Titre publié : Haiti: Renewable Energy for All

Millions de dollars US sauf indication contraire. Exercice fiscal haïtien, d’octobre à septembre. L’exercice FY2026-27 a commencé le 1er octobre 2026.

Objectif

The Project Development Objective is to scale-up renewable energy investments in Haiti in order to expand and improve access to electricity for households, businesses and community services.

Tel que publié par Projets de la Banque mondiale, dans sa langue d’origine.

Description

The development objective of the Renewable Energy (RE) for All Project for Haiti is to scale-up renewable energy investments in Haiti in order to expand and improve access to electricity for households, businesses, and community services. The project comprises of two components. The first component, grid-connected distributed RE will initiate the scaling up of on-grid RE investments in Haiti, by demonstrating the feasibility and benefits of injecting solar photovoltaic (PV) generation into electricity of Haiti (EDH) grids and developing a supportive policy and regulatory environment for private sector-driven RE investments. It consists of following sub-components: (i) demonstration pilot solar PV investments; and (ii) technical assistance and enabling framework for RE scale up. The second component, off-grid distributed RE will extend

suite

access to clean and modern energy services to households, communities, and enterprises that are not served by EDH by deploying a wide range of off-grid electrification options. It consists of following sub-components: (i) RE municipal grids; (ii) RE for productive and community use; (iii) distributed systems; and (iv) capacity building and technical assistance.

Partenaire
World Bank Group, World Bank
Secteur
Énergie
Stade
En cours depuis le 25 octobre 2017
Approbation
25 octobre 2017
Clôture
30 juin 2027
Instrument
Don d’un fonds fiduciaire exécuté par le bénéficiaire, Grants
Écart du non décaissé
25,4 : les fonds fiduciaires ne figurent pas dans l’état de l’IDA, qui ne donne le non décaissé que pour l’argent de l’IDA; l’état de l’IDA évalue les crédits non décaissés en droits de tirage spéciaux au taux de change du jour
Emprunteur
Republic of Haiti
Agence d’exécution
MTPTC Energy Cell,Ministry of Public Works, Transportation and Communication
Entrée en vigueur
23 juillet 2018
Départements
Sud, Artibonite, Nord-Ouest, Ouest, Centre, Grande Anse, Sud-Est, Nord
Dernière transaction
30 septembre 2026
Identifiant de l’opération
P156719
Cycle de vie3 stades, 12 dates

Historique des stades

StadeDepuis le
Prévue21 mai 2017
Approuvée25 octobre 2017
En cours25 octobre 2017

Événements datés

ÉvénementDateSource
Début prévu16 août 2016IATI
Revue du concept21 mai 2017Projets de la Banque mondiale
Évaluation préalable29 mai 2017Projets de la Banque mondiale
Négociation18 septembre 2017Projets de la Banque mondiale
Début effectif25 octobre 2017IATI
Approbation25 octobre 2017Projets de la Banque mondiale
Premier engagement25 octobre 2017Écritures
Entrée en vigueur23 juillet 2018Projets de la Banque mondiale
Premier décaissement30 avril 2021Écritures
Dernier décaissement30 septembre 2026Écritures
Date de clôture30 juin 2027IATI
Rapport d’achèvement attendu30 décembre 2027Projets de la Banque mondiale

Non décaissé : 12,3 millions de dollars US au 30 septembre 2026, clôture le 30 juin 2027. Décaissé en FY2025-26 : 8,4 millions de dollars US.

Financement

Tableau 1.Financement, millions de dollars US

BailleurMontantMillions de dollars USRôleSource
IDA Grant24,0InstitutionProjets de la Banque mondiale
Strategic Climate Fund Grant23,2Fonds fiduciaireProjets de la Banque mondiale
Energy Sector Management Assistance Program2,9Fonds fiduciaireProjets de la Banque mondiale

Tableau 2.Opérations liées, millions de dollars US

OpérationLienPartenaireStadeEngagementMillions de dollars US
Additional Financing Haiti Renewable Energy for AllFinancement additionnel ou opération filleGroupe de la Banque mondialeEn cours6,9
Additional Financing: Haiti Renewable Energy For AllFinancement additionnel ou opération filleGroupe de la Banque mondialeEn cours39,6
Renewable Energy for AllFinancement additionnel ou opération filleGroupe de la Banque mondialeApprouvée7,1

Tableau 3.Position à la date des données par source (stocks), millions de dollars US

Cette pageMillions de dollars USSourceIATIMillions de dollars US
Engagement50,1IDA, état des crédits et dons24,0
Décaissé12,3IDA, état des crédits et dons10,4
Non décaissé12,3IDA, état des crédits et dons
Coût total19,6Projets de la Banque mondiale

Montants de la Banque mondiale. Approuvé: Engagement net, montant approuvé moins les annulations, en $ É.-U. à la date des données. Décaissé à ce jour: Les décaissements de l'état IDA et de l'API des projets à ce jour, en $ É.-U. Non décaissé: Le solde non décaissé que publie l'état IDA, en $ É.-U. à la date des données. Colonne IATI : les engagements et les décaissements que le partenaire publie dans IATI, convertis en $ É.-U. Les montants selon la source

Modifications de l'opération6 restructurations, pas de composante d'urgence
Date de clôture initiale
Non publié
Prorogations de la date de clôture
Non publié
Restructurations
6
Composante d'urgence
Aucune composante d'intervention d'urgence contingente

Nouveaux engagements et décaissements par exercice

Décaissements, millions de dollars US
FY2017-18, non publién.p.17-18FY2019-20, non publién.p.19-20FY2020-21, 0,7 millions de dollars US0,720-21FY2021-22, 0,8 millions de dollars US0,821-22FY2022-23, 0,5 millions de dollars US0,522-23FY2023-24, 0,4 millions de dollars US0,423-24FY2024-25, 1,5 millions de dollars US224-25FY2025-26, 8,4 millions de dollars US825-26FY2017-18, non publién.p.17-18FY2019-20, non publién.p.19-20FY2020-21, 0,7 millions de dollars US0,720-21FY2021-22, 0,8 millions de dollars US0,821-22FY2022-23, 0,5 millions de dollars US0,522-23FY2023-24, 0,4 millions de dollars US0,423-24FY2024-25, 1,5 millions de dollars US224-25FY2025-26, 8,4 millions de dollars US825-26

Tableau 4.Nouveaux engagements et décaissements par exercice (flux), millions de dollars US

FY2017-18Millions de dollars USFY2019-20Millions de dollars USFY2020-21Millions de dollars USFY2021-22Millions de dollars USFY2022-23Millions de dollars USFY2023-24Millions de dollars USFY2024-25Millions de dollars USFY2025-26Millions de dollars US
Nouveaux engagements26,14,0Non publiéNon publiéNon publiéNon publié20,0Non publié
DécaissementsNon publiéNon publié0,70,80,50,41,58,4
Décaissements cumulésNon publiéNon publié0,71,52,02,43,912,3

Fiches et documents

Écritures29 écritures, du 25 octobre 2017 au 30 septembre 2026

Tableau 5.Écritures, millions de dollars US

DateMesureMontantMillions de dollars USSourceMéthode
25 octobre 2017Engagement26,1Projets de la Banque mondialetrust funds in the Projects API financier list, not in the IDA statement, at the board approval date
30 septembre 2020Engagement4,0IDA, état des crédits et donscredit original principal at board approval
18 octobre 2024Engagement20,0IDA, état des crédits et donscredit original principal at board approval
30 avril 2021Décaissements0,4IDA, état des crédits et donsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
31 mai 2021Décaissements0,3IDA, état des crédits et donsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
31 octobre 2021Décaissements0,5IDA, état des crédits et donsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
30 novembre 2021Décaissements0,3IDA, état des crédits et donsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
31 décembre 2022Décaissements0,1IDA, état des crédits et donsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
28 février 2023Décaissements0,1IDA, état des crédits et donsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
30 avril 2023Décaissements<0,1IDA, état des crédits et donsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
31 mai 2023Décaissements0,1IDA, état des crédits et donsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
31 août 2023Décaissements0,1IDA, état des crédits et donsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
30 novembre 2023Décaissements0,2IDA, état des crédits et donsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
31 décembre 2023Décaissements0,1IDA, état des crédits et donsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
31 mai 2024Décaissements0,1IDA, état des crédits et donsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
30 novembre 2024Décaissements0,4IDA, état des crédits et donsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
28 février 2025Décaissements0,5IDA, état des crédits et donsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
30 avril 2025Décaissements0,5IDA, état des crédits et donsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
30 juin 2025Décaissements<0,1IDA, état des crédits et donsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
30 novembre 2025Décaissements0,3IDA, état des crédits et donsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
31 janvier 2026Décaissements1,1IDA, état des crédits et donsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
28 février 2026Décaissements3,8IDA, état des crédits et donsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
31 mars 2026Décaissements0,3IDA, état des crédits et donsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
31 mars 2026Décaissements<0,1IDA, état des crédits et donsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
30 juin 2026Décaissements1,0IDA, état des crédits et donsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
31 juillet 2026Décaissements0,4IDA, état des crédits et donsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
31 juillet 2026Décaissements<0,1IDA, état des crédits et donsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
31 août 2026Décaissements1,2IDA, état des crédits et donsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
30 septembre 2026Décaissements0,2IDA, état des crédits et donsdifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
Conditions4 des 6 publiés
Type de financement
110 Don standard
Type de flux
Non publié
Type d’aide
C01 Interventions de type projet
Aide liée ou non liée
5 Non lié
Type de collaboration
2 Apports multilatéraux entrants
Humanitaire
Non publié
Localisation8 départements, 23 lieux nommés, 42 lieux avec coordonnées
DépartementsSud, Artibonite, Nord-Ouest, Ouest, Centre, Grande Anse, Sud-Est, Nord
Lieux nommés par la sourceAquin, Arrondissement des Coteaux, Camp Perrin, Cap Haitien, Chivre, DEpartement de l'Artibonite, Drouet, Département de l'Artibonite, Jacmel, Jeremi, Les Anglais, Les Cayes, PEligre, Plateau, Port-au-Prince, Port-de-Paix, Port-à-Piment, Péligre, Republic of Haiti, Roche-à-Bateau, Saint-Marc, Tiburon, Tigwav
Lieux avec coordonnées42
Indicateurs de résultats45 indicateurs
IndicateurValeur de référenceCibleDernière valeurDate de la dernière valeur
Actions are taken in a timely manner in response to beneficiary feedback from phone surveys and household visitsNoYesYes15 juin 2026
Annual electricity output from renewable energy, as a result of SREP interventions (Component 1)0.008.801315 juin 2026
Annual electricity output from renewable energy, as a result of SREP interventions (Component 2)0.0010.201.7415 juin 2026
Annual greenhouse gas emission reductions (Component 1)0.007,000.00350015 juin 2026
Annual greenhouse gas emission reductions (Component 2)0.0018,475.0015,95415 juin 2026
Electricity access gap between mono-parental rural households and other rural households (Component 2)Baseline to be established based on a survey, to be completed within the first year of implementation after the approval of the AFBaseline minus 5 pp015 juin 2026
Enabling framework for mini-grids, including Tripartite Service Agreements in place (Component 2)NoYesYes15 juin 2026
Gap between the share of men and women not feeling safe to go out after darkBaseline to be established based on a survey, to be completed within the first year of implementation after the approval of the AFBaseline minus 3pp015 juin 2026
Generation capacity of energy constructed or rehabilitated (Component 1)0.005.503.515 juin 2026
Generation capacity of energy constructed or rehabilitated (Component 2)0.005.001.215 juin 2026
Increased public and private investments in targeted subsectors as a result of SREP interventions (Component 1)0.0013.5026.915 juin 2026
Increased public and private investments in targeted subsectors as a result of SREP interventions (Component 2)0.00648.36515 juin 2026
Number of businesses and community services benefitting from improved access to electricity and fuels, as a result of SREP interventions (Component 1)0.00800.0093.0030 novembre 2023
Number of businesses and community services benefitting from improved access to electricity and fuels, as a result of SREP interventions (Component 2)0.003900.00957.0030 novembre 2023
Number of female jobs and female-headed (micro-) enterprises created (Component 2)0.001000.00157.0030 novembre 2023
Number of people benefitting from improved access to electricity and fuels, as a result of SREP interventions (Component 1)0.0080000.0053000.0030 novembre 2023
Number of people trained in renewable energy (Component 2)0.003000.0020.0030 novembre 2023
Number of people, benefitting from improved access to electricity and fuels, as a result of SREP interventions (Component 2)0.00350000.0080920.0030 novembre 2023
Number of women benefitting from improved access to electricity and fuels, as a result of SREP interventions (Component 1)0.0042000.0026500.0030 novembre 2023
Number of women with improved access to electricity and fuels, as a result of SREP interventions (Component 2)0.00178000.0040460.0030 novembre 2023
People served by facilities with new or improved electricity supply in response to COVID-19 (Component 1)0.00900,000.0053,00015 juin 2026
People served by facilities with new or improved electricity supply in response to COVID-19 (Component 2)0.00100,000.00015 juin 2026
Users reporting mini-grid or off-grid electricity service provided according to the advertised performance0.0080.00015 juin 2026
of which prioritized healthcare and water facilities in the context of COVID-19 (Component 1)0.0024.008.0030 novembre 2023
of which prioritized healthcare and water facilities in the context of COVID-19 (Component 2)0.006.006.0030 novembre 2023
Enabling policy and regulatory framework for clean energy and access enacted11.0035.0022.715 juin 2026
Enterprises and community services with new or improved electricity service0.00300.0040915 juin 2026
People provided with new or improved electricity service0.00330,000.00241,76915 juin 2026
Private investment and other commercial financing leveraged0.0040.0012.36515 juin 2026
Total Private Capital Mobilized($m)0.0040.0012.365Non publié
Women and girls provided with new or improved electricity service0.00179,000.00111,88415 juin 2026
Businesses and community services benefitting from improved access to electricity and fuels, as a result of SREP interventions (Component 1)0.00350.009315 juin 2026
Businesses and community services benefitting from improved access to electricity and fuels, as a result of SREP interventions (Component 2)0.00350.0095715 juin 2026
Female jobs and female-headed (micro-) enterprises created (Component 2)0.00250.0015715 juin 2026
Net GHG emissions per year (Component 1)0.0080003500Non publié
Net GHG emissions per year (Component 2)0.0018,475.0024,756Non publié
People benefitting from improved access to electricity and fuels, as a result of SREP interventions (Component 1)0.0080,000.0053,00015 juin 2026
People trained in renewable energy (Component 2)0.001,000.002015 juin 2026
People, benefitting from improved access to electricity and fuels, as a result of SREP interventions (Component 2)0.00350,000.00234,00015 juin 2026
Total Private Capital Mobilized as a result of SREP interventions (Component 2)0.00408.64Non publié
Total Private Capital Mobilized ($m) as a result of SREP interventions (Component 1)0.0013.5026.9Non publié
Women benefitting from improved access to electricity and fuels, as a result of SREP interventions (Component 1)0.0042,000.0026.50015 juin 2026
Women with improved access to electricity and fuels, as a result of SREP interventions (Component 2)0.00178,000.00117,00015 juin 2026
People served by facilities with new or improved electricity supply in response to COVID-190.000.00Non publiéNon publié
of which prioritized healthcare and water facilities in the context of COVID-190.0030.006.0030 novembre 2023
Notations6 notations
NotationValeurDate
ISR Financial ManagementModerately Satisfactory23 juillet 2026
ISR Monitoring and EvaluationSatisfactory23 juillet 2026
ISR Overall Implementation Progress (IP)Moderately Satisfactory23 juillet 2026
ISR ProcurementSatisfactory23 juillet 2026
ISR Progress towards achievement of PDOSatisfactory23 juillet 2026
ISR Project ManagementModerately Satisfactory23 juillet 2026
Marchés attribués27 marchés
FournisseurDateMéthodeMontant
Societe de GENIE Conseil S.A.3 juin 2026QCBS302 799,56 USD
Sunpower and Technology27 mai 2026RFQ45 240 USD
TRAMA Tecnoambiental (TTA) S.L.23 avril 2026CDS949 175,07 USD
Emerens Limited (Lead)27 mars 2026CDS487 200 USD
Institut Haitien de l'Energie2 décembre 2025CDS5 779 911,26 HTG
Esd Engineering & Service, SRL12 novembre 2025RFB18 688 595,2 USD
Esd Engineering & Service, SRL12 novembre 2025RFBNon publié
Firme Turnier26 février 2025LCS933 000 HTG
Odyssey Energy Solutions Inc23 novembre 2023DIR17 451 USD
Elmecen S.A.19 octobre 2023RFB335 870 USD
Iideveloppement GmbH14 novembre 2022CDS378 947 USD
Nom non affiché29 juin 2022CDS280 046 USD
Nom non affiché9 juin 2022INDV27 000 USD
Experts Conseils et Associes14 mars 2022LCS6 971 520 HTG
Centre for Consultancy Research and Development Enterprise (CCORD)15 décembre 2021LCS416 340 USD
Emerens Consulting Limited15 décembre 2021LCSNon publié
Société du Canal de Provence (SCP)30 septembre 2021CDS326 050,13 EUR
Société Génie Conseil S.A30 septembre 2021CDSNon publié
Hydroconseil12 mai 2021CQS304 237,5 EUR
Centrale de Gestion et de Service (CGS)12 mai 2021CQSNon publié
Accounting & Finance Corp. (Acfinco)8 avril 2021CDS1 330 000 Gourde haïtienne
United Nations Office Project Services (UNOPS)19 janvier 2021DIR4 499 981 USD
Digitalkap15 décembre 2020RFQ23 087 USD
Odyssey Energy Solutions, Inc.19 août 2020DIR216 092,63 USD
Accounting & Finance Corp. (Acfinco)12 juin 2020LCS1 330 000 HTG
TRAMA Tecnoambiental (TTA) S.L.15 janvier 2020QCBS266 050,53 EUR
TRAMA Tecnoambiental (TTA) S.L.15 janvier 2020QCBS346 134,87 EUR
Fonds transférés24 mouvements
BénéficiaireMouvementDateMillions de dollars US
Ministry of Public Works, Transportation and Communication; MTPTC Energy CellDécaissement30 juin 20261,0
Ministry of Public Works, Transportation and Communication; MTPTC Energy CellDécaissement31 mars 20260,3
Ministry of Public Works, Transportation and Communication; MTPTC Energy CellDécaissement31 mars 2026<0,1
Ministry of Public Works, Transportation and Communication; MTPTC Energy CellDécaissement28 février 20263,8
Ministry of Public Works, Transportation and Communication; MTPTC Energy CellDécaissement31 janvier 20261,1
Ministry of Public Works, Transportation and Communication; MTPTC Energy CellDécaissement30 novembre 20250,3
Ministry of Public Works, Transportation and Communication; MTPTC Energy CellDécaissement30 juin 2025<0,1
Ministry of Public Works, Transportation and Communication; MTPTC Energy CellDécaissement30 avril 20250,5
Ministry of Public Works, Transportation and Communication; MTPTC Energy CellDécaissement28 février 20250,5
Ministry of Public Works, Transportation and Communication; MTPTC Energy CellDécaissement30 novembre 20240,4
Ministry of Public Works, Transportation and Communication; MTPTC Energy CellEngagement31 octobre 202420,0
Ministry of Public Works, Transportation and Communication; MTPTC Energy CellDécaissement31 mai 20240,1
Ministry of Public Works, Transportation and Communication; MTPTC Energy CellDécaissement31 décembre 20230,1
Ministry of Public Works, Transportation and Communication; MTPTC Energy CellDécaissement30 novembre 20230,2
Ministry of Public Works, Transportation and Communication; MTPTC Energy CellDécaissement31 août 20230,1
Ministry of Public Works, Transportation and Communication; MTPTC Energy CellDécaissement31 mai 20230,1
Ministry of Public Works, Transportation and Communication; MTPTC Energy CellDécaissement30 avril 2023<0,1
Ministry of Public Works, Transportation and Communication; MTPTC Energy CellDécaissement28 février 20230,1
Ministry of Public Works, Transportation and Communication; MTPTC Energy CellDécaissement31 décembre 20220,1
Ministry of Public Works, Transportation and Communication; MTPTC Energy CellDécaissement30 novembre 20210,3
Ministry of Public Works, Transportation and Communication; MTPTC Energy CellDécaissement31 octobre 20210,5
Ministry of Public Works, Transportation and Communication; MTPTC Energy CellDécaissement31 mai 20210,3
Ministry of Public Works, Transportation and Communication; MTPTC Energy CellDécaissement30 avril 20210,4
Ministry of Public Works, Transportation and Communication; MTPTC Energy CellEngagement30 septembre 20204,0
Identifiants8 identifiants
SystèmeIdentifiantSource
Identifiant IATI44000-P156719IATI
Crédit ou don IDAIDAD7300IDA, état des crédits et dons
Crédit ou don IDAIDAE3580IDA, état des crédits et dons
Ligne du programme d’investissement public1114-1-12-55-42Programme d’investissement public
Prêt de la Banque mondialeIDA-D7300Projets de la Banque mondiale
Prêt de la Banque mondialeIDA-E3580Projets de la Banque mondiale
Prêt de la Banque mondialeTF-C9683Projets de la Banque mondiale
Projet de la Banque mondialeP156719Fiche de l’opération
Écarts entre les sources1 champ
ChampSourceValeurRetenue
EngagementIDA, état des crédits et dons50,1 millions de dollars US✓
EngagementIATI24,0 millions de dollars US
Documents du partenaire86 documents
Avis de marchés (2)

Documents sur HaitiDocs

Sources

Données au 18 octobre 2026
SourceLu le
IATI18 octobre 2026
IATI18 octobre 2026
IDA, état des crédits et dons18 octobre 2026
Programme d’investissement public18 octobre 2026
Avis de passation de marchés de la Banque mondiale18 octobre 2026
Projets de la Banque mondiale18 octobre 2026
Documents de la Banque mondiale18 octobre 2026
Citer cette page

HaitiDocs. Énergie renouvelable pour tous. Portefeuille des partenaires, données au 18 octobre 2026. https://www.haitidocs.org/portfolio/projects/WB%3AP156719?lang=fr