Données / Portefeuille des partenaires / Groupe de la Banque mondiale / IDA
Projet de développement urbain piloté par les communautés - AF
Titre publié : Haiti - Urban Community Driven Development Project - AF
Millions de dollars US sauf indication contraire. Exercice fiscal haïtien, d’octobre à septembre. L’exercice FY2026-27 a commencé le 1er octobre 2026.
Objectif
To improve access to, and satisfaction with: (i) basic and social infrastructure and services, including housing repair, reconstruction and community infrastructure improvements needed as a result of the Emergency; and (ii) income-generating opportunities for residents of selected disadvantaged urban areas.
Tel que publié par Projets de la Banque mondiale, dans sa langue d’origine.
- Partenaire
- World Bank Group, IDA
- Secteur
- Eau et assainissement
- Stade
- Clôturée depuis le 31 décembre 2016
- Approbation
- 20 juin 2014
- Clôture
- 31 décembre 2016
- Instrument
- Financement BIRD/IDA, IDA
- Entrée en vigueur
- 7 novembre 2014
- Identifiant de l’opération
- P149116
Cycle de vie4 stades, 6 dates
Historique des stades
| Stade | Depuis le |
|---|---|
| Approuvée | 20 juin 2014 |
| En cours | 7 novembre 2014 |
| En clôture | 31 décembre 2016 |
| Clôturée | 31 décembre 2016 |
Événements datés
| Événement | Date | Source |
|---|---|---|
| Évaluation préalable | 14 avril 2014 | Projets de la Banque mondiale |
| Négociation | 1er mai 2014 | Projets de la Banque mondiale |
| Approbation | 20 juin 2014 | Projets de la Banque mondiale |
| Entrée en vigueur | 7 novembre 2014 | IDA, état des crédits et dons |
| Date de clôture | 31 décembre 2016 | Projets de la Banque mondiale |
| Rapport d’achèvement attendu | 31 octobre 2017 | Projets de la Banque mondiale |
Financement
Tableau 1.Financement, millions de dollars US
| Bailleur | MontantMillions de dollars US | Rôle | Source |
|---|---|---|---|
| IDA Grant | 7,5 | Institution | Projets de la Banque mondiale |
Tableau 2.Opérations liées, millions de dollars US
| Opération | Lien | Partenaire | Stade | EngagementMillions de dollars US |
|---|---|---|---|---|
| Urban Community Driven Development Project / PRODEPUR | Opération mère | Groupe de la Banque mondiale | Clôturée | 52,9 |
| Housing Reconstruction - Urban Community Driven Development Additional Financing | Même opération mère | Groupe de la Banque mondiale | Clôturée | 30,0 |
Tableau 3.Position à la date des données par source (stocks), millions de dollars US
| Cette pageMillions de dollars US | Source | |
|---|---|---|
| Engagement | 7,5 | Projets de la Banque mondiale |
| Décaissé | Non publié | |
| Non décaissé | Non publié | |
| Coût total | 7,5 | Projets de la Banque mondiale |
Montants de la Banque mondiale. Approuvé: Engagement net, montant approuvé moins les annulations, en $ É.-U. à la date des données. Décaissé à ce jour: Les décaissements de l'état IDA et de l'API des projets à ce jour, en $ É.-U. Non décaissé: Le solde non décaissé que publie l'état IDA, en $ É.-U. à la date des données. Les montants selon la source
Modifications de l'opération1 prorogation
- Date de clôture initiale
- 30 juin 2016
- Prorogations de la date de clôture
- 1
- Prorogée du 30 juin 2016 au 31 décembre 2016 (document du 31 mai 2016)
- Restructurations
- Non publié
- Composante d'urgence
- Non publié
Fiches et documents
Indicateurs de résultats28 indicateurs
| Indicateur | Valeur de référence | Cible | Dernière valeur | Date de la dernière valeur |
|---|---|---|---|---|
| AF. Cumulative number of housing repair and reconstruction works financed through grants and completed | 1153 | Original: 5000Revised: 1204 | 1153 | 30 septembre 2013 |
| Cumulative number of housing repair and reconstruction works financed through grants and completed | 0.00 | 1384.00 | 1153.00 | 30 septembre 2013 |
| Health facilities constructed, renovated, and/or equipped (number) | 0.00 | 5.00 | 3.00 | 21 mars 2014 |
| Number of corridors repaired | 0.00 | 108.00 | 31.00 | 30 septembre 2013 |
| Number of eligible CBOs joining COPRODEPs | 0.00 | 1173.00 | 1119.00 | 21 mars 2014 |
| Number of eligible CBOs joining COPRODEPs. | N/A | Original: 80%Revised: 1000 | 1275 | 28 juin 2013 |
| Number of people in urban areas provided with access to Improved Water Sources under the project | 0.00 | 63650.00 | 47150.00 | 21 mars 2014 |
| Percent of municipal governments successfully proposing and implementing subprojects in coordination with CBOs | 0.00 | 100.00 | 100.00 | 21 mars 2014 |
| Percent of prioritized projects submitted by women’s CBOs | 13.00 | 15.00 | 13.00 | 21 mars 2014 |
| Percent of subprojects completed in a timely manner | 0.00 | 85.00 | 74.00 | 21 mars 2014 |
| Percent of subprojects successfully implemented, operated, and maintained (as per technical audits) | 0.00 | 70.00 | 70.00 | 21 mars 2014 |
| Percent of women holding membership in COPRODEP’s executive committee | 24.00 | 30.00 | 24.00 | 21 mars 2014 |
| Roads rehabilitated, Non-rural | 0.00 | 16.00 | 7.44 | 21 mars 2013 |
| Volume of construction debris cleared in Project neighborhoods | 0.00 | 41747.00 | 13347.00 | 30 septembre 2013 |
| Increased access to rehabilitated street and drainage infrastructure in disadvantaged urban areas that selected such subprojects (i.e., cleared and rehabilitated drainage canals, ditches, etc.) | 27.85 | 53.00 | 44.00 | 21 mars 2014 |
| Increased access to rehabilitated street and drainage infrastructure in disadvantaged urban areas that selected such subprojects(i.e., cleared and rehabilitated drainage canals, ditches, etc.) | 27.85% | Original: +10%Revised: +10% | 41.47% | 28 juin 2013 |
| Increased access to sanitation in disadvantaged urban areas that selected such subprojects (i.e., garbage collection, solid waste disposal, recycling, composting, sanitary blocks, etc.). | 13.47 | 29.00 | 23.47 | 21 mars 2014 |
| Increased access to sanitation in disadvantaged urban areas that selected such subprojects (i.e., garbage collection, solid wastedisposal, recycling, composting, sanitary blocks, etc.). | 13.47% | Original: +20%Revised: +23.47% | 23.78% | 28 juin 2013 |
| Increased access to social infrastructure and services in disadvantaged urban areas that selected such subprojects (daycare centers, primary schools, secondary schools, health clinics, job training | 24.51 | 51.00 | 41.00 | 21 mars 2014 |
| Increased access to social infrastructure and services in disadvantaged urban areas that selected such subprojects (daycarecenters,primary schools, secondary schools, health clinics, job training, e | 24.51% | Original: +10%Revised: +10% | 38.8% | 28 juin 2013 |
| Increased access to water in disadvantaged urban areas that selected such subprojects (i.e., water kiosks, standpipes, community cisterns, rainwater capture, etc.). | 85.51 | 95.00 | 92.63 | 21 mars 2014 |
| Increased access to water in disadvantaged urban areas that selected such subprojects (i.e., water kiosks, standpipes, communitycisterns, rainwater capture, etc.). | 85.51% | Original: +15%Revised: +7.5% | 92.63% (+7.12%) | 28 juin 2013 |
| Number of productive/income generating subprojects fully operational. | 0.00 | 650.00 | 493.00 | 21 mars 2014 |
| Number of productive/income generating subprojects that are self-sustaining six months after being fully operational. | 0 | 25 | 25 | 28 juin 2013 |
| Percent of beneficiaries for whom the majority of expected subproject results, as defined by beneficiaries at the start of the project, were achieved (as per results from community evaluation forms) | 0.00 | 85.00 | 0.00 | 21 mars 2014 |
| Percent of beneficiaries for whom the majority of expected subproject results, as defined by beneficiaries at the start of theproject, were achieved (as per results from community evaluation forms) | 0 | 85% | Non publié | Non publié |
| Percentage of productive/income generating subprojects that are self-sustaining six months after being fully operational. | 0.00 | 80.00 | 15.00 | 21 mars 2014 |
| Residents that have returned to neighborhoods upon completion of housing reconstruction and repair works or receiving a rental grant | 0.00 | 5480.00 | 2000.00 | 21 mars 2014 |
Identifiants1 identifiant
| Système | Identifiant | Source |
|---|---|---|
| Projet de la Banque mondiale | P149116 | Fiche de l’opération |
Documents du partenaire
- Haiti - Urban Community Driven Development Project : additional financing and restructuring, 29 mai 2014, documents.worldbank.org
- Project Information Document (Appraisal Stage) - Haiti - Urban Community Driven Development Project - AF - P149116, 7 mai 2014, documents.worldbank.org
- Integrated Safeguards Data Sheet (Appraisal Stage) - Haiti - Urban Community Driven Development Project - AF - P149116, 16 avril 2014, documents.worldbank.org
- Haiti - Urban Community Driven Development Project : additionnal financing - resettlement plan : Projet de Développement Communautaire Participatif en Milieu Urbain : financement additionnel - cadre de politique de réinstallation, 1er avril 2014, documents.worldbank.org
- Haiti - Urban Community Driven Development Project : additional financing - environmental assessment (Vol. 1 of 2) : Cadre de gestion environnementale et sociale, 1er mars 2014, documents.worldbank.org
- Haiti - Urban Community Driven Development Project : additional financing - environmental assessment (Vol. 2 of 2) : Cadre de gestion du patrimoine culturel physique, 1er décembre 2013, documents.worldbank.org
Sources
- IDA, état des crédits et dons: World Bank data, CC BY 4.0 (https://datacatalog.worldbank.org/public-licenses).
- Fiche de l’opération: conditions d’utilisation fixées par l’éditeur
- Page du projet, Banque mondiale: conditions d’utilisation fixées par l’éditeur
- Documents de la Banque mondiale: conditions d’utilisation fixées par l’éditeur
Données au 18 octobre 2026
| Source | Lu le |
|---|---|
| IDA, état des crédits et dons | 18 octobre 2026 |
| Projets de la Banque mondiale | 18 octobre 2026 |
| Documents de la Banque mondiale | 18 octobre 2026 |