HaitiDocs

Data / Partner portfolio / United States / USAID

Repairs to the perimeter wall and internal fencing at the CHP

Published title: The OIEE office seeks the mission director S approval of the attached statement of work (SOW) and IGCE for repairs to the perimeter wall and internal fencing at the CHP. USAID has been collaborating with the U.S. coast GUARD (USCG) and the government of Haiti (GoH) to identify basic I

US$ millions unless stated. Haitian fiscal year, October to September. FY2026-27 began October 1, 2026.

Description

The OIEE office seeks the mission director S approval of the attached statement of work (SOW) and IGCE for repairs to the perimeter wall and internal fencing at the CHP. USAID has been collaborating with the U.S. coast GUARD (USCG) and the government of Haiti (GoH) to identify basic improvements to infrastructure and equipment that could be made in the short- term to assist the Cap-Haïtien port (CHP) to become compliant with international port security standards. While the work is anticipated to be completed as soon as possible, the proposed period of performance is through January 31, 2015. The IGCE for this purchase order is $148,545. OAA requires approval of the requested action in order to solicit quotes for the services requested in the attached SOW.

Partner
United States, USAID
Sector
Sector not identified
Stage
Closed since December 12, 2014
Start
October 30, 2014
Closing
December 12, 2014
Disbursed as of
Not reported
Instrument
Purchase order, contracts
Implementing agency
LMN Construction SA
Effectiveness
Not reported
Last transaction
June 30, 2016
Operation ID
AID521O1500003
Life cycle4 stages, 5 dates

Stage history

StageFrom
ApprovedOctober 30, 2014
Under wayOctober 30, 2014
ClosingDecember 12, 2014
ClosedDecember 12, 2014

Dates

EventDateSource
ApprovalOctober 30, 2014USAspending
First commitmentOctober 30, 2014Transactions
Planned startOctober 30, 2014USAspending
SigningOctober 30, 2014USAspending
Planned closing dateDecember 12, 2014USAspending

Financing

Table 1.Position at the data date by source (stocks), US$ millions

This pageUS$ millionsSource
Commitment0.1USAspending
DisbursedNot reported
UndisbursedThe balance each partner reports as not yet disbursed, summed only when every operation in scope reports it.Not reported
Total costNot reported

USAspending amounts. Approved: The obligations of the award, in US$: the legal commitment of federal funds. Disbursed to date: The outlays of the award, in US$. Undisbursed: The undisbursed balance the record gives, where the source reports one, in US$. Amounts by source

Changes to the operation0 restructurings
Original closing date
Not reported
Closing date extensions
Not reported
Restructurings
0
Emergency component
Not reported

New commitments and disbursements by fiscal year

Table 2.New commitments and disbursements by fiscal year (flows), US$ millions

FY2014-15US$ millionsFY2015-16US$ millions
New commitments0.1−0.0
DisbursementsNot reportedNot reported
Cumulative disbursementsNot reportedNot reported

Records and documents

Transactions2 transactions, October 30, 2014 to June 30, 2016

Table 3.Transactions, US$ millions

DateMeasureAmountUS$ millionsSourceMethod
October 30, 2014Commitment0.1USAspendingUSAspending obligation
June 30, 2016Commitment−0.0USAspendingnegative commitment as reported: a reduction or correction of an earlier commitment, not a cancellation in the source; USAspending obligation
Identifiers1 identifier
SystemIdentifierSource
US awardAID521O1500003Operation record

Partner documents

No document is listed for this operation.

Sources

Data as of October 18, 2026
SourceAccessed on
USAspendingOctober 18, 2026
USAspendingOctober 18, 2026
Cite this page

HaitiDocs. Repairs to the perimeter wall and internal fencing at the CHP. Partner portfolio, data as of October 18, 2026. https://www.haitidocs.org/portfolio/projects/US%3AAID521O1500003