Objektif
The objectives of the Project are to: (a) support the development of the Centre Artibonite Loop region, primarily by enhancing all-weather connectivity and logistics for producers, and the region’s resilience to climate change; and (b) support the Recipient’s capacity to respond promptly and effectively to an Eligible Emergency, as needed.
Jan Pwojè Bank Mondyal pibliye l, nan lang orijinal li.
Deskripsyon
The development objectives of the Center and Artibonite Regional Development Project for Haiti are to: (a) support the development of the Centre Artibonite Loop (CAL) region, primarily by enhancing all-weather connectivity and logistics for producers, and the region's resilience to climate change; and (b) support the recipient's capacity to respond promptly and effectively to an eligible emergency, as needed. The project comprises of five components. The first component, enhancing logistics, transport connectivity, and climate resilience aims to link the CAL region to economic growth poles outside the region, and to improve the internal connectivity of the CAL, by increasing all-weather access to agricultural production areas, markets and services, and by increasing the rural access index and the macro-resilience of the
plis
road network to natural events and effects of climate change. It has following four sub-components: (i) improving the structuring road network; (ii) improving the rural road network; (iii) strengthening road maintenance capacity and mechanisms at the local level; and (iv) supporting the application of best practices addressing the issue of climate resilience. The second component will improve the infrastructure and management capacity of key selected urban markets (2 to 4) and rural markets (4 to 8) to link agricultural producers with the roads provided under first component. It comprises of following two sub-components: (i) urban markets and associated facilities; and (ii) rural markets. The third component, supporting the development of regional knowledge, planning capacity, and local participation aims to support the Government of Haiti (GoH), municipalities, and local stakeholders to effectively plan and make consensual decisions. It has following two sub-components: (i) improving regional knowledge; and (ii) supporting the development of regional planning capacity and local participation. The fourth component, contingent emergency response include triggers and conditions for the use of funds, included in most investment projects in Haiti in keeping with the recommendations of the 2011 World Development Report (WDR) on conflict, security and development, and with the operational experience acquired in Haiti since the 2010 earthquake. The fifth component, project implementation, monitoring and evaluation will finance the activities of the implementing agency for the project: the unite technique d'execution (UTE), an existing project implementation unit (PIU) under the responsibility of Ministry of Economy and Finance (MEF).
- Patnè
- World Bank Group, World Bank
- Sektè
- Transpò
- Etap
- Fèmen depi 31 out 2020
- Apwobasyon
- 19 me 2014
- Fèmen
- 31 out 2020
- Enstriman
- Finansman BIRD/IDA, Grants
- Diferans nan sa ki poko dekese
- 9.8: fon fidisyè yo pa nan eta IDA a, ki bay montan ki poko dekese pou lajan IDA sèlman; eta IDA a evalye kredi ki poko dekese an dwa tiraj espesyal yo nan to chanj jodi a
- Anprentè
- Ministry of Economy and Finance
- Ajans egzekisyon
- Unite Centale d'Execution (UCE),Unite Technique d'Execution (UTE)
- Antre an vigè
- 6 oktòb 2014
- Depatman
- Lwès, Nò, Sant, Latibonit
- Dènye tranzaksyon
- 30 jen 2021
- Idantifyan operasyon an
- P133352
Sik lavi4 etap, 12 dat
Istwa etap yo
| Etap | Depi |
|---|---|
| Apwouve | 19 me 2014 |
| An kou | 19 me 2014 |
| Ap fèmen | 31 out 2020 |
| Fèmen | 31 out 2020 |
Evènman ki gen dat
| Evènman | Dat | Sous |
|---|---|---|
| Kòmansman prevwa | 26 desanm 2013 | IATI |
| Evalyasyon davans | 13 janvye 2014 | Pwojè Bank Mondyal |
| Negosyasyon | 2 avril 2014 | Pwojè Bank Mondyal |
| Kòmansman reyèl | 19 me 2014 | IATI |
| Apwobasyon | 19 me 2014 | Pwojè Bank Mondyal |
| Premye angajman | 19 me 2014 | Tranzaksyon |
| Antre an vigè | 6 oktòb 2014 | Pwojè Bank Mondyal |
| Premye dekèsman | 31 oktòb 2014 | Tranzaksyon |
| Fen reyèl | 31 out 2020 | IATI |
| Dat fèmti | 31 out 2020 | IATI |
| Dènye dekèsman | 31 desanm 2020 | Tranzaksyon |
| Rapò fen atann | 27 fevriye 2021 | Pwojè Bank Mondyal |
Pa dekèse: 0.0 milyon dola ameriken jiska 30 septanm 2026, dat fèmti 31 out 2020.
Finansman
Tablo 1.Finansman, milyon dola ameriken
| Finansè | MontanMilyon dola ameriken | Wòl | Sous |
|---|---|---|---|
| IDA Grant | 50.0 | Enstitisyon | Pwojè Bank Mondyal |
| Strategic Climate Fund Grant | 8.0 | Fon fidisyè | Pwojè Bank Mondyal |
Tablo 2.Pozisyon nan dat done yo pa sous (stòk), milyon dola ameriken
| Paj sa aMilyon dola ameriken | Sous | IATIMilyon dola ameriken | |
|---|---|---|---|
| Angajman | 25.3 | IDA, eta kredi ak don | 20.8 |
| Dekèse | 15.5 | IDA, eta kredi ak don | 15.5 |
| Pa dekèse | 0.0 | IDA, eta kredi ak don | |
| Pri total | 58.0 | Pwojè Bank Mondyal |
Montan Bank Mondyal. Apwouve: Angajman nèt, montan apwouve mwens anilasyon yo, an US$ nan dat done yo. Dekèse jiska jodi a: Dekèsman deklarasyon IDA a ak API pwojè yo jiska jodi a, an US$. Pa dekèse: Balans ki pa dekèse deklarasyon IDA a pibliye, an US$ nan dat done yo. Kolòn IATI: angajman ak dekèsman patnè a pibliye nan IATI, konvèti an US$. Montan yo dapre sous la
Chanjman nan operasyon an1 pwolongasyon, omwen 2 restriktirasyon
- Dat fèmti orijinal
- 28 fevriye 2020
- Pwolongasyon dat fèmti
- 1
- Pwolonje soti 28 fevriye 2020 rive 31 out 2020 (dokiman 31 mas 2020)
- Restriktirasyon
- omwen 2
- 27 jen 2018 (dokiman 27 jen 2018) dokiman restriktirasyon
- 25 fevriye 2020 (dokiman 25 fevriye 2020) dokiman restriktirasyon
- Konpozan ijans
- Pa rapòte
Nouvo angajman ak dekèsman pa ane fiskal
Tablo 3.Nouvo angajman ak dekèsman pa ane fiskal (flo), milyon dola ameriken
| FY2013-14Milyon dola ameriken | FY2014-15Milyon dola ameriken | FY2016-17Milyon dola ameriken | FY2017-18Milyon dola ameriken | FY2018-19Milyon dola ameriken | FY2019-20Milyon dola ameriken | FY2020-21Milyon dola ameriken | |
|---|---|---|---|---|---|---|---|
| Nouvo angajman | 58.0 | Pa rapòte | Pa rapòte | Pa rapòte | Pa rapòte | −26.2 | −6.5 |
| Dekèsman | Pa rapòte | 2.5 | 2.0 | 2.0 | 13.8 | −3.0 | −1.9 |
| Dekèsman kimile | Pa rapòte | 2.5 | 4.5 | 6.5 | 20.3 | 17.3 | 15.5 |
Fich ak dokiman
Tranzaksyon19 liy, 19 me 2014 rive 30 jen 2021
Tablo 4.Tranzaksyon, milyon dola ameriken
| Dat | Mezi | MontanMilyon dola ameriken | Sous | Metòd |
|---|---|---|---|---|
| 19 me 2014 | Angajman | 50.0 | IDA, eta kredi ak don | credit original principal at board approval |
| 19 me 2014 | Angajman | 8.0 | Pwojè Bank Mondyal | trust funds in the Projects API financier list, not in the IDA statement, at the board approval date |
| 31 mas 2020 | Angajman | −26.2 | IDA, eta kredi ak don | cancellation: increase in cumulative cancelled amount between snapshots (non-USD credit: includes exchange revaluation) |
| 30 jen 2021 | Angajman | −6.5 | IDA, eta kredi ak don | cancellation: increase in cumulative cancelled amount between snapshots (non-USD credit: includes exchange revaluation) |
| 31 oktòb 2014 | Dekèsman | 0.5 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 31 janvye 2015 | Dekèsman | 1.0 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 31 jiyè 2015 | Dekèsman | 1.0 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 31 oktòb 2016 | Dekèsman | 1.0 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 31 me 2017 | Dekèsman | 1.0 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 31 jiyè 2018 | Dekèsman | 2.0 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 31 oktòb 2018 | Dekèsman | 3.0 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 30 novanm 2018 | Dekèsman | 8.5 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 31 jiyè 2019 | Dekèsman | 2.3 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 31 mas 2020 | Dekèsman | 0.9 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 31 out 2020 | Dekèsman | −3.9 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 31 desanm 2020 | Dekèsman | 0.8 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 28 fevriye 2021 | Dekèsman | −1.9 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 31 mas 2021 | Dekèsman | −0.7 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 30 avril 2021 | Dekèsman | −0.0 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
Kondisyon4 sou 6 rapòte
- Kalite finansman
- 110 Don estanda
- Kalite koule
- Pa rapòte
- Kalite èd
- C01 Entèvansyon kalite pwojè
- Èd mare oswa pa mare
- 5 Pa mare
- Kalite kolaborasyon
- 2 Apò miltilateral k ap antre
- Imanitè
- Pa rapòte
Kote4 depatman, 4 kote nonmen, 8 kote ki gen kowòdone
| Depatman | Lwès, Nò, Sant, Latibonit |
| Kote sous la nonmen | Centre, Departement de l'Artibonite, Departement de l'Ouest, Nord |
| Kote ki gen kowòdone | 8 |
Endikatè rezilta13 endikatè
| Endikatè | Valè referans | Sib | Dènye valè | Dat dènye valè |
|---|---|---|---|---|
| Number of Road Maintenance Centers build or rehabilitated | 0.00 | 1.00 | 0.00 | 31 out 2020 |
| Number of events/activities dedicated for knowledge dissemination and consultation | 0.00 | 0.00 | 12.00 | 31 out 2020 |
| Number of people trained within selected communities on basic Rural Road Maintenance (disaggregated by gender) | 0.00 | 300.00 | 284.00 | 28 fevriye 2020 |
| Roads rehabilitated, Non-rural | 0.00 | 60.00 | 55.87 | 31 out 2020 |
| Roads rehabilitated, Rural | 0.00 | 40.00 | 30.00 | 31 out 2020 |
| Spot interventions to enhance all-weather and resilient connectivity | 0.00 | 44.00 | 64.00 | 31 out 2020 |
| Urban plans developed and consulted with Local officials and local stakeholders | 0.00 | 3.00 | 2.00 | 31 out 2020 |
| disaggregated by gender, in % of women | 0.00 | 0.00 | Pa rapòte | Pa rapòte |
| Number of producers and users serviced by an all-weather-road accessing urban and rural markets. | 0.00 | 0.00 | 123500.00 | 31 out 2020 |
| Share of rural population with access to an all-season road | 39.00 | 45.00 | 44.00 | 28 out 2020 |
| Share of the population in the Project area satisfied with the quality and impact of infrastructure financed by the Project | 0.00 | 0.00 | 97.50 | 30 jen 2020 |
| Female beneficiaries | 0.00 | 0.00 | 0.00 | 18 jiyè 2018 |
| Number of rural people with access to an all-season road | 374400.00 | 0.00 | 0.00 | 18 jiyè 2018 |
Nòt17 nòt
| Nòt | Valè | Dat |
|---|---|---|
| IEG bankqualityofsupervision | Moderately Satisfactory | 21 jen 2021 |
| IEG borrowcompliance | Not Rated | 21 jen 2021 |
| IEG evaltype | ES | 21 jen 2021 |
| IEG icrquality | Substantial | 21 jen 2021 |
| IEG mequality | Modest | 21 jen 2021 |
| IEG outcome | Moderately Unsatisfactory | 21 jen 2021 |
| IEG overallbankperf | Moderately Satisfactory | 21 jen 2021 |
| ICR bankqualityentry | Not Rated | 27 fevriye 2021 |
| ICR banksupervision | Not Rated | 27 fevriye 2021 |
| ICR outratingind | Moderately Unsatisfactory | 27 fevriye 2021 |
| ICR overallrating | Moderately Satisfactory | 27 fevriye 2021 |
| ISR Financial Management | Moderately Satisfactory | 31 out 2020 |
| ISR Monitoring and Evaluation | Moderately Satisfactory | 31 out 2020 |
| ISR Overall Implementation Progress (IP) | Moderately Satisfactory | 31 out 2020 |
| ISR Procurement | Moderately Satisfactory | 31 out 2020 |
| ISR Progress towards achievement of PDO | Moderately Satisfactory | 31 out 2020 |
| ISR Project Management | Moderately Satisfactory | 31 out 2020 |
Kontra yo bay10 kontra
| Founisè | Dat | Metòd | Montan |
|---|---|---|---|
| Civil Design & Construction | 8 jen 2020 | DIR | 894,400 HTG |
| Global Communities | 6 novanm 2019 | FBS | 3,795,000 USD |
| SETEC International | 31 oktòb 2019 | QCBS | 112,348,069.39 HTG |
| SETEC International | 31 oktòb 2019 | QCBS | 41,016.36 USD |
| BETA Ingnieurs-Conseils | 31 oktòb 2019 | QCBS | Pa rapòte |
| Non an pa afiche | 25 avril 2019 | CDS | 4,143,422.11 Haitian Gourdes |
| Non an pa afiche | 15 janvye 2019 | CDS | 7,648,647 Haitian Gourdes |
| Non an pa afiche | 16 novanm 2018 | RFQ | 16,281,998 HTG |
| Non an pa afiche | 16 novanm 2018 | RFQ | 14,425,950 HTG |
| Non an pa afiche | 16 novanm 2018 | RFQ | 15,600,000 HTG |
Lajan ki pase bay lòt18 mouvman
| Benefisyè | Mouvman | Dat | Milyon dola ameriken |
|---|---|---|---|
| Unite Centale d'Execution (UCE); Unite Technique d'Execution (UTE) | Angajman | 30 jen 2021 | −6.0 |
| Unite Centale d'Execution (UCE); Unite Technique d'Execution (UTE) | Dekèsman | 30 avril 2021 | −0.0 |
| Unite Centale d'Execution (UCE); Unite Technique d'Execution (UTE) | Dekèsman | 31 mas 2021 | −0.7 |
| Unite Centale d'Execution (UCE); Unite Technique d'Execution (UTE) | Dekèsman | 28 fevriye 2021 | −1.9 |
| Unite Centale d'Execution (UCE); Unite Technique d'Execution (UTE) | Dekèsman | 31 desanm 2020 | 0.8 |
| Unite Centale d'Execution (UCE); Unite Technique d'Execution (UTE) | Dekèsman | 31 out 2020 | −3.9 |
| Unite Centale d'Execution (UCE); Unite Technique d'Execution (UTE) | Angajman | 31 mas 2020 | −23.2 |
| Unite Centale d'Execution (UCE); Unite Technique d'Execution (UTE) | Dekèsman | 31 mas 2020 | 0.9 |
| Unite Centale d'Execution (UCE); Unite Technique d'Execution (UTE) | Dekèsman | 31 jiyè 2019 | 2.3 |
| Unite Centale d'Execution (UCE); Unite Technique d'Execution (UTE) | Dekèsman | 30 novanm 2018 | 8.5 |
| Unite Centale d'Execution (UCE); Unite Technique d'Execution (UTE) | Dekèsman | 31 oktòb 2018 | 3.0 |
| Unite Centale d'Execution (UCE); Unite Technique d'Execution (UTE) | Dekèsman | 31 jiyè 2018 | 2.0 |
| Unite Centale d'Execution (UCE); Unite Technique d'Execution (UTE) | Dekèsman | 31 me 2017 | 1.0 |
| Unite Centale d'Execution (UCE); Unite Technique d'Execution (UTE) | Dekèsman | 31 oktòb 2016 | 1.0 |
| Unite Centale d'Execution (UCE); Unite Technique d'Execution (UTE) | Dekèsman | 31 jiyè 2015 | 1.0 |
| Unite Centale d'Execution (UCE); Unite Technique d'Execution (UTE) | Dekèsman | 31 janvye 2015 | 1.0 |
| Unite Centale d'Execution (UCE); Unite Technique d'Execution (UTE) | Dekèsman | 31 oktòb 2014 | 0.5 |
| Unite Centale d'Execution (UCE); Unite Technique d'Execution (UTE) | Angajman | 31 me 2014 | 50.0 |
Idantifyan4 idantifyan
| Sistèm | Idantifyan | Sous |
|---|---|---|
| Idantifyan IATI | 44000-P133352 | IATI |
| Kredi oswa don IDA | IDAH9500 | IDA, eta kredi ak don |
| Prè Bank mondyal | IDA-H9500 | Pwojè Bank Mondyal |
| Pwojè Bank mondyal | P133352 | Fich operasyon an |
Kote sous yo pa dakò2 chan
| Chan | Sous | Valè | Itilize |
|---|---|---|---|
| Angajman | IDA, eta kredi ak don | 25.3 milyon dola ameriken | ✓ |
| Angajman | IATI | 20.8 milyon dola ameriken | |
| Angajman | Pwojè Bank Mondyal | 58.0 milyon dola ameriken | |
| Estati | Pwojè Bank Mondyal | Fèmen | ✓ |
| Estati | IATI | Aktif |
Dokiman patnè a64 dokiman
- Fich sou projects.worldbank.org, projects.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN - P133352 - HT Center and Artibonite Regional Development - Audited Financial Statement, 9 jiyè 2021, documents.worldbank.org
- Haiti - HT - Ctr Artibonite Reg Dev., 21 jen 2021, documents.worldbank.org
- Haiti - Center and Artibonite Regional Development Project, 28 fevriye 2021, documents.worldbank.org
- Disclosable Version of the ISR - HT Center and Artibonite Regional Development - P133352 - Sequence No : 12, 1 septanm 2020, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P133352- HT Center and Artibonite Regional Development - Procurement Plan, 17 out 2020, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P133352- HT Center and Artibonite Regional Development - Procurement Plan, 6 out 2020, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P133352- HT Center and Artibonite Regional Development - Procurement Plan, 9 jen 2020, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P133352- HT Center and Artibonite Regional Development - Procurement Plan, 20 me 2020, documents.worldbank.org
- P133352 - Haiti Center and Artibonite Reg. Dev. Proj. - Audit Statements as of Sept. 2019, 19 avril 2020, documents.worldbank.org
- Official Documents- Amendment to the Agreement Providing for the Amendment and Restatement of the Financing Agreement for Grant H950-HT, 27 fevriye 2020, documents.worldbank.org
- Disclosable Restructuring Paper - HT Center and Artibonite Regional Development - P133352, 25 fevriye 2020, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P133352- HT Center and Artibonite Regional Development - Procurement Plan, 21 fevriye 2020, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P133352- HT Center and Artibonite Regional Development - Procurement Plan, 21 fevriye 2020, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P133352- HT Center and Artibonite Regional Development - Procurement Plan, 4 fevriye 2020, documents.worldbank.org
- Disclosable Version of the ISR - HT Center and Artibonite Regional Development - P133352 - Sequence No : 11, 14 janvye 2020, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P133352- HT Center and Artibonite Regional Development - Procurement Plan, 11 novanm 2019, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P133352- HT Center and Artibonite Regional Development - Procurement Plan, 4 septanm 2019, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P133352- HT Center and Artibonite Regional Development - Procurement Plan, 24 jiyè 2019, documents.worldbank.org
- Disclosable Version of the ISR - HT Center and Artibonite Regional Development - P133352 - Sequence No : 10, 5 jiyè 2019, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P133352- HT Center and Artibonite Regional Development - Procurement Plan, 7 jen 2019, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P133352- HT Center and Artibonite Regional Development - Procurement Plan, 14 me 2019, documents.worldbank.org
- P133352 - Haiti Center and Artibonite Reg. Dev. Proj. - Audit Statements as of Sept. 2018, 21 avril 2019, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P133352- HT Center and Artibonite Regional Development - Procurement Plan, 4 avril 2019, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P133352- HT Center and Artibonite Regional Development - Procurement Plan, 20 mas 2019, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P133352- HT Center and Artibonite Regional Development - Procurement Plan, 19 fevriye 2019, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P133352- HT Center and Artibonite Regional Development - Procurement Plan, 7 fevriye 2019, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P133352- HT Center and Artibonite Regional Development - Procurement Plan, 31 janvye 2019, documents.worldbank.org
- Disclosable Version of the ISR - HT Center and Artibonite Regional Development - P133352 - Sequence No : 09, 10 janvye 2019, documents.worldbank.org
- Haiti - Center and Artibonite Regional Development Project : Environmental Assessment (Vol. 3 of 3) : Plan de Gestion Environnementale et Sociale pour le Traitement des Points Critiques sur le Tronçon Titanyen-Saut d’Eau, 1 janvye 2019, documents.worldbank.org
- Haiti - Center and Artibonite Regional Development Project : Resettlement Plan (Vol. 3 of 3) : Plan Succinct de Réinstallation, 1 oktòb 2018, documents.worldbank.org
- Haiti - Center and Artibonite Regional Development Project : Resettlement Plan (Vol. 2 of 3) : Déviation pour Construction des Dalots au Pk 1+083 et au Pk 8+959, 1 out 2018, documents.worldbank.org
- Disclosable Version of the ISR - HT Center and Artibonite Regional Development - P133352 - Sequence No : 08, 1 out 2018, documents.worldbank.org
- Official Documents- Amended and Restated Financing Agreement for Grant H950-HT, 6 jiyè 2018, documents.worldbank.org
- Official Documents- Fiirst Restatement of the Disbursement Letter for Grant H950-HT, 29 jen 2018, documents.worldbank.org
- Disclosable Restructuring Paper - HT Center and Artibonite Regional Development - P133352, 27 jen 2018, documents.worldbank.org
- Haiti - Center and Artibonite Regional Development Project : Resettlement Plan (Vol. 1 of 3) : Plan Succinct de Réinstallation : Traitement des Points Critiques sur le Tronçon RoutierHinche–Maïssade, 1 jen 2018, documents.worldbank.org
- Haiti - Center and Artibonite Regional Development Project : Mid-term Review Mission - 21 February to 2 March and 2 to 11 April, 2018, 11 avril 2018, documents.worldbank.org
- Disclosable Version of the ISR - HT Center and Artibonite Regional Development - P133352 - Sequence No : 07, 2 janvye 2018, documents.worldbank.org
- Haiti - HT Center and Artibonite Regional Development : P133352 - Implementation Status Results Report : Sequence 06, 30 jen 2017, documents.worldbank.org
- Haiti - HT Center and Artibonite Regional Development : P133352 - Implementation Status Results Report : Sequence 05, 3 janvye 2017, documents.worldbank.org
- Haiti - Center and Artibonite Regional Development Project : Environmental Assessment (Vol. 1 of 3) : Plan de gestion environnementale et sociale pour la construction des points critiques sur les deux tronçons Saint-Michel de l’Attalaye et Saint-Raphaël et Hinche-Maïssade, 1 desanm 2016, documents.worldbank.org
- Haiti - HT Center and Artibonite Regional Development : P133352 - Implementation Status Results Report : Sequence 04, 31 me 2016, documents.worldbank.org
- Haiti - HT Center and Artibonite Regional Development : P133352 - Implementation Status Results Report : Sequence 03, 24 novanm 2015, documents.worldbank.org
- Haiti - HT Center and Artibonite Regional Development : P133352 - Implementation Status Results Report : Sequence 02, 12 me 2015, documents.worldbank.org
- Haiti - HT Center and Artibonite Regional Development : P133352 - Implementation Status Results Report : Sequence 01, 11 oktòb 2014, documents.worldbank.org
- Haiti - Center and Artibonite Regional Development Project : Environmental Assessment (Vol. 2 of 3) : Plan de Gestion Environnementale et Sociale (PGES), 7 oktòb 2014, documents.worldbank.org
- Haiti - Center and Artibonite Regional Development Project : environmental assessment : Cadre de gestion environnementale et sociale, 1 oktòb 2014, documents.worldbank.org
- Haiti - Center and Artibonite Regional Development Project : resettlement plan : Cadre de la politique de réinstallation (CPR), 1 septanm 2014, documents.worldbank.org
- Official Documents- Financing Agreement for Grant H950-HT (Closing Package), 9 jiyè 2014, documents.worldbank.org
- Official Documents- Supplemental Letter Ref. Financial Data for Grant H950-HT (Closing Package), 9 jiyè 2014, documents.worldbank.org
- Official Documents- Disbursement Letter for Grant H950-HT (Closing Package), 9 jiyè 2014, documents.worldbank.org
- Official Documents- Recommendation of Statutory Committee for Grant H950-HT and TF017021 (Closing Package), 28 avril 2014, documents.worldbank.org
- Haiti - Center and Artibonite Regional Development Project, 15 avril 2014, documents.worldbank.org
- Official Documents- Amendment to the Disbursement Letter for Advance Q904-HT, 24 mas 2014, documents.worldbank.org
- Project Information Document (Concept Stage) - HT Center and Artibonite Regional Development - P133352, 6 fevriye 2014, documents.worldbank.org
- Official Documents- Agreement for Advance Q904-HT, 4 fevriye 2014, documents.worldbank.org
- Official Documents- Disbursement Letter for Advance Q904-HT, 4 fevriye 2014, documents.worldbank.org
- Haiti - Center and Artibonite Regional Development Project : Integrated Safeguards Data Sheet (Appraisal Stage) - HT Center and Artibonite Regional Development - P133352, 24 janvye 2014, documents.worldbank.org
- Haiti - Center and Artibonite Regional Development Project : Haiti - Projet de developpement regional de la boucle Centre Artibonite, 24 janvye 2014, documents.worldbank.org
- Haiti - Center and Artibonite Regional Development Project : Project Information Document (Appraisal Stage) - HT Center and Artibonite Regional Development - P133352, 16 janvye 2014, documents.worldbank.org
- Haiti - Center and Artibonite Regional Development Project, 12 desanm 2013, documents.worldbank.org
- Haiti - Center and Artibonite Regional Development Project : Integrated Safeguards Data Sheet (Concept Stage) - HT Center and Artibonite Regional Development - P133352, 30 novanm 2013, documents.worldbank.org
- Haiti - Center and Artibonite Regional Development Project : Projet de developpement regional de la boucle Centre Artibonite, 14 novanm 2013, documents.worldbank.org
Avi apèl dòf (2)
- Procurement Notices, projects.worldbank.org
- Contract Awards, projects.worldbank.org
Sous
- Fich IATI (d-portal): kondisyon itilizasyon piblikatè a fikse
- IATI: kondisyon itilizasyon piblikatè a fikse
- Relve kredi ak don IDA (seri done): World Bank data, CC BY 4.0 (https://datacatalog.worldbank.org/public-licenses).
- Tranzaksyon: kondisyon itilizasyon piblikatè a fikse
- Fich operasyon an: kondisyon itilizasyon piblikatè a fikse
- Avi pasasyon mache Bank mondyal: kondisyon itilizasyon piblikatè a fikse
- Paj pwojè a, Bank Mondyal: kondisyon itilizasyon piblikatè a fikse
- Dokiman Bank Mondyal: kondisyon itilizasyon piblikatè a fikse
Done jiska 18 oktòb 2026
| Sous | Li nan dat |
|---|---|
| IATI | 18 oktòb 2026 |
| IATI | 18 oktòb 2026 |
| IDA, eta kredi ak don | 18 oktòb 2026 |
| Avi pasasyon mache Bank mondyal | 18 oktòb 2026 |
| Pwojè Bank Mondyal | 18 oktòb 2026 |
| Dokiman Bank Mondyal | 18 oktòb 2026 |