Data / Partner portfolio / World Bank Group / IDA
Emergency Development Policy Operation
Published title: Emergency Development Policy Operation
US$ millions unless stated. Haitian fiscal year, October to September. FY2026-27 began October 1, 2026.
Objective
The objective of the proposed operation is to support enhanced accountability and transparency in the management of public resources in the context of the reconstruction. The operation supports the government's capacity to manage public resources efficiently and transparently. More specifically, the operation supports the following measures: (i) increasing transparency in budget transfers to the electricity sector; (ii) reinstating budget controls and external and internal audit processes; (iii) improving enforcement of the Law on Declaration of Assets; and(iv) reinforcing public procurement regulation and enhancing transparency in procurement practices.
As published by World Bank Projects, in its original language.
Description
This program document presents the Emergency Development Policy Grant (DPG) for the Republic of Haiti. This is the fourth DPG supporting the Republic of Haiti, after its successful reengagement with the donor community in 2005. The grant is a single-tranche operation supporting the FY2009-10 budget, with an additional co-financing of US$25 million by the Haiti Reconstruction Fund (HRF), of which the Bank is the partner agency. The operation supports maintaining sound economic governance in the post-earthquake period and strengthening the reforms started before the earthquake. First, the operation supports the implementation of the Government Action Plan for National Recovery and Development of Haiti presented to the international community in March 2010, aimed at rebuilding the country. The Government Action Plan
more
puts emphasis on decentralization presents economic and social reforms as well as the institutional strengthening strategy of the authorities in the aftermath of the earthquake that devastated Haiti on January 12, 2010. Second, it supports the government's program for enhancing transparency and accountability mechanisms, especially in view of the massive pledges made by donors to support the reconstruction process. The Government Action Plan and governance program are in line with the strategy contained in the country's Poverty Reduction Strategy (PRS/DSNCRP) for the period 2008-2010, of which one pillar aims at strengthening state capacity and management of public resources.
- Partner
- World Bank Group, IDA
- Sector
- Governance and security
- Stage
- Closed since September 30, 2011
- Approval
- August 5, 2010
- Closing
- September 30, 2011
- Instrument
- IBRD/IDA financing, IDA
- Undisbursed gap
- −0.6: the IDA statement values undisbursed credits in special drawing rights at the current exchange rate
- Effectiveness
- August 23, 2010
- Last transaction
- August 5, 2010
- Operation ID
- P118239
Life cycle5 stages, 9 dates
Stage history
| Stage | From |
|---|---|
| Planned | June 3, 2010 |
| Approved | August 5, 2010 |
| Under way | August 23, 2010 |
| Closing | September 30, 2011 |
| Closed | September 30, 2011 |
Dated events
| Event | Date | Source |
|---|---|---|
| Concept review | June 3, 2010 | World Bank Projects |
| Appraisal | June 25, 2010 | World Bank Projects |
| Negotiation | July 2, 2010 | World Bank Projects |
| Disclosure | July 6, 2010 | World Bank Projects |
| Approval | August 5, 2010 | World Bank Projects |
| First commitment | August 5, 2010 | Transactions |
| Effectiveness | August 23, 2010 | World Bank Projects |
| Closing date | September 30, 2011 | World Bank Projects |
| Completion report due | March 28, 2012 | World Bank Projects |
Undisbursed: US$0.0 million on September 30, 2026, with closing on September 30, 2011.
Financing
Table 1.Financing, US$ millions
| Financier | AmountUS$ millions | Role | Source |
|---|---|---|---|
| IDA Grant | 30.0 | Institution | World Bank Projects |
Table 2.Position at the data date by source (stocks), US$ millions
| This pageUS$ millions | Source | |
|---|---|---|
| Commitment | 30.0 | IDA Statement of Credits and Grants |
| Disbursed | 30.6 | IDA Statement of Credits and Grants |
| Undisbursed | 0.0 | IDA Statement of Credits and Grants |
| Total cost | 30.0 | World Bank Projects |
World Bank amounts. Approved: Net commitment, the amount approved less cancellations, in US$ at the data date. Disbursed to date: The disbursements of the IDA statement and the Projects API to date, in US$. Undisbursed: The undisbursed balance the IDA statement publishes, in US$ at the data date. Amounts by source
Changes to the operationnot reported
- Original closing date
- Not reported
- Closing date extensions
- Not reported
- Restructurings
- Not reported
- Emergency component
- Not reported
New commitments and disbursements by fiscal year
Table 3.New commitments and disbursements by fiscal year (flows), US$ millions
| FY2009-10US$ millions | |
|---|---|
| New commitments | 30.0 |
| Disbursements | Not reported |
| Cumulative disbursements | Not reported |
The running total starts at the opening balance of US$30.6 million.
Records and documents
Transactions2 records, August 5, 2010 to April 30, 2011
Table 4.Transactions, US$ millions
Terms1 of 6 reported
- Finance type
- 110 Standard grant
- Flow type
- Not reported
- Aid type
- Not reported
- Tied status
- Not reported
- Collaboration type
- Not reported
- Humanitarian
- Not reported
Results indicators13 indicators
| Indicator | Baseline | Target | Latest value | Date of latest value |
|---|---|---|---|---|
| (i) the MEF submits to the Court of Accounts the 2009-10 government accounts no more than 8 months after the end of the FY 2010; | Submission of the results of external audits by th | Met | Met | September 27, 2011 |
| (i) the inventory of Government and NGOs# projects; | The operationalization ofthe internal audit body | Met | Not reported | Not reported |
| (iii) analysis of audit reports issued by the Court of Accounts; | The operationalization ofthe internal audit body | Met | Not reported | Not reported |
| All invoice payments by the Ministry of Finance (MEF) to the Independent Power Providers (IPP) follow the rules described in the joint memorandum signed by the MEF and the Ministry of Public Work. | No formal framework is in place to monitor the tra | Met. | Not reported | Not reported |
| Data on payments to IPPs published on the Ministry of Finance's website and actual payment are reconciled by the MTPTC and MEF. | No formal framework is in place to monitor the tra | Partially Met. | Not reported | Not reported |
| Improved compliance of external audits and Budget review Law submission within the statutory timeframe | Submission of the results of external audits by th | Partially Met | Not reported | Not reported |
| The IGF activities comply with the plan of action endorsed by the Ministry of Finance (2010-14) and audit reports are disseminated to the beneficiaries and the competent authorities, including at leas | The operationalization ofthe internal audit body | Met | Not reported | Not reported |
| The Prime Minister has given prior authorization to all contracts awarded by invoking the Emergency Law#s accelerated procedures. | Not applicable. | To be confirmed | Not reported | Not reported |
| The compliance rate with the Declaration of Assets Law of the members of the government increased from 87 percent (as of May 2010) to 100 percent. | 87.00 | 100.00 | 100.00 | September 27, 2011 |
| The share of non-competitive procurement in total procurement has decreased from 56 percent (as of 2008) to 45 percent. | 56.00 | 45.00 | 0.00 | September 27, 2011 |
| and (ii) the Court of Accounts communicates to the MEF the results of the audits of the 2008-09 and 2009-10 government accounts by September 30, 2011. | Submission of the results of external audits by th | Partially Met | Not reported | Not reported |
| and (iv) audits of public accountants activities in the MEF. | The operationalization ofthe internal audit body | Met | Not reported | Not reported |
| ii) audits of subsidies in the education sector and the transfers by theMEF; | The operationalization ofthe internal audit body | Met | Not reported | Not reported |
Ratings22 ratings
| Rating | Value | Date |
|---|---|---|
| IEG bankqualityofsupervision | Satisfactory | November 21, 2012 |
| IEG borrowcompliance | Moderately Satisfactory | November 21, 2012 |
| IEG borrowimplementation | Moderately Satisfactory | November 21, 2012 |
| IEG evaltype | ES | November 21, 2012 |
| IEG evaluation_riskdo | Significant | November 21, 2012 |
| IEG icrquality | Satisfactory | November 21, 2012 |
| IEG mequality | Substantial | November 21, 2012 |
| IEG outcome | Moderately Satisfactory | November 21, 2012 |
| IEG overallbankperf | Moderately Satisfactory | November 21, 2012 |
| IEG overallborrowperf | Moderately Satisfactory | November 21, 2012 |
| ICR bankqualityentry | Not Rated | March 28, 2012 |
| ICR banksupervision | Not Rated | March 28, 2012 |
| ICR borrgovt | Moderately Satisfactory | March 28, 2012 |
| ICR borrimplegency | Moderately Satisfactory | March 28, 2012 |
| ICR borroverall | Moderately Satisfactory | March 28, 2012 |
| ICR completion_riskdo | Modest | March 28, 2012 |
| ICR outratingind | Moderately Satisfactory | March 28, 2012 |
| ICR overallrating | Substantial | March 28, 2012 |
| ISR Monitoring and Evaluation | Satisfactory | November 2, 2011 |
| ISR Overall Implementation Progress (IP) | Moderately Satisfactory | November 2, 2011 |
| ISR Program Management | Satisfactory | November 2, 2011 |
| ISR Progress towards achievement of PDO | Moderately Satisfactory | November 2, 2011 |
Identifiers3 identifiers
| System | Identifier | Source |
|---|---|---|
| IDA credit or grant | IDAH6090 | IDA Statement of Credits and Grants |
| World Bank loan | IDA-H6090 | World Bank Projects |
| World Bank project | P118239 | Operation record |
Partner documents11 documents
- Haiti - Emergency Development Policy Operation, November 21, 2012, documents.worldbank.org
- Haiti - Emergency Development Policy Operation Project, March 22, 2012, documents.worldbank.org
- Haiti - Emergency Development Policy Operation Project : Haiti - Operation D'urgence D'Appui a la Politique de Developpement, March 22, 2012, documents.worldbank.org
- Haiti - Emergency Development Policy Operation : P118239 - Implementation Status Results Report : Sequence 04, November 2, 2011, documents.worldbank.org
- Haiti - Emergency Development Policy Operation : P118239 - Implementation Status Results Report : Sequence 02, April 17, 2011, documents.worldbank.org
- Haiti - Emergency Development Policy Operation : P118239 - Implementation Status Results Report : Sequence 01, February 8, 2011, documents.worldbank.org
- Haiti - Emergency Development Policy Operation Project, September 9, 2010, documents.worldbank.org
- Financing Agreement for IDA Grant H609-HT Conformed, August 10, 2010, documents.worldbank.org
- Haiti - Emergency Development Policy Operation Project : summary of discussion, August 5, 2010, documents.worldbank.org
- Haiti - Emergency Development Policy Operation Project : Haiti - Descriptif de Programme Operation D'urgence al'appui de la Politique de Developpement, July 9, 2010, documents.worldbank.org
- Haiti - Emergency Development Policy Operation Project, May 21, 2010, documents.worldbank.org
Sources
- IDA statement of credits and grants (dataset): World Bank data, CC BY 4.0 (https://datacatalog.worldbank.org/public-licenses).
- Transactions: terms of use set by the publisher
- Operation record: terms of use set by the publisher
- World Bank project page: terms of use set by the publisher
- World Bank documents: terms of use set by the publisher
Data as of October 18, 2026
| Source | Read on |
|---|---|
| IDA Statement of Credits and Grants | October 18, 2026 |
| World Bank Projects | October 18, 2026 |
| World Bank documents | October 18, 2026 |
Cite this page
HaitiDocs. Emergency Development Policy Operation. Partner portfolio, data as of October 18, 2026. https://www.haitidocs.org/portfolio/projects/WB%3AP118239