Done / Pòtfolyo patnè yo / Gwoup Bank Mondyal / IDA
Pwojè Devlopman Iben ki Dirije pa Kominote / PRODEPUR
Tit pibliye: Haiti - Urban Community Driven Development Project / PRODEPUR
An milyon dola ameriken sof si yo di lòt bagay. Ane fiskal ayisyen, soti oktòb rive septanm. FY2026-27 te kòmanse 1 oktòb 2026.
Objektif
To improve access to, and satisfaction with: (i) basic and social infrastructure and services, including housing repair, reconstruction and community infrastructure improvements needed as a result of the Emergency; and (ii) income-generating opportunities for residents of selected disadvantaged urban areas.
Jan Pwojè Bank Mondyal pibliye l, nan lang orijinal li.
Deskripsyon
The Urban Community Driven Development Project (PRODEPUR) development objective for Government of Haiti (GoH) is to improve access to and satisfaction with: (a) basic and social infrastructures and services, and (b) income-generating opportunities for residents of targeted disadvantaged urban areas. This objective will be achieved through a participatory process in which CBOs propose, select, implement, and maintain subprojects. The key indicators for this project will include: (a) increased access to water in disadvantaged urban areas that selected such subprojects (that is, water kiosks, standpipes, community cisterns, rainwater capture, and so forth); (b) increased access to sanitation in disadvantaged urban areas that selected such subprojects (that is, garbage collection, solid waste disposal, recycling, composting, sanitary blocks, and so forth); and (c)
plis
increased access to rehabilitated street and drainage infrastructure in disadvantaged urban areas that selected such subprojects (that is, clear and rehabilitated drainage canals, ditches, rehabilitated street and/or footpaths, and so forth). There are three components to the project. The first component of the project community subproject funding, management, and support will finance: (a) small-scale socioeconomic infrastructure and productive/income-generating subprojects; and (b) contracting of service providers. The first component of the project capacity building and technical assistance will finance: (a) training-of-trainer events; (b) capacity-building and technical assistance; (c) workshops with service providers to harmonize practices to accompany Community-Based Organization (CBO) and Project Development Councils in carrying out the activities under Component 1; (d) training of Bureau de Monetisation staff in order to effectively supervise overall project implementation; (e) various consultant services; and (f) policy dialogue to engage GoH and other relevant stakeholders on a medium to long term national strategy to facilitate the mainstreaming of the urban community-driven development (CDD) approach and mechanisms. The third component of the project administration, supervision, and monitoring and evaluation will finance incremental costs associated with project implementation, administration, supervision, and monitoring and evaluation by the Bureau de Monetisation through its project coordination unit, which operates under the oversight of the ministry of economy and finance.
- Patnè
- World Bank Group, IDA
- Sektè
- Dlo ak asenisman
- Etap
- Fèmen depi 31 desanm 2016
- Apwobasyon
- 3 jen 2008
- Fèmen
- 31 desanm 2016
- Enstriman
- Finansman BIRD/IDA, IDA
- Diferans nan sa ki poko dekese
- 1.8: eta IDA a evalye kredi ki poko dekese an dwa tiraj espesyal yo nan to chanj jodi a
- Anprentè
- Ministry of Finance
- Ajans egzekisyon
- BMPAD
- Antre an vigè
- 27 oktòb 2008
- Depatman
- Latibonit, Lwès, Sant, Nò
- Dènye tranzaksyon
- 30 jen 2017
- Idantifyan operasyon an
- P106699
Sik lavi5 etap, 14 dat
Istwa etap yo
| Etap | Depi |
|---|---|
| Planifye | 29 oktòb 2007 |
| Apwouve | 3 jen 2008 |
| An kou | 3 jen 2008 |
| Ap fèmen | 31 desanm 2016 |
| Fèmen | 31 desanm 2016 |
Evènman ki gen dat
| Evènman | Dat | Sous |
|---|---|---|
| Revizyon konsèp | 29 oktòb 2007 | Pwojè Bank Mondyal |
| Piblikasyon | 9 novanm 2007 | Pwojè Bank Mondyal |
| Evalyasyon davans | 11 mas 2008 | Pwojè Bank Mondyal |
| Negosyasyon | 15 avril 2008 | Pwojè Bank Mondyal |
| Kòmansman prevwa | 29 me 2008 | IATI |
| Kòmansman reyèl | 3 jen 2008 | IATI |
| Apwobasyon | 3 jen 2008 | Pwojè Bank Mondyal |
| Premye angajman | 3 jen 2008 | Tranzaksyon |
| Antre an vigè | 27 oktòb 2008 | Pwojè Bank Mondyal |
| Premye dekèsman | 31 me 2011 | Tranzaksyon |
| Fen reyèl | 31 desanm 2016 | IATI |
| Dat fèmti | 31 desanm 2016 | IATI |
| Dènye dekèsman | 30 jen 2017 | Tranzaksyon |
| Rapò fen atann | 31 oktòb 2017 | Pwojè Bank Mondyal |
Pa dekèse: 0.0 milyon dola ameriken jiska 30 septanm 2026, dat fèmti 31 desanm 2016.
Finansman
Tablo 1.Finansman, milyon dola ameriken
| Finansè | MontanMilyon dola ameriken | Wòl | Sous |
|---|---|---|---|
| IDA Guarantee | 30.0 | Kofinansye | Pwojè Bank Mondyal |
| Local Communities | 1.0 | Kontrepati | Pwojè Bank Mondyal |
| IDA Grant | 15.7 | Enstitisyon | Pwojè Bank Mondyal |
Tablo 2.Operasyon ki gen rapò, milyon dola ameriken
| Operasyon | Rapò | Patnè | Etap | AngajmanMilyon dola ameriken |
|---|---|---|---|---|
| Housing Reconstruction - Urban Community Driven Development Additional Financing | Finansman adisyonèl oswa operasyon pitit | Gwoup Bank Mondyal | Fèmen | 30.0 |
| Urban Community Driven Development Project - AF | Finansman adisyonèl oswa operasyon pitit | Gwoup Bank Mondyal | Fèmen | 7.5 |
Tablo 3.Pozisyon nan dat done yo pa sous (stòk), milyon dola ameriken
| Paj sa aMilyon dola ameriken | Sous | IATIMilyon dola ameriken | |
|---|---|---|---|
| Angajman | 52.9 | IDA, eta kredi ak don | 53.0 |
| Dekèse | 51.1 | IDA, eta kredi ak don | 51.1 |
| Pa dekèse | 0.0 | IDA, eta kredi ak don | |
| Pri total | 46.7 | Pwojè Bank Mondyal |
Montan Bank Mondyal. Apwouve: Angajman nèt, montan apwouve mwens anilasyon yo, an US$ nan dat done yo. Dekèse jiska jodi a: Dekèsman deklarasyon IDA a ak API pwojè yo jiska jodi a, an US$. Pa dekèse: Balans ki pa dekèse deklarasyon IDA a pibliye, an US$ nan dat done yo. Kolòn IATI: angajman ak dekèsman patnè a pibliye nan IATI, konvèti an US$. Montan yo dapre sous la
Chanjman nan operasyon anpa rapòte
- Dat fèmti orijinal
- Pa rapòte
- Pwolongasyon dat fèmti
- Pa rapòte
- Pwolonje soti 31 mas 2014 rive 30 jen 2015 (dokiman 24 out 2014) dokiman
- Restriktirasyon
- Pa rapòte
- Konpozan ijans
- Pa rapòte
Nouvo angajman ak dekèsman pa ane fiskal
Tablo 4.Nouvo angajman ak dekèsman pa ane fiskal (flo), milyon dola ameriken
| FY2007-08Milyon dola ameriken | FY2010-11Milyon dola ameriken | FY2011-12Milyon dola ameriken | FY2012-13Milyon dola ameriken | FY2013-14Milyon dola ameriken | FY2014-15Milyon dola ameriken | FY2015-16Milyon dola ameriken | FY2016-17Milyon dola ameriken | |
|---|---|---|---|---|---|---|---|---|
| Nouvo angajman | 15.7 | 30.0 | Pa rapòte | Pa rapòte | 7.5 | Pa rapòte | Pa rapòte | −0.3 |
| Dekèsman | Pa rapòte | 1.9 | 8.4 | 11.9 | 8.4 | 4.0 | 7.7 | 2.6 |
| Dekèsman kimile | Pa rapòte | 8.2 | 16.6 | 28.5 | 36.9 | 40.8 | 48.6 | 51.1 |
Total kimile a kòmanse ak balans ouvèti 6.2 milyon dola ameriken.
Fich ak dokiman
Tranzaksyon69 liy, 3 jen 2008 rive 30 jen 2017
Tablo 5.Tranzaksyon, milyon dola ameriken
| Dat | Mezi | MontanMilyon dola ameriken | Sous | Metòd |
|---|---|---|---|---|
| 3 jen 2008 | Angajman | 15.7 | IDA, eta kredi ak don | credit original principal at board approval |
| 26 oktòb 2010 | Angajman | 30.0 | IDA, eta kredi ak don | credit original principal at board approval |
| 20 jen 2014 | Angajman | 7.5 | IDA, eta kredi ak don | credit original principal at board approval |
| 30 jen 2017 | Angajman | −0.2 | IDA, eta kredi ak don | cancellation: increase in cumulative cancelled amount between snapshots (non-USD credit: includes exchange revaluation) |
| 30 jen 2017 | Angajman | −0.1 | IDA, eta kredi ak don | cancellation: increase in cumulative cancelled amount between snapshots (non-USD credit: includes exchange revaluation) |
| 30 jen 2017 | Angajman | −0.0 | IDA, eta kredi ak don | cancellation: increase in cumulative cancelled amount between snapshots (non-USD credit: includes exchange revaluation) |
| 30 avril 2011 | Dekèsman | 6.2 | IDA, eta kredi ak don | cumulative at first snapshot (balans ouvèti) |
| 31 me 2011 | Dekèsman | 0.6 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 30 jen 2011 | Dekèsman | 1.0 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 30 septanm 2011 | Dekèsman | 0.3 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 31 oktòb 2011 | Dekèsman | 2.2 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 31 oktòb 2011 | Dekèsman | 1.2 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 30 novanm 2011 | Dekèsman | 0.7 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 30 novanm 2011 | Dekèsman | 0.2 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 31 desanm 2011 | Dekèsman | 0.2 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 31 desanm 2011 | Dekèsman | 1.0 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 29 fevriye 2012 | Dekèsman | 0.6 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 31 mas 2012 | Dekèsman | 0.9 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 31 mas 2012 | Dekèsman | 0.8 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 31 jiyè 2012 | Dekèsman | 0.4 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 31 jiyè 2012 | Dekèsman | 0.1 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 30 septanm 2012 | Dekèsman | 0.1 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 31 oktòb 2012 | Dekèsman | 2.0 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 31 oktòb 2012 | Dekèsman | 0.9 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 30 novanm 2012 | Dekèsman | 0.1 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 31 desanm 2012 | Dekèsman | 0.3 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 31 desanm 2012 | Dekèsman | 0.2 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 31 janvye 2013 | Dekèsman | 0.1 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 28 fevriye 2013 | Dekèsman | 0.9 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 30 avril 2013 | Dekèsman | 2.1 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 31 me 2013 | Dekèsman | 0.6 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 30 jen 2013 | Dekèsman | 0.7 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 30 jen 2013 | Dekèsman | 1.2 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 31 jiyè 2013 | Dekèsman | 0.1 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 31 out 2013 | Dekèsman | 2.3 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 30 septanm 2013 | Dekèsman | 0.3 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 30 septanm 2013 | Dekèsman | <0.1 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 30 novanm 2013 | Dekèsman | 0.5 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 31 desanm 2013 | Dekèsman | 1.4 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 31 janvye 2014 | Dekèsman | 1.6 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 30 avril 2014 | Dekèsman | 2.5 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 30 jen 2014 | Dekèsman | 0.2 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 30 jen 2014 | Dekèsman | 0.1 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 31 out 2014 | Dekèsman | 1.2 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 30 septanm 2014 | Dekèsman | 1.0 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 31 desanm 2014 | Dekèsman | 1.3 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 31 mas 2015 | Dekèsman | 0.7 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 30 avril 2015 | Dekèsman | 1.1 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 31 jiyè 2015 | Dekèsman | 0.9 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 30 novanm 2015 | Dekèsman | 0.7 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 31 desanm 2015 | Dekèsman | 1.1 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 31 janvye 2016 | Dekèsman | 1.9 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 31 mas 2016 | Dekèsman | 0.6 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 30 avril 2016 | Dekèsman | 0.8 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 31 jiyè 2016 | Dekèsman | 1.1 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 31 jiyè 2016 | Dekèsman | 0.6 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 31 out 2016 | Dekèsman | 0.5 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 30 septanm 2016 | Dekèsman | 0.2 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 30 septanm 2016 | Dekèsman | 0.3 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 31 oktòb 2016 | Dekèsman | 0.5 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 30 novanm 2016 | Dekèsman | 1.4 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 30 novanm 2016 | Dekèsman | 0.3 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 31 desanm 2016 | Dekèsman | 0.3 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 28 fevriye 2017 | Dekèsman | <0.1 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 31 mas 2017 | Dekèsman | <0.1 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 31 me 2017 | Dekèsman | <0.1 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 31 me 2017 | Dekèsman | −0.0 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 31 me 2017 | Dekèsman | −0.0 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 30 jen 2017 | Dekèsman | <0.1 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
Kondisyon4 sou 6 rapòte
- Kalite finansman
- 110 Don estanda
- Kalite koule
- Pa rapòte
- Kalite èd
- C01 Entèvansyon kalite pwojè
- Èd mare oswa pa mare
- 5 Pa mare
- Kalite kolaborasyon
- 2 Apò miltilateral k ap antre
- Imanitè
- Pa rapòte
Kote4 depatman, 11 kote nonmen, 22 kote ki gen kowòdone
| Depatman | Latibonit, Lwès, Sant, Nò |
| Kote sous la nonmen | Cap-Haitien, Cite Soleil, Dondon, Gonaives, Hinche, Martissant, Milot, Mirebalais, Port-au-Prince, Republic of Haiti, Saint-Marc |
| Kote ki gen kowòdone | 22 |
Endikatè rezilta20 endikatè
| Endikatè | Valè referans | Sib | Dènye valè | Dat dènye valè |
|---|---|---|---|---|
| Cumulative number of housing repair and reconstruction works financed through grants and completed | 1906.00 | 1906.00 | 1906.00 | 31 desanm 2016 |
| Health facilities constructed, renovated, and/or equipped (number) | 0.00 | 5.00 | 5.00 | 31 desanm 2016 |
| Number of corridors repaired | 99.00 | 108.00 | 108.00 | 31 desanm 2016 |
| Number of eligible CBOs joining COPRODEPs | 0.00 | 1173.00 | 1218.00 | 31 desanm 2016 |
| Number of people in urban areas provided with access to Improved Water Sources under the project | 47150.00 | 63650.00 | 61501.00 | 31 desanm 2016 |
| Percent of municipal governments successfully proposing and implementing subprojects in coordination with CBOs | 100.00 | 100.00 | 100.00 | 31 desanm 2016 |
| Percent of prioritized projects submitted by women?s CBOs | 13.00 | 15.00 | 13.00 | 31 desanm 2016 |
| Percent of subprojects completed in a timely manner | 74.00 | 85.00 | 69.02 | 31 desanm 2016 |
| Percent of subprojects successfully implemented, operated, and maintained (as per technical audits) | 0.00 | 70.00 | 70.00 | 31 desanm 2016 |
| Percent of women holding membership in COPRODEP?s executive committee | 24.00 | 30.00 | 24.00 | 31 desanm 2016 |
| Roads rehabilitated, Non-rural | 0.00 | 16.00 | 22.28 | 31 desanm 2016 |
| Volume of construction debris cleared in Project neighborhoods | 42800.00 | 41747.00 | 42800.00 | 31 desanm 2016 |
| Increased access to rehabilitated street and drainage infrastructure in disadvantaged urban areas that selected such subprojects (i.e., cleared and rehabilitated drainage canals, ditches, etc.) | 26.40 | 35.40 | 45.78 | 31 desanm 2016 |
| Increased access to sanitation in disadvantaged urban areas that selected such subprojects (i.e., garbage collection, solid waste disposal, recycling, composting, sanitary blocks, etc.). | 27.91 | 33.44 | 30.03 | 31 desanm 2016 |
| Increased access to social infrastructure and services in disadvantaged urban areas that selected such subprojects (daycare centers, primary schools, secondary schools, health clinics, job training | 56.43 | 66.43 | 73.64 | 31 desanm 2016 |
| Increased access to water in disadvantaged urban areas that selected such subprojects (i.e., water kiosks, standpipes, community cisterns, rainwater capture, etc.). | 74.33 | 76.70 | 86.34 | 31 desanm 2016 |
| Percent of beneficiaries for whom the majority of expected subproject results, as defined by beneficiaries at the start of the project, were achieved (as per results from community evaluation forms) | 0.00 | 85.00 | 0.00 | 31 desanm 2016 |
| Residents that have returned to neighborhoods upon completion of housing reconstruction and repair works or receiving a rental grant | 0.00 | 8844.00 | 8844.00 | 31 desanm 2016 |
| Number of productive/income generating subprojects fully operational. | 493.00 | 650.00 | 501.00 | 30 desanm 2016 |
| Percentage of productive/income generating subprojects that are self-sustaining six months after being fully operational. | 15.00 | 16.00 | 12.06 | 30 desanm 2016 |
Nòt28 nòt
| Nòt | Valè | Dat |
|---|---|---|
| IEG bankqualityofsupervision | Moderately Satisfactory | 30 mas 2018 |
| IEG borrowcompliance | Moderately Satisfactory | 30 mas 2018 |
| IEG borrowimplementation | Moderately Unsatisfactory | 30 mas 2018 |
| IEG evaltype | ES | 30 mas 2018 |
| IEG evaluation_riskdo | High | 30 mas 2018 |
| IEG icrquality | Modest | 30 mas 2018 |
| IEG mequality | Modest | 30 mas 2018 |
| IEG outcome | Moderately Satisfactory | 30 mas 2018 |
| IEG overallbankperf | Moderately Satisfactory | 30 mas 2018 |
| IEG overallborrowperf | Moderately Satisfactory | 30 mas 2018 |
| ICR bankqualityentry | Not Rated | 31 oktòb 2017 |
| ICR banksupervision | Substantial | 31 oktòb 2017 |
| ICR banksupervision | Not Rated | 31 oktòb 2017 |
| ICR banksupervision | Moderately Satisfactory | 31 oktòb 2017 |
| ICR borrgovt | Moderately Satisfactory | 31 oktòb 2017 |
| ICR borrimplegency | Moderately Satisfactory | 31 oktòb 2017 |
| ICR borroverall | Moderately Satisfactory | 31 oktòb 2017 |
| ICR completion_riskdo | Substantial | 31 oktòb 2017 |
| ICR outratingind | Moderately Satisfactory | 31 oktòb 2017 |
| ICR overallrating | Moderately Satisfactory | 31 oktòb 2017 |
| ISR Financial Management | Moderately Satisfactory | 4 jen 2017 |
| ISR Monitoring and Evaluation | Moderately Satisfactory | 4 jen 2017 |
| ISR Overall Implementation Progress (IP) | Moderately Satisfactory | 4 jen 2017 |
| ISR Overall Safeguards Rating | Moderately Satisfactory | 4 jen 2017 |
| ISR Overall Safeguards Rating | Moderately Satisfactory | 4 jen 2017 |
| ISR Procurement | Moderately Satisfactory | 4 jen 2017 |
| ISR Progress towards achievement of PDO | Moderately Satisfactory | 4 jen 2017 |
| ISR Project Management | Satisfactory | 4 jen 2017 |
Lajan ki pase bay lòt76 mouvman
| Benefisyè | Mouvman | Dat | Milyon dola ameriken |
|---|---|---|---|
| BMPAD | Angajman | 30 jen 2017 | −0.2 |
| BMPAD | Dekèsman | 30 jen 2017 | <0.1 |
| BMPAD | Angajman | 30 jen 2017 | −0.1 |
| BMPAD | Angajman | 30 jen 2017 | −0.0 |
| BMPAD | Dekèsman | 31 me 2017 | −0.0 |
| BMPAD | Dekèsman | 31 me 2017 | −0.0 |
| BMPAD | Dekèsman | 31 me 2017 | <0.1 |
| BMPAD | Dekèsman | 31 mas 2017 | <0.1 |
| BMPAD | Dekèsman | 28 fevriye 2017 | <0.1 |
| BMPAD | Dekèsman | 31 desanm 2016 | 0.3 |
| BMPAD | Dekèsman | 30 novanm 2016 | 1.4 |
| BMPAD | Dekèsman | 30 novanm 2016 | 0.3 |
| BMPAD | Dekèsman | 31 oktòb 2016 | 0.5 |
| BMPAD | Dekèsman | 30 septanm 2016 | 0.2 |
| BMPAD | Dekèsman | 30 septanm 2016 | 0.3 |
| BMPAD | Dekèsman | 31 out 2016 | 0.5 |
| BMPAD | Dekèsman | 31 jiyè 2016 | 0.6 |
| BMPAD | Dekèsman | 31 jiyè 2016 | 1.1 |
| BMPAD | Dekèsman | 30 avril 2016 | 0.8 |
| BMPAD | Dekèsman | 31 mas 2016 | 0.6 |
| BMPAD | Dekèsman | 31 janvye 2016 | 1.9 |
| BMPAD | Dekèsman | 31 desanm 2015 | 1.1 |
| BMPAD | Dekèsman | 30 novanm 2015 | 0.7 |
| BMPAD | Dekèsman | 31 jiyè 2015 | 0.9 |
| BMPAD | Dekèsman | 30 avril 2015 | 1.1 |
| BMPAD | Dekèsman | 31 mas 2015 | 0.7 |
| BMPAD | Dekèsman | 31 desanm 2014 | 1.3 |
| BMPAD | Dekèsman | 30 septanm 2014 | 1.0 |
| BMPAD | Dekèsman | 31 out 2014 | 1.2 |
| BMPAD | Dekèsman | 30 jen 2014 | 0.2 |
| BMPAD | Angajman | 30 jen 2014 | 7.5 |
| BMPAD | Dekèsman | 30 jen 2014 | 0.1 |
| BMPAD | Dekèsman | 30 avril 2014 | 2.5 |
| BMPAD | Dekèsman | 31 janvye 2014 | 1.6 |
| BMPAD | Dekèsman | 31 desanm 2013 | 1.4 |
| BMPAD | Dekèsman | 30 novanm 2013 | 0.5 |
| BMPAD | Dekèsman | 30 septanm 2013 | <0.1 |
| BMPAD | Dekèsman | 30 septanm 2013 | 0.3 |
| BMPAD | Dekèsman | 31 out 2013 | 2.3 |
| BMPAD | Dekèsman | 31 jiyè 2013 | 0.1 |
| BMPAD | Dekèsman | 30 jen 2013 | 1.2 |
| BMPAD | Dekèsman | 30 jen 2013 | 0.7 |
| BMPAD | Dekèsman | 31 me 2013 | 0.6 |
| BMPAD | Dekèsman | 30 avril 2013 | 2.1 |
| BMPAD | Dekèsman | 28 fevriye 2013 | 0.9 |
| BMPAD | Dekèsman | 31 janvye 2013 | 0.1 |
| BMPAD | Dekèsman | 31 desanm 2012 | 0.2 |
| BMPAD | Dekèsman | 31 desanm 2012 | 0.3 |
| BMPAD | Dekèsman | 30 novanm 2012 | 0.1 |
| BMPAD | Dekèsman | 31 oktòb 2012 | 2.0 |
| BMPAD | Dekèsman | 31 oktòb 2012 | 0.9 |
| BMPAD | Dekèsman | 30 septanm 2012 | 0.1 |
| BMPAD | Dekèsman | 31 jiyè 2012 | 0.1 |
| BMPAD | Dekèsman | 31 jiyè 2012 | 0.4 |
| BMPAD | Dekèsman | 31 mas 2012 | 0.8 |
| BMPAD | Dekèsman | 31 mas 2012 | 0.9 |
| BMPAD | Dekèsman | 29 fevriye 2012 | 0.6 |
| BMPAD | Dekèsman | 31 desanm 2011 | 1.0 |
| BMPAD | Dekèsman | 31 desanm 2011 | 0.2 |
| BMPAD | Dekèsman | 30 novanm 2011 | 0.2 |
| BMPAD | Dekèsman | 30 novanm 2011 | 0.7 |
| BMPAD | Dekèsman | 31 oktòb 2011 | 1.2 |
| BMPAD | Dekèsman | 31 oktòb 2011 | 2.2 |
| BMPAD | Dekèsman | 30 septanm 2011 | 0.3 |
| BMPAD | Dekèsman | 30 jen 2011 | 1.0 |
| BMPAD | Dekèsman | 31 me 2011 | 0.6 |
| BMPAD | Dekèsman | 30 avril 2011 | 0.2 |
| BMPAD | Dekèsman | 31 mas 2011 | 0.9 |
| BMPAD | Dekèsman | 28 fevriye 2011 | 0.2 |
| BMPAD | Dekèsman | 31 janvye 2011 | 0.8 |
| BMPAD | Angajman | 31 oktòb 2010 | 30.0 |
| BMPAD | Dekèsman | 30 septanm 2010 | 0.9 |
| BMPAD | Dekèsman | 30 jen 2010 | 0.4 |
| BMPAD | Dekèsman | 30 septanm 2009 | 0.5 |
| BMPAD | Dekèsman | 31 jiyè 2009 | 2.4 |
| BMPAD | Angajman | 30 jen 2008 | 15.7 |
Idantifyan8 idantifyan
| Sistèm | Idantifyan | Sous |
|---|---|---|
| Idantifyan IATI | 44000-P106699 | IATI |
| Kredi oswa don IDA | IDAH3940 | IDA, eta kredi ak don |
| Kredi oswa don IDA | IDAH6210 | IDA, eta kredi ak don |
| Kredi oswa don IDA | IDAH9730 | IDA, eta kredi ak don |
| Prè Bank mondyal | IDA-H3940 | Pwojè Bank Mondyal |
| Prè Bank mondyal | IDA-H6210 | Pwojè Bank Mondyal |
| Prè Bank mondyal | IDA-H9730 | Pwojè Bank Mondyal |
| Pwojè Bank mondyal | P106699 | Fich operasyon an |
Kote sous yo pa dakò2 chan
| Chan | Sous | Valè | Itilize |
|---|---|---|---|
| Angajman | IDA, eta kredi ak don | 52.9 milyon dola ameriken | ✓ |
| Angajman | Pwojè Bank Mondyal | 15.7 milyon dola ameriken | |
| Estati | Pwojè Bank Mondyal | Fèmen | ✓ |
| Estati | IATI | Aktif |
Dokiman patnè a43 dokiman
- Fich sou projects.worldbank.org, projects.worldbank.org
- Haiti - HT Urban CDD PRODEPUR, 30 mas 2018, documents.worldbank.org
- Haiti - Urban Community Driven Development Project, 31 oktòb 2017, documents.worldbank.org
- Haiti - Haiti - Urban Community Driven Development Project / PRODEPUR : P106699 - Implementation Status Results Report : Sequence 20, 4 jen 2017, documents.worldbank.org
- Haiti - Haiti - Urban Community Driven Development Project / PRODEPUR : P106699 - Implementation Status Results Report : Sequence 19, 24 oktòb 2016, documents.worldbank.org
- Haiti - Haiti - Urban Community Driven Development Project / PRODEPUR : P106699 - Implementation Status Results Report : Sequence 19, 24 oktòb 2016, documents.worldbank.org
- Haiti - Haiti - Urban Community Driven Development Project / PRODEPUR : P106699 - Implementation Status Results Report : Sequence 18, 23 mas 2016, documents.worldbank.org
- Haiti - Haiti - Urban Community Driven Development Project / PRODEPUR : P106699 - Implementation Status Results Report : Sequence 17, 30 jiyè 2015, documents.worldbank.org
- Haiti - Port-au-Prince Neighborhood Housing Reconstruction Project (PREKAD) and Additional financing of Urban Community Driven Development Project (PRODEPUR) : supervision mission - May 11 to 15, 2015 : Haïti - Port au Prince Neighborhood Housing Reconstruction Project (PREKAD) et un financement additionnel de Urban Community Driven développement projet (PRODEPUR) : mission de supervision - 11 au 15 mai 2015, 11 me 2015, documents.worldbank.org
- Haiti - Haiti - Urban Community Driven Development Project / PRODEPUR : P106699 - Implementation Status Results Report : Sequence 16, 5 mas 2015, documents.worldbank.org
- Haiti - Haiti - Urban Community Driven Development Project / PRODEPUR : P106699 - Implementation Status Results Report : Sequence 15, 24 out 2014, documents.worldbank.org
- Official Documents- Financing Agreement for Grant H973-HT, Additional Financing (Closing Package), 9 jiyè 2014, documents.worldbank.org
- Official Documents- Supplemental Letter Ref. Financial Data for Grant H973-HT (Closing Package), 9 jiyè 2014, documents.worldbank.org
- Official Documents- Disbursement Letter for Grant H973-HT (Closing Package), 9 jiyè 2014, documents.worldbank.org
- Official Documents- Recommendation of Statutory Committee for Grant H973-HT (Closing Package), 11 jen 2014, documents.worldbank.org
- Haiti - Urban Community Driven Development Project : additional financing and restructuring, 29 me 2014, documents.worldbank.org
- Haiti - Haiti - Urban Community Driven Development Project / PRODEPUR : P106699 - Implementation Status Results Report : Sequence 14, 16 fevriye 2014, documents.worldbank.org
- Haiti - Port-au-Prince Neighborhood Housing Reconstruction Project and Urban Community Driven Development Project : technical supervision mission - December 16 to 20, 2013 : Haiti - Projet d'Amelioration des Quartiers Precaires de Port-au-Prince et du Projet de Developpement Communautaire Participatif Urbain-Habitat : mission de supervision technique - 16 au 20 Decembre 2013, 20 desanm 2013, documents.worldbank.org
- Haiti - Haiti - Urban Community Driven Development Project / PRODEPUR : P106699 - Implementation Status Results Report : Sequence 13, 16 desanm 2013, documents.worldbank.org
- Haiti - Haiti - Urban Community Driven Development Project / PRODEPUR : P106699 - Implementation Status Results Report : Sequence 12, 7 fevriye 2013, documents.worldbank.org
- Haiti - Haiti - Urban Community Driven Development Project / PRODEPUR : P106699 - Implementation Status Results Report : Sequence 11, 7 jiyè 2012, documents.worldbank.org
- Haiti - Haiti - Urban Community Driven Development Project / PRODEPUR : P106699 - Implementation Status Results Report : Sequence 10, 10 desanm 2011, documents.worldbank.org
- Final AM PRODEPUR-JSDF-OCT2011.pdf, 28 novanm 2011, documents.worldbank.org
- Haiti - Additional Financing for Housing Reconstruction - Urban Community Driven Development Project : restructuring (Vol. 2 of 2) : Data sheet, 26 oktòb 2011, documents.worldbank.org
- Haiti - Additional Financing for Housing Reconstruction - Urban Community Driven Development Project : restructuring (Vol. 1 of 2) : Main report, 21 oktòb 2011, documents.worldbank.org
- Haiti - Urban Community Driven Development Project : technical supervision mission - October 18 to 21, 2011 : Haití - Proyecto de desarrollo impulsado por comunidad urbana : la mision supervision tecnica - 18 al 21 de octubre de 2011, 21 oktòb 2011, documents.worldbank.org
- Haiti - Additional Financing for Housing Reconstruction - Urban Community Driven Development Project : environmental and social management framework : Resume du cadre de gestion environnementale et sociale, 8 avril 2011, documents.worldbank.org
- Haiti - Haiti - Urban Community Driven Development Project / PRODEPUR : P106699 - Implementation Status Results Report : Sequence 09, 7 mas 2011, documents.worldbank.org
- Haiti - Haiti - Urban Community Driven Development Project / PRODEPUR : P106699 - Implementation Status Results Report : Sequence 08, 21 fevriye 2011, documents.worldbank.org
- Financing Agreement for IDA Grant H621-HT Conformed, 23 novanm 2010, documents.worldbank.org
- Haïti - Projet de développement communautaire participatif en milieu urbain, 2 novanm 2010, documents.worldbank.org
- Haiti - Urban Community Driven Development Project : additional financing : Haiti - Projet de Developpement Communautaire Participatif en Milieu Urbain : financement additionnel, 6 oktòb 2010, documents.worldbank.org
- Haiti - Urban Community Driven Development Project : additional financing, 6 oktòb 2010, documents.worldbank.org
- Annexe au Cadre de gestion environnementale de PRODEPUR pour le Projet JSDF Cash for Work, 28 septanm 2010, documents.worldbank.org
- Haiti - Housing Reconstruction - Urban Community Driven Development Project : additional financing, 20 septanm 2010, documents.worldbank.org
- Financing Agreement, Grant H394-HT Conformed, 30 jen 2008, documents.worldbank.org
- Announcement of World Bank Approves Fifteen Million Seven Hundred Thousand US Dollars Grant to Haiti for Urban Community-Driven Development on June 3, 2008, 3 jen 2008, documents.worldbank.org
- Haiti - Urban Community Driven Development Project (PRODEPUR), 29 avril 2008, documents.worldbank.org
- Haiti - Urban Community Driven Development Project / PRODEPUR, 11 avril 2008, documents.worldbank.org
- Haiti - Urban Community Driven Development Project / PRODEPUR, 11 avril 2008, documents.worldbank.org
- Haïti - Projet national de développement communautaire participatif en milieu urbain (PRODEPUR) : Cadre de gestion environnementale, 1 mas 2008, documents.worldbank.org
- Haiti - Urban & Peri-Urban Areas Community Driven Development Project / PRODEPUR, 9 novanm 2007, documents.worldbank.org
- Haiti - Urban & Peri-Urban Areas Community Driven Development Project / PRODEPUR, 2 novanm 2007, documents.worldbank.org
Avi apèl dòf (2)
- Procurement Notices, projects.worldbank.org
- Contract Awards, projects.worldbank.org
Sous
- Fich IATI (d-portal): kondisyon itilizasyon piblikatè a fikse
- IATI: kondisyon itilizasyon piblikatè a fikse
- Relve kredi ak don IDA (seri done): World Bank data, CC BY 4.0 (https://datacatalog.worldbank.org/public-licenses).
- Tranzaksyon: kondisyon itilizasyon piblikatè a fikse
- Fich operasyon an: kondisyon itilizasyon piblikatè a fikse
- Paj pwojè a, Bank Mondyal: kondisyon itilizasyon piblikatè a fikse
- Dokiman Bank Mondyal: kondisyon itilizasyon piblikatè a fikse
Done jiska 18 oktòb 2026
| Sous | Li nan dat |
|---|---|
| IATI | 18 oktòb 2026 |
| IATI | 18 oktòb 2026 |
| IDA, eta kredi ak don | 18 oktòb 2026 |
| Pwojè Bank Mondyal | 18 oktòb 2026 |
| Dokiman Bank Mondyal | 18 oktòb 2026 |
Site paj sa a
HaitiDocs. Pwojè Devlopman Iben ki Dirije pa Kominote / PRODEPUR. Pòtfolyo patnè yo, done jiska 18 oktòb 2026. https://www.haitidocs.org/portfolio/projects/WB%3AP106699?lang=ht