Données / Portefeuille des partenaires / Groupe de la Banque mondiale / IDA
HT : Projet d’urgence de reconstruction des écoles
Titre publié : HT: Emergency School Reconstruction Project
Millions de dollars US sauf indication contraire. Exercice fiscal haïtien, d’octobre à septembre. L’exercice FY2026-27 a commencé le 1er octobre 2026.
Objectif
The objective of the Project is to assist the Recipient in restoring and improving access to basic education in selected destroyed and/or heavily damaged public primary schools of its territory.
Tel que publié par Projets de la Banque mondiale, dans sa langue d’origine.
- Partenaire
- World Bank Group, IDA
- Secteur
- Éducation
- Stade
- Clôturée depuis le 31 mai 2012
- Approbation
- 5 mars 2009
- Clôture
- 31 mai 2012
- Instrument
- Financement BIRD/IDA, IDA
- Écart du non décaissé
- −0,3 : l’état de l’IDA évalue les crédits non décaissés en droits de tirage spéciaux au taux de change du jour
- Entrée en vigueur
- 25 juin 2009
- Départements
- Sud-Est
- Dernière transaction
- 31 décembre 2012
- Identifiant de l’opération
- P115261
Cycle de vie5 stades, 14 dates
Historique des stades
| Stade | Depuis le |
|---|---|
| Prévue | 13 novembre 2008 |
| Approuvée | 5 mars 2009 |
| En cours | 5 mars 2009 |
| En clôture | 31 mai 2012 |
| Clôturée | 31 mai 2012 |
Événements datés
| Événement | Date | Source |
|---|---|---|
| Revue du concept | 13 novembre 2008 | Projets de la Banque mondiale |
| Évaluation préalable | 11 février 2009 | Projets de la Banque mondiale |
| Négociation | 11 février 2009 | Projets de la Banque mondiale |
| Publication | 14 février 2009 | Projets de la Banque mondiale |
| Début prévu | 27 février 2009 | IATI |
| Début effectif | 5 mars 2009 | IATI |
| Approbation | 5 mars 2009 | Projets de la Banque mondiale |
| Premier engagement | 5 mars 2009 | Écritures |
| Entrée en vigueur | 25 juin 2009 | Projets de la Banque mondiale |
| Premier décaissement | 31 mai 2011 | Écritures |
| Fin effective | 31 mai 2012 | IATI |
| Date de clôture | 31 mai 2012 | IATI |
| Dernier décaissement | 30 juin 2012 | Écritures |
| Rapport d’achèvement attendu | 3 décembre 2012 | Projets de la Banque mondiale |
Non décaissé : 0,0 millions de dollars US au 30 septembre 2026, clôture le 31 mai 2012.
Financement
Tableau 1.Financement, millions de dollars US
| Bailleur | MontantMillions de dollars US | Rôle | Source |
|---|---|---|---|
| IDA Grant | 5,4 | Institution | Projets de la Banque mondiale |
Tableau 2.Position à la date des données par source (stocks), millions de dollars US
| Cette pageMillions de dollars US | Source | |
|---|---|---|
| Engagement | 4,7 | IDA, état des crédits et dons |
| Décaissé | 5,0 | IDA, état des crédits et dons |
| Non décaissé | 0,0 | IDA, état des crédits et dons |
| Coût total | 5,4 | Projets de la Banque mondiale |
Montants de la Banque mondiale. Approuvé: Engagement net, montant approuvé moins les annulations, en $ É.-U. à la date des données. Décaissé à ce jour: Les décaissements de l'état IDA et de l'API des projets à ce jour, en $ É.-U. Non décaissé: Le solde non décaissé que publie l'état IDA, en $ É.-U. à la date des données. Les montants selon la source
Modifications de l'opérationnon publié
- Date de clôture initiale
- Non publié
- Prorogations de la date de clôture
- Non publié
- Restructurations
- Non publié
- Composante d'urgence
- Non publié
Nouveaux engagements et décaissements par exercice
Tableau 3.Nouveaux engagements et décaissements par exercice (flux), millions de dollars US
| FY2008-09Millions de dollars US | FY2010-11Millions de dollars US | FY2011-12Millions de dollars US | FY2012-13Millions de dollars US | |
|---|---|---|---|---|
| Nouveaux engagements | 5,0 | Non publié | Non publié | −0,3 |
| Décaissements | Non publié | 2,2 | 1,4 | Non publié |
| Décaissements cumulés | Non publié | 3,5 | 5,0 | Non publié |
Le cumul part du solde d’ouverture de 1,4 millions de dollars US.
Fiches et documents
Écritures8 écritures, du 5 mars 2009 au 31 décembre 2012
Tableau 4.Écritures, millions de dollars US
| Date | Mesure | MontantMillions de dollars US | Source | Méthode |
|---|---|---|---|---|
| 5 mars 2009 | Engagement | 5,0 | IDA, état des crédits et dons | credit original principal at board approval |
| 31 décembre 2012 | Engagement | −0,3 | IDA, état des crédits et dons | cancellation: increase in cumulative cancelled amount between snapshots (non-USD credit: includes exchange revaluation) |
| 30 avril 2011 | Décaissements | 1,4 | IDA, état des crédits et dons | cumulative at first snapshot (solde d’ouverture) |
| 31 mai 2011 | Décaissements | 0,8 | IDA, état des crédits et dons | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 31 août 2011 | Décaissements | 1,4 | IDA, état des crédits et dons | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 31 octobre 2011 | Décaissements | 0,5 | IDA, état des crédits et dons | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 31 janvier 2012 | Décaissements | 0,7 | IDA, état des crédits et dons | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 30 juin 2012 | Décaissements | 0,2 | IDA, état des crédits et dons | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
Conditions5 des 6 publiés
- Type de financement
- 110 Don standard
- Type de flux
- Non publié
- Type d’aide
- C01 Interventions de type projet
- Aide liée ou non liée
- 5 Non lié
- Type de collaboration
- 2 Apports multilatéraux entrants
- Humanitaire
- Oui
Localisation1 département, 2 lieux nommés, 2 lieux avec coordonnées
| Départements | Sud-Est |
| Lieux nommés par la source | DÃÂ(c)partement du Sud-Est, Département du Sud-Est |
| Lieux avec coordonnées | 2 |
Indicateurs de résultats20 indicateurs
| Indicateur | Valeur de référence | Cible | Dernière valeur | Date de la dernière valeur |
|---|---|---|---|---|
| A NAPSS which will sustain the activities beyond the project life, as it will function as a business plan of the GoH over the medium to long-terms | Non publié | NAPSS prepared, adopted, and presented to donors in 2011. | Draft NAPSS prepared in 2011. | 31 mai 2012 |
| Development of training modules on measures to increase safety in all schools | Non publié | 7 training modules prepared | 7 training modules prepared. | 31 mai 2012 |
| Increased awareness of the vulnerabilities to disasters and the mitigation measures for the education sector, amongst the stakeholders | Non publié | 2 workshops and 9 consultations with stakeholders carried out | 2 workshops and 10 consultations carried out. | 31 mai 2012 |
| Methods for safe school construction are adopted | NA | Methods for safe school construction are adopted i | Methods for safe schools construction are discusse | 4 mai 2012 |
| Number of DGS staff trained to become Master Trainers on NAPSS issues | 0.00 | 10.00 | 0.00 | 4 mai 2012 |
| Number of general quality assurance supervision missions carried out by the DGS for each school built | 0 | 2 per school built and per year | 1 per school built. | 4 mai 2012 |
| Number of schools rebuilt or rehabilitated with satisfactory technical standards | 0.00 | 11.00 | 0.00 | 31 mai 2012 |
| Number of schools retrofitted as emergency temporary shelter | 0.00 | 4.00 | 3.00 | 31 mai 2012 |
| Percentage of schools rebuilt for which prequalification visits were conducted | 0.00 | 100.00 | 100.00 | 4 mai 2012 |
| Occupation rate of rebuilt schools will be maintained at 75% or above following completion of civil works, as measured within six monthsof Project closing. | 0.00 | 100.00 | 0.00 | 31 mai 2012 |
| Occupation rate of rebuilt schools will be maintained at 75% or above following completion of civil works, as measured within six monthsof Project closing. | 0.00 | 100.00 | 0.00 | 31 mai 2012 |
| Methods for safe school construction are adopted | Non publié | Methods for safe school construction are adopted in 2011 | Methods for safe schools construction are discussed in 2011 and 2012. | 31 mai 2012 |
| Methods for safe school construction are adopted | Non publié | Methods for safe school construction are adopted in 2011 | Methods for safe schools construction are discussed in 2011 and 2012. | 31 mai 2012 |
| Number of DGS staff trained to become Master Trainers on NAPSS issues | 0.00 | 10.00 | 0.00 | 31 mai 2012 |
| Number of DGS staff trained to become Master Trainers on NAPSS issues | 0.00 | 10.00 | 0.00 | 31 mai 2012 |
| Number of general quality assurance supervision missions carried out by the DGS for each school built | 0 | 2 per school built and per year | 1 per school built. | 31 mai 2012 |
| Number of general quality assurance supervision missions carried out by the DGS for each school built | 0 | 2 per school built and per year | 1 per school built. | 31 mai 2012 |
| Percentage of schools rebuilt for which prequalification visits were conducted | 0.00 | 100.00 | 100.00 | 31 mai 2012 |
| Percentage of schools rebuilt for which prequalification visits were conducted | 0.00 | 100.00 | 100.00 | 31 mai 2012 |
| Occupation rate of rebuilt schools will be maintained at 75% or above following completion of civil works, as measured within six monthsof Project closing. | 0.00 | 100.00 | 0.00 | 4 mai 2012 |
Notations29 notations
| Notation | Valeur | Date |
|---|---|---|
| IEG bankqualityofsupervision | Moderately Satisfactory | 3 avril 2013 |
| IEG borrowcompliance | Moderately Satisfactory | 3 avril 2013 |
| IEG borrowimplementation | Moderately Satisfactory | 3 avril 2013 |
| IEG evaltype | ES | 3 avril 2013 |
| IEG evaluation_riskdo | High | 3 avril 2013 |
| IEG icrquality | Satisfactory | 3 avril 2013 |
| IEG mequality | Negligible | 3 avril 2013 |
| IEG outcome | Moderately Satisfactory | 3 avril 2013 |
| IEG overallbankperf | Moderately Satisfactory | 3 avril 2013 |
| IEG overallborrowperf | Moderately Satisfactory | 3 avril 2013 |
| ICR bankqualityentry | Not Rated | 3 décembre 2012 |
| ICR banksupervision | Substantial | 3 décembre 2012 |
| ICR banksupervision | Not Rated | 3 décembre 2012 |
| ICR banksupervision | Moderately Unsatisfactory | 3 décembre 2012 |
| ICR borrgovt | Substantial | 3 décembre 2012 |
| ICR borrimplegency | Moderately Unsatisfactory | 3 décembre 2012 |
| ICR borroverall | Moderately Satisfactory | 3 décembre 2012 |
| ICR completion_riskdo | High | 3 décembre 2012 |
| ICR completion_riskdo | Substantial | 3 décembre 2012 |
| ICR outratingind | Moderately Satisfactory | 3 décembre 2012 |
| ICR overallrating | Moderately Satisfactory | 3 décembre 2012 |
| ISR Counterpart Funding | Satisfactory | 16 mai 2012 |
| ISR Financial Management | Moderately Satisfactory | 16 mai 2012 |
| ISR Monitoring and Evaluation | Satisfactory | 16 mai 2012 |
| ISR Overall Implementation Progress (IP) | Moderately Satisfactory | 16 mai 2012 |
| ISR Overall Safeguards Rating | Satisfactory | 16 mai 2012 |
| ISR Procurement | Moderately Satisfactory | 16 mai 2012 |
| ISR Progress towards achievement of PDO | Moderately Satisfactory | 16 mai 2012 |
| ISR Project Management | Satisfactory | 16 mai 2012 |
Identifiants4 identifiants
| Système | Identifiant | Source |
|---|---|---|
| Identifiant IATI | 44000-P115261 | IATI |
| Crédit ou don IDA | IDAH4600 | IDA, état des crédits et dons |
| Prêt de la Banque mondiale | IDA-H4600 | Projets de la Banque mondiale |
| Projet de la Banque mondiale | P115261 | Fiche de l’opération |
Écarts entre les sources2 champs
| Champ | Source | Valeur | Retenue |
|---|---|---|---|
| Engagement | IDA, état des crédits et dons | 4,7 millions de dollars US | ✓ |
| Engagement | Projets de la Banque mondiale | 5,4 millions de dollars US | |
| Statut | Projets de la Banque mondiale | Clôturé | ✓ |
| Statut | IATI | Actif |
Documents du partenaire18 documents
- Fiche sur projects.worldbank.org, projects.worldbank.org
- Haiti - Emergency School Reconstruction Project, 3 avril 2013, documents.worldbank.org
- Haiti - Emergency School Reconstruction Project, 30 novembre 2012, documents.worldbank.org
- Haiti - HT: Emergency School Reconstruction Project : P115261 - Implementation Status Results Report : Sequence 07, 16 mai 2012, documents.worldbank.org
- Haiti - Emergency School Reconstruction Project : restructuring (Vol. 2 of 2) : Data sheet, 27 décembre 2011, documents.worldbank.org
- Haiti - Emergency School Reconstruction Project : restructuring (Vol. 1 of 2) : Main report, 14 décembre 2011, documents.worldbank.org
- Haiti - HT: Emergency School Reconstruction Project : P115261 - Implementation Status Results Report : Sequence 06, 11 septembre 2011, documents.worldbank.org
- Haiti - Emergency School Reconstruction Project : restructuring (Vol. 1 of 2) : Main report, 4 mai 2011, documents.worldbank.org
- Haiti - Emergency School Reconstruction Project : restructuring (Vol. 2 of 2) : Data sheet, 3 mai 2011, documents.worldbank.org
- Haiti - HT: Emergency School Reconstruction Project : P115261 - Implementation Status Results Report : Sequence 05, 23 février 2011, documents.worldbank.org
- Cadre de gestion environnementale et sociale, 1er septembre 2010, documents.worldbank.org
- Cadre de politique de réinstallation, 1er août 2010, documents.worldbank.org
- Haïti - Plan de passation des marchés : plan de passation des marchés, 1er septembre 2009, documents.worldbank.org
- Financing Agreement, Grant H460-HT Conformed, 8 avril 2009, documents.worldbank.org
- Announcement of Five Million US Dollars Grant for Emergency School Reconstruction on March 5, 2009, 5 mars 2009, documents.worldbank.org
- Haiti - Emergency School Reconstruction Project, 17 février 2009, documents.worldbank.org
- Haiti - Emergency School Reconstruction Project, 17 février 2009, documents.worldbank.org
- Haiti - Emergency School Reconstruction Project, 8 décembre 2008, documents.worldbank.org
Avis de marchés (2)
- Contract Awards, projects.worldbank.org
- Procurement Notices, projects.worldbank.org
Sources
- Fiche IATI (d-portal): conditions d’utilisation fixées par l’éditeur
- Relevé des crédits et dons de l’IDA (jeu de données): World Bank data, CC BY 4.0 (https://datacatalog.worldbank.org/public-licenses).
- Écritures: conditions d’utilisation fixées par l’éditeur
- Fiche de l’opération: conditions d’utilisation fixées par l’éditeur
- Page du projet, Banque mondiale: conditions d’utilisation fixées par l’éditeur
- Documents de la Banque mondiale: conditions d’utilisation fixées par l’éditeur
Données au 18 octobre 2026
| Source | Lu le |
|---|---|
| IATI | 18 octobre 2026 |
| IDA, état des crédits et dons | 18 octobre 2026 |
| Projets de la Banque mondiale | 18 octobre 2026 |
| Documents de la Banque mondiale | 18 octobre 2026 |
Citer cette page
HaitiDocs. HT : Projet d’urgence de reconstruction des écoles. Portefeuille des partenaires, données au 18 octobre 2026. https://www.haitidocs.org/portfolio/projects/WB%3AP115261?lang=fr