Data / Partner portfolio / World Bank Group / World Bank
Strengthening Primary Health Care and Surveillance
Published title: Strengthening Primary Health Care and Surveillance in Haiti
US$ millions unless stated. Haitian fiscal year, October to September. FY2026-27 began October 1, 2026.
Objective
The PDO of the proposed Project is to: (i) increase utilization of primary health care services in selected geographical areas; (ii) strengthen surveillance capacity especially for cholera, and (iii) provide an immediate and effective response to an eligible crisis or emergency.
As published by World Bank Projects, in its original language.
Description
Objectives of Strengthening Primary Health Care and Surveillance Project for Haiti are to increase utilization of primary health care services in selected geographical areas, and strengthen surveillance capacity especially for cholera. The project has 4 components. (1) Strengthening primary health care service delivery component will finance activities to strengthen Primary Health Care (PHC) service delivery via PHC referral networks, with each network consisting of: (i) a community referral hospital, health centers and dispensaries operating at different levels within the network; and (ii) Community Health Workers at the community level. (2) Strengthening surveillance and control for infectious diseases component will help maintain the Ministry of Public Health and Population (MSPP’s) effective nationwide surveillance and response capacity in the fight against cholera
more
achieved under the ongoing Improving Maternal and Child Health through Integrated Social Services (PASMISSI), while integrating cholera surveillance and response tools into the general surveillance and response systems. This component will continue to ensure the financing of critical surveillance and control activities for cholera and will expand to cover other infectious diseases, including two vaccine-preventable diseases – diphtheria and measles – and maternal deaths (all of which are part of the list of mandatory notifiable diseases), complementing the support of the Centers for Disease Control and Prevention (CDC) for MSPP’s surveillance capacity. (3) Supporting project management and implementation support component will finance activities to strengthen the capacity of the central MSPP units and Departmental health authorities in the coordination, implementation management and supervision of the Project (including fiduciary aspects and monitoring and evaluation, safeguards and reporting of Project activities and results), and the carrying out of Project audits. (4) Contingent emergency response component will provide funding following an eligible emergency.
- Partner
- World Bank Group, World Bank
- Sector
- Health
- Stage
- Under way since May 16, 2019
- Approval
- May 16, 2019
- Closing
- December 31, 2026
- Instrument
- IBRD/IDA financing, Grants
- Undisbursed gap
- 15.9: trust funds are not in the IDA statement, which gives undisbursed amounts for IDA money only; the IDA statement values undisbursed credits in special drawing rights at the current exchange rate
- Borrower
- Republic of Haiti
- Implementing agency
- Ministry of Public Health and Population,Project Management Unit
- Effectiveness
- August 28, 2019
- Departments
- Nord-Ouest, Nord-Est, Grande Anse, Centre, Artibonite, Nippes
- Last transaction
- September 30, 2026
- Operation ID
- P167512
Implemented through
- World Food Programme, US$1.5 million, matched by amount and date
- United Nations Development Programme, US$0.6 million, World Bank contract award
Life cycle3 stages, 13 dates
Stage history
| Stage | From |
|---|---|
| Planned | September 6, 2018 |
| Approved | May 16, 2019 |
| Under way | May 16, 2019 |
Dated events
| Event | Date | Source |
|---|---|---|
| Concept review | September 6, 2018 | World Bank Projects |
| Disclosure | October 19, 2018 | World Bank Projects |
| Planned start | March 21, 2019 | IATI |
| Appraisal | March 26, 2019 | World Bank Projects |
| Negotiation | April 5, 2019 | World Bank Projects |
| Actual start | May 16, 2019 | IATI |
| Approval | May 16, 2019 | World Bank Projects |
| First commitment | May 16, 2019 | Transactions |
| Effectiveness | August 28, 2019 | World Bank Projects |
| First disbursement | March 31, 2020 | Transactions |
| Last disbursement | September 30, 2026 | Transactions |
| Closing date | December 31, 2026 | IATI |
| Completion report due | June 30, 2027 | World Bank Projects |
Undisbursed: US$13.0 million on September 30, 2026, with closing on December 31, 2026. Disbursed in FY2025-26: US$8.1 million.
Financing
Table 1.Financing, US$ millions
| Financier | AmountUS$ millions | Role | Source |
|---|---|---|---|
| The Global Fund to Fight AIDS, Tuberculosis & Malaria | 22.2 | Cofinancier | World Bank Projects |
| IDA Grant | 75.0 | Institution | World Bank Projects |
| Global Financing Facility | 15.0 | Trust fund | World Bank Projects |
Table 2.Related operations, US$ millions
| Operation | Relation | Partner | Stage | CommitmentUS$ millions |
|---|---|---|---|---|
| AF Strengthening Primary Health Care and Surveillance | Additional financing or child operation | World Bank Group | Under way | 20.0 |
Table 3.Position at the data date by source (stocks), US$ millions
| This pageUS$ millions | Source | IATIUS$ millions | |
|---|---|---|---|
| Commitment | 90.0 | IDA Statement of Credits and Grants | Not reported |
| Disbursed | 61.2 | IDA Statement of Credits and Grants | 74.9 |
| Undisbursed | 13.0 | IDA Statement of Credits and Grants | |
| Total cost | 70.0 | World Bank Projects |
World Bank amounts. Approved: Net commitment, the amount approved less cancellations, in US$ at the data date. Disbursed to date: The disbursements of the IDA statement and the Projects API to date, in US$. Undisbursed: The undisbursed balance the IDA statement publishes, in US$ at the data date. IATI column: the commitments and disbursements the partner reports to IATI, converted to US$. Amounts by source
Changes to the operation1 extension, 4 restructurings, emergency component included
- Original closing date
- December 31, 2024
- Closing date extensions
- 1
- Extended from December 31, 2024 to December 31, 2026 (document of June 30, 2024)
- Restructurings
- 4
- April 9, 2021 (document of April 9, 2021) restructuring paper
- May 3, 2021 (document of May 3, 2021) restructuring paper
- May 22, 2024, Level 2, approved by management (document of May 22, 2024) restructuring paper
- Emergency component
- Contingent emergency response component included (document of May 22, 2024) restructuring paper
New commitments and disbursements by fiscal year
Table 4.New commitments and disbursements by fiscal year (flows), US$ millions
| FY2018-19US$ millions | FY2019-20US$ millions | FY2020-21US$ millions | FY2021-22US$ millions | FY2022-23US$ millions | FY2023-24US$ millions | FY2024-25US$ millions | FY2025-26US$ millions | |
|---|---|---|---|---|---|---|---|---|
| New commitments | 70.0 | Not reported | Not reported | 20.0 | Not reported | Not reported | Not reported | Not reported |
| Disbursements | Not reported | 5.5 | 8.5 | 5.7 | 16.7 | 16.5 | 0.1 | 8.1 |
| Cumulative disbursements | Not reported | 5.5 | 14.0 | 19.8 | 36.4 | 52.9 | 53.1 | 61.2 |
Records and documents
Transactions45 records, May 16, 2019 to September 30, 2026
Table 5.Transactions, US$ millions
| Date | Measure | AmountUS$ millions | Source | Method |
|---|---|---|---|---|
| May 16, 2019 | Commitment | 55.0 | IDA Statement of Credits and Grants | credit original principal at board approval |
| May 16, 2019 | Commitment | 15.0 | World Bank Projects | trust funds in the Projects API financier list, not in the IDA statement, at the board approval date |
| June 16, 2022 | Commitment | 20.0 | IDA Statement of Credits and Grants | credit original principal at board approval |
| March 31, 2020 | Disbursements | 5.5 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| February 28, 2021 | Disbursements | 0.3 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| May 31, 2021 | Disbursements | 4.0 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| August 31, 2021 | Disbursements | 4.3 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| December 31, 2021 | Disbursements | 3.5 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| February 28, 2022 | Disbursements | 0.3 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| June 30, 2022 | Disbursements | 2.0 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| July 31, 2022 | Disbursements | −0.1 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| October 31, 2022 | Disbursements | 0.2 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| November 30, 2022 | Disbursements | 2.6 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| December 31, 2022 | Disbursements | 0.3 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| January 31, 2023 | Disbursements | 2.0 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| January 31, 2023 | Disbursements | <0.1 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| April 30, 2023 | Disbursements | 5.0 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| May 31, 2023 | Disbursements | 0.1 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| May 31, 2023 | Disbursements | 5.7 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| June 30, 2023 | Disbursements | 0.2 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| July 31, 2023 | Disbursements | 0.3 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| August 31, 2023 | Disbursements | 0.2 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| September 30, 2023 | Disbursements | 0.1 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| October 31, 2023 | Disbursements | 4.4 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| November 30, 2023 | Disbursements | 5.2 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| January 31, 2024 | Disbursements | 0.2 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| February 29, 2024 | Disbursements | 1.3 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| March 31, 2024 | Disbursements | 0.3 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| April 30, 2024 | Disbursements | 1.6 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| June 30, 2024 | Disbursements | 1.4 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| July 31, 2024 | Disbursements | 0.9 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| August 31, 2024 | Disbursements | 0.9 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| August 31, 2024 | Disbursements | 0.2 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| August 31, 2025 | Disbursements | −0.3 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| September 30, 2025 | Disbursements | 0.4 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| November 30, 2025 | Disbursements | 0.2 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| February 28, 2026 | Disbursements | <0.1 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| March 31, 2026 | Disbursements | 0.3 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| March 31, 2026 | Disbursements | 0.5 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| April 30, 2026 | Disbursements | 1.4 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| May 31, 2026 | Disbursements | 1.0 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| June 30, 2026 | Disbursements | 1.6 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| June 30, 2026 | Disbursements | 0.6 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| July 31, 2026 | Disbursements | 0.6 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| September 30, 2026 | Disbursements | 1.8 | IDA Statement of Credits and Grants | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
Terms4 of 6 reported
- Finance type
- 110 Standard grant
- Flow type
- Not reported
- Aid type
- C01 Project-type interventions
- Tied status
- 5 Untied
- Collaboration type
- 2 Multilateral inflows
- Humanitarian
- Not reported
Locations6 departments, 6 places named, 12 places with coordinates
| Departments | Nord-Ouest, Nord-Est, Grande Anse, Centre, Artibonite, Nippes |
| Places named by the source | Centre, Departement de Nippes, Departement de l'Artibonite, Departement du Nord-Est, Grandans, Nord-Ouest |
| Places with coordinates | 12 |
Results indicators43 indicators
| Indicator | Baseline | Target | Latest value | Date of latest value |
|---|---|---|---|---|
| Citizen Engagement: percentage of facilities under RBF that developed an action plan(s) based on the results of community satisfaction surveys | 0.00 | 50.00 | 19.00 | June 11, 2024 |
| Contracted health providers supervised at least quarterly | 100.00 | 80.00 | 57.00 | April 28, 2023 |
| Contracted service providers achieving the minimum quality score | 71.00 | 78.00 | 70.00 | June 11, 2024 |
| Number of Community Health Workers who were trained based on the new Community Health Strategy | 0.00 | 500.00 | 205.00 | June 11, 2024 |
| Number of children immunized | 0.00 | 800000.00 | 641347.00 | June 11, 2024 |
| Number of deliveries attended by skilled health personnel | 0.00 | 100000.00 | 67298.00 | June 11, 2024 |
| Number of laboratories who comply with national standard requirements for infrastructure and equipment | 0.00 | 10.00 | 8.00 | June 11, 2024 |
| Number of peripheral storage warehouses upgraded based on identified need and in accordance with minimum national standards on storage of medical products | 0.00 | 2.00 | 0.00 | June 11, 2024 |
| Number of women and children who have received basic nutrition services | 0.00 | 1000000.00 | 665138.00 | June 11, 2024 |
| People who have received essential health, nutrition, and population (HNP) services | 0.00 | 1900000.00 | 1373783.00 | June 11, 2024 |
| People who have received essential health, nutrition, and population (HNP) services - Female (RMS requirement) | 000000 | 150000.00 | 0.00 | January 1, 1900 |
| Percentage of notified maternal deaths investigated per year | 0.00 | 10.00 | 80.00 | June 11, 2024 |
| Percentage of suspected cases of diphtheria investigated and responded to within 48h after notification | 72.00 | 90.00 | 100.00 | June 11, 2024 |
| Number of health facilities rehabilitated or reconstructed | 0.00 | 80.00 | 51.00 | Not reported |
| Number of health facilities rehabilitated or reconstructed | 0.00 | 80.00 | 62.00 | Not reported |
| Percentage of children aged between 0 and 11 months vaccinated with Penta 3 in Project intervention areas | 78.75 | 83 | 79.7 | Not reported |
| Percentage of children aged between 0 and 11 months vaccinated with Penta 3 in Project intervention areas | 78.75 | 83.00 | 95.80 | Not reported |
| Percentage of institutional deliveries in Project intervention areas | 68.7 | 78 | 73.7 | Not reported |
| Percentage of institutional deliveries in Project intervention areas | 68.70 | 78.00 | 75.20 | Not reported |
| Percentage of notifications of suspected cases of cholera for which laboratory results are available to the Health Departmental Directorates (DDSs) within 10 days of collection | 45.00 | 70.00 | 100.00 | Not reported |
| Percentage of notifications of suspected cases of cholera for which laboratory results are available to the Health Departmental Directorates (DDSs) within 10 days of collection | 45.00 | 70.00 | 98.00 | Not reported |
| Citizen Engagement: percentage of facilities under RBF that developed an action plan(s) based on the results of community satisfaction surveys | 0.00 | 50.00 | 38.00 | Not reported |
| Citizen Engagement: percentage of facilities under RBF that developed an action plan(s) based on the results of community satisfaction surveys | 0.00 | 50.00 | 19.00 | Not reported |
| Contracted health providers supervised at least quarterly | 100.00 | 80.00 | 100 | Not reported |
| Contracted health providers supervised at least quarterly | 100.00 | 80.00 | 57.00 | Not reported |
| Contracted service providers achieving the minimum quality score | 71.00 | 78.00 | 72.00 | Not reported |
| Contracted service providers achieving the minimum quality score | 71.00 | 78.00 | 70.00 | Not reported |
| Number of Community Health Workers who were trained based on the new Community Health Strategy | 0.00 | 500.00 | 567 | Not reported |
| Number of Community Health Workers who were trained based on the new Community Health Strategy | 0.00 | 500.00 | 205.00 | Not reported |
| Number of laboratories who comply with national standard requirements for infrastructure and equipment | 0.00 | 10.00 | 8.00 | Not reported |
| Number of laboratories who comply with national standard requirements for infrastructure and equipment | 0.00 | 10.00 | 8.00 | Not reported |
| Number of peripheral storage warehouses upgraded based on identified need and in accordance with minimum national standards on storage of medical products | 0.00 | 2.00 | 0 | Not reported |
| Number of peripheral storage warehouses upgraded based on identified need and in accordance with minimum national standards on storage of medical products | 0.00 | 2.00 | 0.00 | Not reported |
| People who have received essential health, nutrition, and population (HNP) services | 0.00 | 1,900,000.00 | 2,241,609 | Not reported |
| People who have received essential health, nutrition, and population (HNP) services | 0.00 | 1900000.00 | 1373783.00 | Not reported |
| Percentage of notified maternal deaths investigated per year | 0.00 | 10.00 | 80.00 | Not reported |
| Percentage of notified maternal deaths investigated per year | 0.00 | 10.00 | 71 | Not reported |
| Percentage of suspected cases of diphtheria investigated and responded to within 48h after notification | 72.00 | 90.00 | 82 | Not reported |
| Percentage of suspected cases of diphtheria investigated and responded to within 48h after notification | 72.00 | 90.00 | 100.00 | Not reported |
| Number of health facilities rehabilitated or reconstructed | 0.00 | 80.00 | 51.00 | June 11, 2024 |
| Percentage of children aged between 0 and 11 months vaccinated with Penta 3 in Project intervention areas | 78.75 | 83.00 | 95.80 | June 11, 2024 |
| Percentage of institutional deliveries in Project intervention areas | 68.70 | 78.00 | 75.20 | June 11, 2024 |
| Percentage of notifications of suspected cases of cholera for which laboratory results are available to the Health Departmental Directorates (DDSs) within 10 days of collection | 45.00 | 70.00 | 98.00 | June 11, 2024 |
Ratings6 ratings
| Rating | Value | Date |
|---|---|---|
| ISR Financial Management | Moderately Unsatisfactory | May 26, 2026 |
| ISR Monitoring and Evaluation | Satisfactory | May 26, 2026 |
| ISR Overall Implementation Progress (IP) | Moderately Satisfactory | May 26, 2026 |
| ISR Procurement | Moderately Satisfactory | May 26, 2026 |
| ISR Progress towards achievement of PDO | Satisfactory | May 26, 2026 |
| ISR Project Management | Moderately Satisfactory | May 26, 2026 |
Contract awards196 awards
| Supplier | Date | Method | Amount |
|---|---|---|---|
| 3D TECH | September 15, 2026 | DIR | 10,258.6 USD |
| Groupe Gabriel Construction | September 14, 2026 | DIR | 59,350 USD |
| Supeco SA | September 14, 2026 | DIR | 173,475 USD |
| Firme Linteau Construction (FLICO) | September 9, 2026 | DIR | 61,875 USD |
| Henry, Henri et Co(BIRHA) | September 9, 2026 | DIR | 59,875 USD |
| Scetra Construction | September 9, 2026 | DIR | 56,360 USD |
| SOPEC Plus | September 9, 2026 | DIR | 58,375.5 USD |
| CJMCO | September 9, 2026 | DIR | 69,125 USD |
| Access Office | August 28, 2026 | RFQ | 313,225.34 USD |
| CAPRI Medica | August 11, 2026 | DIR | 35,375 USD |
| Name not shown | July 30, 2026 | CDS | 3,204.6 USD |
| Organisation Entraide Medical Internationale (EMI) | July 29, 2026 | DIR | 52,308.07 USD |
| Bioanalytical Instruments | July 7, 2026 | DIR | 14,980 USD |
| Bioanalytical Instruments | July 7, 2026 | DIR | 18,154 USD |
| Bioanalytical Instruments | July 7, 2026 | DIR | 1,275 USD |
| Kay Kermens Distribution | June 19, 2026 | DIR | 25,000 USD |
| MAKOL OCR S.A. | June 16, 2026 | DIR | 11,200 USD |
| SHIFO Foundation | June 9, 2026 | DIR | 2,716,423.5 USD |
| JMB Medical Agency | May 5, 2026 | RFQ | 14,267,975 HTG |
| JMB Medical Agency | May 5, 2026 | RFQ | 12,243,440 HTG |
| Name not shown | April 16, 2026 | CDS | 10,150 USD |
| Henry, Henri et Co(BIRHA) | April 6, 2026 | RFB | 845,957 USD |
| Solutions S.A | March 30, 2026 | DIR | 10,000 USD |
| Msupply Foundation | March 27, 2026 | DIR | 156,822.96 USD |
| Hopital Foyer Saint Camille | February 20, 2026 | DIR | 500,000 USD |
| Name not shown | January 30, 2026 | CDS | 5,000 USD |
| Noelsaint Construction | December 4, 2025 | RFQ | 456,438.27 USD |
| M.V.L Construction | December 4, 2025 | RFQ | 440,686.5 USD |
| Name not shown | November 26, 2025 | CDS | 58,906.83 USD |
| Name not shown | November 4, 2025 | RFQ | 472,213.71 USD |
| Elmecen SA | September 17, 2025 | RFQ | 11,400 USD |
| Elmecen SA | September 17, 2025 | RFQ | 108,370 USD |
| Elmecen SA | September 17, 2025 | RFQ | 16,150 USD |
| Epsilon Medical Supplies | September 15, 2025 | RFQ | 5,950 USD |
| JEBA Better World Design Construction (JEBA) | September 11, 2025 | RFQ | 259,295.57 USD |
| Hydrauccarte | September 8, 2025 | RFQ | 449,633.69 USD |
| Firme Linteau Construction (FLICO) | September 8, 2025 | RFQ | 328,217.4 USD |
| FH Entreprise | September 1, 2025 | RFQ | 255,982.88 USD |
| Turenne Gnrale Construction | August 29, 2025 | RFQ | 28,441.94 USD |
| Internegoce S.A. | August 21, 2025 | RFQ | 499,627.92 HTG |
| Valerio CANEZ S.A. | August 17, 2025 | RFQ | 227,812.5 HTG |
| SOPEC Plus | July 15, 2025 | RFQ | 388,893.15 USD |
| Civil Design & Construction | July 10, 2025 | RFQ | 328,612.07 USD |
| Accounting & Finance Corp. (Acfinco) | May 16, 2025 | LCS | 55,600 USD |
| Solutions S.A | April 14, 2025 | CDS | 200,000 USD |
| Global Printing and Services | February 28, 2025 | RFQ | 300,000 USD |
| Name not shown | January 27, 2025 | CQS | 109,507 USD |
| Ap-HP International | January 27, 2025 | CQS | Not reported |
| Nouvelle Pharmacie Sante Publique (NPS-Ci) | January 27, 2025 | CQS | Not reported |
| World Food Programme (WFP) | October 31, 2024 | DIR | 2,536,371 USD |
| Name not shown | October 31, 2024 | INDV | 3,000 USD |
| Name not shown | October 14, 2024 | INDV | 3,600 USD |
| SUNAUTO | October 11, 2024 | RFQ | 3,962,000 HTG |
| Name not shown | October 3, 2024 | INDV | 1,500 USD |
| Name not shown | October 3, 2024 | INDV | 1,500 USD |
| FH Entreprise | September 27, 2024 | RFQ | 258,505.57 USD |
| Name not shown | September 26, 2024 | INDV | 2,500 USD |
| Name not shown | September 23, 2024 | INDV | 650 USD |
| Civil Design & Construction | September 10, 2024 | RFQ | 284,392.05 USD |
| Name not shown | September 9, 2024 | INDV | 3,000 USD |
| Ed Entreprise | September 5, 2024 | RFQ | 40,550 USD |
| CAPRI Medica | August 29, 2024 | DIR | 40,000 USD |
| Name not shown | July 2, 2024 | INDV | 2,500 USD |
| JEBA Better World Design Construction (JEBA) | June 3, 2024 | RFQ | 126,779.81 USD |
| Name not shown | May 10, 2024 | INDV | 3,000 USD |
| Name not shown | March 4, 2024 | INDV | 1,500 USD |
| Comphaiti | February 26, 2024 | RFQ | 15,808 USD |
| Global Home and Office Smart | February 26, 2024 | RFQ | 2,400 USD |
| Global Home and Office Smart | February 26, 2024 | RFQ | 9,768 USD |
| Name not shown | February 12, 2024 | INDV | 3,000 USD |
| Name not shown | January 30, 2024 | INDV | 1,000 USD |
| Solutions S.A | January 30, 2024 | CDS | 10,000 USD |
| Name not shown | December 28, 2023 | CDS | 4,261,866 KGS |
| IMATEK | December 27, 2023 | RFQ | 373,275.13 USD |
| Name not shown | December 27, 2023 | INDV | 1,500 USD |
| IMATEK | December 27, 2023 | RFQ | 68,221.48 USD |
| Access Office | December 22, 2023 | RFQ | 225,000 USD |
| Name not shown | December 14, 2023 | INDV | 3,000 USD |
| Ed Entreprise | December 12, 2023 | RFQ | 41,100 USD |
| Capris Medica | November 24, 2023 | DIR | 117,460 USD |
| AMEX Export-Import GmbH WIEN | November 17, 2023 | DIR | 1,125,924.23 USD |
| Bucotech Construction | November 3, 2023 | RFB | 769,734.45 USD |
| Thasmotiv Distribution | November 3, 2023 | RFQ | 157,500 USD |
| C.E.S Group | November 3, 2023 | RFB | Not reported |
| Marcoren Construction | November 3, 2023 | RFB | Not reported |
| Name not shown | October 31, 2023 | INDV | 2,000 USD |
| Name not shown | October 27, 2023 | INDV | 968.84 USD |
| Name not shown | October 19, 2023 | INDV | 2,500 USD |
| Name not shown | October 11, 2023 | INDV | 2,500 USD |
| Name not shown | October 11, 2023 | INDV | 2,500 USD |
| Name not shown | October 11, 2023 | INDV | 2,500 USD |
| Name not shown | October 6, 2023 | INDV | 4,000 USD |
| XEOS | September 29, 2023 | RFQ | 9,841.97 USD |
| Technozi Haiti | September 29, 2023 | RFQ | 24,555 USD |
| Azillion Distribution S.A | September 29, 2023 | RFQ | 10,807.42 USD |
| Name not shown | September 11, 2023 | RFQ | 59,746,600 HTG |
| PRODASA | September 1, 2023 | RFQ | 204,562 USD |
| Name not shown | August 24, 2023 | INDV | 1,000 USD |
| Bureau d'Etudes des Technologies de la Telecommunication et de la Recherche Scientifique (Betters) | August 22, 2023 | CDS | 85,250 USD |
| Name not shown | August 21, 2023 | INDV | 1,500 USD |
| Name not shown | August 18, 2023 | INDV | 3,000 USD |
| Name not shown | August 8, 2023 | INDV | 2,800 USD |
| Name not shown | August 8, 2023 | INDV | 3,000 USD |
| Name not shown | August 8, 2023 | INDV | 1,820.83 USD |
| Name not shown | July 24, 2023 | INDV | 2,730 USD |
| Name not shown | July 15, 2023 | INDV | 3,000 USD |
| Name not shown | July 12, 2023 | CDS | 45,000 USD |
| Name not shown | June 29, 2023 | INDV | 3,500 USD |
| Name not shown | June 28, 2023 | INDV | 2,000 USD |
| Name not shown | June 7, 2023 | INDV | 3,000 USD |
| Name not shown | June 3, 2023 | INDV | 3,500 USD |
| Name not shown | May 26, 2023 | INDV | 3,000 USD |
| Iidevelopment : Innovative Infrastructure (IIDEV) | May 23, 2023 | CDS | 378,000 USD |
| Institut Haitien de Santé Communautaire | May 4, 2023 | CDS | 163,184 USD |
| Name not shown | May 2, 2023 | INDV | 2,000 USD |
| Name not shown | April 26, 2023 | INDV | 2,500 USD |
| Name not shown | April 25, 2023 | INDV | 2,500 USD |
| Name not shown | April 22, 2023 | INDV | 6,000 USD |
| United Nations Children's Fund (UNICEF) | March 22, 2023 | DIR | 7,090,293 USD |
| Name not shown | February 14, 2023 | CDS | 3,500 USD |
| Name not shown | February 7, 2023 | CDS | 30,000 USD |
| Name not shown | February 7, 2023 | INDV | 2,100 USD |
| Name not shown | February 7, 2023 | INDV | 3,000 USD |
| Name not shown | December 28, 2022 | CDS | 5,000 USD |
| United Nations Office Project Services (UNOPS) | December 27, 2022 | DIR | 3,500,000 USD |
| Expertise en Travaux d'Amnagement et de Construction (Extraco S.A) | December 9, 2022 | RFQ | 197,079.35 USD |
| Name not shown | November 22, 2022 | INDV | 2,500 USD |
| Elmecen SA | November 17, 2022 | RFB | 57,500 USD |
| Elmecen SA | November 17, 2022 | RFB | 31,620 USD |
| Elmecen SA | November 17, 2022 | RFB | 13,430 USD |
| Elmecen SA | November 17, 2022 | RFB | Not reported |
| Experts Conseils et Associes | November 16, 2022 | LCS | 13,269,000 HTG |
| Name not shown | November 3, 2022 | RFQ | 138,135.98 USD |
| Carribean Products and Services | October 27, 2022 | RFQ | 197,063.58 USD |
| Global Home and Office Smart | July 29, 2022 | RFQ | 3,247 USD |
| Global Home and Office Smart | July 29, 2022 | RFQ | 3,490 USD |
| PC Express | July 28, 2022 | RFQ | 66,792 USD |
| Name not shown | June 13, 2022 | INDV | 4,050 USD |
| Name not shown | June 3, 2022 | INDV | 3,500 USD |
| Name not shown | June 2, 2022 | INDV | 2,500 USD |
| United Nations Development Programme (UNDP) | May 19, 2022 | DIR | 729,145.82 USD |
| Fondation pour la Sant Reproductive et l'Ducation Familiale (Fosref) | May 12, 2022 | QCBS | 2,444,100 USD |
| Groupintellconsult | May 12, 2022 | QCBS | Not reported |
| Name not shown | May 9, 2022 | INDV | 24,000 USD |
| Name not shown | May 5, 2022 | INDV | 12,500 USD |
| Comphaiti SA | April 28, 2022 | RFQ | 8,050 USD |
| Comphaiti SA | April 28, 2022 | RFQ | 4,770 USD |
| Comphaiti SA | April 28, 2022 | RFQ | 4,410 USD |
| Comphaiti SA | April 28, 2022 | RFQ | 33,750 USD |
| Comphaiti SA | April 28, 2022 | RFQ | 14,790 USD |
| Name not shown | April 19, 2022 | RFQ | 55,690 USD |
| Name not shown | April 4, 2022 | CDS | Not reported |
| Name not shown | April 1, 2022 | CDS | 24,000 USD |
| IT-SYS INC. | February 24, 2022 | CDS | 14,025 USD |
| Name not shown | February 21, 2022 | CDS | 208,137.8 USD |
| LOGIK | February 10, 2022 | RFB | 1,033,707.13 USD |
| Name not shown | February 9, 2022 | INDV | 3,000 USD |
| Fondation pour la Santé Reproductive et l'Éducation Familiale (Fosref) | January 28, 2022 | CDS | 208,440 USD |
| Société d'Étude et de Formation en Information Stratégique (SEFIS) | January 18, 2022 | RFB | 1,095,429 USD |
| Name not shown | January 11, 2022 | RFQ | 4,548,290 HTG |
| Domond Cabinet d'Experts Comptables | November 30, 2021 | CDS | 25,035 USD |
| Name not shown | November 24, 2021 | INDV | 115,870.3 USD |
| Name not shown | November 23, 2021 | INDV | 100,677.28 USD |
| Name not shown | November 23, 2021 | INDV | 96,261.48 USD |
| Name not shown | November 16, 2021 | INDV | 184,998.86 USD |
| Name not shown | November 10, 2021 | CDS | 3,575 USD |
| Management Science for Health | November 8, 2021 | CDS | 141,833 USD |
| Name not shown | November 4, 2021 | CDS | 3,638 USD |
| Bluesquare | October 21, 2021 | CDS | 184,050 USD |
| Fondation SHIFO | October 21, 2021 | CDS | 3,155,915 USD |
| Hopital Foyer Saint Camille | October 12, 2021 | DIR | 30,654,750 HTG |
| Name not shown | October 11, 2021 | INDV | 42,000 USD |
| Name not shown | October 5, 2021 | INDV | 36,000 USD |
| Name not shown | October 4, 2021 | CDS | 42,900 USD |
| Name not shown | September 30, 2021 | CDS | 1,444.5 USD |
| Name not shown | September 27, 2021 | CDS | 4,815 USD |
| Name not shown | September 27, 2021 | CDS | 59,320.8 USD |
| Name not shown | September 27, 2021 | CDS | 3,210 USD |
| Luminex Corporation | September 22, 2021 | DIR | 78,571 USD |
| A&P Construction | July 5, 2021 | RFQ | 32,575,877.4 HTG |
| Global Printing and Services | May 5, 2021 | RFQ | 311,385.25 USD |
| Société d'Étude et de Formation en Information Stratégique (SEFIS) | April 5, 2021 | CDS | 211,090 USD |
| LOGIK | April 5, 2021 | CDS | 239,471.14 USD |
| Haiti Outreach | April 11, 2019 | DIR | 408,892.5 USD |
| Name not shown | March 22, 2019 | RFQ | 266,000 USD |
| Rehabilitation Travaux Publics ( RTP) | November 28, 2018 | RFQ | 38,301,898.42 HTG |
| MVF Construction | November 26, 2018 | RFQ | 31,646,468.88 HTG |
| ED | November 26, 2018 | RFQ | 25,877,495.5 HTG |
| Ayiti Etudes et Construction | November 26, 2018 | RFQ | 15,078,957 HTG |
| Name not shown | November 26, 2018 | RFQ | 35,969,198.3 HTG |
| ALM Construction | August 13, 2018 | RFQ | 20,470,603.07 HTG |
| A&P Construction | August 8, 2018 | RFQ | 27,758,884.18 HTG |
| BECOCI | August 6, 2018 | RFQ | 23,573,023.5 HTG |
| Etudes Techniques Rehabilitation Execution Expertise ( ETREX) | July 30, 2018 | RFQ | 29,085,597 HTG |
| Etudes Techniques Rehabilitation Execution Expertise ( ETREX) | July 30, 2018 | RFQ | 29,085,597 PGK |
| BUREC SA | May 21, 2018 | RFQ | 21,950,000 HTG |
Funds passed on126 transactions
| Receiver | Transaction | Date | US$ millions |
|---|---|---|---|
| Ministry of Public Health and Population; Project Management Unit | Disbursement | June 30, 2026 | 0.6 |
| Ministry of Public Health and Population; Project Management Unit | Disbursement | June 30, 2026 | 1.6 |
| Ministry of Public Health and Population; Project Management Unit | Disbursement | May 31, 2026 | 1.0 |
| Ministry of Public Health and Population; Project Management Unit | Disbursement | April 30, 2026 | 1.4 |
| HAITI | Expenditure | March 31, 2026 | 0.1 |
| Ministry of Public Health and Population; Project Management Unit | Disbursement | March 31, 2026 | 0.3 |
| Ministry of Public Health and Population; Project Management Unit | Disbursement | March 31, 2026 | 0.5 |
| HAITI | Expenditure | February 28, 2026 | 0.1 |
| Ministry of Public Health and Population; Project Management Unit | Disbursement | February 28, 2026 | <0.1 |
| HAITI | Expenditure | January 31, 2026 | −0.0 |
| HAITI | Expenditure | January 31, 2026 | 0.1 |
| HAITI | Expenditure | December 31, 2025 | <0.1 |
| Ministry of Public Health and Population; Project Management Unit | Disbursement | November 30, 2025 | 0.2 |
| HAITI | Expenditure | November 30, 2025 | <0.1 |
| HAITI | Expenditure | October 31, 2025 | 0.1 |
| HAITI | Expenditure | September 30, 2025 | 0.1 |
| Ministry of Public Health and Population; Project Management Unit | Disbursement | September 30, 2025 | 0.4 |
| HAITI | Expenditure | August 31, 2025 | <0.1 |
| Ministry of Public Health and Population; Project Management Unit | Disbursement | August 31, 2025 | −0.3 |
| HAITI | Expenditure | July 31, 2025 | <0.1 |
| HAITI | Expenditure | June 30, 2025 | <0.1 |
| HAITI | Expenditure | May 31, 2025 | <0.1 |
| HAITI | Expenditure | April 30, 2025 | −0.0 |
| HAITI | Expenditure | April 30, 2025 | <0.1 |
| HAITI | Expenditure | March 31, 2025 | <0.1 |
| HAITI | Expenditure | February 28, 2025 | <0.1 |
| HAITI | Expenditure | January 31, 2025 | <0.1 |
| HAITI | Expenditure | December 31, 2024 | <0.1 |
| HAITI | Expenditure | November 30, 2024 | <0.1 |
| HAITI | Expenditure | October 31, 2024 | −0.0 |
| HAITI | Disbursement | October 31, 2024 | 1.4 |
| HAITI | Expenditure | October 31, 2024 | <0.1 |
| HAITI | Expenditure | September 30, 2024 | <0.1 |
| Ministry of Public Health and Population; Project Management Unit | Disbursement | August 31, 2024 | 0.9 |
| HAITI | Disbursement | August 31, 2024 | 1.3 |
| Ministry of Public Health and Population; Project Management Unit | Disbursement | August 31, 2024 | 0.2 |
| Ministry of Public Health and Population; Project Management Unit | Disbursement | July 31, 2024 | 0.9 |
| HAITI | Expenditure | July 31, 2024 | <0.1 |
| HAITI | Expenditure | June 30, 2024 | <0.1 |
| HAITI | Disbursement | June 30, 2024 | 1.4 |
| Ministry of Public Health and Population; Project Management Unit | Disbursement | June 30, 2024 | 1.4 |
| HAITI | Expenditure | May 31, 2024 | 0.1 |
| HAITI | Expenditure | April 30, 2024 | −0.0 |
| HAITI | Disbursement | April 30, 2024 | 0.3 |
| HAITI | Expenditure | April 30, 2024 | <0.1 |
| Ministry of Public Health and Population; Project Management Unit | Disbursement | April 30, 2024 | 1.6 |
| HAITI | Expenditure | March 31, 2024 | −0.0 |
| Ministry of Public Health and Population; Project Management Unit | Disbursement | March 31, 2024 | 0.3 |
| HAITI | Expenditure | March 31, 2024 | <0.1 |
| Ministry of Public Health and Population; Project Management Unit | Disbursement | February 29, 2024 | 1.3 |
| HAITI | Disbursement | February 29, 2024 | 1.3 |
| HAITI | Expenditure | February 29, 2024 | <0.1 |
| HAITI | Expenditure | January 31, 2024 | 0.1 |
| Ministry of Public Health and Population; Project Management Unit | Disbursement | January 31, 2024 | 0.2 |
| HAITI | Expenditure | December 31, 2023 | 0.1 |
| HAITI | Expenditure | November 30, 2023 | 0.1 |
| HAITI | Disbursement | November 30, 2023 | 1.1 |
| Ministry of Public Health and Population; Project Management Unit | Disbursement | November 30, 2023 | 5.2 |
| Ministry of Public Health and Population; Project Management Unit | Disbursement | October 31, 2023 | 4.4 |
| HAITI | Expenditure | October 31, 2023 | 0.1 |
| HAITI | Expenditure | September 30, 2023 | 0.1 |
| Ministry of Public Health and Population; Project Management Unit | Disbursement | September 30, 2023 | 0.1 |
| Ministry of Public Health and Population; Project Management Unit | Disbursement | August 31, 2023 | 0.2 |
| HAITI | Disbursement | August 31, 2023 | 1.5 |
| HAITI | Expenditure | August 31, 2023 | <0.1 |
| HAITI | Disbursement | July 31, 2023 | 1.0 |
| HAITI | Expenditure | July 31, 2023 | <0.1 |
| Ministry of Public Health and Population; Project Management Unit | Disbursement | July 31, 2023 | 0.3 |
| HAITI | Expenditure | June 30, 2023 | 0.1 |
| Ministry of Public Health and Population; Project Management Unit | Disbursement | June 30, 2023 | 0.2 |
| Ministry of Public Health and Population; Project Management Unit | Disbursement | May 31, 2023 | 5.7 |
| HAITI | Expenditure | May 31, 2023 | 0.1 |
| Ministry of Public Health and Population; Project Management Unit | Disbursement | May 31, 2023 | 0.1 |
| HAITI | Expenditure | April 30, 2023 | −0.0 |
| HAITI | Expenditure | April 30, 2023 | 0.1 |
| Ministry of Public Health and Population; Project Management Unit | Disbursement | April 30, 2023 | 5.0 |
| HAITI | Disbursement | March 31, 2023 | 1.4 |
| HAITI | Expenditure | March 31, 2023 | 0.1 |
| HAITI | Expenditure | February 28, 2023 | <0.1 |
| Ministry of Public Health and Population; Project Management Unit | Disbursement | January 31, 2023 | 2.0 |
| Ministry of Public Health and Population; Project Management Unit | Disbursement | January 31, 2023 | <0.1 |
| HAITI | Expenditure | January 31, 2023 | <0.1 |
| Ministry of Public Health and Population; Project Management Unit | Disbursement | December 31, 2022 | 0.3 |
| HAITI | Expenditure | December 31, 2022 | <0.1 |
| HAITI | Expenditure | November 30, 2022 | <0.1 |
| Ministry of Public Health and Population; Project Management Unit | Disbursement | November 30, 2022 | 2.6 |
| HAITI | Disbursement | October 31, 2022 | 0.7 |
| Ministry of Public Health and Population; Project Management Unit | Disbursement | October 31, 2022 | 0.2 |
| HAITI | Expenditure | October 31, 2022 | <0.1 |
| HAITI | Expenditure | September 30, 2022 | <0.1 |
| HAITI | Expenditure | August 31, 2022 | <0.1 |
| HAITI | Disbursement | August 31, 2022 | 2.3 |
| Ministry of Public Health and Population; Project Management Unit | Disbursement | July 31, 2022 | −0.1 |
| Ministry of Public Health and Population; Project Management Unit | Commitment | June 30, 2022 | 20.0 |
| HAITI | Expenditure | June 30, 2022 | <0.1 |
| Ministry of Public Health and Population; Project Management Unit | Disbursement | June 30, 2022 | 2.0 |
| HAITI | Expenditure | May 31, 2022 | <0.1 |
| HAITI | Expenditure | April 30, 2022 | <0.1 |
| HAITI | Expenditure | March 31, 2022 | <0.1 |
| Ministry of Public Health and Population; Project Management Unit | Disbursement | February 28, 2022 | 0.3 |
| HAITI | Expenditure | February 28, 2022 | <0.1 |
| HAITI | Expenditure | January 31, 2022 | <0.1 |
| HAITI | Expenditure | December 31, 2021 | 0.1 |
| Ministry of Public Health and Population; Project Management Unit | Disbursement | December 31, 2021 | 3.5 |
| HAITI | Expenditure | November 30, 2021 | <0.1 |
| HAITI | Expenditure | October 31, 2021 | <0.1 |
| HAITI | Expenditure | September 30, 2021 | <0.1 |
| HAITI | Expenditure | August 31, 2021 | <0.1 |
| Ministry of Public Health and Population; Project Management Unit | Disbursement | August 31, 2021 | 4.3 |
| HAITI | Expenditure | June 30, 2021 | <0.1 |
| Ministry of Public Health and Population; Project Management Unit | Disbursement | May 31, 2021 | 4.0 |
| HAITI | Expenditure | May 31, 2021 | <0.1 |
| HAITI | Expenditure | April 30, 2021 | <0.1 |
| HAITI | Expenditure | March 31, 2021 | <0.1 |
| HAITI | Expenditure | February 28, 2021 | <0.1 |
| Ministry of Public Health and Population; Project Management Unit | Disbursement | February 28, 2021 | 0.3 |
| HAITI | Expenditure | January 31, 2021 | <0.1 |
| HAITI | Expenditure | December 31, 2020 | <0.1 |
| HAITI | Expenditure | November 30, 2020 | <0.1 |
| HAITI | Expenditure | October 31, 2020 | <0.1 |
| HAITI | Expenditure | September 30, 2020 | −0.0 |
| HAITI | Expenditure | September 30, 2020 | <0.1 |
| HAITI | Expenditure | August 31, 2020 | <0.1 |
| HAITI | Expenditure | June 30, 2020 | <0.1 |
| Ministry of Public Health and Population; Project Management Unit | Disbursement | March 31, 2020 | 5.5 |
| Ministry of Public Health and Population; Project Management Unit | Commitment | May 31, 2019 | 55.0 |
Identifiers6 identifiers
| System | Identifier | Source |
|---|---|---|
| IATI identifier | XI-IATI-WBTF-P167512 | IATI |
| IDA credit or grant | IDAD4670 | IDA Statement of Credits and Grants |
| IDA credit or grant | IDAE0610 | IDA Statement of Credits and Grants |
| World Bank loan | IDA-D4670 | World Bank Projects |
| World Bank loan | IDA-E0610 | World Bank Projects |
| World Bank project | P167512 | Operation record |
Where sources differ2 fields
| Field | Source | Value | Used |
|---|---|---|---|
| Closing date | World Bank Projects | December 31, 2026 | ✓ |
| Closing date | IATI | June 30, 2027 | |
| Commitment | IDA Statement of Credits and Grants | US$90.0 million | ✓ |
| Commitment | World Bank Projects | US$112.2 million |
Partner documents143 documents
- Project Appraisal Document, documents.worldbank.org
- Financing Agreement, documents.worldbank.org
- Financing Agreement, documents.worldbank.org
- Agreement, documents.worldbank.org
- Agreement, documents.worldbank.org
- Agreement, documents.worldbank.org
- Agreement, documents.worldbank.org
- Agreement, documents.worldbank.org
- Agreement, documents.worldbank.org
- Agreement, documents.worldbank.org
- Agreement, documents.worldbank.org
- Implementation Status and Results Report, documents.worldbank.org
- Implementation Status and Results Report, documents.worldbank.org
- Implementation Status and Results Report, documents.worldbank.org
- Implementation Status and Results Report, documents.worldbank.org
- Implementation Status and Results Report, documents.worldbank.org
- Implementation Status and Results Report, documents.worldbank.org
- Implementation Status and Results Report, documents.worldbank.org
- Implementation Status and Results Report, documents.worldbank.org
- Implementation Status and Results Report, documents.worldbank.org
- Implementation Status and Results Report, documents.worldbank.org
- Implementation Status and Results Report, documents.worldbank.org
- Implementation Status and Results Report, documents.worldbank.org
- Record on projects.worldbank.org, projects.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P167512- Strengthening Primary Health Care and Surveillance in Haiti - Procurement Plan, October 13, 2026, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P167512- Strengthening Primary Health Care and Surveillance in Haiti - Procurement Plan, October 6, 2026, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P167512- Strengthening Primary Health Care and Surveillance in Haiti - Procurement Plan, August 24, 2026, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P167512- Strengthening Primary Health Care and Surveillance in Haiti - Procurement Plan, August 21, 2026, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P167512- Strengthening Primary Health Care and Surveillance in Haiti - Procurement Plan, July 29, 2026, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P167512- Strengthening Primary Health Care and Surveillance in Haiti - Procurement Plan, June 23, 2026, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P167512- Strengthening Primary Health Care and Surveillance in Haiti - Procurement Plan, June 23, 2026, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P167512- Strengthening Primary Health Care and Surveillance in Haiti - Procurement Plan, June 18, 2026, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P167512- Strengthening Primary Health Care and Surveillance in Haiti - Procurement Plan, June 3, 2026, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P167512- Strengthening Primary Health Care and Surveillance in Haiti - Procurement Plan, May 26, 2026, documents.worldbank.org
- Disclosable Version of the ISR - Strengthening Primary Health Care and Surveillance in Haiti - P167512 - Sequence No : 12, May 26, 2026, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P167512- Strengthening Primary Health Care and Surveillance in Haiti - Procurement Plan, April 29, 2026, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN - P167512 - Strengthening Primary Health Care and Surveillance in Haiti - Audited Financial Statement, April 26, 2026, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P167512- Strengthening Primary Health Care and Surveillance in Haiti - Procurement Plan, April 20, 2026, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN - P167512 - Strengthening Primary Health Care and Surveillance in Haiti - Audited Financial Statement, March 31, 2026, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P167512- Strengthening Primary Health Care and Surveillance in Haiti - Procurement Plan, March 30, 2026, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P167512- Strengthening Primary Health Care and Surveillance in Haiti - Procurement Plan, March 9, 2026, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P167512- Strengthening Primary Health Care and Surveillance in Haiti - Procurement Plan, February 17, 2026, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P167512- Strengthening Primary Health Care and Surveillance in Haiti - Procurement Plan, February 4, 2026, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P167512- Strengthening Primary Health Care and Surveillance in Haiti - Procurement Plan, January 26, 2026, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P167512- Strengthening Primary Health Care and Surveillance in Haiti - Procurement Plan, January 6, 2026, documents.worldbank.org
- Disclosable Version of the ISR - Strengthening Primary Health Care and Surveillance in Haiti - P167512 - Sequence No : 11, October 31, 2025, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P167512- Strengthening Primary Health Care and Surveillance in Haiti - Procurement Plan, October 22, 2025, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P167512- Strengthening Primary Health Care and Surveillance in Haiti - Procurement Plan, September 25, 2025, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P167512- Strengthening Primary Health Care and Surveillance in Haiti - Procurement Plan, August 7, 2025, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P167512- Strengthening Primary Health Care and Surveillance in Haiti - Procurement Plan, July 29, 2025, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P167512- Strengthening Primary Health Care and Surveillance in Haiti - Procurement Plan, July 14, 2025, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN - P167512 - Strengthening Primary Health Care and Surveillance in Haiti - Audited Financial Statement, July 12, 2025, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P167512- Strengthening Primary Health Care and Surveillance in Haiti - Procurement Plan, June 2, 2025, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P167512- Strengthening Primary Health Care and Surveillance in Haiti - Procurement Plan, April 16, 2025, documents.worldbank.org
- Disclosable Version of the ISR - Strengthening Primary Health Care and Surveillance in Haiti - P167512 - Sequence No : 10, April 1, 2025, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN - P167512 - Strengthening Primary Health Care and Surveillance in Haiti - Audited Financial Statement, March 17, 2025, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P167512- Strengthening Primary Health Care and Surveillance in Haiti - Procurement Plan, March 11, 2025, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P167512- Strengthening Primary Health Care and Surveillance in Haiti - Procurement Plan, February 19, 2025, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P167512- Strengthening Primary Health Care and Surveillance in Haiti - Procurement Plan, January 14, 2025, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P167512- Strengthening Primary Health Care and Surveillance in Haiti - Procurement Plan, December 13, 2024, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P167512- Strengthening Primary Health Care and Surveillance in Haiti - Procurement Plan, October 7, 2024, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P167512- Strengthening Primary Health Care and Surveillance in Haiti - Procurement Plan, September 24, 2024, documents.worldbank.org
- Disclosable Version of the ISR - Strengthening Primary Health Care and Surveillance in Haiti - P167512 - Sequence No : 9, September 23, 2024, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P167512- Strengthening Primary Health Care and Surveillance in Haiti - Procurement Plan, August 30, 2024, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P167512- Strengthening Primary Health Care and Surveillance in Haiti - Procurement Plan, July 18, 2024, documents.worldbank.org
- Official Documents- Second Amendment to the Financing Agreement for Grant D467-HT.pdf, June 5, 2024, documents.worldbank.org
- Official Documents- Amendment to the Financing Agreement for Additional Financing for Grant E061-HT.pdf, June 5, 2024, documents.worldbank.org
- Official Documents- Second Amendment to the Grant Agreement for GFF Grant TF0B0067-HT.pdf, June 5, 2024, documents.worldbank.org
- Official Documents- Amendment Letter for Amendment No. 1 to the Co-financing Agreement Ref. P167512.pdf, May 27, 2024, documents.worldbank.org
- Disclosable Restructuring Paper - Strengthening Primary Health Care and Surveillance in Haiti - P167512, May 22, 2024, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P167512- Strengthening Primary Health Care and Surveillance in Haiti - Procurement Plan, May 14, 2024, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P167512- Strengthening Primary Health Care and Surveillance in Haiti - Procurement Plan, April 9, 2024, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P167512- Strengthening Primary Health Care and Surveillance in Haiti - Procurement Plan, February 29, 2024, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P167512- Strengthening Primary Health Care and Surveillance in Haiti - Procurement Plan, January 18, 2024, documents.worldbank.org
- Disclosable Version of the ISR - Strengthening Primary Health Care and Surveillance in Haiti - P167512 - Sequence No : 08, November 27, 2023, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P167512- Strengthening Primary Health Care and Surveillance in Haiti - Procurement Plan, November 7, 2023, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P167512- Strengthening Primary Health Care and Surveillance in Haiti - Procurement Plan, November 1, 2023, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P167512- Strengthening Primary Health Care and Surveillance in Haiti - Procurement Plan, October 25, 2023, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P167512- Strengthening Primary Health Care and Surveillance in Haiti - Procurement Plan, September 22, 2023, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P167512- Strengthening Primary Health Care and Surveillance in Haiti - Procurement Plan, June 14, 2023, documents.worldbank.org
- Disclosable Version of the ISR - Strengthening Primary Health Care and Surveillance in Haiti - P167512 - Sequence No : 07, May 8, 2023, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P167512- Strengthening Primary Health Care and Surveillance in Haiti - Procurement Plan, March 21, 2023, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P167512- Strengthening Primary Health Care and Surveillance in Haiti - Procurement Plan, January 23, 2023, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P167512- Strengthening Primary Health Care and Surveillance in Haiti - Procurement Plan, November 30, 2022, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P167512- Strengthening Primary Health Care and Surveillance in Haiti - Procurement Plan, November 3, 2022, documents.worldbank.org
- Disclosable Version of the ISR - Strengthening Primary Health Care and Surveillance in Haiti - P167512 - Sequence No : 06, October 28, 2022, documents.worldbank.org
- Official Documents- Second Amendment to the Grant TF0B0067.pdf, August 4, 2022, documents.worldbank.org
- Official Documents- Disbursement and Financial Information Letter for Additional Financing Grant E061-HT.pdf, August 4, 2022, documents.worldbank.org
- Official Documents- Second Amendment to the Financing Agreement for Grant D467-HT.pdf, August 4, 2022, documents.worldbank.org
- Official Documents- Financing Agreement for Additional Financing Grant E061-HT.pdf, August 4, 2022, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P167512- Strengthening Primary Health Care and Surveillance in Haiti - Procurement Plan, July 25, 2022, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P167512- Strengthening Primary Health Care and Surveillance in Haiti - Procurement Plan, June 8, 2022, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P167512- Strengthening Primary Health Care and Surveillance in Haiti - Procurement Plan, May 30, 2022, documents.worldbank.org
- Haiti - Strengthening Primary Health Care and Surveillance Project : Additional Financing, May 23, 2022, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P167512- Strengthening Primary Health Care and Surveillance in Haiti - Procurement Plan, May 5, 2022, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P167512- Strengthening Primary Health Care and Surveillance in Haiti - Procurement Plan, April 12, 2022, documents.worldbank.org
- Haiti - - P167512 - Strengthening Primary Health Care and Surveillance in Haiti - Audited Financial Statement, April 11, 2022, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P167512- Strengthening Primary Health Care and Surveillance in Haiti - Procurement Plan, March 30, 2022, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P167512- Strengthening Primary Health Care and Surveillance in Haiti - Procurement Plan, March 10, 2022, documents.worldbank.org
- Disclosable Version of the ISR - Strengthening Primary Health Care and Surveillance in Haiti - P167512 - Sequence No : 05, February 25, 2022, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P167512- Strengthening Primary Health Care and Surveillance in Haiti - Procurement Plan, February 21, 2022, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P167512- Strengthening Primary Health Care and Surveillance in Haiti - Procurement Plan, February 4, 2022, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P167512- Strengthening Primary Health Care and Surveillance in Haiti - Procurement Plan, January 31, 2022, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P167512- Strengthening Primary Health Care and Surveillance in Haiti - Procurement Plan, December 16, 2021, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P167512- Strengthening Primary Health Care and Surveillance in Haiti - Procurement Plan, December 6, 2021, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P167512- Strengthening Primary Health Care and Surveillance in Haiti - Procurement Plan, November 29, 2021, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P167512- Strengthening Primary Health Care and Surveillance in Haiti - Procurement Plan, October 19, 2021, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P167512- Strengthening Primary Health Care and Surveillance in Haiti - Procurement Plan, September 3, 2021, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P167512- Strengthening Primary Health Care and Surveillance in Haiti - Procurement Plan, September 3, 2021, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P167512- Strengthening Primary Health Care and Surveillance in Haiti - Procurement Plan, August 31, 2021, documents.worldbank.org
- Disclosable Version of the ISR - Strengthening Primary Health Care and Surveillance in Haiti - P167512 - Sequence No : 04, August 22, 2021, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P167512- Strengthening Primary Health Care and Surveillance in Haiti - Procurement Plan, August 4, 2021, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P167512- Strengthening Primary Health Care and Surveillance in Haiti - Procurement Plan, July 26, 2021, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P167512- Strengthening Primary Health Care and Surveillance in Haiti - Procurement Plan, June 29, 2021, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P167512- Strengthening Primary Health Care and Surveillance in Haiti - Procurement Plan, May 24, 2021, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P167512- Strengthening Primary Health Care and Surveillance in Haiti - Procurement Plan, May 24, 2021, documents.worldbank.org
- Official Documents- First Restatement of the Disbursement and Financial Information Letter for Grant D467-HT, May 19, 2021, documents.worldbank.org
- Official Documents- Amendment and Restatement of the GFF Grant Agreement for TF0B0067, May 19, 2021, documents.worldbank.org
- Official Documents- Amendment and Restatement of the Financing Agreement for Grant D467-HT, May 19, 2021, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P167512- Strengthening Primary Health Care and Surveillance in Haiti - Procurement Plan, May 11, 2021, documents.worldbank.org
- Disclosable Restructuring Paper - Strengthening Primary Health Care and Surveillance in Haiti - P167512, May 3, 2021, documents.worldbank.org
- Disclosable Restructuring Paper - Strengthening Primary Health Care and Surveillance in Haiti - P167512, April 9, 2021, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P167512- Strengthening Primary Health Care and Surveillance in Haiti - Procurement Plan, March 22, 2021, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P167512- Strengthening Primary Health Care and Surveillance in Haiti - Procurement Plan, March 9, 2021, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P167512- Strengthening Primary Health Care and Surveillance in Haiti - Procurement Plan, January 22, 2021, documents.worldbank.org
- Disclosable Version of the ISR - Strengthening Primary Health Care and Surveillance in Haiti - P167512 - Sequence No : 03, January 21, 2021, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P167512- Strengthening Primary Health Care and Surveillance in Haiti - Procurement Plan, December 29, 2020, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P167512- Strengthening Primary Health Care and Surveillance in Haiti - Procurement Plan, December 9, 2020, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P167512- Strengthening Primary Health Care and Surveillance in Haiti - Procurement Plan, November 12, 2020, documents.worldbank.org
- Disclosable Version of the ISR - Strengthening Primary Health Care and Surveillance in Haiti - P167512 - Sequence No : 02, June 26, 2020, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P167512- Strengthening Primary Health Care and Surveillance in Haiti - Procurement Plan, February 13, 2020, documents.worldbank.org
- Disclosable Version of the ISR - Strengthening Primary Health Care and Surveillance in Haiti - P167512 - Sequence No : 01, September 3, 2019, documents.worldbank.org
- Official Documents - Disbursement and Financial Information Letter for Grant D467-HT, June 5, 2019, documents.worldbank.org
- Official Documents - Financing Agreement for Grant for D467-HT, June 5, 2019, documents.worldbank.org
- Official Documents - Disbursement Letter for TF0B0067, June 5, 2019, documents.worldbank.org
- Minutes of a Meeting of the Executive Directors of the Bank and IDA held on May 28, 2019 and Record of Approvals May 24 thru 28, May 28, 2019, documents.worldbank.org
- Haiti - Strengthening Primary Health Care and Surveillance Project, April 25, 2019, documents.worldbank.org
- Project Information Document-Integrated Safeguards Data Sheet - Strengthening Primary Health Care and Surveillance in Haiti - P167512, March 25, 2019, documents.worldbank.org
- Haiti - Strengthening Primary Health Care and Surveillance in Haiti : Environmental Assessment : Cadre de Gestion Environnementale et Sociale, February 1, 2019, documents.worldbank.org
- Haiti - Strengthening Primary Health Care and Surveillance in Haiti : Environmental Assessment : Cadre de gestion environnementale et sociale, February 1, 2019, documents.worldbank.org
- Haiti - Strengthening Primary Health Care and Surveillance in Haiti : Environmental Assessment : Cadre de gestion environnementale et sociale, February 1, 2019, documents.worldbank.org
- Haiti - Strengthening Primary Health Care and Surveillance Project : Resettlement Plan : Cadre de Politique de Reinstallation des Populations, December 1, 2018, documents.worldbank.org
- Concept Project Information Document-Integrated Safeguards Data Sheet - Strengthening Primary Health Care and Surveillance in Haiti - P167512, October 19, 2018, documents.worldbank.org
Procurement notices (2)
- Contract Awards, projects.worldbank.org
- Procurement Notices, projects.worldbank.org
Documents on HaitiDocs
- Environmental and Social Management Framework, additional financing, Primary Health Care and Epidemiological Surveillance Strengthening Project (PROSYS), 2022
- Environmental and Social Management Framework for the Contingent Emergency Response Component after the 14 August 2021 earthquake (PROSYS), 2021
- Environmental and Social Management Framework, Primary Health Care and Epidemiological Surveillance Strengthening Project (PROSYS), 2019
- Resettlement Policy Framework, Primary Health Care and Epidemiological Surveillance Strengthening Project (PROSYS), 2018
Sources
- Partner documents: terms of use set by the publisher
- IATI record (d-portal): terms of use set by the publisher
- IATI: terms of use set by the publisher
- IDA statement of credits and grants (dataset): World Bank data, CC BY 4.0 (https://datacatalog.worldbank.org/public-licenses).
- Transactions: terms of use set by the publisher
- Operation record: terms of use set by the publisher
- World Bank procurement notices: terms of use set by the publisher
- World Bank project page: terms of use set by the publisher
- World Bank documents: terms of use set by the publisher
Data as of October 18, 2026
| Source | Read on |
|---|---|
| IATI | October 18, 2026 |
| IATI | October 18, 2026 |
| IDA Statement of Credits and Grants | October 18, 2026 |
| Public investment program | October 18, 2026 |
| World Bank procurement notices | October 11, 2026 |
| World Bank Projects | October 18, 2026 |
| World Bank documents | October 18, 2026 |
Cite this page
HaitiDocs. Strengthening Primary Health Care and Surveillance. Partner portfolio, data as of October 18, 2026. https://www.haitidocs.org/portfolio/projects/WB%3AP167512