9, 2021, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P144614- Cultural Heritage Preservation and Tourism Sector Support Project - Procurement Plan, September 6, 2021, documents.worldbank.org
- Disclosable Version of the ISR - Cultural Heritage Preservation and Tourism Sector Support Project - P144614 - Sequence No : 14, June 30, 2021, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P144614- Cultural Heritage Preservation and Tourism Sector Support Project - Procurement Plan, June 7, 2021, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN - P144614 - Cultural Heritage Preservation and Tourism Sector Support Project - Audited Financial Statement, May 20, 2021, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P144614- Cultural Heritage Preservation and Tourism Sector Support Project - Procurement Plan, February 17, 2021, documents.worldbank.org
- Disclosable Version of the ISR - Cultural Heritage Preservation and Tourism Sector Support Project - P144614 - Sequence No : 13, December 23, 2020, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P144614- Cultural Heritage Preservation and Tourism Sector Support Project - Procurement Plan, December 1, 2020, documents.worldbank.org
- Disclosable Restructuring Paper - Cultural Heritage Preservation and Tourism Sector Support Project - P144614, August 27, 2020, documents.worldbank.org
- Disclosable Version of the ISR - Cultural Heritage Preservation and Tourism Sector Support Project - P144614 - Sequence No : 12, June 21, 2020, documents.worldbank.org
- Disclosable Restructuring Paper - Cultural Heritage Preservation and Tourism Sector Support Project - P144614, June 6, 2020, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P144614- Cultural Heritage Preservation and Tourism Sector Support Project - Procurement Plan, April 27, 2020, documents.worldbank.org
- Haiti - P144614 - Cultural Heritage Preservation and Tour. Sect. Support - Audit report financial statements for the year ended September 30 2019, April 26, 2020, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P144614- Cultural Heritage Preservation and Tourism Sector Support Project - Procurement Plan, March 27, 2020, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P144614- Cultural Heritage Preservation and Tourism Sector Support Project - Procurement Plan, February 11, 2020, documents.worldbank.org
- Disclosable Version of the ISR - Cultural Heritage Preservation and Tourism Sector Support Project - P144614 - Sequence No : 11, January 8, 2020, documents.worldbank.org
- Disclosable Version of the ISR - Cultural Heritage Preservation and Tourism Sector Support Project - P144614 - Sequence No : 10, June 15, 2019, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P144614- Cultural Heritage Preservation and Tourism Sector Support Project - Procurement Plan, June 4, 2019, documents.worldbank.org
- Haiti - P144614 - Cultural Heritage Preservation and Tour. Sect. Support - Audit report financial statements for the year ended September 30 2018, March 31, 2019, documents.worldbank.org
- Disclosable Version of the ISR - Cultural Heritage Preservation and Tourism Sector Support Project - P144614 - Sequence No : 09, November 19, 2018, documents.worldbank.org
- Official Documents- Amendment to the Financing Agreement for Grant H944-HT, July 12, 2018, documents.worldbank.org
- Disclosable Restructuring Paper - Cultural Heritage Preservation and Tourism Sector Support Project - P144614, June 29, 2018, documents.worldbank.org
- Disclosable Version of the ISR - Cultural Heritage Preservation and Tourism Sector Support Project - P144614 - Sequence No : 08, June 27, 2018, documents.worldbank.org
- Disclosable Version of the ISR - Cultural Heritage Preservation and Tourism Sector Support Project - P144614 - Sequence No : 07, December 31, 2017, documents.worldbank.org
- Haiti - Cultural Heritage Preservation and Tourism Sector Support Project : P144614 - Implementation Status Results Report : Sequence 06, June 30, 2017, documents.worldbank.org
- Haiti - Cultural Heritage Preservation and Tourism Sector Support Project : P144614 - Implementation Status Results Report : Sequence 05, January 6, 2017, documents.worldbank.org
- Haiti - Cultural Heritage Preservation and Tourism Sector Support Project : P144614 - Implementation Status Results Report : Sequence 04, June 30, 2016, documents.worldbank.org
- Haiti - Cultural Heritage Preservation and Tourism Sector Support Project : P144614 - Implementation Status Results Report : Sequence 03, September 7, 2015, documents.worldbank.org
- Haiti - Cultural Heritage Preservation and Tourism Sector Support Project : technical mission - July 13 to 17, 2015 : Haïti - Préservation du Patrimoine et Appui aux Services Touristiques (PAST) : mission technique - 13 au 17 Juillet, 2015, July 13, 2015, documents.worldbank.org
- Haiti - Cultural Heritage Preservation and Tourism Sector Support Project : P144614 - Implementation Status Results Report : Sequence 02, March 25, 2015, documents.worldbank.org
- Haiti - Cultural Heritage Preservation and Tourism Sector Support Project : P144614 - Implementation Status Results Report : Sequence 01, August 27, 2014, documents.worldbank.org
- Official Documents- Disbursement Letter for Grant H944-HT (Closing Package), July 9, 2014, documents.worldbank.org
- Official Documents- Supplemental Letter Ref. Financial Data for Grant H944-HT (Closing Package), July 9, 2014, documents.worldbank.org
- Official Documents- Financing Agreement for Grant H944-HT (Closing Package), July 9, 2014, documents.worldbank.org
- Official Documents- Recommendation of Statutory Committee for Grant H944-HT (Closing Package), April 28, 2014, documents.worldbank.org
- Haiti - Cultural Heritage Preservation and Tourism Sector Support Project, April 10, 2014, documents.worldbank.org
- Haiti - Cultural Heritage Preservation and Tourism Sector Development Support in the North of Haiti Project : environmental assessment (Vol. 3 of 4), March 13, 2014, documents.worldbank.org
- Integrated Safeguards Data Sheet (Appraisal Stage) - Cultural Heritage Preservation and Tourism Sector Support Project - P144614, January 15, 2014, documents.worldbank.org
- Project Information Document (Appraisal Stage) - Cultural Heritage Preservation and Tourism Sector Support Project - P144614, January 9, 2014, documents.worldbank.org
- Haiti - Cultural Heritage Preservation and Tourism Sector Development Support in the North of Haiti Project : environmental assessment (Vol. 4 of 4) : Cadre de gestion environnementale et sociale, December 5, 2013, documents.worldbank.org
- Haiti - Cultural Heritage Preservation and Tourism Sector Development Support in the North of Haiti Project : environmental assessment (Vol. 2 of 4) : Plan de gestion environnementale, December 5, 2013, documents.worldbank.org
- Haiti - Cultural Heritage Preservation and Tourism Sector Development Support Project : resettlement plan : Haiti - Preservation du Patrimoine Culturel et Developpement du Secteur du Tourisme Projet d'Appui : plan de reinstallation, December 1, 2013, documents.worldbank.org
- Haiti - Cultural Heritage Preservation and Tourism Sector Development Support in the North of Haiti Project : environmental assessment (Vol. 1 of 4) : Cadre de gestion du patrimoine culturel physique, December 1, 2013, documents.worldbank.org
- Official Documents- Disbursement Letter for Advance for Q859, May 28, 2013, documents.worldbank.org
- Official Documents - Agreement for Advance for Q859, May 28, 2013, documents.worldbank.org
- Integrated Safeguards Data Sheet (Concept Stage) - Heritage and Sustainable Tourism in the North Region of Haiti - P144614, May 22, 2013, documents.worldbank.org
- Project Information Document (Concept Stage) - Heritage and Sustainable Tourism in the North Region of Haiti - P144614, April 30, 2013, documents.worldbank.org
Procurement notices (2)
- Procurement Notices, projects.worldbank.org
- Contract Awards, projects.worldbank.org
Sources
- IATI record (d-portal): terms of use set by the publisher
- IATI: terms of use set by the publisher
- IDA statement of credits and grants (dataset): World Bank data, CC BY 4.0 (https://datacatalog.worldbank.org/public-licenses).
- Transactions: terms of use set by the publisher
- Operation record: terms of use set by the publisher
- World Bank procurement notices: terms of use set by the publisher
- World Bank project page: terms of use set by the publisher
- World Bank documents: terms of use set by the publisher
Data as of October 18, 2026
| Source | Read on |
|---|---|
| IATI | October 18, 2026 |
| IATI | October 18, 2026 |
| IDA Statement of Credits and Grants | October 18, 2026 |
| World Bank procurement notices | October 18, 2026 |
| World Bank Projects | October 18, 2026 |
| World Bank documents | October 18, 2026 |
Cite this page
HaitiDocs. Cultural Heritage Preservation and Tourism Sector Support Project. Partner portfolio, data as of October 18, 2026. https://www.haitidocs.org/portfolio/projects/WB%3AP144614