Productive Infrastructure Program V

US$ millions unless stated. Haitian fiscal year, October to September. FY2026-27 began October 1, 2026.

Objective

The project objective is to contribute to the sustainable economic development of Northern Haiti. The specific objective is to create formal employment in the North and Northeast Departments of Haiti by providing the necessary conditions for the establishment of firms in the Parc Industriel de Caracol (PIC) and ensuring its adequate management and long term sustainability.

As published by IDB projects dataset, in its original language.

Partner
IDB Group, IDB
Sector
Water and sanitation
Stage
Under way since November 10, 2021
Approval
November 3, 2021
Closing
November 22, 2027
Instrument
Grant, Sovereign Guaranteed
Effectiveness
Not reported
Last transaction
November 30, 2025
Operation ID
HA-L1143
Life cycle2 stages, 8 dates

Stage history

StageFrom
ApprovedNovember 3, 2021
Under wayNovember 10, 2021

Dated events

EventDateSource
ApprovalNovember 3, 2021IDB projects dataset
First commitmentNovember 3, 2021Transactions
SigningNovember 10, 2021IDB projects dataset
Planned startNovember 22, 2022IATI
Actual startDecember 15, 2022IATI
First disbursementDecember 31, 2022Transactions
Last disbursementNovember 30, 2025Transactions
Closing dateNovember 22, 2027IATI

Disbursed in FY2025-26: US$12.7 million.

Financing

Table 1.Financing, US$ millions

FinancierAmountUS$ millionsRoleSource
IDB65.0InstitutionIDB projects dataset

Table 2.Position at the data date by source (stocks), US$ millions

This pageUS$ millionsSourceIATIUS$ millions
Commitment65.0IDB projects dataset65.0
Disbursed33.7IATI33.7
UndisbursedNot reported
Total cost65.0IDB projects dataset

Each amount is given as the source publishes it, converted to US$. IATI column: the commitments and disbursements the partner reports to IATI, converted to US$. Amounts by source

This page uses IDB projects dataset for the commitment and IATI for disbursements.

Changes to the operationnot reported
Original closing date
Not reported
Closing date extensions
Not reported
Restructurings
Not reported
Emergency component
Not reported

New commitments and disbursements by fiscal year

Disbursements, US$ millions
FY2021-22, not reportedn.r.21-22FY2022-23, US$2.0 million222-23FY2023-24, US$9.6 million1023-24FY2024-25, US$9.3 million924-25FY2025-26, US$12.7 million1325-26FY2021-22, not reportedn.r.21-22FY2022-23, US$2.0 million222-23FY2023-24, US$9.6 million1023-24FY2024-25, US$9.3 million924-25FY2025-26, US$12.7 million1325-26

Table 3.New commitments and disbursements by fiscal year (flows), US$ millions

FY2021-22US$ millionsFY2022-23US$ millionsFY2023-24US$ millionsFY2024-25US$ millionsFY2025-26US$ millions
New commitments65.0Not reportedNot reportedNot reportedNot reported
DisbursementsNot reported2.09.69.312.7
Cumulative disbursementsNot reported2.011.621.033.7

Records and documents

Transactions7 records, November 3, 2021 to November 30, 2025

Table 4.Transactions, US$ millions

DateMeasureAmountUS$ millionsSourceMethod
November 3, 2021Commitment65.0IDB projects datasetcommitment at approval date
December 31, 2022Disbursements2.0IATIIATI disbursement (transaction type 3), paid to another organization
November 30, 2023Disbursements7.6IATIIATI disbursement (transaction type 3), paid to another organization
July 31, 2024Disbursements2.0IATIIATI disbursement (transaction type 3), paid to another organization
November 30, 2024Disbursements0.6IATIIATI disbursement (transaction type 3), paid to another organization
December 31, 2024Disbursements8.7IATIIATI disbursement (transaction type 3), paid to another organization
November 30, 2025Disbursements12.7IATIIATI disbursement (transaction type 3), paid to another organization
Terms5 of 6 reported
Finance type
110 Standard grant
Flow type
20 Other official flows, excluding export credits
Aid type
C01 Project-type interventions
Tied status
5 Untied
Collaboration type
4 Multilateral outflows
Humanitarian
Not reported
Locations1 place named
DepartmentsNot reported
Places named by the sourceHaiti, 5, AVENUE CHARLES SUMMER, PORT-AU-PRINCE
Places with coordinates0
Results indicators130 indicators
IndicatorBaselineTargetLatest valueDate of latest value
Additional studies and supervision for flood prevention works of Trou du Nord River bankNot reported1.000.20December 31, 2025
Ambulance purchased and delivered to UTENot reported1.000.00December 31, 2024
Amount billed monthly to tenants that is collected by the entity in charge of the PIC's managementNot reported100.000.00Not reported
Annual rental payments made by PIC's tenants or firmsNot reported4.100.00Not reported
Average time it takes PIC tenants to resolve non-compliance gender issues according to PIC's rules and regulations in effectNot reported3.003.00Not reported
Complaints filed by PIC workers that have been resolved or that are being investigated by the entity in charge of the PICNot reported100.00100.00Not reported
Compost facility inside de PIC builtNot reported1.000.00December 31, 2024
Conception and construction of a propane gas stationNot reported1.000.00December 31, 2023
CoordinationNot reported1.000.00December 31, 2025
Drainage network expandedNot reported0.900.00December 31, 2024
Electrical network expandedNot reported0.900.00December 31, 2024
Emergency works for the closure of the PICNot reported1745.001641.00December 31, 2023
Employees in middle or supervisory positions who are HaitiansNot reported12.000.00December 31, 2025
Employees with middle or supervisory positions in new firms/tenants at the PIC that are Haitian womenNot reported5.000.00December 31, 2025
Existing canteens rehabilitated Fulfilling EDGE Certification V 3.0 conditionsNot reported1.000.40December 31, 2024
Firefighter truck purchased and delivered to UTENot reported1.000.00December 31, 2024
Flood prevention works of the Trou-du-Nord Riverbank builtNot reported4.200.00December 31, 2025
Floor supervisors employed by current tenants in the PIC who are Haitian womenNot reported20.000.00Not reported
Guidelines identifying curricula for training based on employers’ needs assessments and learning pathways developedNot reported1.000.00December 31, 2024
Haitian workers employed in formal jobs by PIC's tenantsNot reported14199.002500.00Not reported
Hazardous solid waste produced within the PIC that is adequately stored (long term storage facility)Not reported100.000.00December 31, 2025
Hazardous waste storage facility (250 sq. m.) builtNot reported1.000.00December 31, 2024
Hydraulic equipment purchased and delivered to UTENot reported1.000.00December 31, 2024
Industrial buildings for international tenants (12,000 sq. m.) built fulfilling EDGE Certification V 3.0 conditionsNot reported2.000.40December 31, 2024
Industrial wastewater produced by the PIC that is adequately treated (water samples comply with maximum biochemical oxygen demand of <30mg/L and absence of toxic chemicals)Not reported100.000.00December 31, 2025
Industrial water network expandedNot reported0.900.00December 31, 2024
Infrastructure for reception of pretreated sludges (dewatered, nonhazardous) from industrial wastewater constructedNot reported1.000.00December 31, 2024
Internal road expandedNot reported0.900.00December 31, 2024
Lactation equipment installed in rooms specifically designated for lactating mothers.Not reported1.000.00December 31, 2024
Management plans related to PIC services management implementedNot reported4.000.00December 31, 2024
New canteens built fulfilling EDGE Certification V 3.0 conditionsNot reported2.000.00December 31, 2025
New employees hired by PIC tenants that were trained and certified in basic socioemotional and employability skillsNot reported75.000.00Not reported
New equipment installed at the health center localized at PIC entranceNot reported1.000.00December 31, 2025
Occupancy ratio of new buildings in the PIC by tenants or firmsNot reported100.000.00Not reported
PIC Gender action plan developed and finalizedNot reported1.000.00December 31, 2025
PIC employees trained and certified in gender awarenessNot reported75.000.00December 31, 2025
PIC tenants’ skill needs assessments and barriers for training identified for new hires and current employeesNot reported1.000.00December 31, 2024
PIC tenants’ workers, supervisors and management employees training sessions on gender issues realizedNot reported1.000.00December 31, 2025
PIC's annual operating margin (revenues /operation and maintenance expenses)Not reported149.000.00Not reported
Plan for PIC Management implementedNot reported1.000.00December 31, 2024
Plan for procedures for grievance mechanisms, communication plan and stakeholder’s engagement updated and implemented.Not reported1.000.20December 31, 2025
Potable and industrial water treatment plant improved and in operationNot reported1.000.00December 31, 2024
Potable water network expandedNot reported0.900.00December 31, 2024
Potable water supplied to the PIC with sufficient quality (water samples comply with maximum iron of <0.3mg/L and manganese pf <0.05mg/L mineral content).Not reported100.000.00December 31, 2025
Rehabilitation of existing buildings including study and supervisionNot reported10.000.00December 31, 2024
Selected PIC employees trained and certified for delivering training to their colleagues in basic socioemotional and employability skillsNot reported75.000.00December 31, 2025
Selected PIC employees who are trained and certified in supervisory and leadership skillsNot reported75.000.00December 31, 2025
Sewerage network expandedNot reported0.900.00December 31, 2024
Sexual harassment and SGBV complaints in the transport system servicing PIC that have been resolved or that are being investigated by the entity in charge of the PICNot reported100.00100.00Not reported
Solid waste produced within the PIC that is adequately disposed (in a sanitary landfill or composted)Not reported100.00100.00December 31, 2025
Subsidy to PIC operational and maintenance costsNot reported1.000.00December 31, 2025
Supervision contract for PIC extension signed and executed as per RFPNot reported1.001.00December 31, 2024
Supervision contract for construction/rehabilitation of canteens executed as per RFPNot reported1.001.00December 31, 2025
Supervision contract for flood prevention works of Trou du Nord River Bank executed as per RFPNot reported1.000.00December 31, 2025
Supervision contract for water and sanitation infrastructures executed as per RFPNot reported1.000.00December 31, 2024
System for operationalizing PIC’s pipeline of talent designed and operatingNot reported1.000.00December 31, 2023
System for the evaluation of training’s pertinence, quality and effectiveness designed and operatingNot reported1.000.00December 31, 2024
Tenants in the PIC that are in compliance with updated PIC rules and regulations on a yearly basisNot reported90.00100.00Not reported
Training program of trainers to deliver basic, socio-emotional and employability skills program to current workers developed and deliveredNot reported2.000.00December 31, 2025
Training program on basic and socioemotional skills delivered to job seekers developed and deliveredNot reported5.000.00December 31, 2025
Training program on middle management and line supervisory skills developed and deliveredNot reported5.000.00December 31, 2025
Trainings related to ESHS aspects (transportation, solid waste management, first aid, natural disaster etc.) implementedNot reported2.000.00December 31, 2025
Updated environmental, social, health, and security (ESHS) system developed and implementedNot reported1.000.00December 31, 2025
Water truck purschased and delivered to UTENot reported1.000.00December 31, 2024
Works for Mouchinette CGIS (Financial compensation to HA-L1106 project)Not reported1.000.00December 31, 2025
Additional studies and supervision for flood prevention works of Trou du Nord River bankNot reported1.000.20December 31, 2025
Ambulance purchased and delivered to UTENot reported1.000.00December 31, 2024
Amount billed monthly to tenants that is collected by the entity in charge of the PIC's managementNot reported100.000.00Not reported
Annual rental payments made by PIC's tenants or firmsNot reported4.100.00Not reported
Average time it takes PIC tenants to resolve non-compliance gender issues according to PIC's rules and regulations in effectNot reported3.003.00Not reported
Complaints filed by PIC workers that have been resolved or that are being investigated by the entity in charge of the PICNot reported100.00100.00Not reported
Compost facility inside de PIC builtNot reported1.000.00December 31, 2024
Conception and construction of a propane gas stationNot reported1.000.00December 31, 2023
CoordinationNot reported1.000.00December 31, 2025
Drainage network expandedNot reported0.900.00December 31, 2024
Electrical network expandedNot reported0.900.00December 31, 2024
Emergency works for the closure of the PICNot reported1745.001641.00December 31, 2023
Employees in middle or supervisory positions who are HaitiansNot reported12.000.00December 31, 2025
Employees with middle or supervisory positions in new firms/tenants at the PIC that are Haitian womenNot reported5.000.00December 31, 2025
Existing canteens rehabilitated Fulfilling EDGE Certification V 3.0 conditionsNot reported1.000.40December 31, 2024
Firefighter truck purchased and delivered to UTENot reported1.000.00December 31, 2024
Flood prevention works of the Trou-du-Nord Riverbank builtNot reported4.200.00December 31, 2025
Floor supervisors employed by current tenants in the PIC who are Haitian womenNot reported20.000.00Not reported
Guidelines identifying curricula for training based on employers’ needs assessments and learning pathways developedNot reported1.000.00December 31, 2024
Haitian workers employed in formal jobs by PIC's tenantsNot reported14199.002500.00Not reported
Hazardous solid waste produced within the PIC that is adequately stored (long term storage facility)Not reported100.000.00December 31, 2025
Hazardous waste storage facility (250 sq. m.) builtNot reported1.000.00December 31, 2024
Hydraulic equipment purchased and delivered to UTENot reported1.000.00December 31, 2024
Industrial buildings for international tenants (12,000 sq. m.) built fulfilling EDGE Certification V 3.0 conditionsNot reported2.000.40December 31, 2024
Industrial wastewater produced by the PIC that is adequately treated (water samples comply with maximum biochemical oxygen demand of <30mg/L and absence of toxic chemicals)Not reported100.000.00December 31, 2025
Industrial water network expandedNot reported0.900.00December 31, 2024
Infrastructure for reception of pretreated sludges (dewatered, nonhazardous) from industrial wastewater constructedNot reported1.000.00December 31, 2024
Internal road expandedNot reported0.900.00December 31, 2024
Lactation equipment installed in rooms specifically designated for lactating mothers.Not reported1.000.00December 31, 2024
Management plans related to PIC services management implementedNot reported4.000.00December 31, 2024
New canteens built fulfilling EDGE Certification V 3.0 conditionsNot reported2.000.00December 31, 2025
New employees hired by PIC tenants that were trained and certified in basic socioemotional and employability skillsNot reported75.000.00Not reported
New equipment installed at the health center localized at PIC entranceNot reported1.000.00December 31, 2025
Occupancy ratio of new buildings in the PIC by tenants or firmsNot reported100.000.00Not reported
PIC Gender action plan developed and finalizedNot reported1.000.00December 31, 2025
PIC employees trained and certified in gender awarenessNot reported75.000.00December 31, 2025
PIC tenants’ skill needs assessments and barriers for training identified for new hires and current employeesNot reported1.000.00December 31, 2024
PIC tenants’ workers, supervisors and management employees training sessions on gender issues realizedNot reported1.000.00December 31, 2025
PIC's annual operating margin (revenues /operation and maintenance expenses)Not reported149.000.00Not reported
Plan for PIC Management implementedNot reported1.000.00December 31, 2024
Plan for procedures for grievance mechanisms, communication plan and stakeholder’s engagement updated and implemented.Not reported1.000.20December 31, 2025
Potable and industrial water treatment plant improved and in operationNot reported1.000.00December 31, 2024
Potable water network expandedNot reported0.900.00December 31, 2024
Potable water supplied to the PIC with sufficient quality (water samples comply with maximum iron of <0.3mg/L and manganese pf <0.05mg/L mineral content).Not reported100.000.00December 31, 2025
Rehabilitation of existing buildings including study and supervisionNot reported10.000.00December 31, 2024
Selected PIC employees trained and certified for delivering training to their colleagues in basic socioemotional and employability skillsNot reported75.000.00December 31, 2025
Selected PIC employees who are trained and certified in supervisory and leadership skillsNot reported75.000.00December 31, 2025
Sewerage network expandedNot reported0.900.00December 31, 2024
Sexual harassment and SGBV complaints in the transport system servicing PIC that have been resolved or that are being investigated by the entity in charge of the PICNot reported100.00100.00Not reported
Solid waste produced within the PIC that is adequately disposed (in a sanitary landfill or composted)Not reported100.00100.00December 31, 2025
Subsidy to PIC operational and maintenance costsNot reported1.000.00December 31, 2025
Supervision contract for PIC extension signed and executed as per RFPNot reported1.001.00December 31, 2024
Supervision contract for construction/rehabilitation of canteens executed as per RFPNot reported1.001.00December 31, 2025
Supervision contract for flood prevention works of Trou du Nord River Bank executed as per RFPNot reported1.000.00December 31, 2025
Supervision contract for water and sanitation infrastructures executed as per RFPNot reported1.000.00December 31, 2024
System for operationalizing PIC’s pipeline of talent designed and operatingNot reported1.000.00December 31, 2023
System for the evaluation of training’s pertinence, quality and effectiveness designed and operatingNot reported1.000.00December 31, 2024
Tenants in the PIC that are in compliance with updated PIC rules and regulations on a yearly basisNot reported90.00100.00Not reported
Training program of trainers to deliver basic, socio-emotional and employability skills program to current workers developed and deliveredNot reported2.000.00December 31, 2025
Training program on basic and socioemotional skills delivered to job seekers developed and deliveredNot reported5.000.00December 31, 2025
Training program on middle management and line supervisory skills developed and deliveredNot reported5.000.00December 31, 2025
Trainings related to ESHS aspects (transportation, solid waste management, first aid, natural disaster etc.) implementedNot reported2.000.00December 31, 2025
Updated environmental, social, health, and security (ESHS) system developed and implementedNot reported1.000.00December 31, 2025
Water truck purschased and delivered to UTENot reported1.000.00December 31, 2024
Works for Mouchinette CGIS (Financial compensation to HA-L1106 project)Not reported1.000.00December 31, 2025
Funds passed on13 transactions
ReceiverTransactionDateUS$ millions
Bureau D Ingenierie et D ExpertiseDisbursementNovember 30, 20250.1
Ministere de L Economie et des FinancesDisbursementNovember 30, 202511.5
Technique Industrie AgricultureDisbursementNovember 30, 20251.0
Coamco Haiti S.A.DisbursementDecember 31, 20240.2
Technique Industrie AgricultureDisbursementDecember 31, 20240.5
Ministere de L Economie et des FinancesDisbursementDecember 31, 20248.0
Technique Industrie AgricultureDisbursementNovember 30, 20240.3
Coamco Haiti S.A.DisbursementNovember 30, 20240.3
Ministere de L Economie et des FinancesDisbursementJuly 31, 20242.0
VF Construction SADisbursementNovember 30, 20231.2
Coamco Haiti S.A.DisbursementNovember 30, 20232.9
Technique Industrie AgricultureDisbursementNovember 30, 20233.5
Ministere de L Economie et des FinancesDisbursementDecember 31, 20222.0
Identifiers3 identifiers
SystemIdentifierSource
IATI identifierXI-IATI-IADB-HA-L1143IATI
IDB operationHA-L1143Operation record
Public investment program line1112-1-12-52-31Public investment program
Partner documents14 documents
Procurement notices (19)

Sources

Data as of October 18, 2026
SourceRead on
IATIOctober 18, 2026
IATIOctober 18, 2026
IDB projects datasetOctober 18, 2026
Public investment programOctober 18, 2026