Data / Partner portfolio / IDB Group / IDB
Modernization of Agricultural Health Public Services
US$ millions unless stated. Haitian fiscal year, October to September. FY2026-27 began October 1, 2026.
Objective
The Program will contribute to increase the productivity of the agricultural sector and to improve the access of agricultural products to national and international markets, through the strengthening of public capacity to provide and integrate the animal and plant health and food safety services.
As published by IDB projects dataset, in its original language.
- Stage
- Closed since July 2, 2024
- Approval
- July 23, 2014
- Closing
- July 2, 2024
- Instrument
- Grant, Sovereign Guaranteed
- Effectiveness
- Not reported
- Last transaction
- September 30, 2021
- Operation ID
- HA-L1094
Life cycle4 stages, 9 dates
Stage history
| Stage | From |
|---|---|
| Approved | July 23, 2014 |
| Under way | August 21, 2014 |
| Closing | October 30, 2022 |
| Closed | July 2, 2024 |
Dated events
| Event | Date | Source |
|---|---|---|
| Approval | July 23, 2014 | IDB projects dataset |
| First commitment | July 23, 2014 | Transactions |
| Signing | August 21, 2014 | IDB projects dataset |
| Planned start | June 24, 2015 | IATI |
| Actual start | July 6, 2015 | IATI |
| First disbursement | July 31, 2015 | Transactions |
| Last disbursement | September 30, 2021 | Transactions |
| Closing date | October 30, 2022 | IATI |
| Actual end | July 2, 2024 | IATI |
Financing
Table 1.Financing, US$ millions
| Financier | AmountUS$ millions | Role | Source |
|---|---|---|---|
| Local counterpart | 2.0 | Counterpart | IDB projects dataset |
| IDB | 14.0 | Institution | IDB projects dataset |
Table 2.Position at the data date by source (stocks), US$ millions
| This pageUS$ millions | Source | IATIUS$ millions | |
|---|---|---|---|
| Commitment | 14.0 | IDB projects dataset | 14.0 |
| Disbursed | 14.0 | IATI | 14.0 |
| Undisbursed | Not reported | ||
| Total cost | 16.0 | IDB projects dataset |
Each amount is given as the source publishes it, converted to US$. IATI column: the commitments and disbursements the partner reports to IATI, converted to US$. Amounts by source
This page uses IDB projects dataset for the commitment and IATI for disbursements.
Changes to the operationnot reported
- Original closing date
- Not reported
- Closing date extensions
- Not reported
- Restructurings
- Not reported
- Emergency component
- Not reported
New commitments and disbursements by fiscal year
Table 3.New commitments and disbursements by fiscal year (flows), US$ millions
| FY2013-14US$ millions | FY2014-15US$ millions | FY2015-16US$ millions | FY2016-17US$ millions | FY2017-18US$ millions | FY2018-19US$ millions | FY2019-20US$ millions | FY2020-21US$ millions | |
|---|---|---|---|---|---|---|---|---|
| New commitments | 14.0 | Not reported | Not reported | Not reported | Not reported | Not reported | Not reported | Not reported |
| Disbursements | Not reported | 0.5 | 0.5 | 1.2 | 2.0 | 2.7 | 2.8 | 4.2 |
| Cumulative disbursements | Not reported | 0.5 | 1.0 | 2.2 | 4.2 | 6.9 | 9.8 | 14.0 |
Records and documents
Transactions14 records, July 23, 2014 to September 30, 2021
Table 4.Transactions, US$ millions
| Date | Measure | AmountUS$ millions | Source | Method |
|---|---|---|---|---|
| July 23, 2014 | Commitment | 14.0 | IDB projects dataset | commitment at approval date |
| July 31, 2015 | Disbursements | 0.5 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| March 31, 2016 | Disbursements | 0.5 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| October 31, 2016 | Disbursements | 0.1 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| December 31, 2016 | Disbursements | 0.6 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| July 31, 2017 | Disbursements | 0.5 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| December 31, 2017 | Disbursements | 0.7 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| June 30, 2018 | Disbursements | 1.3 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| November 30, 2018 | Disbursements | 0.1 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| December 31, 2018 | Disbursements | 2.6 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| December 31, 2019 | Disbursements | 0.5 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| May 31, 2020 | Disbursements | 0.2 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| July 31, 2020 | Disbursements | 2.2 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| September 30, 2021 | Disbursements | 4.2 | IATI | IATI disbursement (transaction type 3), paid to another organization |
Terms5 of 6 reported
- Finance type
- 110 Standard grant
- Flow type
- 20 Other official flows, excluding export credits
- Aid type
- C01 Project-type interventions
- Tied status
- 5 Untied
- Collaboration type
- 4 Multilateral outflows
- Humanitarian
- Not reported
Locations1 place named
| Departments | Not reported |
| Places named by the source | Haiti, ROUTE NATIONALE 1 DAMIEN, PORT AU PRINCE |
| Places with coordinates | 0 |
Results indicators27 indicators
| Indicator | Baseline | Target | Latest value | Date of latest value |
|---|---|---|---|---|
| Biosecurity plan and quality and laboratory protocols developed and in force | Not reported | 2.00 | 0.00 | December 31, 2016 |
| Central infrastructure (building for integrated services) and county (zoophytosanitaires multipurpose centers) equiped | Not reported | 1.00 | 0.00 | December 31, 2019 |
| Health protection centers built departmental polyvalent | Not reported | 1.00 | 0.00 | December 31, 2019 |
| Infrastructure LVCQAT rehabilitated / completed | Not reported | 1.00 | 0.00 | December 31, 2017 |
| Integrated information (animal health, plant protection, quarantine laboratory) accessible from the website of the MARNDR | Not reported | 1.00 | 0.00 | December 31, 2017 |
| LVCQAT equipped | Not reported | 1.00 | 0.00 | December 31, 2017 |
| List of pests defined , updated , published | Not reported | 1.00 | 1.00 | December 31, 2019 |
| List of veterinary professionals and para ( i) identified ( ii) accredited by the MARNDR (iii) members of the Ordre National Veterinary established, updated annually , and published on the website MARNDR | Not reported | 1.00 | 0.00 | December 31, 2018 |
| MARNDR functions for which a cost recovery mechanism is established and officially entered into force | Not reported | 2.00 | 0.00 | December 31, 2018 |
| Maintenance service of refrigeration units produced solar ( 150 per year for 4 years) | Not reported | 150.00 | 15.00 | December 31, 2019 |
| Monthly animal disease surveillance bulletin distributed on the ground and published on the website of the MARNDR | Not reported | 12.00 | 0.00 | December 31, 2018 |
| Monthly vegetable epidemiological bulletin released on the field and published on the website MARNDR | Not reported | 12.00 | 0.00 | December 31, 2018 |
| PPC and Teschen epidemiological surveys conducted | Not reported | 2.00 | 0.00 | December 31, 2016 |
| Pigs vaccinated against PPC and Teschen disease (simultaneous vaccination) and identified by an earring | Not reported | 800000.00 | 0.00 | December 31, 2016 |
| Plant Pathology and Virology Laboratory furnished and equipped | Not reported | 2.00 | 0.00 | December 31, 2016 |
| Planters volunteer members of the plant epidemiological surveillance network formed | Not reported | 5500.00 | 4500.00 | December 31, 2019 |
| Private veterinary paraprofessionals trained or retrained | Not reported | 250.00 | 0.00 | December 31, 2019 |
| Procedures established for LVCQAT and in force | Not reported | 3.00 | 0.00 | December 31, 2017 |
| Procedures, Plans, Financial and Administrative Manuals prepared officially validated and published on the website of the MARNDR (included : trained staff) | Not reported | 4.00 | 4.00 | December 31, 2015 |
| Samples (blood, tissue , organs) collected and sent for analysis to LVCQAT ( 35,000 per year) | Not reported | 35000.00 | 0.00 | December 31, 2019 |
| Staff laboratories of plant protection trained | Not reported | 4.00 | 0.00 | December 31, 2016 |
| Staff of the risk analysis cell of the Plant Protection formed | Not reported | 3.00 | 0.00 | December 31, 2017 |
| Staff of the risk analysis cell trained for Animal Health | Not reported | 2.00 | 4.00 | December 31, 2017 |
| Staff trained for LVCQAT | Not reported | 7.00 | 0.00 | December 31, 2018 |
| Traps for control of the crazy ant installed and replenished every week bait continuously throughout the campaign | Not reported | 218250.00 | 0.00 | December 31, 2017 |
| Traps for surveillance of fruit fly installed and replenished every week / fortnight bait , continuously throughout the campaign | Not reported | 196000.00 | 0.00 | December 31, 2016 |
| Volunteer members of the animal epidemiological surveillance network trained (1 per year ) | Not reported | 5500.00 | 0.00 | December 31, 2019 |
Funds passed on14 transactions
| Receiver | Transaction | Date | US$ millions |
|---|---|---|---|
| Ministere de L Agriculture des Resources | Disbursement | September 30, 2021 | 4.2 |
| Name not shown | Disbursement | July 31, 2020 | 2.2 |
| Heifer Project International | Disbursement | May 31, 2020 | 0.2 |
| INTE Trade Limited | Disbursement | December 31, 2019 | 0.5 |
| Name not shown | Disbursement | December 31, 2018 | 2.6 |
| Heifer Project International | Disbursement | November 30, 2018 | 0.1 |
| Name not shown | Disbursement | June 30, 2018 | 1.3 |
| Name not shown | Disbursement | December 31, 2017 | 0.7 |
| Heifer Project International | Disbursement | December 31, 2017 | 0.1 |
| Name not shown | Disbursement | July 31, 2017 | 0.5 |
| Name not shown | Disbursement | December 31, 2016 | 0.6 |
| Schippers Export B.V | Disbursement | October 31, 2016 | 0.1 |
| Name not shown | Disbursement | March 31, 2016 | 0.5 |
| Name not shown | Disbursement | July 31, 2015 | 0.5 |
Identifiers3 identifiers
| System | Identifier | Source |
|---|---|---|
| IATI identifier | XI-IATI-IADB-HA-L1094 | IATI |
| IDB operation | HA-L1094 | Operation record |
| Public investment program line | 1113-1-12-54-29 | Public investment program |
Partner documents35 documents
- HA-L1094 - Modernization of Agricultural Health Public Services 38913960.PDF, iadb.org
- Link - ESMR HA-L1094 38781328.docx, iadb.org
- Link - Monitoring and Evaluation Plan HA-L1094 38780663.docx, iadb.org
- Link - Results Matrix complete version HA-L1094 38780965.docx, iadb.org
- HA-L1094 - Modernizacin de los Servicios Pblicos de Sanidad 38913950.PDF, iadb.org
- Link - Component 2 - Plant Health HA-L1094 38780368.xls, iadb.org
- Link - Component 4 - Laboratory HA-L1094 38780394.xls, iadb.org
- Link - Economic Analysis HA-L1094 38776304.docx, iadb.org
- HA-L1094 - Analyse environnementale et plan de gestion V1docx 38799493.DOCX, iadb.org
- Link - Component 1 - Institutional Management HA-L1094 38780364.xls, iadb.org
- Link - Component 3 - Animal Health HA-L1094 38780373.xls, iadb.org
- Link - Detailed Budget HA-L1094 38776268.xlsx, iadb.org
- Link - Essential staff needed in the departmental agricultural health centers HA-L1094 38801623.xls, iadb.org
- Link - General Plan - Strategic and Investment Plan for Ag Health and Food Safety 2014 - 2019 HA-L1094 38780399.docx, iadb.org
- Link - PEP HA-L1094 38801609.docx, iadb.org
- Link - POA - Plan of Activities for first disbursement and the first 18 months of implementation HA-L1094 38776289.xls, iadb.org
- Link - Procurement Plan HA-L1094 38781325.xlsx, iadb.org
- HA-L1094 Second period Jan-Dec 2018-Public Report.pdf, iadb.org
- HA-L1094 Second period Jan-Dec 2019-Public Report.pdf, iadb.org
- IDB-PCR-Production-Timeline.pdf, iadb.org
- PCR Public Version - HA-L1094.pdf, iadb.org
- HA-L1094 First period Jan-Jun 2017-Public Report.pdf, iadb.org
- HA-L1094 First period Jan-Jun 2018-Public Report.pdf, iadb.org
- HA-L1094 First period Jan-Jun 2019-Public Report.pdf, iadb.org
- HA-L1094 Second period Jan-Dec 2020 - Public Report.pdf, iadb.org
- HA-L1094 Second period Jan-Dec 2021 - Public Report.PDF, iadb.org
- HA-L1094 First period Jan-Jun 2020 - Public Report.pdf, iadb.org
- HA-L1094 First period Jan-Jun 2021 - Public Report.pdf, iadb.org
- HA-L1094 First period Jan-Jun 2022 - Public Report.PDF, iadb.org
- HA-L1094 First period Jan-Jun 2023 - Public Report.PDF, iadb.org
- HA-L1094 First period Jan-Jun 2024 - Public Report.PDF, iadb.org
- HA-L1094 Second period Jan-Dec 2016-Public Report.pdf, iadb.org
- HA-L1094 Second period Jan-Dec 2017-Public Report.pdf, iadb.org
- HA-L1094 Second period Jan-Dec 2022 - Public Report.PDF, iadb.org
- HA-L1094 Second period Jan-Dec 2023 - Public Report.PDF, iadb.org
Procurement notices (14)
- HA-L1094 28.pdf, iadb.org
- IDB_Procurement_Notices.xlsx, iadb.org
- HA-L1094 1432.pdf, iadb.org
- HA-L1094 171.pdf, iadb.org
- HA-L1094 172.pdf, iadb.org
- HA-L1094 39329631.PDF, iadb.org
- HA-L1094 39331772.PDF, iadb.org
- HA-L1094 39863612.PDF, iadb.org
- HA-L1094 40057735.PDF, iadb.org
- HA-L1094 40791135.PDF, iadb.org
- HA-L1094 40819630.PDF, iadb.org
- HA-L109416202SP.pdf, iadb.org
- HA-L1094P531620SP.pdf, iadb.org
- IDB_Project_Procurement_Contract_Awards_Data.xlsx, iadb.org
Documents on HaitiDocs
Sources
- IATI record (d-portal): terms of use set by the publisher
- IATI: terms of use set by the publisher
- IDB project page: terms of use set by the publisher
- Transactions: terms of use set by the publisher
- Operation record: terms of use set by the publisher
- Public investment program: terms of use set by the publisher
Data as of October 18, 2026
| Source | Read on |
|---|---|
| IATI | October 18, 2026 |
| IATI | October 18, 2026 |
| IDB projects dataset | October 18, 2026 |
| Public investment program | October 18, 2026 |
Cite this page
HaitiDocs. Modernization of Agricultural Health Public Services. Partner portfolio, data as of October 18, 2026. https://www.haitidocs.org/portfolio/projects/IDB%3AHA-L1094