HaitiDocs

Data / Partner portfolio / The Netherlands Red Cross

Haiti earthquake 2010: Water and sanitation facilities for affected families

US$ millions unless stated. Haitian fiscal year, October to September. FY2026-27 began October 1, 2026.

Description

As part of an on-going response to the January 12, 2010 earthquake, the Canadian Red Cross Society (CRC) and the Netherlands Red Cross are undertaking a series of health projects in the Southeast department of Haiti. Among these projects is a community-based health and first aid in action project (CBHFA) which includes the construction of 5,000 latrines. The overall goal of building latrines is increased disease and injury-resilience.

Partner
The Netherlands Red Cross
Sector
Humanitarian
Stage
Closed since December 30, 2015
Start
August 31, 2013
Closing
December 30, 2015
Disbursed as of
December 31, 2016
Implementing agency
Not reported
Effectiveness
Not reported
Departments
Sud-Est
Last transaction
December 31, 2016
IATI identifier
NL-KVK-40409352-PRJ08-172-0002
Life cycle3 stages, 5 dates

Stage history

StageFrom
Under wayAugust 31, 2013
ClosingDecember 30, 2015
ClosedDecember 30, 2015

Dates

EventDateSource
Actual startAugust 31, 2013IATI
Planned startAugust 31, 2013IATI
First disbursementSeptember 16, 2013Transactions
Planned closing dateDecember 30, 2015IATI
Last disbursementDecember 31, 2016Transactions

Financing

Table 1.Position at the data date by source (stocks), US$ millions

This pageUS$ millionsSource
CommitmentNot reported
Disbursed2.0IATI
UndisbursedThe balance each partner reports as not yet disbursed, summed only when every operation in scope reports it.Not reported
Total costNot reported

IATI amounts. Approved: The commitments the partner reports, converted to US$. Disbursed to date: The disbursements (IATI transaction type 3, funds paid to another organization) and expenditure (type 4, funds spent by the publisher) the partner reports, converted to US$. Undisbursed: The undisbursed balance the record gives, where the partner reports one, in US$. Amounts by source

Changes to the operationnot reported
Original closing date
Not reported
Closing date extensions
Not reported
Restructurings
Not reported
Emergency component
Not reported

Disbursements by fiscal year

Disbursements, US$ millions
FY2012-13, US$0.1 million0.112-13FY2013-14, US$0.9 million0.913-14FY2014-15, US$1.0 million114-15FY2015-16, US$0.1 million0.115-16FY2016-17, US$−0.0 million−0.016-17FY2012-13, US$0.1 million0.112-13FY2013-14, US$0.9 million0.913-14FY2014-15, US$1.0 million114-15FY2015-16, US$0.1 million0.115-16FY2016-17, US$−0.0 million−0.016-17

Table 2.Disbursements by fiscal year, US$ millions

FY2012-13US$ millionsFY2013-14US$ millionsFY2014-15US$ millionsFY2015-16US$ millionsFY2016-17US$ millions
Disbursements0.10.91.00.1−0.0
Cumulative disbursements0.10.92.02.02.0

Records and documents

Transactions26 transactions, September 16, 2013 to December 31, 2016

Table 3.Transactions, US$ millions

DateMeasureAmountUS$ millionsSourceMethod
September 16, 2013Disbursements<0.1IATIIATI expenditure (transaction type 4), spent by the publisher
September 24, 2013Disbursements<0.1IATIIATI disbursement (transaction type 3), paid to another organization
September 30, 2013Disbursements<0.1IATIIATI expenditure (transaction type 4), spent by the publisher
December 31, 2013Disbursements<0.1IATIIATI expenditure (transaction type 4), spent by the publisher
March 12, 2014Disbursements<0.1IATIIATI expenditure (transaction type 4), spent by the publisher
March 12, 2014Disbursements0.2IATIIATI disbursement (transaction type 3), paid to another organization
March 31, 2014Disbursements<0.1IATIIATI expenditure (transaction type 4), spent by the publisher
May 31, 2014Disbursements0.3IATIIATI disbursement (transaction type 3), paid to another organization
June 10, 2014Disbursements<0.1IATIIATI expenditure (transaction type 4), spent by the publisher
June 30, 2014Disbursements<0.1IATIIATI expenditure (transaction type 4), spent by the publisher
July 28, 2014Disbursements0.2IATIIATI disbursement (transaction type 3), paid to another organization
September 16, 2014Disbursements0.1IATIIATI expenditure (transaction type 4), spent by the publisher
September 30, 2014Disbursements<0.1IATIIATI expenditure (transaction type 4), spent by the publisher
December 31, 2014Disbursements0.1IATIIATI expenditure (transaction type 4), spent by the publisher
March 24, 2015Disbursements<0.1IATIIATI expenditure (transaction type 4), spent by the publisher
March 31, 2015Disbursements0.3IATIIATI disbursement (transaction type 3), paid to another organization
May 12, 2015Disbursements0.3IATIIATI disbursement (transaction type 3), paid to another organization
June 23, 2015Disbursements0.1IATIIATI expenditure (transaction type 4), spent by the publisher
June 30, 2015Disbursements<0.1IATIIATI expenditure (transaction type 4), spent by the publisher
August 28, 2015Disbursements0.2IATIIATI disbursement (transaction type 3), paid to another organization
September 21, 2015Disbursements0.1IATIIATI expenditure (transaction type 4), spent by the publisher
September 30, 2015Disbursements<0.1IATIIATI expenditure (transaction type 4), spent by the publisher
December 31, 2015Disbursements0.1IATIIATI expenditure (transaction type 4), spent by the publisher
February 1, 2016Disbursements<0.1IATIIATI expenditure (transaction type 4), spent by the publisher
December 31, 2016Disbursements<0.1IATIIATI expenditure (transaction type 4), spent by the publisher
December 31, 2016Disbursements−0.1IATIIATI disbursement (transaction type 3), paid to another organization
Terms6 of 6 reported
Finance type
110 Standard grant
Flow type
30 Private development finance
Aid type
C01 Project-type interventions
Tied status
5 Untied
Collaboration type
1 Bilateral
Humanitarian
Yes
Locations1 department, 9 places named, 9 places with coordinates
DepartmentsSud-Est
Places named by the sourceCayes-Jacmel, Gaillard, Haiti, La Vallée, Macary, Marigot, Musac, South-East Department, Ternier
Places with coordinates9
Funds transferred onward8 transactions
RecipientTransactionDateUS$ millions
Haiti Red Cross SocietyDisbursementDecember 31, 2016−0.1
Haiti Red Cross SocietyDisbursementAugust 28, 20150.2
Haiti Red Cross SocietyDisbursementMay 12, 20150.3
Haiti Red Cross SocietyDisbursementMarch 31, 20150.3
Haiti Red Cross SocietyDisbursementJuly 28, 20140.2
Haiti Red Cross SocietyDisbursementMay 31, 20140.3
Haiti Red Cross SocietyDisbursementMarch 12, 20140.2
Haiti Red Cross SocietyDisbursementSeptember 24, 2013<0.1
Identifiers1 identifier
SystemIdentifierSource
IATI identifierNL-KVK-40409352-PRJ08-172-0002IATI

Partner documents

No document is listed for this operation.

Sources

Data as of October 18, 2026
SourceAccessed on
IATIOctober 18, 2026
IATIOctober 18, 2026
Cite this page

HaitiDocs. Haiti earthquake 2010: Water and sanitation facilities for affected families. Partner portfolio, data as of October 18, 2026. https://www.haitidocs.org/portfolio/projects/IATI%3ANL-KVK-40409352-PRJ08-172-0002