Construction of the Artibonite Provincial Hospital in Gonaïves - I
US$ millions unless stated. Haitian fiscal year, October to September. FY2026-27 began October 1, 2026.
Description
This project contributes to the construction of a new 200-bed provincial hospital in Gonaïves. It is one of three parts of a $30-million initiative. This component supports the design, construction of the majority of the hospital, its medical equipment and hospital management. As the partner agency, UNOPS is responsible for the implementation of these activities, including the $14.5 million contract for the construction of the hospital. The Gonaïves hospital initiative aims to improve access to and the quality of specialized health services for children, women, and men in Artibonite Department. It also aims to improve the health system in Haiti and to establish a replicable model for provincial-level hospitals in Haiti. The initiative includes the design, construction, and equipping of
more
the new hospital. It also includes initial institutional support such as training in hospital management, hospital equipment usage, and maintenance, as well as specialized training in maternal, neonatal, and child health issues. The project is financially divided for administrative reasons. The sub-project I includes the majority of funds reserved for the design, construction and supervision; sub-project II includes the contribution allocated from Canada's Maternal, Neonatal and Child Health priority; and sub-project III represents funds set aside for monitoring and evaluation of the project. The expected results of the project are: 1- The specialized service offer, including obstetrics, gynecology and paediatrics is reinforced in the Artibonite Department; 2- The Ministry of Public Health and Population’s management of service offer, particularly for mothers and children, is more efficient.
- Sector
- Health
- Stage
- Closed since May 31, 2017
- Start
- January 11, 2011
- Closing
- May 31, 2017
- Effectiveness
- Not reported
- Departments
- Artibonite
- Last transaction
- December 2, 2014
- IATI identifier
Life cycle4 stages, 7 dates
Stage history
| Stage | From |
|---|---|
| Approved | January 11, 2011 |
| Under way | January 11, 2011 |
| Closing | May 31, 2017 |
| Closed | May 31, 2017 |
Dated events
| Event | Date | Source |
|---|---|---|
| Actual start | January 11, 2011 | IATI |
| First commitment | January 11, 2011 | Transactions |
| Planned start | January 11, 2011 | IATI |
| First disbursement | February 6, 2012 | Transactions |
| Last disbursement | December 2, 2014 | Transactions |
| Actual end | May 31, 2017 | IATI |
| Closing date | May 31, 2017 | IATI |
Financing
Table 1.Position at the data date by source (stocks), US$ millions
| This pageUS$ millions | Source | |
|---|---|---|
| Commitment | 19.5 | IATI |
| Disbursed | 18.7 | IATI |
| Undisbursed | Not reported | |
| Total cost | Not reported |
IATI amounts. Approved: The commitments the partner reports, converted to US$. Disbursed to date: The disbursements (IATI transaction type 3, money paid to another organization) and expenditure (type 4, money the publisher spent itself) the partner reports, converted to US$. Undisbursed: The undisbursed balance the record gives, where the partner reports one, in US$. Amounts by source
Changes to the operationnot reported
- Original closing date
- Not reported
- Closing date extensions
- Not reported
- Restructurings
- Not reported
- Emergency component
- Not reported
New commitments and disbursements by fiscal year
Table 2.New commitments and disbursements by fiscal year (flows), US$ millions
| FY2010-11US$ millions | FY2011-12US$ millions | FY2012-13US$ millions | FY2013-14US$ millions | FY2014-15US$ millions | |
|---|---|---|---|---|---|
| New commitments | 19.5 | Not reported | Not reported | Not reported | Not reported |
| Disbursements | Not reported | 0.8 | 14.2 | 3.7 | <0.1 |
| Cumulative disbursements | Not reported | 0.8 | 14.9 | 18.6 | 18.7 |
Records and documents
Transactions6 records, January 11, 2011 to December 2, 2014
Table 3.Transactions, US$ millions
| Date | Measure | AmountUS$ millions | Source | Method |
|---|---|---|---|---|
| January 11, 2011 | Commitment | 19.5 | IATI | IATI commitment (transaction type 2); converted: CAD at 2011 annual average (Federal Reserve G.5A/G.5 via FRED) |
| February 6, 2012 | Disbursements | 0.8 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| February 21, 2013 | Disbursements | 11.6 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| May 13, 2013 | Disbursements | 2.6 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| March 14, 2014 | Disbursements | 3.7 | IATI | IATI disbursement (transaction type 3), paid to another organization |
| December 2, 2014 | Disbursements | <0.1 | IATI | IATI disbursement (transaction type 3), paid to another organization |
Terms6 of 6 reported
- Finance type
- 110 Standard grant
- Flow type
- 10 Official development assistance
- Aid type
- C01 Project-type interventions
- Tied status
- 5 Untied
- Collaboration type
- 1 Bilateral
- Humanitarian
- No
Policy markers4 policy markers
| Policy marker | Significance | Source |
|---|---|---|
| Gender equality | Significant objective | IATI |
| Participatory development and good governance | Significant objective | IATI |
| 10 | Significant objective | IATI |
| 9 | Principal objective | IATI |
Locations1 department, 1 place with coordinates
| Departments | Artibonite |
| Places named by the source | Not reported |
| Places with coordinates | 1 |
Results indicators1 indicator
| Indicator | Baseline | Target | Latest value | Date of latest value |
|---|---|---|---|---|
| Results achieved | Not reported | Not reported | Not reported | Not reported |
Funds passed on5 transactions
Identifiers2 identifiers
| System | Identifier | Source |
|---|---|---|
| OECD CRS identifier | 2011200129 | IATI |
| IATI identifier | CA-3-A034921001 | IATI |
Partner documents
- Description, w05.international.gc.ca
- Description, w05.international.gc.ca
- Activity website, unops.org
- Site web de l'activité, unops.org
Procurement notices (2)
- Proactive disclosure, search.open.canada.ca
- Divulgation proactive, rechercher.ouvert.canada.ca
Sources
- IATI record (d-portal): terms of use set by the publisher
- IATI: terms of use set by the publisher
- Transactions: terms of use set by the publisher
Data as of October 18, 2026
| Source | Read on |
|---|---|
| Exchange rates (Federal Reserve, IMF) | October 18, 2026 |
| IATI | October 18, 2026 |
| IATI | October 18, 2026 |