Enèji renouvlab pou tout moun

Tit pibliye: Haiti: Renewable Energy for All

An milyon dola ameriken sof si yo di lòt bagay. Ane fiskal ayisyen, soti oktòb rive septanm. FY2026-27 te kòmanse 1 oktòb 2026.

Objektif

The Project Development Objective is to scale-up renewable energy investments in Haiti in order to expand and improve access to electricity for households, businesses and community services.

Jan Pwojè Bank Mondyal pibliye l, nan lang orijinal li.

Deskripsyon

The development objective of the Renewable Energy (RE) for All Project for Haiti is to scale-up renewable energy investments in Haiti in order to expand and improve access to electricity for households, businesses, and community services. The project comprises of two components. The first component, grid-connected distributed RE will initiate the scaling up of on-grid RE investments in Haiti, by demonstrating the feasibility and benefits of injecting solar photovoltaic (PV) generation into electricity of Haiti (EDH) grids and developing a supportive policy and regulatory environment for private sector-driven RE investments. It consists of following sub-components: (i) demonstration pilot solar PV investments; and (ii) technical assistance and enabling framework for RE scale up. The second component, off-grid distributed RE will extend

plis

access to clean and modern energy services to households, communities, and enterprises that are not served by EDH by deploying a wide range of off-grid electrification options. It consists of following sub-components: (i) RE municipal grids; (ii) RE for productive and community use; (iii) distributed systems; and (iv) capacity building and technical assistance.

Patnè
World Bank Group, World Bank
Sektè
Enèji
Etap
An kou depi 25 oktòb 2017
Apwobasyon
25 oktòb 2017
Fèmen
30 jen 2027
Enstriman
Don yon fon fidisyè benefisyè a egzekite, Grants
Diferans nan sa ki poko dekese
25.4: fon fidisyè yo pa nan eta IDA a, ki bay montan ki poko dekese pou lajan IDA sèlman; eta IDA a evalye kredi ki poko dekese an dwa tiraj espesyal yo nan to chanj jodi a
Anprentè
Republic of Haiti
Ajans egzekisyon
MTPTC Energy Cell,Ministry of Public Works, Transportation and Communication
Antre an vigè
23 jiyè 2018
Depatman
Sid, Latibonit, Nòdwès, Lwès, Sant, Grandans, Sidès, Nò
Dènye tranzaksyon
30 septanm 2026
Idantifyan operasyon an
P156719
Sik lavi3 etap, 12 dat

Istwa etap yo

EtapDepi
Planifye21 me 2017
Apwouve25 oktòb 2017
An kou25 oktòb 2017

Evènman ki gen dat

EvènmanDatSous
Kòmansman prevwa16 out 2016IATI
Revizyon konsèp21 me 2017Pwojè Bank Mondyal
Evalyasyon davans29 me 2017Pwojè Bank Mondyal
Negosyasyon18 septanm 2017Pwojè Bank Mondyal
Kòmansman reyèl25 oktòb 2017IATI
Apwobasyon25 oktòb 2017Pwojè Bank Mondyal
Premye angajman25 oktòb 2017Tranzaksyon
Antre an vigè23 jiyè 2018Pwojè Bank Mondyal
Premye dekèsman30 avril 2021Tranzaksyon
Dènye dekèsman30 septanm 2026Tranzaksyon
Dat fèmti30 jen 2027IATI
Rapò fen atann30 desanm 2027Pwojè Bank Mondyal

Pa dekèse: 12.3 milyon dola ameriken jiska 30 septanm 2026, dat fèmti 30 jen 2027. Dekèse nan FY2025-26: 8.4 milyon dola ameriken.

Finansman

Tablo 1.Finansman, milyon dola ameriken

FinansèMontanMilyon dola amerikenWòlSous
IDA Grant24.0EnstitisyonPwojè Bank Mondyal
Strategic Climate Fund Grant23.2Fon fidisyèPwojè Bank Mondyal
Energy Sector Management Assistance Program2.9Fon fidisyèPwojè Bank Mondyal

Tablo 2.Operasyon ki gen rapò, milyon dola ameriken

OperasyonRapòPatnèEtapAngajmanMilyon dola ameriken
Additional Financing Haiti Renewable Energy for AllFinansman adisyonèl oswa operasyon pititGwoup Bank MondyalAn kou6.9
Additional Financing: Haiti Renewable Energy For AllFinansman adisyonèl oswa operasyon pititGwoup Bank MondyalAn kou39.6
Renewable Energy for AllFinansman adisyonèl oswa operasyon pititGwoup Bank MondyalApwouve7.1

Tablo 3.Pozisyon nan dat done yo pa sous (stòk), milyon dola ameriken

Paj sa aMilyon dola amerikenSousIATIMilyon dola ameriken
Angajman50.1IDA, eta kredi ak don24.0
Dekèse12.3IDA, eta kredi ak don10.4
Pa dekèse12.3IDA, eta kredi ak don
Pri total19.6Pwojè Bank Mondyal

Montan Bank Mondyal. Apwouve: Angajman nèt, montan apwouve mwens anilasyon yo, an US$ nan dat done yo. Dekèse jiska jodi a: Dekèsman deklarasyon IDA a ak API pwojè yo jiska jodi a, an US$. Pa dekèse: Balans ki pa dekèse deklarasyon IDA a pibliye, an US$ nan dat done yo. Kolòn IATI: angajman ak dekèsman patnè a pibliye nan IATI, konvèti an US$. Montan yo dapre sous la

Chanjman nan operasyon an6 restriktirasyon, pa gen konpozan ijans
Dat fèmti orijinal
Pa rapòte
Pwolongasyon dat fèmti
Pa rapòte
Restriktirasyon
6
Konpozan ijans
Pa gen konpozan repons ijans kontenjan

Nouvo angajman ak dekèsman pa ane fiskal

Dekèsman, milyon dola ameriken
FY2017-18, pa rapòtep.r.17-18FY2019-20, pa rapòtep.r.19-20FY2020-21, 0.7 milyon dola ameriken0.720-21FY2021-22, 0.8 milyon dola ameriken0.821-22FY2022-23, 0.5 milyon dola ameriken0.522-23FY2023-24, 0.4 milyon dola ameriken0.423-24FY2024-25, 1.5 milyon dola ameriken224-25FY2025-26, 8.4 milyon dola ameriken825-26FY2017-18, pa rapòtep.r.17-18FY2019-20, pa rapòtep.r.19-20FY2020-21, 0.7 milyon dola ameriken0.720-21FY2021-22, 0.8 milyon dola ameriken0.821-22FY2022-23, 0.5 milyon dola ameriken0.522-23FY2023-24, 0.4 milyon dola ameriken0.423-24FY2024-25, 1.5 milyon dola ameriken224-25FY2025-26, 8.4 milyon dola ameriken825-26

Tablo 4.Nouvo angajman ak dekèsman pa ane fiskal (flo), milyon dola ameriken

FY2017-18Milyon dola amerikenFY2019-20Milyon dola amerikenFY2020-21Milyon dola amerikenFY2021-22Milyon dola amerikenFY2022-23Milyon dola amerikenFY2023-24Milyon dola amerikenFY2024-25Milyon dola amerikenFY2025-26Milyon dola ameriken
Nouvo angajman26.14.0Pa rapòtePa rapòtePa rapòtePa rapòte20.0Pa rapòte
DekèsmanPa rapòtePa rapòte0.70.80.50.41.58.4
Dekèsman kimilePa rapòtePa rapòte0.71.52.02.43.912.3

Fich ak dokiman

Tranzaksyon29 liy, 25 oktòb 2017 rive 30 septanm 2026

Tablo 5.Tranzaksyon, milyon dola ameriken

DatMeziMontanMilyon dola amerikenSousMetòd
25 oktòb 2017Angajman26.1Pwojè Bank Mondyaltrust funds in the Projects API financier list, not in the IDA statement, at the board approval date
30 septanm 2020Angajman4.0IDA, eta kredi ak doncredit original principal at board approval
18 oktòb 2024Angajman20.0IDA, eta kredi ak doncredit original principal at board approval
30 avril 2021Dekèsman0.4IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
31 me 2021Dekèsman0.3IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
31 oktòb 2021Dekèsman0.5IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
30 novanm 2021Dekèsman0.3IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
31 desanm 2022Dekèsman0.1IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
28 fevriye 2023Dekèsman0.1IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
30 avril 2023Dekèsman<0.1IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
31 me 2023Dekèsman0.1IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
31 out 2023Dekèsman0.1IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
30 novanm 2023Dekèsman0.2IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
31 desanm 2023Dekèsman0.1IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
31 me 2024Dekèsman0.1IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
30 novanm 2024Dekèsman0.4IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
28 fevriye 2025Dekèsman0.5IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
30 avril 2025Dekèsman0.5IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
30 jen 2025Dekèsman<0.1IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
30 novanm 2025Dekèsman0.3IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
31 janvye 2026Dekèsman1.1IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
28 fevriye 2026Dekèsman3.8IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
31 mas 2026Dekèsman0.3IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
31 mas 2026Dekèsman<0.1IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
30 jen 2026Dekèsman1.0IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
31 jiyè 2026Dekèsman0.4IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
31 jiyè 2026Dekèsman<0.1IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
31 out 2026Dekèsman1.2IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
30 septanm 2026Dekèsman0.2IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
Kondisyon4 sou 6 rapòte
Kalite finansman
110 Don estanda
Kalite koule
Pa rapòte
Kalite èd
C01 Entèvansyon kalite pwojè
Èd mare oswa pa mare
5 Pa mare
Kalite kolaborasyon
2 Apò miltilateral k ap antre
Imanitè
Pa rapòte
Kote8 depatman, 23 kote nonmen, 42 kote ki gen kowòdone
DepatmanSid, Latibonit, Nòdwès, Lwès, Sant, Grandans, Sidès, Nò
Kote sous la nonmenAquin, Arrondissement des Coteaux, Camp Perrin, Cap Haitien, Chivre, DEpartement de l'Artibonite, Drouet, Département de l'Artibonite, Jacmel, Jeremi, Les Anglais, Les Cayes, PEligre, Plateau, Port-au-Prince, Port-de-Paix, Port-à-Piment, Péligre, Republic of Haiti, Roche-à-Bateau, Saint-Marc, Tiburon, Tigwav
Kote ki gen kowòdone42
Endikatè rezilta45 endikatè
EndikatèValè referansSibDènye valèDat dènye valè
Actions are taken in a timely manner in response to beneficiary feedback from phone surveys and household visitsNoYesYes15 jen 2026
Annual electricity output from renewable energy, as a result of SREP interventions (Component 1)0.008.801315 jen 2026
Annual electricity output from renewable energy, as a result of SREP interventions (Component 2)0.0010.201.7415 jen 2026
Annual greenhouse gas emission reductions (Component 1)0.007,000.00350015 jen 2026
Annual greenhouse gas emission reductions (Component 2)0.0018,475.0015,95415 jen 2026
Electricity access gap between mono-parental rural households and other rural households (Component 2)Baseline to be established based on a survey, to be completed within the first year of implementation after the approval of the AFBaseline minus 5 pp015 jen 2026
Enabling framework for mini-grids, including Tripartite Service Agreements in place (Component 2)NoYesYes15 jen 2026
Gap between the share of men and women not feeling safe to go out after darkBaseline to be established based on a survey, to be completed within the first year of implementation after the approval of the AFBaseline minus 3pp015 jen 2026
Generation capacity of energy constructed or rehabilitated (Component 1)0.005.503.515 jen 2026
Generation capacity of energy constructed or rehabilitated (Component 2)0.005.001.215 jen 2026
Increased public and private investments in targeted subsectors as a result of SREP interventions (Component 1)0.0013.5026.915 jen 2026
Increased public and private investments in targeted subsectors as a result of SREP interventions (Component 2)0.00648.36515 jen 2026
Number of businesses and community services benefitting from improved access to electricity and fuels, as a result of SREP interventions (Component 1)0.00800.0093.0030 novanm 2023
Number of businesses and community services benefitting from improved access to electricity and fuels, as a result of SREP interventions (Component 2)0.003900.00957.0030 novanm 2023
Number of female jobs and female-headed (micro-) enterprises created (Component 2)0.001000.00157.0030 novanm 2023
Number of people benefitting from improved access to electricity and fuels, as a result of SREP interventions (Component 1)0.0080000.0053000.0030 novanm 2023
Number of people trained in renewable energy (Component 2)0.003000.0020.0030 novanm 2023
Number of people, benefitting from improved access to electricity and fuels, as a result of SREP interventions (Component 2)0.00350000.0080920.0030 novanm 2023
Number of women benefitting from improved access to electricity and fuels, as a result of SREP interventions (Component 1)0.0042000.0026500.0030 novanm 2023
Number of women with improved access to electricity and fuels, as a result of SREP interventions (Component 2)0.00178000.0040460.0030 novanm 2023
People served by facilities with new or improved electricity supply in response to COVID-19 (Component 1)0.00900,000.0053,00015 jen 2026
People served by facilities with new or improved electricity supply in response to COVID-19 (Component 2)0.00100,000.00015 jen 2026
Users reporting mini-grid or off-grid electricity service provided according to the advertised performance0.0080.00015 jen 2026
of which prioritized healthcare and water facilities in the context of COVID-19 (Component 1)0.0024.008.0030 novanm 2023
of which prioritized healthcare and water facilities in the context of COVID-19 (Component 2)0.006.006.0030 novanm 2023
Enabling policy and regulatory framework for clean energy and access enacted11.0035.0022.715 jen 2026
Enterprises and community services with new or improved electricity service0.00300.0040915 jen 2026
People provided with new or improved electricity service0.00330,000.00241,76915 jen 2026
Private investment and other commercial financing leveraged0.0040.0012.36515 jen 2026
Total Private Capital Mobilized($m)0.0040.0012.365Pa rapòte
Women and girls provided with new or improved electricity service0.00179,000.00111,88415 jen 2026
Businesses and community services benefitting from improved access to electricity and fuels, as a result of SREP interventions (Component 1)0.00350.009315 jen 2026
Businesses and community services benefitting from improved access to electricity and fuels, as a result of SREP interventions (Component 2)0.00350.0095715 jen 2026
Female jobs and female-headed (micro-) enterprises created (Component 2)0.00250.0015715 jen 2026
Net GHG emissions per year (Component 1)0.0080003500Pa rapòte
Net GHG emissions per year (Component 2)0.0018,475.0024,756Pa rapòte
People benefitting from improved access to electricity and fuels, as a result of SREP interventions (Component 1)0.0080,000.0053,00015 jen 2026
People trained in renewable energy (Component 2)0.001,000.002015 jen 2026
People, benefitting from improved access to electricity and fuels, as a result of SREP interventions (Component 2)0.00350,000.00234,00015 jen 2026
Total Private Capital Mobilized as a result of SREP interventions (Component 2)0.00408.64Pa rapòte
Total Private Capital Mobilized ($m) as a result of SREP interventions (Component 1)0.0013.5026.9Pa rapòte
Women benefitting from improved access to electricity and fuels, as a result of SREP interventions (Component 1)0.0042,000.0026.50015 jen 2026
Women with improved access to electricity and fuels, as a result of SREP interventions (Component 2)0.00178,000.00117,00015 jen 2026
People served by facilities with new or improved electricity supply in response to COVID-190.000.00Pa rapòtePa rapòte
of which prioritized healthcare and water facilities in the context of COVID-190.0030.006.0030 novanm 2023
Nòt6 nòt
NòtValèDat
ISR Financial ManagementModerately Satisfactory23 jiyè 2026
ISR Monitoring and EvaluationSatisfactory23 jiyè 2026
ISR Overall Implementation Progress (IP)Moderately Satisfactory23 jiyè 2026
ISR ProcurementSatisfactory23 jiyè 2026
ISR Progress towards achievement of PDOSatisfactory23 jiyè 2026
ISR Project ManagementModerately Satisfactory23 jiyè 2026
Kontra yo bay27 kontra
FounisèDatMetòdMontan
Societe de GENIE Conseil S.A.3 jen 2026QCBS302,799.56 USD
Sunpower and Technology27 me 2026RFQ45,240 USD
TRAMA Tecnoambiental (TTA) S.L.23 avril 2026CDS949,175.07 USD
Emerens Limited (Lead)27 mas 2026CDS487,200 USD
Institut Haitien de l'Energie2 desanm 2025CDS5,779,911.26 HTG
Esd Engineering & Service, SRL12 novanm 2025RFB18,688,595.2 USD
Esd Engineering & Service, SRL12 novanm 2025RFBPa rapòte
Firme Turnier26 fevriye 2025LCS933,000 HTG
Odyssey Energy Solutions Inc23 novanm 2023DIR17,451 USD
Elmecen S.A.19 oktòb 2023RFB335,870 USD
Iideveloppement GmbH14 novanm 2022CDS378,947 USD
Non an pa afiche29 jen 2022CDS280,046 USD
Non an pa afiche9 jen 2022INDV27,000 USD
Experts Conseils et Associes14 mas 2022LCS6,971,520 HTG
Centre for Consultancy Research and Development Enterprise (CCORD)15 desanm 2021LCS416,340 USD
Emerens Consulting Limited15 desanm 2021LCSPa rapòte
Société du Canal de Provence (SCP)30 septanm 2021CDS326,050.13 EUR
Société Génie Conseil S.A30 septanm 2021CDSPa rapòte
Hydroconseil12 me 2021CQS304,237.5 EUR
Centrale de Gestion et de Service (CGS)12 me 2021CQSPa rapòte
Accounting & Finance Corp. (Acfinco)8 avril 2021CDS1,330,000 Gourde haïtienne
United Nations Office Project Services (UNOPS)19 janvye 2021DIR4,499,981 USD
Digitalkap15 desanm 2020RFQ23,087 USD
Odyssey Energy Solutions, Inc.19 out 2020DIR216,092.63 USD
Accounting & Finance Corp. (Acfinco)12 jen 2020LCS1,330,000 HTG
TRAMA Tecnoambiental (TTA) S.L.15 janvye 2020QCBS266,050.53 EUR
TRAMA Tecnoambiental (TTA) S.L.15 janvye 2020QCBS346,134.87 EUR
Lajan ki pase bay lòt24 mouvman
BenefisyèMouvmanDatMilyon dola ameriken
Ministry of Public Works, Transportation and Communication; MTPTC Energy CellDekèsman30 jen 20261.0
Ministry of Public Works, Transportation and Communication; MTPTC Energy CellDekèsman31 mas 20260.3
Ministry of Public Works, Transportation and Communication; MTPTC Energy CellDekèsman31 mas 2026<0.1
Ministry of Public Works, Transportation and Communication; MTPTC Energy CellDekèsman28 fevriye 20263.8
Ministry of Public Works, Transportation and Communication; MTPTC Energy CellDekèsman31 janvye 20261.1
Ministry of Public Works, Transportation and Communication; MTPTC Energy CellDekèsman30 novanm 20250.3
Ministry of Public Works, Transportation and Communication; MTPTC Energy CellDekèsman30 jen 2025<0.1
Ministry of Public Works, Transportation and Communication; MTPTC Energy CellDekèsman30 avril 20250.5
Ministry of Public Works, Transportation and Communication; MTPTC Energy CellDekèsman28 fevriye 20250.5
Ministry of Public Works, Transportation and Communication; MTPTC Energy CellDekèsman30 novanm 20240.4
Ministry of Public Works, Transportation and Communication; MTPTC Energy CellAngajman31 oktòb 202420.0
Ministry of Public Works, Transportation and Communication; MTPTC Energy CellDekèsman31 me 20240.1
Ministry of Public Works, Transportation and Communication; MTPTC Energy CellDekèsman31 desanm 20230.1
Ministry of Public Works, Transportation and Communication; MTPTC Energy CellDekèsman30 novanm 20230.2
Ministry of Public Works, Transportation and Communication; MTPTC Energy CellDekèsman31 out 20230.1
Ministry of Public Works, Transportation and Communication; MTPTC Energy CellDekèsman31 me 20230.1
Ministry of Public Works, Transportation and Communication; MTPTC Energy CellDekèsman30 avril 2023<0.1
Ministry of Public Works, Transportation and Communication; MTPTC Energy CellDekèsman28 fevriye 20230.1
Ministry of Public Works, Transportation and Communication; MTPTC Energy CellDekèsman31 desanm 20220.1
Ministry of Public Works, Transportation and Communication; MTPTC Energy CellDekèsman30 novanm 20210.3
Ministry of Public Works, Transportation and Communication; MTPTC Energy CellDekèsman31 oktòb 20210.5
Ministry of Public Works, Transportation and Communication; MTPTC Energy CellDekèsman31 me 20210.3
Ministry of Public Works, Transportation and Communication; MTPTC Energy CellDekèsman30 avril 20210.4
Ministry of Public Works, Transportation and Communication; MTPTC Energy CellAngajman30 septanm 20204.0
Idantifyan8 idantifyan
SistèmIdantifyanSous
Idantifyan IATI44000-P156719IATI
Kredi oswa don IDAIDAD7300IDA, eta kredi ak don
Kredi oswa don IDAIDAE3580IDA, eta kredi ak don
Liy pwogram envestisman piblik1114-1-12-55-42Pwogram envestisman piblik
Prè Bank mondyalIDA-D7300Pwojè Bank Mondyal
Prè Bank mondyalIDA-E3580Pwojè Bank Mondyal
Prè Bank mondyalTF-C9683Pwojè Bank Mondyal
Pwojè Bank mondyalP156719Fich operasyon an
Kote sous yo pa dakò1 chan
ChanSousValèItilize
AngajmanIDA, eta kredi ak don50.1 milyon dola ameriken✓
AngajmanIATI24.0 milyon dola ameriken
Dokiman patnè a86 dokiman
Avi apèl dòf (2)

Dokiman sou HaitiDocs

Sous

Done jiska 18 oktòb 2026
SousLi nan dat
IATI18 oktòb 2026
IATI18 oktòb 2026
IDA, eta kredi ak don18 oktòb 2026
Pwogram envestisman piblik18 oktòb 2026
Avi pasasyon mache Bank mondyal18 oktòb 2026
Pwojè Bank Mondyal18 oktòb 2026
Dokiman Bank Mondyal18 oktòb 2026
Site paj sa a