HaitiDocs

Data / Partner portfolio / World Bank Group / IDA

Education for All Project - Additional Financing

US$ millions unless stated. Haitian fiscal year, October to September. FY2026-27 began October 1, 2026.

Objective

The PDO is to (a) to improve access and equity of primary education; (b) to operationalize partnerships between public and non public sectors; and (c) to build capacity to assess learning outcomes.

As published by World Bank Projects, in its original language.

Partner
World Bank Group, IDA
Sector
Education
Stage
Closed since May 31, 2012
Approval
May 27, 2010
Closing
May 31, 2012
Instrument
IBRD/IDA financing, IDA
Effectiveness
July 15, 2010
Departments
Sud-Est, Ouest, Nord-Ouest, Nord-Est, Nord, Grande Anse, Centre, Artibonite, Nippes
Operation ID
P121193
Life cycle4 stages, 6 dates

Stage history

StageFrom
ApprovedMay 27, 2010
Under wayJuly 15, 2010
ClosingMay 31, 2012
ClosedMay 31, 2012

Dated events

EventDateSource
AppraisalMay 5, 2010World Bank Projects
NegotiationMay 5, 2010World Bank Projects
ApprovalMay 27, 2010World Bank Projects
EffectivenessJuly 15, 2010IDA Statement of Credits and Grants
Closing dateMay 31, 2012World Bank Projects
Completion report dueDecember 3, 2012World Bank Projects

Financing

Table 1.Financing, US$ millions

FinancierAmountUS$ millionsRoleSource
IDA Grant12.0InstitutionWorld Bank Projects

Table 2.Related operations, US$ millions

OperationRelationPartnerStageCommitmentUS$ millions
HT Education For All Adaptable Program Grant Phase 1Parent operationWorld Bank GroupClosed36.6

Table 3.Position at the data date by source (stocks), US$ millions

This pageUS$ millionsSource
Commitment12.0World Bank Projects
DisbursedNot reported
UndisbursedNot reported
Total cost12.0World Bank Projects

World Bank amounts. Approved: Net commitment, the amount approved less cancellations, in US$ at the data date. Disbursed to date: The disbursements of the IDA statement and the Projects API to date, in US$. Undisbursed: The undisbursed balance the IDA statement publishes, in US$ at the data date. Amounts by source

Changes to the operationnot reported
Original closing date
Not reported
Closing date extensions
Not reported
Restructurings
Not reported
Emergency component
Not reported

Records and documents

Locations9 departments, 9 places named, 9 places with coordinates
DepartmentsSud-Est, Ouest, Nord-Ouest, Nord-Est, Nord, Grande Anse, Centre, Artibonite, Nippes
Places named by the sourceDepartement de Nippes, Departement de l'Artibonite, Departement de l'Ouest, Departement de la Grand'Anse, Departement du Centre, Departement du Nord, Departement du Nord-Est, Departement du Nord-Ouest, Departement du Sud-Est
Places with coordinates9
Identifiers1 identifier
SystemIdentifierSource
World Bank projectP121193Operation record

Partner documents

Sources

Data as of October 18, 2026
SourceRead on
IDA Statement of Credits and GrantsOctober 18, 2026
World Bank ProjectsOctober 18, 2026
World Bank documentsOctober 18, 2026
Cite this page

HaitiDocs. Education for All Project - Additional Financing. Partner portfolio, data as of October 18, 2026. https://www.haitidocs.org/portfolio/projects/WB%3AP121193