HaitiDocs

Done / Pòtfolyo patnè yo / Gwoup BID / IDB

Pwogram enfrastrikti pwodiktif V

Tit pibliye: Productive Infrastructure Program V

An milyon dola ameriken sof si yo di lòt bagay. Ane fiskal ayisyen, soti oktòb rive septanm. FY2026-27 te kòmanse 1 oktòb 2026.

Objektif

The project objective is to contribute to the sustainable economic development of Northern Haiti. The specific objective is to create formal employment in the North and Northeast Departments of Haiti by providing the necessary conditions for the establishment of firms in the Parc Industriel de Caracol (PIC) and ensuring its adequate management and long term sustainability.

Jan Done pwojè BID pibliye l, nan lang orijinal li.

Patnè
IDB Group, IDB
Sektè
Dlo ak asenisman
Etap
An kou depi 10 novanm 2021
Apwobasyon
3 novanm 2021
Fèmen
22 novanm 2027
Enstriman
Don, Sovereign Guaranteed
Antre an vigè
Pa rapòte
Dènye tranzaksyon
30 novanm 2025
Idantifyan operasyon an
HA-L1143
Sik lavi2 etap, 8 dat

Istwa etap yo

EtapDepi
Apwouve3 novanm 2021
An kou10 novanm 2021

Evènman ki gen dat

EvènmanDatSous
Apwobasyon3 novanm 2021Done pwojè BID
Premye angajman3 novanm 2021Tranzaksyon
Siyati10 novanm 2021Done pwojè BID
Kòmansman prevwa22 novanm 2022IATI
Kòmansman reyèl15 desanm 2022IATI
Premye dekèsman31 desanm 2022Tranzaksyon
Dènye dekèsman30 novanm 2025Tranzaksyon
Dat fèmti22 novanm 2027IATI

Dekèse nan FY2025-26: 12.7 milyon dola ameriken.

Finansman

Tablo 1.Finansman, milyon dola ameriken

FinansèMontanMilyon dola amerikenWòlSous
IDB65.0EnstitisyonDone pwojè BID

Tablo 2.Pozisyon nan dat done yo pa sous (stòk), milyon dola ameriken

Paj sa aMilyon dola amerikenSousIATIMilyon dola ameriken
Angajman65.0Done pwojè BID65.0
Dekèse33.7IATI33.7
Pa dekèsePa rapòte
Pri total65.0Done pwojè BID

Chak montan bay jan sous la pibliye l, konvèti an US$. Kolòn IATI: angajman ak dekèsman patnè a pibliye nan IATI, konvèti an US$. Montan yo dapre sous la

Paj sa a sèvi ak Done pwojè BID pou angajman an ak IATI pou dekèsman yo.

Chanjman nan operasyon anpa rapòte
Dat fèmti orijinal
Pa rapòte
Pwolongasyon dat fèmti
Pa rapòte
Restriktirasyon
Pa rapòte
Konpozan ijans
Pa rapòte

Nouvo angajman ak dekèsman pa ane fiskal

Dekèsman, milyon dola ameriken
FY2021-22, pa rapòtep.r.21-22FY2022-23, 2.0 milyon dola ameriken222-23FY2023-24, 9.6 milyon dola ameriken1023-24FY2024-25, 9.3 milyon dola ameriken924-25FY2025-26, 12.7 milyon dola ameriken1325-26FY2021-22, pa rapòtep.r.21-22FY2022-23, 2.0 milyon dola ameriken222-23FY2023-24, 9.6 milyon dola ameriken1023-24FY2024-25, 9.3 milyon dola ameriken924-25FY2025-26, 12.7 milyon dola ameriken1325-26

Tablo 3.Nouvo angajman ak dekèsman pa ane fiskal (flo), milyon dola ameriken

FY2021-22Milyon dola amerikenFY2022-23Milyon dola amerikenFY2023-24Milyon dola amerikenFY2024-25Milyon dola amerikenFY2025-26Milyon dola ameriken
Nouvo angajman65.0Pa rapòtePa rapòtePa rapòtePa rapòte
DekèsmanPa rapòte2.09.69.312.7
Dekèsman kimilePa rapòte2.011.621.033.7

Fich ak dokiman

Tranzaksyon7 liy, 3 novanm 2021 rive 30 novanm 2025

Tablo 4.Tranzaksyon, milyon dola ameriken

DatMeziMontanMilyon dola amerikenSousMetòd
3 novanm 2021Angajman65.0Done pwojè BIDcommitment at approval date
31 desanm 2022Dekèsman2.0IATIIATI disbursement (transaction type 3), paid to another organization
30 novanm 2023Dekèsman7.6IATIIATI disbursement (transaction type 3), paid to another organization
31 jiyè 2024Dekèsman2.0IATIIATI disbursement (transaction type 3), paid to another organization
30 novanm 2024Dekèsman0.6IATIIATI disbursement (transaction type 3), paid to another organization
31 desanm 2024Dekèsman8.7IATIIATI disbursement (transaction type 3), paid to another organization
30 novanm 2025Dekèsman12.7IATIIATI disbursement (transaction type 3), paid to another organization
Kondisyon5 sou 6 rapòte
Kalite finansman
110 Don estanda
Kalite koule
20 Lòt apò ofisyèl, san kredi ekspòtasyon
Kalite èd
C01 Entèvansyon kalite pwojè
Èd mare oswa pa mare
5 Pa mare
Kalite kolaborasyon
4 Apò miltilateral k ap soti
Imanitè
Pa rapòte
Kote1 kote nonmen
DepatmanPa rapòte
Kote sous la nonmenHaiti, 5, AVENUE CHARLES SUMMER, PORT-AU-PRINCE
Kote ki gen kowòdone0
Endikatè rezilta130 endikatè
EndikatèValè referansSibDènye valèDat dènye valè
Additional studies and supervision for flood prevention works of Trou du Nord River bankPa rapòte1.000.2031 desanm 2025
Ambulance purchased and delivered to UTEPa rapòte1.000.0031 desanm 2024
Amount billed monthly to tenants that is collected by the entity in charge of the PIC's managementPa rapòte100.000.00Pa rapòte
Annual rental payments made by PIC's tenants or firmsPa rapòte4.100.00Pa rapòte
Average time it takes PIC tenants to resolve non-compliance gender issues according to PIC's rules and regulations in effectPa rapòte3.003.00Pa rapòte
Complaints filed by PIC workers that have been resolved or that are being investigated by the entity in charge of the PICPa rapòte100.00100.00Pa rapòte
Compost facility inside de PIC builtPa rapòte1.000.0031 desanm 2024
Conception and construction of a propane gas stationPa rapòte1.000.0031 desanm 2023
CoordinationPa rapòte1.000.0031 desanm 2025
Drainage network expandedPa rapòte0.900.0031 desanm 2024
Electrical network expandedPa rapòte0.900.0031 desanm 2024
Emergency works for the closure of the PICPa rapòte1745.001641.0031 desanm 2023
Employees in middle or supervisory positions who are HaitiansPa rapòte12.000.0031 desanm 2025
Employees with middle or supervisory positions in new firms/tenants at the PIC that are Haitian womenPa rapòte5.000.0031 desanm 2025
Existing canteens rehabilitated Fulfilling EDGE Certification V 3.0 conditionsPa rapòte1.000.4031 desanm 2024
Firefighter truck purchased and delivered to UTEPa rapòte1.000.0031 desanm 2024
Flood prevention works of the Trou-du-Nord Riverbank builtPa rapòte4.200.0031 desanm 2025
Floor supervisors employed by current tenants in the PIC who are Haitian womenPa rapòte20.000.00Pa rapòte
Guidelines identifying curricula for training based on employers’ needs assessments and learning pathways developedPa rapòte1.000.0031 desanm 2024
Haitian workers employed in formal jobs by PIC's tenantsPa rapòte14199.002500.00Pa rapòte
Hazardous solid waste produced within the PIC that is adequately stored (long term storage facility)Pa rapòte100.000.0031 desanm 2025
Hazardous waste storage facility (250 sq. m.) builtPa rapòte1.000.0031 desanm 2024
Hydraulic equipment purchased and delivered to UTEPa rapòte1.000.0031 desanm 2024
Industrial buildings for international tenants (12,000 sq. m.) built fulfilling EDGE Certification V 3.0 conditionsPa rapòte2.000.4031 desanm 2024
Industrial wastewater produced by the PIC that is adequately treated (water samples comply with maximum biochemical oxygen demand of <30mg/L and absence of toxic chemicals)Pa rapòte100.000.0031 desanm 2025
Industrial water network expandedPa rapòte0.900.0031 desanm 2024
Infrastructure for reception of pretreated sludges (dewatered, nonhazardous) from industrial wastewater constructedPa rapòte1.000.0031 desanm 2024
Internal road expandedPa rapòte0.900.0031 desanm 2024
Lactation equipment installed in rooms specifically designated for lactating mothers.Pa rapòte1.000.0031 desanm 2024
Management plans related to PIC services management implementedPa rapòte4.000.0031 desanm 2024
New canteens built fulfilling EDGE Certification V 3.0 conditionsPa rapòte2.000.0031 desanm 2025
New employees hired by PIC tenants that were trained and certified in basic socioemotional and employability skillsPa rapòte75.000.00Pa rapòte
New equipment installed at the health center localized at PIC entrancePa rapòte1.000.0031 desanm 2025
Occupancy ratio of new buildings in the PIC by tenants or firmsPa rapòte100.000.00Pa rapòte
PIC Gender action plan developed and finalizedPa rapòte1.000.0031 desanm 2025
PIC employees trained and certified in gender awarenessPa rapòte75.000.0031 desanm 2025
PIC tenants’ skill needs assessments and barriers for training identified for new hires and current employeesPa rapòte1.000.0031 desanm 2024
PIC tenants’ workers, supervisors and management employees training sessions on gender issues realizedPa rapòte1.000.0031 desanm 2025
PIC's annual operating margin (revenues /operation and maintenance expenses)Pa rapòte149.000.00Pa rapòte
Plan for PIC Management implementedPa rapòte1.000.0031 desanm 2024
Plan for procedures for grievance mechanisms, communication plan and stakeholder’s engagement updated and implemented.Pa rapòte1.000.2031 desanm 2025
Potable and industrial water treatment plant improved and in operationPa rapòte1.000.0031 desanm 2024
Potable water network expandedPa rapòte0.900.0031 desanm 2024
Potable water supplied to the PIC with sufficient quality (water samples comply with maximum iron of <0.3mg/L and manganese pf <0.05mg/L mineral content).Pa rapòte100.000.0031 desanm 2025
Rehabilitation of existing buildings including study and supervisionPa rapòte10.000.0031 desanm 2024
Selected PIC employees trained and certified for delivering training to their colleagues in basic socioemotional and employability skillsPa rapòte75.000.0031 desanm 2025
Selected PIC employees who are trained and certified in supervisory and leadership skillsPa rapòte75.000.0031 desanm 2025
Sewerage network expandedPa rapòte0.900.0031 desanm 2024
Sexual harassment and SGBV complaints in the transport system servicing PIC that have been resolved or that are being investigated by the entity in charge of the PICPa rapòte100.00100.00Pa rapòte
Solid waste produced within the PIC that is adequately disposed (in a sanitary landfill or composted)Pa rapòte100.00100.0031 desanm 2025
Subsidy to PIC operational and maintenance costsPa rapòte1.000.0031 desanm 2025
Supervision contract for PIC extension signed and executed as per RFPPa rapòte1.001.0031 desanm 2024
Supervision contract for construction/rehabilitation of canteens executed as per RFPPa rapòte1.001.0031 desanm 2025
Supervision contract for flood prevention works of Trou du Nord River Bank executed as per RFPPa rapòte1.000.0031 desanm 2025
Supervision contract for water and sanitation infrastructures executed as per RFPPa rapòte1.000.0031 desanm 2024
System for operationalizing PIC’s pipeline of talent designed and operatingPa rapòte1.000.0031 desanm 2023
System for the evaluation of training’s pertinence, quality and effectiveness designed and operatingPa rapòte1.000.0031 desanm 2024
Tenants in the PIC that are in compliance with updated PIC rules and regulations on a yearly basisPa rapòte90.00100.00Pa rapòte
Training program of trainers to deliver basic, socio-emotional and employability skills program to current workers developed and deliveredPa rapòte2.000.0031 desanm 2025
Training program on basic and socioemotional skills delivered to job seekers developed and deliveredPa rapòte5.000.0031 desanm 2025
Training program on middle management and line supervisory skills developed and deliveredPa rapòte5.000.0031 desanm 2025
Trainings related to ESHS aspects (transportation, solid waste management, first aid, natural disaster etc.) implementedPa rapòte2.000.0031 desanm 2025
Updated environmental, social, health, and security (ESHS) system developed and implementedPa rapòte1.000.0031 desanm 2025
Water truck purschased and delivered to UTEPa rapòte1.000.0031 desanm 2024
Works for Mouchinette CGIS (Financial compensation to HA-L1106 project)Pa rapòte1.000.0031 desanm 2025
Additional studies and supervision for flood prevention works of Trou du Nord River bankPa rapòte1.000.2031 desanm 2025
Ambulance purchased and delivered to UTEPa rapòte1.000.0031 desanm 2024
Amount billed monthly to tenants that is collected by the entity in charge of the PIC's managementPa rapòte100.000.00Pa rapòte
Annual rental payments made by PIC's tenants or firmsPa rapòte4.100.00Pa rapòte
Average time it takes PIC tenants to resolve non-compliance gender issues according to PIC's rules and regulations in effectPa rapòte3.003.00Pa rapòte
Complaints filed by PIC workers that have been resolved or that are being investigated by the entity in charge of the PICPa rapòte100.00100.00Pa rapòte
Compost facility inside de PIC builtPa rapòte1.000.0031 desanm 2024
Conception and construction of a propane gas stationPa rapòte1.000.0031 desanm 2023
CoordinationPa rapòte1.000.0031 desanm 2025
Drainage network expandedPa rapòte0.900.0031 desanm 2024
Electrical network expandedPa rapòte0.900.0031 desanm 2024
Emergency works for the closure of the PICPa rapòte1745.001641.0031 desanm 2023
Employees in middle or supervisory positions who are HaitiansPa rapòte12.000.0031 desanm 2025
Employees with middle or supervisory positions in new firms/tenants at the PIC that are Haitian womenPa rapòte5.000.0031 desanm 2025
Existing canteens rehabilitated Fulfilling EDGE Certification V 3.0 conditionsPa rapòte1.000.4031 desanm 2024
Firefighter truck purchased and delivered to UTEPa rapòte1.000.0031 desanm 2024
Flood prevention works of the Trou-du-Nord Riverbank builtPa rapòte4.200.0031 desanm 2025
Floor supervisors employed by current tenants in the PIC who are Haitian womenPa rapòte20.000.00Pa rapòte
Guidelines identifying curricula for training based on employers’ needs assessments and learning pathways developedPa rapòte1.000.0031 desanm 2024
Haitian workers employed in formal jobs by PIC's tenantsPa rapòte14199.002500.00Pa rapòte
Hazardous solid waste produced within the PIC that is adequately stored (long term storage facility)Pa rapòte100.000.0031 desanm 2025
Hazardous waste storage facility (250 sq. m.) builtPa rapòte1.000.0031 desanm 2024
Hydraulic equipment purchased and delivered to UTEPa rapòte1.000.0031 desanm 2024
Industrial buildings for international tenants (12,000 sq. m.) built fulfilling EDGE Certification V 3.0 conditionsPa rapòte2.000.4031 desanm 2024
Industrial wastewater produced by the PIC that is adequately treated (water samples comply with maximum biochemical oxygen demand of <30mg/L and absence of toxic chemicals)Pa rapòte100.000.0031 desanm 2025
Industrial water network expandedPa rapòte0.900.0031 desanm 2024
Infrastructure for reception of pretreated sludges (dewatered, nonhazardous) from industrial wastewater constructedPa rapòte1.000.0031 desanm 2024
Internal road expandedPa rapòte0.900.0031 desanm 2024
Lactation equipment installed in rooms specifically designated for lactating mothers.Pa rapòte1.000.0031 desanm 2024
Management plans related to PIC services management implementedPa rapòte4.000.0031 desanm 2024
New canteens built fulfilling EDGE Certification V 3.0 conditionsPa rapòte2.000.0031 desanm 2025
New employees hired by PIC tenants that were trained and certified in basic socioemotional and employability skillsPa rapòte75.000.00Pa rapòte
New equipment installed at the health center localized at PIC entrancePa rapòte1.000.0031 desanm 2025
Occupancy ratio of new buildings in the PIC by tenants or firmsPa rapòte100.000.00Pa rapòte
PIC Gender action plan developed and finalizedPa rapòte1.000.0031 desanm 2025
PIC employees trained and certified in gender awarenessPa rapòte75.000.0031 desanm 2025
PIC tenants’ skill needs assessments and barriers for training identified for new hires and current employeesPa rapòte1.000.0031 desanm 2024
PIC tenants’ workers, supervisors and management employees training sessions on gender issues realizedPa rapòte1.000.0031 desanm 2025
PIC's annual operating margin (revenues /operation and maintenance expenses)Pa rapòte149.000.00Pa rapòte
Plan for PIC Management implementedPa rapòte1.000.0031 desanm 2024
Plan for procedures for grievance mechanisms, communication plan and stakeholder’s engagement updated and implemented.Pa rapòte1.000.2031 desanm 2025
Potable and industrial water treatment plant improved and in operationPa rapòte1.000.0031 desanm 2024
Potable water network expandedPa rapòte0.900.0031 desanm 2024
Potable water supplied to the PIC with sufficient quality (water samples comply with maximum iron of <0.3mg/L and manganese pf <0.05mg/L mineral content).Pa rapòte100.000.0031 desanm 2025
Rehabilitation of existing buildings including study and supervisionPa rapòte10.000.0031 desanm 2024
Selected PIC employees trained and certified for delivering training to their colleagues in basic socioemotional and employability skillsPa rapòte75.000.0031 desanm 2025
Selected PIC employees who are trained and certified in supervisory and leadership skillsPa rapòte75.000.0031 desanm 2025
Sewerage network expandedPa rapòte0.900.0031 desanm 2024
Sexual harassment and SGBV complaints in the transport system servicing PIC that have been resolved or that are being investigated by the entity in charge of the PICPa rapòte100.00100.00Pa rapòte
Solid waste produced within the PIC that is adequately disposed (in a sanitary landfill or composted)Pa rapòte100.00100.0031 desanm 2025
Subsidy to PIC operational and maintenance costsPa rapòte1.000.0031 desanm 2025
Supervision contract for PIC extension signed and executed as per RFPPa rapòte1.001.0031 desanm 2024
Supervision contract for construction/rehabilitation of canteens executed as per RFPPa rapòte1.001.0031 desanm 2025
Supervision contract for flood prevention works of Trou du Nord River Bank executed as per RFPPa rapòte1.000.0031 desanm 2025
Supervision contract for water and sanitation infrastructures executed as per RFPPa rapòte1.000.0031 desanm 2024
System for operationalizing PIC’s pipeline of talent designed and operatingPa rapòte1.000.0031 desanm 2023
System for the evaluation of training’s pertinence, quality and effectiveness designed and operatingPa rapòte1.000.0031 desanm 2024
Tenants in the PIC that are in compliance with updated PIC rules and regulations on a yearly basisPa rapòte90.00100.00Pa rapòte
Training program of trainers to deliver basic, socio-emotional and employability skills program to current workers developed and deliveredPa rapòte2.000.0031 desanm 2025
Training program on basic and socioemotional skills delivered to job seekers developed and deliveredPa rapòte5.000.0031 desanm 2025
Training program on middle management and line supervisory skills developed and deliveredPa rapòte5.000.0031 desanm 2025
Trainings related to ESHS aspects (transportation, solid waste management, first aid, natural disaster etc.) implementedPa rapòte2.000.0031 desanm 2025
Updated environmental, social, health, and security (ESHS) system developed and implementedPa rapòte1.000.0031 desanm 2025
Water truck purschased and delivered to UTEPa rapòte1.000.0031 desanm 2024
Works for Mouchinette CGIS (Financial compensation to HA-L1106 project)Pa rapòte1.000.0031 desanm 2025
Lajan ki pase bay lòt13 mouvman
BenefisyèMouvmanDatMilyon dola ameriken
Bureau D Ingenierie et D ExpertiseDekèsman30 novanm 20250.1
Ministere de L Economie et des FinancesDekèsman30 novanm 202511.5
Technique Industrie AgricultureDekèsman30 novanm 20251.0
Coamco Haiti S.A.Dekèsman31 desanm 20240.2
Technique Industrie AgricultureDekèsman31 desanm 20240.5
Ministere de L Economie et des FinancesDekèsman31 desanm 20248.0
Technique Industrie AgricultureDekèsman30 novanm 20240.3
Coamco Haiti S.A.Dekèsman30 novanm 20240.3
Ministere de L Economie et des FinancesDekèsman31 jiyè 20242.0
VF Construction SADekèsman30 novanm 20231.2
Coamco Haiti S.A.Dekèsman30 novanm 20232.9
Technique Industrie AgricultureDekèsman30 novanm 20233.5
Ministere de L Economie et des FinancesDekèsman31 desanm 20222.0
Idantifyan3 idantifyan
SistèmIdantifyanSous
Idantifyan IATIXI-IATI-IADB-HA-L1143IATI
Operasyon BIDHA-L1143Fich operasyon an
Liy pwogram envestisman piblik1112-1-12-52-31Pwogram envestisman piblik
Dokiman patnè a14 dokiman
Avi apèl dòf (19)

Sous

Done jiska 18 oktòb 2026
SousLi nan dat
IATI18 oktòb 2026
IATI18 oktòb 2026
Done pwojè BID18 oktòb 2026
Pwogram envestisman piblik18 oktòb 2026
Site paj sa a

HaitiDocs. Pwogram enfrastrikti pwodiktif V. Pòtfolyo patnè yo, done jiska 18 oktòb 2026. https://www.haitidocs.org/portfolio/projects/IDB%3AHA-L1143?lang=ht