Audit of USAID/Haiti's Protecting the Rights of Children, Women, and Youth Program (Report No. 1-521-15-001-P)
Summary — An Inspector General audit finding that USAID/Haiti's rights programme had a scope too broad to deliver against and did not achieve its objectives.
Key Findings
- Finds the programme scope was broad and its objectives were not achieved, a conclusion donor reporting does not state about itself.
- Carries eleven recommendations, with management decisions reached on ten at the time of issue.
- Reproduces the mission's comments in full as an appendix, so both sides of the finding are on the record.
Full Description
An Inspector General audit finding that USAID/Haiti's rights programme had a scope too broad to deliver against and did not achieve its objectives. Audits of this kind are the only documents that state such a conclusion about a donor programme on the record, and this one carries eleven recommendations with the mission's response reproduced in full.
Full Document Text
Extracted text from the original document for search indexing.
OFFICE OF INSPECTOR GENERAL
AUDIT OF USAID/HAITI’S
PROTECTING THE RIGHTS OF
CHILDREN, WOMEN, AND
YOUTH PROGRAM
AUDIT REPORT NO. 1-521-15-001-P
November 12, 2014
SAN SALVADOR, EL SALVADOR
Office of Inspector General
November 12, 2014
MEMORANDUM
TO: USAID/Haiti Mission Director, John Groarke
FROM: Regional Inspector General/San Salvador, Van Nguyen /s/
SUBJECT: Audit of USAID/Haiti’s Protecting the Rights of Children, Women, and Youth
Program (Report No. 1-521-15-001-P)
This memorandum transmits our final report on the subject audit. We have carefully considered
your comments on the draft and have included them in their entirety in Appendix II. The report
contains 11 recommendations based on the lessons learned from the mission’s Protecting the
Rights of Children, Women, and Youth Program that should help USAID/Haiti manage its next
program.
USAID/Haiti agreed with all eleven recommendations. Based on comments from the mission
and supporting documentation, management decisions have been reached on ten, with final
action taken on all, except Recommendation 7. A management decision has not been reached
on Recommendation 8. For recommendations with questioned costs, a management decision
will be reached when the mission determines the amounts unallowable.
Please provide the Audit Performance and Compliance Division in the USAID Office of the Chief
Financial Officer with the necessary documentation to achieve final action on
Recommendation 7.
Thank you and your staff for the cooperation and assistance extended to us during this audit.
U.S. Agency for International Development
Embajada Americana
Urb. y Blvd Santa Elena
Antiguo Cuscatlan, Depto. La Libertad
San Salvador, El Salvador
http://oig.usaid.gov
CONTENTS
Summary of Results ................................................................................................................... 1
Audit Findings............................................................................................................................. 4
Program Scope Was Broad, and Objectives Were Not Achieved........................................... 4
Mission’s Delay in Issuing Award Contributed to Staffing Difficulties ...................................... 6
Mission Did Not Confirm Agreement’s Accuracy or Completeness ........................................ 7
Consortium Did Not Function as Planned ............................................................................... 7
Key Program Documents Did Not Meet Agreement Requirements ........................................ 8
Implementer Did Not Award Grants as Intended .................................................................. 10
Evaluation of Management Comments................................................................................... 12
Appendix I—Scope and Methodology .................................................................................... 14
Appendix II—Management Comments ................................................................................... 16
Abbreviations
The following abbreviations appear in this report:
ADS Automated Directives System
AKSE Aksyon Kolektif pou Sekirite kont Ekspwatasyon
(Collective Action for the Security of Children, Women, and Youth)
AO agreement officer
AOR agreement officer’s representative
CARE Cooperative for Assistance and Relief Everywhere
COP chief of party
NGO nongovernmental organization
PADF Pan American Development Foundation
RIG Regional Inspector General
SUMMARY OF RESULTS
In Haiti, social, economic, and cultural factors combine to create an environment where gender-
based violence and forms of exploitation can occur, such as human trafficking, prostitution, and
children working as restaveks.1 The Department of State lists Haiti as a Tier Two Watch List
country2 for trafficking in its annual Trafficking in Persons Report because of the extent of the
problem and the government’s limited antitrafficking resources.
These problems were exacerbated by Haiti’s 2010 earthquake, especially for vulnerable
children, women, and youth. To help alleviate the problems, on March 5, 2012, USAID/Haiti
awarded a $22.5 million cooperative agreement to Cooperative for Assistance and Relief
Everywhere (CARE) Inc., with an estimated completion date of March 4, 2017. The objective
was “to improve the safety and security of children, women, and youth in Haiti by decreasing the
incidence of human rights abuses and expanding access to treatment and care.” The program’s
Haitian Creole name was Aksyon Kolektif pou Sekirite kont Ekspwatasyon (AKSE), which
means “Collective Action for the Security of Children, Women, and Youth.” As of
December 2013, AKSE had obligated $7.7 million and disbursed $3.4 million.
The program had five expected results:
1. Develop and expand integrated monitoring, prevention, and response networks.
2. Strengthen the community’s capacity for prevention and response.
3. Strengthen Haitian Government institutions, policy, and legislation.
4. Strengthen the capacity of Haitian nongovernmental organizations (NGOs).
5. Expand access to specialized services for vulnerable children, women, and youth through
innovative interventions.
CARE planned to implement the program as part of a consortium with Save the Children
International Haiti and Plan International Haiti; CARE’s expertise was in gender integration and
gender-based violence, Save’s was in child protection, and Plan’s was in child-centered
community development. The consortium would issue grants to Haitian organizations, service
providers, and community groups. These grantees would carry out activities to (1) improve
community-based services and support at-risk groups, (2) raise public awareness about key
1
Restaveks are children sent by their parents to work as domestic servants for others. UNICEF estimated
in January 2012 that there are about 225,000 restaveks in Haiti.
2
According to the State Department’s Web site, these are “[C]ountries whose governments do not fully
comply with the Trafficking Victims Protection Act’s minimum standards, but are making significant efforts
to bring themselves into compliance with those standards AND:
a. The absolute number of victims of severe forms of trafficking is very significant or is significantly
increasing;
b. There is a failure to provide evidence of increasing efforts to combat severe forms of trafficking in
persons from the previous year; or the determination that a country is making significant efforts to
bring itself into compliance with minimum standards was based on commitments by the country to
take additional future steps over the next year.
1
human rights issues, (3) reduce risk factors among at-risk individuals and groups, and
(4) reduce the number of family separations that resulted from the earthquake. The program
also sought to expand protection of and support for vulnerable populations facing the risks of
gender-based violence, human trafficking, sexual exploitation, child labor, and recruitment into
gangs and criminal activity.
The Regional Inspector General (RIG)/San Salvador initiated this audit in November 2013 to
determine whether AKSE was achieving its main goals of improving the safety and security of
children, women, and youth in Haiti by decreasing the incidence of human rights abuse and
expanding access to treatment and care.
The audit found that during the program’s initial 18 months, CARE had not achieved any
significant results. Only 8 percent of the grants had been awarded to local partners, and the
largest activity completed was a weeklong summer camp for 100 children funded through a
$100,000 grant.
The following problems contributed to the program’s poor performance.
The scope was broad, and objectives were not achieved (page 4). Because USAID/Haiti
designed the program to tackle numerous problems, several sections within the mission
needed to be involved.
The mission found the program difficult to manage, in part because of the type of agreement
used (page 5). Under a cooperative agreement, the mission’s oversight was limited to
approval of key personnel and program documents.
The mission did not award the program until almost a year after it issued a request for
applications (page 6). By then, the consortium’s employees who had worked on the
application had moved on to other programs.
Mission employees did not review the agreement’s program description to be sure it was
accurate and complete before issuing the award (page 7). The document omitted
descriptions of two of the five expected results.
The consortium did not function as intended because of confusion and disagreements over
members’ roles and responsibilities and implementing program activities (page 7). As a
result, the mission dissolved the consortium in March 2013.
The documents CARE submitted to start the program did not meet requirements (page 8).
For example, more than 50 percent of the target communities that CARE included in its
mapping list were not in the corridor areas listed in the agreement, and a baseline survey
that cost $110,000 was deemed unusable.
CARE did not award grants as intended (page 10). Eighteen months after the program
began, only 8 percent of the grant funds intended for local organizations had been awarded.
Because of the lack of progress, in December 2013 CARE agreed to the mission’s request to
cease all program activities and close out the program. To help the mission manage a
replacement program better, RIG/San Salvador recommends that USAID/Haiti:
2
1. Determine whether the scope of the human rights program should be simplified before
designing the new program (page 5).
2. Coordinate and streamline its processes for approving documents for the new program,
including defining roles and responsibilities within the mission and estimating timelines for
approvals (page 5).
3. Develop and document a plan for a rigorous design process in accordance with Automated
Directives System (ADS) 201 for the follow-on human rights program, and determine and
document its expected level of involvement in program implementation before deciding
between acquisition and assistance instruments (page 6).
4. Review its processing time for award actions to identify potential bottlenecks in the
procurement process (page 6).
5. Review the new program’s description for clarity and completeness, and revise as
necessary before issuing the new award (page 7).
6. Confirm with the implementer the geographic coverage of the new program’s areas of
intervention before implementation (page 10).
7. Complete the mission’s planned baseline survey for determining the existing capacity of
local partners (page 10).
8. Make a determination on the allowability of the costs spent on the previous baseline survey
($110,000), and recover any costs deemed to be unallowable (page 10).
9. Define requirements for the specific assessment tools to be used, and clarify them with the
implementer before starting the new program (page 10).
10. Clarify the goals of the grants component of the program and its relationship to institutional
capacity-building before implementing the new human rights program (page 11).
11. Assess the new implementer’s capacity for awarding and managing grants before awarding
the new agreement (page 11).
Detailed findings appear in the following section. The scope and methodology are described in
Appendix I. Management comments are included in their entirety in Appendix II, and our
evaluation of management comments is on page 12.
3
AUDIT FINDINGS
Program Scope Was Broad, and
Objectives Were Not Achieved
ADS 201.3.11 emphasizes the importance of appropriate project design for projects to achieve
intended results. According to the ADS, “Sound strategic planning, undertaken in coordination
with national development priorities and needs, clarify what development results should be
achieved.” The ADS further states, “The rigorous design and implementation of a project helps
identify and understand how best to achieve those results in the most effective manner.”
According to the award, AKSE would improve the safety and security of children, women, and
youth in Haiti by decreasing the incidence of human rights abuse and expanding access to
treatment and care.
However, after 18 months of implementation, the program had not achieved any significant
measurable results. Efforts to develop and expand integrated monitoring, prevention, and
response networks never got beyond preparing a list of NGOs as a first step in building these
networks.
Furthermore, the limited number of grants awarded to local partners and activities conducted
were insufficient to strengthen communities, Haitian Government institutions, and NGOs. While
the activities raised public awareness in targeted communities, those efforts did not result in
expanding access to specialized services for vulnerable children, women, and youth.
Program Scope Was Broad. The mission’s previous human rights program,3 implemented by
the Pan American Development Foundation (PADF), addressed two of Haiti’s most serious
human rights abuses: (1) human trafficking and (2) torture and organized violence. It ended in
2011, 1 year after the earthquake. At that time, mission officials decided the needs for protective
services for women and children had intensified because people displaced by the earthquake
and living in camps or marginalized communities were more vulnerable to crime, gender-based
violence, and exploitation. To meet these needs, the mission designed a broader follow-on
program that addressed child protection, trafficking, political and legislative advocacy, and
capacity building for local NGOs and the Haitian Government.
The technical evaluation committee reviewing the applications submitted in response to the
request for applications found that none covered the entire program description. Additionally,
PADF was the only applicant that had experience implementing a similar program in Haiti.
However, the approach PADF outlined in its application did not build on the successes and
resources of the previous program and proposed instead to use the Organization of American
States’ approaches and resources.
USAID awarded the cooperative agreement for AKSE to CARE in March 2012 with the clear
understanding that CARE’s program description was the “most acceptable” submitted. Despite
some weaknesses in CARE’s proposed approach, the mission’s evaluation committee
determined the strengths outweighed the weaknesses and decided to move forward because of
the pressing needs for support.
3
The program was worth $8.7 million, about a third of the amount of AKSE.
4
The program’s broad scope led to unwieldy management. Because the program addressed
youth, orphans, vulnerable children, disabled people, and individuals affected by HIV/AIDs or
gender-based violence, the mission’s democracy and governance office managed AKSE in
partnership with the health office. In addition, AKSE documents were reviewed by several
different sections of the mission and the regional legal advisor. CARE and its consortium
partners expressed concerns about the amount of time and confusion that ensued from having
to get decisions from multiple sections.
Objectives Were Not Achieved. USAID/Haiti found the program difficult to manage partly
because the cooperative agreement limited the mission’s authority. According to the document,
mission staff could be substantially involved only in approving work plans, the program
performance monitoring and evaluation plan, program coverage, subawards, and key
personnel. Outside of those areas, the mission agreed to the approach CARE defined in the
program description.
However, the first agreement officer’s representative (AOR) assigned to AKSE was much more
involved than the first agreement officer (AO) felt was necessary for a cooperative agreement,
and he decided to assign a new one to “give the program a fresh start” in October 2012. The AO
then left USAID/Haiti.
The program continued to perform poorly. The new AOR raised concerns about this to the new
AO, and the mission AKSE team (including the mission director and the AO) met with CARE
officials in March 2013 to discuss impediments to implementation and how to proceed.
Because AKSE ended its first year of implementation with little progress, the democracy and
governance team concluded that the program should be modified and limited to smaller, more
achievable objectives. The team proposed revising the program description by limiting it to
two parts: one for antitrafficking to include all the child protection activities and one for gender-
based violence. In each part, the main approaches would be delivering services and building the
capacity of Haitian organizations.
In June 2013 the mission asked CARE to develop a program description for the simplified
approach. CARE submitted a revised description, but the mission did not modify the agreement
to adopt the new approach. After the mission met several times with CARE, the implementer
committed to recruiting human rights professionals and experts in Haiti and asked to keep the
program’s original size and scope. Mission officials agreed.
The program sought to increase the safety and security of children, women, and youth by
decreasing the incidence of human rights abuses and expanding access to treatment and care.
However, these important needs remained unaddressed for the duration of the program while
AKSE struggled with an implementation strategy. Therefore, we make the following
recommendations.
Recommendation 1. We recommend that USAID/Haiti determine whether the scope
should be simplified before designing the follow-on program and document its decision.
Recommendation 2. We recommend that USAID/Haiti implement a plan to coordinate
and streamline mission approvals of program documents for the new program, defining
roles and responsibilities within the mission, and estimating timelines for approvals.
5
Recommendation 3. We recommend that USAID/Haiti develop and document a plan for
a rigorous design process in accordance with Automated Directives System 201 for the
follow-on program, and determine and document its expected level of involvement in
program implementation before deciding on the appropriate type of award mechanism.
Mission’s Delay in Issuing Award
Contributed to Staffing Difficulties
ADS 300.3.5 provides guidance for establishing time frames for issuing awards and emphasizes
the importance of understanding the time it takes to process acquisition and assistance actions.
AOs and technical offices are to work together to establish realistic schedules appropriate to the
planned agreement to ensure timely awards. ADS also provides estimated time frames for
processing actions; a cooperative agreement should take 150 days from request for applications
to award.
While USAID/Haiti issued the request for applications for AKSE in April 2011, it did not award
the agreement until March 2012. This happened because the mission amended the request
three times to make corrections and answer questions. Then in November 2011, the mission
discovered that an application sent in June was not received because of a computer network
glitch; the technical evaluation committee subsequently reviewed the application.
By the time the award was issued in March 2012, all of the consortium staff who had worked on
developing the proposed program description for AKSE had moved on to other programs and
were not available. CARE had an especially difficult time finding a chief of party (COP) who
could lead the program effectively. The initial person CARE proposed in its application was no
longer available, so CARE proposed another. USAID/Haiti agreed to the change.
According to officials from the mission and the consortium, the COP adopted a centralized
management structure that excluded the technical team and consortium members from actively
participating. After generating considerable friction, the COP resigned after 6 months in-country.
CARE brought on an interim COP with USAID’s approval in January; however, this official could
not turn the program around during his 5 months in the job. And in May 2013, CARE hired a
third COP.
According to mission staff, hiring of the new chief of party was a turning point in the program.
Documents like the work plan were redone and started receiving approvals, and space was
allocated for AKSE staff to work together as a team. However, the third COP had differences
with CARE leadership on how to implement the program according to the agreement, which led
to USAID’s decision to terminate the agreement.
The delays in awarding the agreement resulted in staff changes that contributed to the
program’s inability to achieve its goals. To prevent the new program from running into this
problem, we make the following recommendation.
Recommendation 4. We recommend that the mission review and document its award-
processing time to identify potential bottlenecks.
6
Mission Did Not Confirm
Agreement’s Accuracy or
Completeness
ADS 303.3.3 states that before making an award, the AO must ensure that the program
description “clearly identifies the purpose of the program” and “clearly and coherently express
the specific understandings of both parties.”
However, the AKSE agreement signed by CARE and USAID/Haiti did not include information for
all result areas in a format that would permit the award to be used as the guiding program
document. The agreement had detailed information on expected program results, intermediate
results, and activities for only two results: (1) expanded monitoring, prevention, and response
networks, and (2) expanded access to specialized services. The agreement did not specify the
expected results for the other three: (3) strengthening community capacity, (4) strengthening
Haitian Government institutions, and (5) strengthening Haitian NGOs.
This happened because mission staff incorrectly copied and pasted sections of the program
description into the agreement and did not proofread it before issuing the award. The AOR said
she noticed the problem in September 2012 and asked the mission’s acquisition specialists to
correct it. A new AO arrived at this time and also noticed the program description needed to be
corrected. But because of the heavy workload and staff shortages, nobody at the mission ever
corrected it.
Thus, the program description could not be used for Results 3, 4, and 5. To prevent this from
happening again, we make the following recommendation.
Recommendation 5. We recommend that USAID/Haiti review the new program’s
description for clarity, revise it as necessary before implementation, and document all
revisions.
Consortium Did Not Function as
Planned
According to CARE’s application, a consortium of three organizations would implement AKSE:
CARE Haiti, Save the Children International Haiti, and Plan International Haiti. The consortium
was expected to contribute expertise in child protection, as well as an established presence in
the south and north of Haiti. In evaluating CARE’s application, the mission documented that it
found the responsibilities of CARE and its two partner organizations well defined, and the
planned approach for how the three would work together to strengthen Haitian partner
institutions was “useful.”
However, the consortium did not function as intended. Almost immediately, misunderstandings
emerged between CARE and its partners. Although roles and responsibilities had been spelled
out in the cooperative agreement, the first COP changed the structure, which led to confusion.
The consortium partners grew increasingly concerned about the lack of progress. In
February 2013 they asked CARE’s Haiti country director to send a memo to USAID/Haiti’s
acting mission director summarizing their apprehensions with the program and inability to move
forward. Mission officials met with CARE a month later to discuss the memo and the
7
impediments to program implementation; and they determined that the consortium was not
functioning as expected. They concluded that it was not adding value and expressed concerned
that each member was representing its own organization rather than AKSE. As a result, the
mission told CARE to dissolve the consortium and to continue as the sole implementer.
The dissolution of the consortium weakened the program by removing the partners with
expertise in child protection. AKSE did not have anyone with that skill until CARE recruited an
expert in June 2013.
Because the consortium has been dissolved, we are not making a recommendation.
Key Program Documents Did Not
Meet Agreement Requirements
ADS 203.3.2 states that USAID analyzes performance by comparing actual results achieved to
targets set at the beginning of a project. According to the ADS, “This analysis is critical in
determining the progress made in achieving the impacts and outcomes. Missions should use
this to confirm or refute the stated assumptions and hypotheses so they can adapt projects and
objectives as necessary.”
The cooperative agreement required CARE to submit the following documents to USAID: a
mapping study to identify communities for program support; a baseline survey to make sure
changes resulting from program interventions could be measured in a meaningful way; work
plans; and a monitoring and evaluation plan. These documents were necessary to support
implementation and manage the program properly.
However, the documents CARE submitted were either not completed in accordance with the
agreement or did not meet USAID requirements.
Mapping Study. CARE planned to conduct a mapping study to identify communities needing
program support. The mapping involved compiling a list of local NGOs or service providers in
the target areas. The study was supposed to provide baseline information on the strengths of
existing institutions, local partners, and community-based efforts in responding to the needs of
targeted groups; provide information on the status and vulnerabilities of targeted populations;
and determine how interested local NGOs were in working with AKSE.
The agreement called for program interventions in the U.S. Government’s designated
development corridors of Cap Haitien, Port-au-Prince, and St. Marc. The AOR said he was
expecting the study to determine needs and available resources and provide a rationale for
including areas outside the corridors. According to the agreement, the border areas are
extremely important because the majority of human trafficking occurs across the border with the
Dominican Republic. The agreement anticipated that 80 percent of the budget for grants would
go to local organizations in the three corridors.
However, AKSE never completed the mapping study as described in the agreement because
USAID/Haiti and CARE had different views on how the mapping should be done. CARE thought
it should be a thorough exercise requiring time and resources, but the AOR and COP agreed to
“keep it simple." According to the AOR, CARE submitted a “mapping list” of 53 communes, 28 of
which were outside the corridors, without sufficient explanation as required by the agreement.
After subsequent discussions between the AOR and COP, CARE produced a second mapping
8
list—this time of NGOs. Neither this list nor the first provided information on the strengths of
existing institutions in responding to the needs of the targeted groups or to give information on
the status and vulnerabilities of the targeted populations.
AKSE’s staff agreed that the mapping was not completed according to the agreement, but said
they were still able to identify NGOs to collaborate with through their experience working in the
human rights sector. As a result, the mapping ended up being a list of NGOs.
Baseline Survey. The agreement required CARE to conduct a baseline survey and submit it to
USAID within 90 days of the award. The baseline process was to include the development of
data collection tools, data entry, and data analysis and interpretation. The baseline methodology
and design, including the sampling strategy, was to make sure that indicator results could be
measured to allow comparisons between the baseline and the end of the program.
CARE contracted a team of consultants to conduct the survey from August through October
2012 for $110,000, and in January 2013 the consultants submitted it. According to mission
officials, the survey recycled old information. They told CARE officials the survey therefore was
unacceptable, and because of that, USAID/Haiti questioned the capacity of AKSE’s leadership
and monitoring and evaluation team. The mission decided it would contract for a new baseline
survey because not having one made it difficult to measure the impact of program interventions.
Work Plans. CARE submitted the first year work plan in June 2012. Mission officials said they
did not approve it because it repeated the text in CARE’s proposal but did not describe the
activities as required. The AOR provided feedback to CARE on the successive work plans
submitted, which CARE revised and resubmitted. The mission approved an interim plan to get
the program going, but did not approve a full work plan until November 2013 for FY 2014.
The multiple versions of the plan that the audit team reviewed, along with the mission’s
comments, were vague. According to the mission, the lack of detail indicated that CARE did not
understand the program requirements.
Monitoring and Evaluation Plan. According to the agreement, CARE was to submit the
program’s monitoring and evaluation plan with indicators and intermediate results to USAID
within 90 days of the award. However, after 18 months of implementation (up to the time of
termination), the program did not have an approved plan.
CARE submitted a first draft in June 2012 for approval. The mission responded with comments,
and CARE submitted revisions in August and October 2012. In October 2012 USAID/Haiti
expressed concerns to CARE about the delay in finalizing the monitoring and evaluation plan
despite the fact that the mission staff had provided guidelines and held working sessions with
AKSE staff. CARE submitted another draft in January 2013, but USAID sent it back, asking
CARE to focus on defining indicators and explanations for target changes. CARE did not, and
the revisions continued throughout the remainder of the program.
According to CARE’s monitoring and evaluation team, the plan did not meet program
requirements because it was completed before the work plan was approved, contrary to best
practices for monitoring and evaluation. As a result, the activities in the work plan did not
correspond to indicators established in the monitoring and evaluation plan. CARE staff said they
used an unapproved plan for guidance and started tracking some indicators in July 2013.
9
Assessment Tools. Another misunderstanding occurred over the methodology CARE used to
create a quality assessment tool that measured the capacity of local organizations. The mission
expected CARE to use USAID’s assessment tools. However, the agreement did not specify
what types of methodologies and tools had to be used.
These key program documents and tools formed the foundation for the proper implementation
of the program; without them, activities and program implementation suffered and the program’s
impact cannot be measured. To apply lessons learned and prevent the same problems from
occurring in the follow-on program, we make the following recommendations.
Recommendation 6. We recommend that USAID/Haiti identify and document areas of
intervention before implementing the follow-on program.
Recommendation 7 We recommend that USAID/Haiti complete and document the
baseline survey to determine the capacity of local partners.
Recommendation 8. We recommend that USAID/Haiti’s agreement officer determine
the allowability of the $110,000 in questioned costs spent on the baseline survey
($110,000) and recover from Cooperative for Assistance and Relief Everywhere Inc. any
amounts determined to be unallowable.
Recommendation 9. We recommend that USAID/Haiti define the assessment tools for
studies required by the agreement, clarify them with the implementer before awarding
the follow-on program, and document the complete process.
Implementer Did Not Award Grants
as Intended
According to the cooperative agreement, the program was supposed to implement the majority
of its activities for three of the five results areas through grants. The program budget allocated
$14 million for grants, of which almost $5 million was budgeted for local institutions and
organizations. However, as of September 30, 2013, 18 months into program implementation,
CARE had awarded only $409,842 (8 percent) in grants to local partners, and most of them
were awarded in the second year.
One reason the grants were not awarded faster was a misunderstanding between the mission
and CARE on whether the primary goal of awarding grants to local organizations was to build
capacity or to carry out program activities. The agreement stated, “A major role of the core
program team would be the selection and oversight of sub-grantees and provision of capacity
building support and technical assistance required to achieve results.” CARE’s primary focus
was on providing technical assistance to the local organizations to build their capacity to
prepare them for receiving grants, but USAID expected that CARE would award grants to the
partner organizations to implement activities, and the capacity building would be achieved by
strengthening the partner through providing resources and implementing activities under the
program.
Furthermore, CARE’s capacity for awarding and managing grants was weak. CARE developed
a grants management manual and submitted it to the mission for approval in November 2012. A
USAID legal advisor met with CARE’s grants management staff to assess their processes for
awarding grants and found a lack of basic understanding of general provisions in awarding
10
grants. The AOR provided provisional approval of the grants manual in December 2012, but
revisions continued into the following year. The regional legal advisor approved the grants
manual in late April 2013.
According to mission staff, some grantees said CARE did not process funding for their activities
in a timely manner. In one case, CARE asked for retroactive payment for work undertaken
before awarding and approving a grant.
Grants to local partner organizations were a vital part of AKSE’s planned approach. By
neglecting this important aspect of the program, program activities suffered and the needs of
local partners were not met. To prevent this problem from reoccurring in the new program, we
make the following recommendations.
Recommendation 10. We recommend that USAID/Haiti clarify and document the goals
of the grants component of the program and its relationship to institutional capacity
building before implementing the follow-on program.
Recommendation 11. We recommend that USAID/Haiti assess the new implementer’s
capacity for awarding and managing grants before awarding the agreement for the
follow-on program and document the results of the assessment.
11
EVALUATION OF MANAGEMENT
COMMENTS
USAID/Haiti agreed with all 11 recommendations. Based on comments from the mission and
supporting documentation, management decisions have been reached on ten, with final action
taken on all, except Recommendation 7. A management decision has not been reached on
Recommendation 8. Our detailed evaluation of management comments follows.
Recommendation 1. The mission developed a smaller program implemented through a field
support mechanism called the Health Policy Project (HPP) managed in Washington, D.C., with
the Global Health Bureau. HPP is more focused and has three results instead of five. We
acknowledge the mission’s management decision and final action on this recommendation.
Recommendation 2. The mission has redistributed Mission Order 496 on the Delegation of
Authority and Clearance Procedures to all mission personnel, reminding them of the required
timeframes for clearing documents. We acknowledge the mission’s management decision and
final action on this recommendation.
Recommendation 3. USAID/Haiti prioritized training for mission staff and updated its mission
order on program design on July 14, 2014. We acknowledge the mission’s management
decision and final action on this recommendation.
Recommendation 4. USAID/Haiti’s Office of Acquisition and Assistance was understaffed,
which caused delays in procurement. In September 2014 the mission contracted a senior
acquisition and assistance specialist to help prevent future delays and bottlenecks. We
acknowledge the mission’s management decision and final action on this recommendation.
Recommendation 5. The mission reviewed the program’s description and incorporated
deliverables for the intermediate program. We acknowledge the mission’s management decision
and final action on this recommendation.
Recommendation 6. USAID/Haiti has narrowed the range of coverage for its intermediate
program. We acknowledge the mission’s management decision and final action on this
recommendation.
Recommendation 7. The mission expects to complete the new baseline survey by
December 31, 2014. We acknowledge the mission’s management decision on this
recommendation.
Recommendation 8. The mission did not reach a management decision for this
recommendation. For all recommendations with questioned costs, a management decision can
be reached only when a mission determines the amounts unallowable.
Recommendation 9. The mission clarified that USAID capacity-building tools should be used
to assess and improve the capacity of local organizations receiving assistance in the new
HPP/AKSE intermediate award. We acknowledge the mission’s management decision and final
action on this recommendation.
12
Recommendation 10. Under the HPP/ASKE intermediate program, the mission has redefined
the goals of the subgrant component and expectations for capacity building for subgrantees. We
acknowledge the mission’s management decision and final action on this recommendation.
Recommendation 11. The mission researched and assessed the new implementer’s grant
management expertise and experience with other countries before electing HPP for the
intermediate program. We acknowledge the mission’s management decision and final action on
this recommendation.
13
Appendix I
SCOPE AND METHODOLOGY
Scope
RIG/San Salvador conducted this performance audit in accordance with generally accepted
government auditing standards. Those standards require that we plan and perform the audit to
obtain sufficient, appropriate evidence to provide a reasonable basis for our findings and
conclusions in accordance with our audit objective. We believe that the evidence obtained
provides that reasonable basis.
The objective of the audit was to determine whether USAID/Haiti’s AKSE program was
achieving its main goals of improving the safety and security of children, women, and youth in
Haiti by decreasing the incidence of human rights abuse and expanding access to treatment
and care.
USAID/Haiti awarded CARE a $22.5 million, 5-year cooperative agreement to implement the
program. As of December 16, 2013, USAID/Haiti had obligated $7,746,000 and disbursed
$3,379,306 for program activities. The disbursed amount represents the amount tested during
this performance audit.
The audit covered the period from the program’s inception on March 5, 2012, through
September 30, 2013. We conducted audit fieldwork from November 13, 2013, to April 9, 2014,
at USAID/Haiti and CARE’s office in Pétion-Ville. We also met with grantees in Pétion-Ville and
Port-au-Prince.
In planning and performing the audit, we assessed the significant internal controls the mission
used to manage the program: work plans, quarterly progress reports, the performance
monitoring and evaluation plan, approval of program coverage and subawards, and meetings
with grantees. We also reviewed the mission’s annual FY 2013 assessment of internal controls
required by the Federal Managers’ Financial Integrity Act of 1982.
Methodology
To determine whether USAID/Haiti appropriately managed the program activities, we met with
USAID/Haiti officials, including the AORs, AO, and child protection adviser. We reviewed the
agreement, technical proposals and evaluation, work plans, mapping study, baseline study,
performance monitoring and evaluation plan, progress reports, consortium final reports, and the
grants manual. We interviewed AKSE’s country director, COP, child protection specialist,
trafficking and human rights specialist, gender adviser, communications officer, and the staffs
for monitoring and evaluation, administrative, and support to understand CARE’s management
controls and their understanding of program activities and constraints to implementation. We
also reviewed CARE’s policies and procedures for program and financial management. We
verified reported results by reviewing source documents and interviewing grantees. We
evaluated the program’s performance against the agreement and reported results from the
progress reports. We could not evaluate performance against the work plans or the
performance management plan because the first work plan that USAID approved was the FY
2014 work plan approved during our fieldwork, and the program did not have an approved
performance management plan the entire time it was implemented.
14
Appendix I
We interviewed grantees and reviewed 11 subaward files out of a universe of 24 to confirm the
grants were awarded and approved, and activities were completed. We judgmentally selected
grantees based on grant size and number of grants awarded. Because the testing and the
grantee selections were based on judgmental samples, the results are limited to the items
tested and cannot be projected to the entire audit universe.
15
Appendix II
MANAGEMENT COMMENTS
ACTION MEMORANDUM
TO: Van Nguyen, Regional Inspector General
FROM: John Groarke, Mission Director /s/
DATE: September 26, 2014
SUBJECT: Mission response to the draft audit report of USAID/Haiti’s Protecting the
Rights of Children, Women, and Youth Program (Report No. 1-521-14-
XXX-P)
This memorandum represents USAID/Haiti’s actions taken to address and reach the management
decisions for the recommendations reported in the draft Audit of USAID/Haiti’s Protecting the
Rights of Children, Women, and Youth Program (RIG Draft Report No. 1-521-14-XXX-P). The
Mission agrees with all eleven recommendations. The responses to these recommendations are
below.
Recommendation 1: We recommend that USAID/Haiti determine whether the scope should be
simplified prior to designing the follow-on program and document its decision.
Mission response:
The scope of work that became the CARE/AKSE program was designed in the immediate post-
earthquake context of 2010 when the Mission was very short-staffed and the urgency of response
often resulted in abbreviated clearance processes for program design. The magnitude of the
human rights needs in the immediate post-earthquake period also contributed to a broad and
overly ambitious program design that proved difficult to implement.
Following the termination of the award with CARE in March 2014 and taking the draft RIG
audit recommendations into account, the Mission negotiated a scaled down program through a
field support mechanism called the Health Policy Project (HPP), CA Agreement Number: OAA-
A-10-00067 managed in USAID/DC through the Global Health Bureau. The new program has
reduced the results framework from five results to three results and has clearly prioritized the
identification and reinforcement of referral networks to assist victims of human rights in the new
scope of work. The previous AKSE program had a significant NGO capacity-building element
that has been minimized under the current HPP award. The current HPP program is also more
16
Appendix II
streamlined and focused. We have, for example, eliminated work on disabilities from this award
because the USAID/Haiti health team already has a robust program helping persons with
disabilities.
Plan of Action and Timeline:
Mission agrees with Recommendation 1 and has already incorporated this recommendation into
the design of the HPP award.
Recommendation 2: We recommend that USAID/Haiti implement a plan to coordinate and
streamline mission approvals of program documents for the new program, defining roles and
responsibilities within the mission, and estimating timelines for approvals.
Mission response:
Since the immediate post-earthquake period when this program was designed and procured, the
Mission has adopted many new tools to help coordinate and streamline approvals of program
documents. The roll out of the GLAAS procurement management tool; an updated Mission
Order on the Delegation of Authority and Clearance Procedures (496), issued June 19, 2012; a
Program Office internal website with sample forms and detailed guidance, as well as a more
robustly staffed Mission have all contributed to more accountability and better clearance
timelines for Mission program documents.
Plan of Action and Timeline:
The Mission agrees with Recommendation 2 and as shown in the preceding paragraph, has taken
clear steps to improve clearance procedures. We have attached a copy of Mission Order 496 as
supporting documentation. The Front Office will send an email reminding all offices to clear or
return with comments all documents within 48 hours, or 24 hours or less for urgent documents in
accordance with the Executive Message issued on January 31, 2011 by October 31, 2014.
Recommendation 3: We recommend that USAID/Haiti develop and document a plan for a
rigorous design process in accordance with Automated Directives System 201 for the follow-on
program, and determine and document its expected level of involvement in program
implementation before deciding on the appropriate type of award mechanism.
Mission response:
The Mission has undertaken an ambitious training program for the many new staff that have
been hired since 2010. Trainings include Programming Foreign Assistance, Program Design and
Management, and Acquisition and Assistance classes, which have been brought to the Mission to
allow the maximum number of people to be trained in a short period of time. The Mission is
adhering to ADS 201’s design process for missions without an approved Country Development
Cooperation Strategy (CDCS). The Mission is also in compliance with the Agency requirement
for a customized mission order on project design, but as the Mission does not have a CDCS, our
activity design process is currently guided by Mission Order 201 (Dec 30, 2009) and updated
17
Appendix II
activity design guidance that was issued by email on July 9, 2014 to the Mission, until the
Mission has an approved CDCS. We have determined that a field support mechanism is
appropriate for the bridge program.
Plan of Action and Timeline:
The Mission agrees with Recommendation 3 and has already taken steps to remedy deficiencies
in the Mission’s design process through rigorous and continuous employee training as well as
application of Mission Order 201 on Program Design with relevant updates issued on July 9,
2014. This updated activity design guidance will be posted on the PCPS intranet site.
Recommendation 4: We recommend that the Mission review and document its award
processing time to identify potential bottlenecks.
Mission response:
The December 2013 Haiti Mission Management Assessment acknowledged that post-earthquake,
the USAID/Haiti Office of Acquisition and Assistance was understaffed and that the result was
delays in moving procurement actions forward and bottlenecks. The Assessment noted that more
recently there had been, “staffing up of both USDH staff and FSN staff,” and that, “the support
and guidance provided to the technical staff is much improved.” The Assessment recommended
the hiring of a PSC Senior Acquisition and Assistance Specialist, who has since been contracted
and is expected to arrive in Haiti in late September 2014.
Plan of Action and Timeline:
The Mission Management Assessment was completed December 31, 2013. A solicitation for a
USTCN Senior Acquisition and Assistance Specialist was posted on FBO.gov in May 2013. A
contract was signed in September 2014.
Recommendation 5: We recommend that USAID/Haiti review the new program’s description
for clarity, revise it as necessary prior to implementation, and document all revisions.
Mission response:
As stated under Recommendation 1, the Mission reviewed and revised the AKSE scope of work
before submitting it to the HPP field support mechanism. An inter-office team, composed of the
Office of Acquisition and Assistance, the Program Office, and the Democracy and Governance
Office edited the scope of work for clarity and feasibility. The new AKSE bridge program is
now simplified and straightforward and will only intervene in areas within the purview of the
DG technical office’s expertise. The bridge program has been re-designed in clear terms with
clearly stated deliverables and results to make it easy to track and evaluate performance.
Plan of Action and Timeline:
18
Appendix II
The Mission agrees with Recommendation 5 and has taken remedial action under the current
award.
Recommendation 6: We recommend that USAID/Haiti identify and document areas of
intervention before implementing the follow-on program
Mission response:
The previous AKSE program was designed at a time when human rights vulnerabilities were at
an all-time high in the post-earthquake period and donor coordination for recovery and
rebuilding was still weak. The program description, therefore, was too broad and ambitious in
terms of its area of intervention. The new HPP/AKSE program has narrowed the range of
geographic coverage it will cover. Future awards will also clearly state in the RFA/RFP and be
confirmed and clearly documented in the post-award conference and discussions prior to the
beginning of the implementation.
Plan of Action and Timeline:
The Mission agrees with Recommendation 6 and has narrowed the area of geographic coverage
in the current bridge program to afford more clarity in activities and expected results.
Recommendation 7: We recommend that USAID/Haiti complete and document the baseline
survey to determine the capacity of local partners.
Mission response:
The mission-planned baseline survey was recently awarded and the information we will be
looking to collect includes the approximate capacity of our local partners in addition to other
information pertaining to the relative prevalence of the problems our program will seek to
address. By the time the new program comes online next year, the Mission will have reliable
field information on these issues in order to allow for a more focused and targeted
implementation.
Plan of Action and Timeline:
The baseline survey was awarded on 7/14/2014 and surveyors are currently in the field. The
USAID/Haiti mission targets finalization of this action by December 31, 2014.
Recommendation 8: We recommend that USAID/Haiti’s agreement officer determine the
allowability of the $110,000 in questioned costs spent on the baseline survey ($110,000) and
recover from Cooperative for Assistance and Relief Everywhere any amounts determined to be
unallowable.
Mission response:
19
Appendix II
The Mission has contracted for an Agency Contracted Financial Audit to determine the
allowability of costs incurred under this program, including the baseline survey costs. The audit
firm will review the expenditures of the program and the Agreement Officer will make a
determination about any costs that are not allowable, allocable and reasonable and not agreed
upon in budget negotiations. Appropriate action will be initiated to recover any costs deemed
unallowable.
Plan of Action and Timeline:
The CPA firm will issue the financial audit report in November 2014. The Agreement Officer
will make final determination of questioned costs – if any- with the help of OFM and DG within
6 months of receipt. A request for reimbursement will subsequently be made, if necessary.
Recommendation 9: We recommend that USAID/Haiti define the assessment tools for studies
required by the agreement, clarify them with the implementer before awarding the follow-on
program and document the complete process.
Mission response:
Under the HPP/AKSE bridge award, and taking note of the draft RIG recommendations, the
Mission has clarified that USAID capacity-building tools should be used to assess and improve
the capacity of local organizations receiving assistance under the HPP/AKSE project. Future
human rights programs will specify the specific toolkits that USAID expects to be used in its
assistance programs in the RFA/RFP and award documents.
Plan of Action and Timeline:
The Mission agrees with Recommendation 10 and has taken a clear position on capacity-building
tools in the HPP/AKSE bridge program. Future RFA/RFPs will be specific in this regard.
Recommendation 10: We recommend that USAID/Haiti clarify and document the goals of the
grants component of the program and its relationship to institutional capacity building before
implementing the follow-on program.
Mission response:
Under the HPP/ASKE bridge program, the Mission has clearly redefined the goals of the sub-
grant component and expectations for capacity building for sub-grantees.
Plan of Action and Timeline:
The Mission agrees with Recommendation 10 and has already taken remedial action in the
HPP/AKSE bridge program.
20
Appendix II
Recommendation 11: We recommend that USAID/Haiti assess the new implementer’s capacity
for awarding and managing grants before awarding the agreement for the follow-on program
and document the results of the assessment.
Mission response:
As stated in Recommendation 5, in the last year, the Mission has undertaken an ambitious
training program for the many new staff that have been hired since 2010. Trainings include
Programming Foreign Assistance, training in Program Design and Management and Acquisition
and Assistance classes which have been brought to the Mission to allow the maximum number of
people to be trained in a short period of time. OAA has also greatly increased its involvement in
reviewing statements of work, program descriptions, and technical evaluation criteria so the
potential awardees are evaluated on relevant criteria to ensure the best chances of a successful
implementation.
For the current HPP/AKSE bridge program, we researched the implementer and spoke with the
IQC holder about the implementer’s grant management capacity and other countries' experience.
Given a positive review, we elected to go with the field support mechanism.
Plan of Action and Timeline:
The Mission agrees with Recommendation 11 and chose a field support mechanism with an
experienced implementing partner with field-tested grantmaking capacity for the bridge program.
21
U.S. Agency for International Development
Office of Inspector General
1300 Pennsylvania Avenue, NW
Washington, DC 20523
Tel: 202-712-1150
Fax: 202-216-3047
http://oig.usaid.gov