Done / Pòtfolyo patnè yo / Gwoup Bank Mondyal / IDA
Pwojè dlo ak asenisman dirab nan zòn riral ak ti vil an Ayiti
Tit pibliye: Haiti Sustainable Rural and Small Towns Water and Sanitation Project
An milyon dola ameriken sof si yo di lòt bagay. Ane fiskal ayisyen, soti oktòb rive septanm. FY2026-27 te kòmanse 1 oktòb 2026.
Objektif
The proposed objectives of the Project are to: (i) increase access to improved water supply and sanitation in targeted rural areas and small towns in zones affected by cholera; (ii) strengthen the Recipient’s water and sanitation service delivery mechanism at thedeconcentrated level; and (iii) improve the Recipient’s capacity to respond promptly and effectively to an Eligible Emergency.
Jan Pwojè Bank Mondyal pibliye l, nan lang orijinal li.
Deskripsyon
The Sustainable Rural and Small Towns Water and Sanitation Project for Haiti will: i) increase access to improved water supply and sanitation in targeted rural areas and small towns in zones affected by cholera; ii) strengthen water and sanitation service delivery mechanism at the deconcentrated level; and iii) improve capacity to respond promptly and effectively to an Eligible Emergency. Implementation of this project will involve the following three components: component 1, institutional strengthening, capacity building and project management; component 2, water supply and sanitation; and component 3, contingent emergency response. The project aims to take a first step toward the effective use of government and donor funding, to build capacity, strengthen institutions and set a foundation for achieving longer term
plis
financial sustainability of the WSS sector’s overarching structure. The project will promote a shift from a project to a programmatic approach, pilot the deconcentrated strengthening of Regional Water and Sanitation Offices and contribute to the provision of operationally sustainable WSS service delivery to rural and small town populations, allowing for recovery of operational costs, and subsequent scale up beyond the targeted communes. This will include the promotion of a corporate culture favorable to the commercial management of service delivery. In order to eliminate cholera (and all other water and excreta-related diseases) from the Island of Hispaniola, sustainable financing is needed for the sector in Haiti, as well as delivery models that are financially viable and can be rolled out universally. The project will support the Government of Haiti’s first step toward this outcome over the coming decade and thus help the Government of Haiti attract additional Financial and Technical Partners to support its implementation.
- Patnè
- World Bank Group, IDA
- Sektè
- Dlo ak asenisman
- Etap
- Fèmen depi 31 mas 2023
- Apwobasyon
- 26 me 2015
- Fèmen
- 31 mas 2023
- Enstriman
- Finansman BIRD/IDA, IDA
- Diferans nan sa ki poko dekese
- −0.9: eta IDA a evalye kredi ki poko dekese an dwa tiraj espesyal yo nan to chanj jodi a
- Anprentè
- Republic of Haiti
- Ajans egzekisyon
- DINEPA,Ministry of Economy and Finance, MEF
- Antre an vigè
- 16 desanm 2015
- Depatman
- Sid, Nòdwès, Grandans, Nip
- Dènye tranzaksyon
- 31 mas 2025
- Idantifyan operasyon an
- P148970
Aplike pa
- UNICEF, 1.9 milyon dola ameriken, kontra Bank Mondyal bay
Sik lavi4 etap, 12 dat
Istwa etap yo
| Etap | Depi |
|---|---|
| Apwouve | 26 me 2015 |
| An kou | 26 me 2015 |
| Ap fèmen | 31 mas 2023 |
| Fèmen | 31 mas 2023 |
Evènman ki gen dat
| Evènman | Dat | Sous |
|---|---|---|
| Kòmansman prevwa | 17 desanm 2014 | IATI |
| Evalyasyon davans | 2 mas 2015 | Pwojè Bank Mondyal |
| Negosyasyon | 21 avril 2015 | Pwojè Bank Mondyal |
| Kòmansman reyèl | 26 me 2015 | IATI |
| Apwobasyon | 26 me 2015 | Pwojè Bank Mondyal |
| Premye angajman | 26 me 2015 | Tranzaksyon |
| Antre an vigè | 16 desanm 2015 | Pwojè Bank Mondyal |
| Premye dekèsman | 31 desanm 2015 | Tranzaksyon |
| Fen reyèl | 31 mas 2023 | IATI |
| Dat fèmti | 31 mas 2023 | IATI |
| Rapò fen atann | 2 oktòb 2023 | Pwojè Bank Mondyal |
| Dènye dekèsman | 30 novanm 2023 | Tranzaksyon |
Pa dekèse: 0.0 milyon dola ameriken jiska 30 septanm 2026, dat fèmti 31 mas 2023.
Finansman
Tablo 1.Finansman, milyon dola ameriken
| Finansè | MontanMilyon dola ameriken | Wòl | Sous |
|---|---|---|---|
| IDA Grant | 70.0 | Enstitisyon | Pwojè Bank Mondyal |
Tablo 2.Operasyon ki gen rapò, milyon dola ameriken
| Operasyon | Rapò | Patnè | Etap | AngajmanMilyon dola ameriken |
|---|---|---|---|---|
| Sustainable rural and small town water supply and sanitation | Finansman adisyonèl oswa operasyon pitit | Gwoup Bank Mondyal | Fèmen | 20.0 |
Tablo 3.Pozisyon nan dat done yo pa sous (stòk), milyon dola ameriken
| Paj sa aMilyon dola ameriken | Sous | IATIMilyon dola ameriken | |
|---|---|---|---|
| Angajman | 64.2 | IDA, eta kredi ak don | 64.3 |
| Dekèse | 65.1 | IDA, eta kredi ak don | 65.1 |
| Pa dekèse | 0.0 | IDA, eta kredi ak don | |
| Pri total | 70.0 | Pwojè Bank Mondyal |
Montan Bank Mondyal. Apwouve: Angajman nèt, montan apwouve mwens anilasyon yo, an US$ nan dat done yo. Dekèse jiska jodi a: Dekèsman deklarasyon IDA a ak API pwojè yo jiska jodi a, an US$. Pa dekèse: Balans ki pa dekèse deklarasyon IDA a pibliye, an US$ nan dat done yo. Kolòn IATI: angajman ak dekèsman patnè a pibliye nan IATI, konvèti an US$. Montan yo dapre sous la
Chanjman nan operasyon an2 pwolongasyon, omwen 4 restriktirasyon, konpozan ijans prevwa
- Dat fèmti orijinal
- 30 septanm 2021
- Pwolongasyon dat fèmti
- 2
- Pwolonje soti 30 septanm 2021 rive 30 septanm 2022 (dokiman 31 out 2021)
- Pwolonje soti 30 septanm 2022 rive 31 mas 2023 (dokiman 31 oktòb 2022)
- Restriktirasyon
- omwen 4
- 22 desanm 2020 (dokiman 22 desanm 2020) dokiman restriktirasyon
- 12 jiyè 2021 (dokiman 12 jiyè 2021) dokiman restriktirasyon
- 30 septanm 2022 (dokiman 30 septanm 2022) dokiman restriktirasyon
- 31 mas 2023 (dokiman 31 mas 2023) dokiman restriktirasyon
- Konpozan ijans
- Konpozan repons ijans kontenjan prevwa (dokiman 21 oktòb 2016) dokiman
Nouvo angajman ak dekèsman pa ane fiskal
Tablo 4.Nouvo angajman ak dekèsman pa ane fiskal (flo), milyon dola ameriken
| FY2014-15Milyon dola ameriken | FY2015-16Milyon dola ameriken | FY2016-17Milyon dola ameriken | FY2017-18Milyon dola ameriken | FY2018-19Milyon dola ameriken | FY2019-20Milyon dola ameriken | FY2020-21Milyon dola ameriken | FY2021-22Milyon dola ameriken | FY2022-23Milyon dola ameriken | FY2023-24Milyon dola ameriken | FY2024-25Milyon dola ameriken | |
|---|---|---|---|---|---|---|---|---|---|---|---|
| Nouvo angajman | 50.0 | Pa rapòte | 20.0 | Pa rapòte | Pa rapòte | Pa rapòte | Pa rapòte | Pa rapòte | −4.1 | Pa rapòte | −1.7 |
| Dekèsman | Pa rapòte | 5.4 | 3.5 | 9.1 | 8.2 | 6.5 | 17.0 | 8.8 | 6.5 | <0.1 | Pa rapòte |
| Dekèsman kimile | Pa rapòte | 5.4 | 9.0 | 18.0 | 26.2 | 32.7 | 49.7 | 58.5 | 65.0 | 65.1 | Pa rapòte |
Fich ak dokiman
Tranzaksyon51 liy, 26 me 2015 rive 31 mas 2025
Tablo 5.Tranzaksyon, milyon dola ameriken
| Dat | Mezi | MontanMilyon dola ameriken | Sous | Metòd |
|---|---|---|---|---|
| 26 me 2015 | Angajman | 50.0 | IDA, eta kredi ak don | credit original principal at board approval |
| 14 jen 2017 | Angajman | 20.0 | IDA, eta kredi ak don | credit original principal at board approval |
| 30 avril 2023 | Angajman | −4.1 | IDA, eta kredi ak don | cancellation: increase in cumulative cancelled amount between snapshots (non-USD credit: includes exchange revaluation) |
| 31 mas 2025 | Angajman | −1.6 | IDA, eta kredi ak don | cancellation: increase in cumulative cancelled amount between snapshots (non-USD credit: includes exchange revaluation) |
| 31 mas 2025 | Angajman | −0.1 | IDA, eta kredi ak don | cancellation: increase in cumulative cancelled amount between snapshots (non-USD credit: includes exchange revaluation) |
| 31 desanm 2015 | Dekèsman | 1.0 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 31 me 2016 | Dekèsman | 4.4 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 30 novanm 2016 | Dekèsman | 0.6 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 31 mas 2017 | Dekèsman | 1.3 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 30 jen 2017 | Dekèsman | 0.2 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 31 jiyè 2017 | Dekèsman | 1.4 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 30 novanm 2017 | Dekèsman | 2.0 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 31 desanm 2017 | Dekèsman | 3.0 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 30 jen 2018 | Dekèsman | 2.2 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 31 out 2018 | Dekèsman | 1.9 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 31 janvye 2019 | Dekèsman | 4.0 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 31 janvye 2019 | Dekèsman | 2.2 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 31 jiyè 2019 | Dekèsman | 2.0 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 31 desanm 2019 | Dekèsman | 3.5 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 30 jen 2020 | Dekèsman | 3.0 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 31 desanm 2020 | Dekèsman | 2.4 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 31 desanm 2020 | Dekèsman | 2.0 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 31 mas 2021 | Dekèsman | 0.5 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 31 mas 2021 | Dekèsman | 1.0 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 30 avril 2021 | Dekèsman | 5.5 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 30 jen 2021 | Dekèsman | 0.6 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 31 jiyè 2021 | Dekèsman | 2.4 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 31 jiyè 2021 | Dekèsman | 0.2 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 30 septanm 2021 | Dekèsman | 1.3 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 30 septanm 2021 | Dekèsman | 1.2 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 31 desanm 2021 | Dekèsman | 3.0 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 31 desanm 2021 | Dekèsman | 2.1 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 31 mas 2022 | Dekèsman | 1.6 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 30 avril 2022 | Dekèsman | 0.1 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 30 jen 2022 | Dekèsman | 1.1 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 30 septanm 2022 | Dekèsman | 0.9 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 30 septanm 2022 | Dekèsman | 0.1 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 30 novanm 2022 | Dekèsman | 0.9 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 30 novanm 2022 | Dekèsman | 0.5 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 31 desanm 2022 | Dekèsman | 1.2 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 28 fevriye 2023 | Dekèsman | 0.5 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 31 mas 2023 | Dekèsman | 0.2 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 30 avril 2023 | Dekèsman | 1.7 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 31 me 2023 | Dekèsman | 1.0 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 30 jen 2023 | Dekèsman | 0.1 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 31 jiyè 2023 | Dekèsman | 0.3 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 31 oktòb 2023 | Dekèsman | 0.4 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 30 novanm 2023 | Dekèsman | 0.1 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 30 novanm 2023 | Dekèsman | −0.0 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 31 me 2024 | Dekèsman | −0.5 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
| 31 me 2024 | Dekèsman | −0.0 | IDA, eta kredi ak don | difference of cumulative snapshots (non-USD credit: includes exchange revaluation) |
Kondisyon4 sou 6 rapòte
- Kalite finansman
- 110 Don estanda
- Kalite koule
- Pa rapòte
- Kalite èd
- C01 Entèvansyon kalite pwojè
- Èd mare oswa pa mare
- 5 Pa mare
- Kalite kolaborasyon
- 2 Apò miltilateral k ap antre
- Imanitè
- Pa rapòte
Kote4 depatman, 5 kote nonmen, 8 kote ki gen kowòdone
| Depatman | Sid, Nòdwès, Grandans, Nip |
| Kote sous la nonmen | DEpartement de Nippes, Département de Nippes, Grandans, Nord-Ouest, Sud |
| Kote ki gen kowòdone | 8 |
Endikatè rezilta36 endikatè
| Endikatè | Valè referans | Sib | Dènye valè | Dat dènye valè |
|---|---|---|---|---|
| A fecal sludge management service chain for rural areas and small towns is defined | N | Y | Y | 31 mas 2023 |
| A national programming mechanism for deconcentrated WSS service delivery is operationalized, as evidenced by tools in place | 0.00 | 5.00 | 5.00 | 31 mas 2023 |
| CAEPAs that include at least 20 percent female representation in project area | 0.00 | 70.00 | 129.00 | 31 mas 2023 |
| Communities where DINEPA and MSPP local structures have jointly been trained or collaborated in water supply, hygiene promotion andsanitation themes and activities | 0.00 | 23.00 | 23.00 | 15 mas 2023 |
| DINEPA acknowledged a gender action plan | N | Y | Y | 31 mas 2023 |
| DINEPA conducts an annual joint Government/ partners sector review | N | Y | Y | 31 mas 2023 |
| Departments covered by WSS baseline information | 0.00 | 10.00 | 10.00 | 31 mas 2023 |
| Grievances registered related to delivery of project benefits addressed (%) | 0.00 | 100.00 | 100.00 | 15 mas 2023 |
| Households with latrine built during project implementation and of which use is verified | 0.00 | 1900.00 | 5449.00 | 31 mas 2023 |
| Improved community water points constructed or rehabilitated under the project | 0.00 | 135.00 | 133.00 | 31 mas 2023 |
| Latrine blocks for public institutions or spaces constructed or rehabilitated with management and maintenance arrangements in placein zones affected by Hurricane Matthew | 0.00 | 0.00 | 24.00 | 15 mas 2023 |
| Latrine blocks for public institutions or spaces constructed or rehabilitated with management and maintenance arrangements in placeunder the project | 0.00 | 70.00 | 51.00 | 15 mas 2023 |
| New piped household water connections that are resulting from the project intervention | 0.00 | 7750.00 | 6576.00 | 31 mas 2023 |
| Number of OREPAs among the 4 existing ones that have installed an accounting system which facilitates the consolidation of financial information at the central level. | 0.00 | 2.00 | 1.00 | 15 mas 2023 |
| Number of OREPAs among the 4 existing ones, using the baseline developed under the project to prioritize. | 0.00 | 4.00 | 4.00 | 31 mas 2023 |
| Number of handwashing facilities built in the context of COVID-19 awareness campaign | 0.00 | 995.00 | 1095.00 | 31 mas 2023 |
| Number of hospitals and health centers whose water supply system was repaired under the COVID-19 emergency | 0.00 | 15.00 | 7.00 | 31 mas 2023 |
| People benefitting from consolidation work (small repairs and expansions) in zones affected by Hurricane Matthew | 0.00 | 270000.00 | 270019.00 | 15 mas 2023 |
| People trained to improve hygiene behavior/sanitation practices under the project | 0.00 | 95000.00 | 981255.00 | 15 mas 2023 |
| Students and teachers benefitting from improved sanitation facilities in public schools under the project | 0.00 | 30000.00 | 19351.00 | 31 mas 2023 |
| DINEPA's system in place to respond to major emergencies | N | Y | Y | 31 mas 2023 |
| Direct project beneficiaries | 0.00 | 618000.00 | 601518.00 | 31 mas 2023 |
| Number of people in rural areas and small towns provided with access to Improved Water Sources under the project | 0.00 | 588000.00 | 570558.00 | 31 mas 2023 |
| People provided with access to "improved sanitation facilities under the proj. | 0.00 | 30000.00 | 30960.00 | 31 mas 2023 |
| Piped water systems managed sustainably by a Professional Operator (PO) under the project | 0.00 | 24.00 | 17.00 | 15 mas 2023 |
| Priority cholera communes targeted under the project | 0.00 | 7.00 | 7.00 | 31 mas 2023 |
| Required functions deconcentrated to targeted OREPA | 0.00 | 6.00 | 6.00 | 15 mas 2023 |
| Latrine blocks for public institutions or spaces constructed or rehabilitated with management and maintenance arrangements in place in zones affected by Hurricane Matthew | 0.00 | Pa rapòte | 24.00 | 1 janvye 1900 |
| Latrine blocks for public institutions or spaces constructed or rehabilitated with management and maintenance arrangements in place under the project | 0.00 | 70.00 | 51.00 | 31 mas 2023 |
| Female beneficiaries | 0.00 | 0.00 | 50.00 | 17 me 2018 |
| Number of people in rural areas provided with access to Improved Water Sources in zones affected by Hurricane Matthew | 0.00 | 320000.00 | 342339.00 | 31 mas 2023 |
| Number of people provided with access to improved water sources under the project except in the areas affected by Hurricane Matthew | 0.00 | 197000.00 | 152319.00 | 31 mas 2023 |
| People in rural areas provided with access to "improved sanitation facilities" - female | 0.00 | 15000.00 | 15000.00 | 31 mas 2023 |
| People provided with access to "improved sanitation facilities” under the proj. | 0.00 | 30000.00 | 30960.00 | 15 mas 2023 |
| Project beneficiaries in localities on the border with the DR including bi-national markets | 0.00 | 34000.00 | 39665.00 | 31 mas 2023 |
| Project beneficiaries of small repairs of water systems in the context of COVID-19 emergency | 0.00 | 71000.00 | 75900.00 | 15 mas 2023 |
Nòt14 nòt
| Nòt | Valè | Dat |
|---|---|---|
| IEG bankqualityofsupervision | Moderately Satisfactory | 6 fevriye 2024 |
| IEG evaltype | ES | 6 fevriye 2024 |
| IEG icrquality | Substantial | 6 fevriye 2024 |
| IEG mequality | Substantial | 6 fevriye 2024 |
| IEG outcome | Moderately Satisfactory | 6 fevriye 2024 |
| IEG overallbankperf | Moderately Satisfactory | 6 fevriye 2024 |
| ICR outratingind | Moderately Satisfactory | 2 oktòb 2023 |
| ICR overallrating | Moderately Satisfactory | 2 oktòb 2023 |
| ISR Financial Management | Moderately Unsatisfactory | 30 mas 2023 |
| ISR Monitoring and Evaluation | Moderately Satisfactory | 30 mas 2023 |
| ISR Overall Implementation Progress (IP) | Moderately Unsatisfactory | 30 mas 2023 |
| ISR Procurement | Moderately Unsatisfactory | 30 mas 2023 |
| ISR Progress towards achievement of PDO | Moderately Satisfactory | 30 mas 2023 |
| ISR Project Management | Moderately Unsatisfactory | 30 mas 2023 |
Kontra yo bay75 kontra
| Founisè | Dat | Metòd | Montan |
|---|---|---|---|
| Universal Motors | 27 mas 2023 | DIR | 238,000 USD |
| Non an pa afiche | 24 mas 2023 | CDS | 23,000 USD |
| Non an pa afiche | 18 janvye 2023 | CDS | 10,800 USD |
| Gardere Experts-Comptables et Conseillers en Gestion | 13 septanm 2022 | CDS | 106,553.89 USD |
| BEASCO | 19 out 2022 | DIR | 59,900.59 USD |
| Experts Conseils et Associes | 1 jiyè 2022 | LCS | 7,133,900 HTG |
| Mwater Foundation | 7 jen 2022 | CDS | 123,675.52 USD |
| BUREC SA | 20 avril 2022 | DIR | 580,000 USD |
| Non an pa afiche | 4 avril 2022 | RFB | Pa rapòte |
| Non an pa afiche | 4 avril 2022 | RFB | Pa rapòte |
| Non an pa afiche | 4 avril 2022 | RFB | Pa rapòte |
| Non an pa afiche | 4 avril 2022 | RFB | Pa rapòte |
| DELVA Construction | 27 septanm 2021 | RFQ | 6,801,916.4 HTG |
| Multimotors | 21 out 2021 | RFQ | 1,209,000 HTG |
| L'Institut de Formation et de Service SA (IFOS SA) | 18 jen 2021 | CDS | 1,179,763.75 Gourde hatienne |
| Non an pa afiche | 9 jen 2021 | INDV | 116,850 USD |
| CECOM Consultants SA | 2 jen 2021 | QCBS | 19,765,139 HTG |
| Vision des Ingenieurs Applique en Technique de Construction et Hydraulique (Viatech) | 20 me 2021 | RFQ | 17,335,280 HTG |
| PECOS Construction | 17 me 2021 | RFQ | 18,086,143.4 HTG |
| IMCO | 3 me 2021 | RFQ | 4,474,683.75 HTG |
| IMCO | 3 me 2021 | RFQ | 8,677,040.61 HTG |
| Plan Consult | 3 me 2021 | RFB | 84,955,870 HTG |
| Techniplan SRL | 26 mas 2021 | QCBS | 299,175 USD |
| CECOM Consultants SA | 26 mas 2021 | QCBS | Pa rapòte |
| VBV Construction | 15 mas 2021 | RFQ | 20,900,000 HTG |
| BK Construction | 15 mas 2021 | RFQ | 2,040,876 HTG |
| Unite de Recherche en Geoscience (URGEO) | 3 mas 2021 | NPO | 129,862 USD |
| Societe de GENIE Conseil S.A. | 15 janvye 2021 | CDS | 132,644.4 EUR |
| Societe de GENIE Conseil S.A. | 15 janvye 2021 | CDS | 6,060,726 Gourde hatienne |
| Sinamec Occinal Librice & Co | 28 desanm 2020 | RFQ | 13,116,400 HTG |
| Non an pa afiche | 24 desanm 2020 | RFQ | 323,154.28 USD |
| Bureau ETUDE et de Construction | 17 desanm 2020 | RFQ | 113,958,834.07 HTG |
| BECAJ | 17 desanm 2020 | RFQ | 79,681 USD |
| FICOSA | 17 desanm 2020 | RFQ | 767,095.83 USD |
| BECAJ | 17 desanm 2020 | RFQ | 122,415.5 USD |
| Haiti Hydraulique Organisation (H2O) | 15 desanm 2020 | RFB | 1,515,295 USD |
| RAZEL | 15 desanm 2020 | RFB | 740,795,360.25 HTG |
| Non an pa afiche | 14 desanm 2020 | INDV | 12,845 USD |
| Non an pa afiche | 12 desanm 2020 | DIR | 11,985 USD |
| GENIE Conseil S.A. | 27 novanm 2020 | CDS | 115,490 EUR |
| GENIE Conseil S.A. | 27 novanm 2020 | CDS | 27,047,521.4 Gourde hatienne |
| Non an pa afiche | 27 novanm 2020 | RFQ | 3,034,786.09 HTG |
| Ces Group | 23 novanm 2020 | RFQ | 108,923 USD |
| SOHECO | 19 oktòb 2020 | RFB | 172,734,407.42 HTG |
| Gretco S.A. | 19 oktòb 2020 | RFB | Pa rapòte |
| AQUAITY | 29 septanm 2020 | DIR | 193,755.24 USD |
| Plan Consult | 10 septanm 2020 | RFB | 114,779,043.58 HTG |
| SOCOA | 3 septanm 2020 | RFQ | 9,915,864.44 HTG |
| Bureau d'ETUDE et d'Execution des Travaux en GENIE Civil (Beetgec) | 3 septanm 2020 | RFQ | 11,809,285.39 HTG |
| Incatema Consulting & Engineering, S.L. | 3 septanm 2020 | RFB | 149,740,427.78 HTG |
| Corps Professionnel en Ingnierie Construction (CPIC) | 3 septanm 2020 | RFQ | 9,620,493.08 HTG |
| Non an pa afiche | 30 jen 2020 | INDV | 2,049,500 Gourde hatienne |
| Non an pa afiche | 14 avril 2020 | CDS | 22,000 USD |
| United Nations Children's Fund (UNICEF) | 2 avril 2020 | UN | 2,014,178 USD |
| North Water Rezo Dlo | 21 janvye 2020 | CDS | 79,652 USD |
| Foratech Environnement S.A. | 29 novanm 2019 | DIR | 1,644,350 HTG |
| Bucotech Construction | 4 oktòb 2019 | RFQ | 25,831,967.74 HTG |
| Societe Caraibeenne Etudes et de Construction (SOCAP S.A.) | 2 septanm 2019 | RFQ | 8,865,070.3 HTG |
| Bureau d’Étude et de Construction (BECO) | 2 septanm 2019 | RFQ | 8,837,574.1 HTG |
| Bureau des Ingénieurs pour la Reconstruction d’Haïti (BIRHA) | 2 septanm 2019 | RFQ | 6,559,928.86 HTG |
| Societe Caraibeenne Etudes et de Construction (SOCAP S.A.) | 26 jiyè 2019 | RFQ | 23,157,108.8 HTG |
| Societe Caraibeenne Etudes et de Construction (SOCAP S.A.) | 26 jiyè 2019 | RFQ | 267,495.77 USD |
| Gardere Experts-Comptables et Conseillers en Gestion | 9 jiyè 2019 | CDS | 236,306.5 USD |
| Perfecta S.A. | 21 jen 2019 | DIR | 136,884 USD |
| Non an pa afiche | 26 desanm 2018 | QCBS | 3,256,247.7 HTG |
| Non an pa afiche | 6 desanm 2018 | RFQ | 10,330,400 HTG |
| Non an pa afiche | 30 novanm 2018 | RFQ | 4,837,500 HTG |
| ETRECO | 24 septanm 2018 | QCBS | 22,203,200 HTG |
| Non an pa afiche | 24 me 2018 | DIR | 6,638,625 HTG |
| Incatema Consulting & Engineering, S.L. | 9 avril 2018 | RFB | 148,650,661.08 HTG |
| Incatema Consulting & Engineering, S.L. | 9 avril 2018 | RFB | 121,138,276.16 HTG |
| SOHECO | 26 mas 2018 | RFB | 119,854,081.28 HTG |
| A & R Construction | 26 mas 2018 | RFB | 129,606,585.99 HTG |
| SOHECO | 26 mas 2018 | RFB | 95,477,167.14 HTG |
| Comite Protos Haiti (CPH) | 1 mas 2018 | QCBS | 6,431,063 HTG |
Lajan ki pase bay lòt51 mouvman
| Benefisyè | Mouvman | Dat | Milyon dola ameriken |
|---|---|---|---|
| DINEPA; Ministry of Economy and Finance, MEF | Angajman | 31 mas 2025 | −0.1 |
| DINEPA; Ministry of Economy and Finance, MEF | Angajman | 31 mas 2025 | −1.6 |
| DINEPA; Ministry of Economy and Finance, MEF | Dekèsman | 31 me 2024 | −0.5 |
| DINEPA; Ministry of Economy and Finance, MEF | Dekèsman | 31 me 2024 | −0.0 |
| DINEPA; Ministry of Economy and Finance, MEF | Dekèsman | 30 novanm 2023 | −0.0 |
| DINEPA; Ministry of Economy and Finance, MEF | Dekèsman | 30 novanm 2023 | 0.1 |
| DINEPA; Ministry of Economy and Finance, MEF | Dekèsman | 31 oktòb 2023 | 0.4 |
| DINEPA; Ministry of Economy and Finance, MEF | Dekèsman | 31 jiyè 2023 | 0.3 |
| DINEPA; Ministry of Economy and Finance, MEF | Dekèsman | 30 jen 2023 | 0.1 |
| DINEPA; Ministry of Economy and Finance, MEF | Dekèsman | 31 me 2023 | 1.0 |
| DINEPA; Ministry of Economy and Finance, MEF | Dekèsman | 30 avril 2023 | 1.7 |
| DINEPA; Ministry of Economy and Finance, MEF | Angajman | 30 avril 2023 | −4.0 |
| DINEPA; Ministry of Economy and Finance, MEF | Dekèsman | 31 mas 2023 | 0.2 |
| DINEPA; Ministry of Economy and Finance, MEF | Dekèsman | 28 fevriye 2023 | 0.5 |
| DINEPA; Ministry of Economy and Finance, MEF | Dekèsman | 31 desanm 2022 | 1.2 |
| DINEPA; Ministry of Economy and Finance, MEF | Dekèsman | 30 novanm 2022 | 0.5 |
| DINEPA; Ministry of Economy and Finance, MEF | Dekèsman | 30 novanm 2022 | 0.9 |
| DINEPA; Ministry of Economy and Finance, MEF | Dekèsman | 30 septanm 2022 | 0.9 |
| DINEPA; Ministry of Economy and Finance, MEF | Dekèsman | 30 septanm 2022 | 0.1 |
| DINEPA; Ministry of Economy and Finance, MEF | Dekèsman | 30 jen 2022 | 1.1 |
| DINEPA; Ministry of Economy and Finance, MEF | Dekèsman | 30 avril 2022 | 0.1 |
| DINEPA; Ministry of Economy and Finance, MEF | Dekèsman | 31 mas 2022 | 1.6 |
| DINEPA; Ministry of Economy and Finance, MEF | Dekèsman | 31 desanm 2021 | 2.1 |
| DINEPA; Ministry of Economy and Finance, MEF | Dekèsman | 31 desanm 2021 | 3.0 |
| DINEPA; Ministry of Economy and Finance, MEF | Dekèsman | 30 septanm 2021 | 1.2 |
| DINEPA; Ministry of Economy and Finance, MEF | Dekèsman | 30 septanm 2021 | 1.3 |
| DINEPA; Ministry of Economy and Finance, MEF | Dekèsman | 31 jiyè 2021 | 0.2 |
| DINEPA; Ministry of Economy and Finance, MEF | Dekèsman | 31 jiyè 2021 | 2.4 |
| DINEPA; Ministry of Economy and Finance, MEF | Dekèsman | 30 jen 2021 | 0.6 |
| DINEPA; Ministry of Economy and Finance, MEF | Dekèsman | 30 avril 2021 | 5.5 |
| DINEPA; Ministry of Economy and Finance, MEF | Dekèsman | 31 mas 2021 | 1.0 |
| DINEPA; Ministry of Economy and Finance, MEF | Dekèsman | 31 mas 2021 | 0.5 |
| DINEPA; Ministry of Economy and Finance, MEF | Dekèsman | 31 desanm 2020 | 2.4 |
| DINEPA; Ministry of Economy and Finance, MEF | Dekèsman | 31 desanm 2020 | 2.0 |
| DINEPA; Ministry of Economy and Finance, MEF | Dekèsman | 30 jen 2020 | 3.0 |
| DINEPA; Ministry of Economy and Finance, MEF | Dekèsman | 31 desanm 2019 | 3.5 |
| DINEPA; Ministry of Economy and Finance, MEF | Dekèsman | 31 jiyè 2019 | 2.0 |
| DINEPA; Ministry of Economy and Finance, MEF | Dekèsman | 31 janvye 2019 | 4.0 |
| DINEPA; Ministry of Economy and Finance, MEF | Dekèsman | 31 janvye 2019 | 2.2 |
| DINEPA; Ministry of Economy and Finance, MEF | Dekèsman | 31 out 2018 | 1.9 |
| DINEPA; Ministry of Economy and Finance, MEF | Dekèsman | 30 jen 2018 | 2.2 |
| DINEPA; Ministry of Economy and Finance, MEF | Dekèsman | 31 desanm 2017 | 3.0 |
| DINEPA; Ministry of Economy and Finance, MEF | Dekèsman | 30 novanm 2017 | 2.0 |
| DINEPA; Ministry of Economy and Finance, MEF | Dekèsman | 31 jiyè 2017 | 1.4 |
| DINEPA; Ministry of Economy and Finance, MEF | Angajman | 30 jen 2017 | 20.0 |
| DINEPA; Ministry of Economy and Finance, MEF | Dekèsman | 30 jen 2017 | 0.2 |
| DINEPA; Ministry of Economy and Finance, MEF | Dekèsman | 31 mas 2017 | 1.3 |
| DINEPA; Ministry of Economy and Finance, MEF | Dekèsman | 30 novanm 2016 | 0.6 |
| DINEPA; Ministry of Economy and Finance, MEF | Dekèsman | 31 me 2016 | 4.4 |
| DINEPA; Ministry of Economy and Finance, MEF | Dekèsman | 31 desanm 2015 | 1.0 |
| DINEPA; Ministry of Economy and Finance, MEF | Angajman | 31 me 2015 | 50.0 |
Idantifyan6 idantifyan
| Sistèm | Idantifyan | Sous |
|---|---|---|
| Idantifyan IATI | 44000-P148970 | IATI |
| Kredi oswa don IDA | IDAD0680 | IDA, eta kredi ak don |
| Kredi oswa don IDA | IDAD2010 | IDA, eta kredi ak don |
| Prè Bank mondyal | IDA-D0680 | Pwojè Bank Mondyal |
| Prè Bank mondyal | IDA-D2010 | Pwojè Bank Mondyal |
| Pwojè Bank mondyal | P148970 | Fich operasyon an |
Kote sous yo pa dakò2 chan
| Chan | Sous | Valè | Itilize |
|---|---|---|---|
| Angajman | IDA, eta kredi ak don | 64.2 milyon dola ameriken | ✓ |
| Angajman | Pwojè Bank Mondyal | 70.0 milyon dola ameriken | |
| Estati | Pwojè Bank Mondyal | Fèmen | ✓ |
| Estati | IATI | Aktif |
Dokiman patnè a90 dokiman
- Fich sou projects.worldbank.org, projects.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN - P148970 - Haiti Sustainable Rural and Small Towns Water and Sanitation Project - Audited Financial Statement, 1 fevriye 2025, documents.worldbank.org
- Haiti - HT Sustainable Rural WSS Project, 6 fevriye 2024, documents.worldbank.org
- Haiti - Sustainable Rural and Small Towns Water and Sanitation Project, 3 oktòb 2023, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN - P148970 - Haiti Sustainable Rural and Small Towns Water and Sanitation Project - Audited Financial Statement, 7 avril 2023, documents.worldbank.org
- Disclosable Restructuring Paper - Haiti Sustainable Rural and Small Towns Water and Sanitation Project - P148970, 31 mas 2023, documents.worldbank.org
- Disclosable Version of the ISR - Haiti Sustainable Rural and Small Towns Water and Sanitation Project - P148970 - Sequence No : 17, 31 mas 2023, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P148970- Haiti Sustainable Rural and Small Towns Water and Sanitation Project - Procurement Plan, 29 mas 2023, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P148970- Haiti Sustainable Rural and Small Towns Water and Sanitation Project - Procurement Plan, 24 mas 2023, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P148970- Haiti Sustainable Rural and Small Towns Water and Sanitation Project - Procurement Plan, 20 mas 2023, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P148970- Haiti Sustainable Rural and Small Towns Water and Sanitation Project - Procurement Plan, 6 fevriye 2023, documents.worldbank.org
- Disclosable Version of the ISR - Haiti Sustainable Rural and Small Towns Water and Sanitation Project - P148970 - Sequence No : 16, 1 fevriye 2023, documents.worldbank.org
- Disclosable Restructuring Paper - Haiti Sustainable Rural and Small Towns Water and Sanitation Project - P148970, 30 septanm 2022, documents.worldbank.org
- Haiti - - P148970 - Haiti Sustainable Rural and Small Towns Water and Sanitation Project - Audited Financial Statement, 16 out 2022, documents.worldbank.org
- Disclosable Version of the ISR - Haiti Sustainable Rural and Small Towns Water and Sanitation Project - P148970 - Sequence No : 15, 22 jiyè 2022, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P148970- Haiti Sustainable Rural and Small Towns Water and Sanitation Project - Procurement Plan, 14 jiyè 2022, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P148970- Haiti Sustainable Rural and Small Towns Water and Sanitation Project - Procurement Plan, 18 me 2022, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P148970- Haiti Sustainable Rural and Small Towns Water and Sanitation Project - Procurement Plan, 24 mas 2022, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P148970- Haiti Sustainable Rural and Small Towns Water and Sanitation Project - Procurement Plan, 23 mas 2022, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P148970- Haiti Sustainable Rural and Small Towns Water and Sanitation Project - Procurement Plan, 13 mas 2022, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P148970- Haiti Sustainable Rural and Small Towns Water and Sanitation Project - Procurement Plan, 15 fevriye 2022, documents.worldbank.org
- Disclosable Version of the ISR - Haiti Sustainable Rural and Small Towns Water and Sanitation Project - P148970 - Sequence No : 14, 2 fevriye 2022, documents.worldbank.org
- Haïti - Projet d'eau et d'assainissement durables en milieu rural et dans les petites villes : Mission virtuelle d'appui à la mise en œuvre - 29 novembre – 8 décembre 2021, 7 desanm 2021, documents.worldbank.org
- Disclosable Version of the ISR - Haiti Sustainable Rural and Small Towns Water and Sanitation Project - P148970 - Sequence No : 13, 13 out 2021, documents.worldbank.org
- Disclosable Restructuring Paper - Haiti Sustainable Rural and Small Towns Water and Sanitation Project - P148970, 12 jiyè 2021, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P148970- Haiti Sustainable Rural and Small Towns Water and Sanitation Project - Procurement Plan, 30 avril 2021, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN - P148970 - Haiti Sustainable Rural and Small Towns Water and Sanitation Project - Audited Financial Statement, 1 avril 2021, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P148970- Haiti Sustainable Rural and Small Towns Water and Sanitation Project - Procurement Plan, 24 mas 2021, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P148970- Haiti Sustainable Rural and Small Towns Water and Sanitation Project - Procurement Plan, 18 mas 2021, documents.worldbank.org
- Disclosable Version of the ISR - Haiti Sustainable Rural and Small Towns Water and Sanitation Project - P148970 - Sequence No : 12, 17 fevriye 2021, documents.worldbank.org
- Disclosable Restructuring Paper - Haiti Sustainable Rural and Small Towns Water and Sanitation Project - P148970, 22 desanm 2020, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P148970- Haiti Sustainable Rural and Small Towns Water and Sanitation Project - Procurement Plan, 7 desanm 2020, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P148970- Haiti Sustainable Rural and Small Towns Water and Sanitation Project - Procurement Plan, 5 novanm 2020, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P148970- Haiti Sustainable Rural and Small Towns Water and Sanitation Project - Procurement Plan, 23 septanm 2020, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P148970- Haiti Sustainable Rural and Small Towns Water and Sanitation Project - Procurement Plan, 20 septanm 2020, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P148970- Haiti Sustainable Rural and Small Towns Water and Sanitation Project - Procurement Plan, 16 septanm 2020, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P148970- HT Sustainable Rural and Small Towns Water and Sanitation Project - Procurement Plan, 29 jen 2020, documents.worldbank.org
- Disclosable Version of the ISR - HT Sustainable Rural and Small Towns Water and Sanitation Project - P148970 - Sequence No : 11, 29 jen 2020, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P148970- HT Sustainable Rural and Small Towns Water and Sanitation Project - Procurement Plan, 16 jen 2020, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P148970- HT Sustainable Rural and Small Towns Water and Sanitation Project - Procurement Plan, 30 avril 2020, documents.worldbank.org
- Haiti P148970 Sustainable Rural and Small Towns Water - Audit Statements as of Sept. 2019, 19 avril 2020, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P148970- HT Sustainable Rural and Small Towns Water and Sanitation Project - Procurement Plan, 15 avril 2020, documents.worldbank.org
- Haiti - Sustainable Rural and Small Towns Water and Sanitation Project : Resettlement Plan : Plan Succinct de Reinstallation pour les Travaux des Systemes d’Approvisionnement en Eau Potable de Tiburon, Les Anglais, Roche a Bateau, Port a Piment, et Port Salut, 1 avril 2020, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P148970- HT Sustainable Rural and Small Towns Water and Sanitation Project - Procurement Plan, 26 mas 2020, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P148970- HT Sustainable Rural and Small Towns Water and Sanitation Project - Procurement Plan, 14 fevriye 2020, documents.worldbank.org
- Disclosable Version of the ISR - HT Sustainable Rural and Small Towns Water and Sanitation Project - P148970 - Sequence No : 10, 20 desanm 2019, documents.worldbank.org
- Disclosable Version of the ISR - HT Sustainable Rural and Small Towns Water and Sanitation Project - P148970 - Sequence No : 09, 9 jen 2019, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P148970- HT Sustainable Rural and Small Towns Water and Sanitation Project - Procurement Plan, 28 me 2019, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P148970- HT Sustainable Rural and Small Towns Water and Sanitation Project - Procurement Plan, 21 me 2019, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P148970- HT Sustainable Rural and Small Towns Water and Sanitation Project - Procurement Plan, 16 me 2019, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P148970- HT Sustainable Rural and Small Towns Water and Sanitation Project - Procurement Plan, 14 me 2019, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P148970- HT Sustainable Rural and Small Towns Water and Sanitation Project - Procurement Plan, 28 avril 2019, documents.worldbank.org
- Haiti P148970 Sustainable Rural and Small Towns Water - Audit Statements as of Sept. 2018, 22 avril 2019, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P148970- HT Sustainable Rural and Small Towns Water and Sanitation Project - Procurement Plan, 15 avril 2019, documents.worldbank.org
- Disclosable Version of the ISR - HT Sustainable Rural and Small Towns Water and Sanitation Project - P148970 - Sequence No : 08, 26 mas 2019, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P148970- HT Sustainable Rural and Small Towns Water and Sanitation Project - Procurement Plan, 13 mas 2019, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P148970- HT Sustainable Rural and Small Towns Water and Sanitation Project - Procurement Plan, 18 desanm 2018, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P148970- HT Sustainable Rural and Small Towns Water and Sanitation Project - Procurement Plan, 28 novanm 2018, documents.worldbank.org
- Haiti - LATIN AMERICA AND CARIBBEAN- P148970- HT Sustainable Rural and Small Towns Water and Sanitation Project - Procurement Plan, 23 oktòb 2018, documents.worldbank.org
- Disclosable Version of the ISR - HT Sustainable Rural and Small Towns Water and Sanitation Project - P148970 - Sequence No : 07, 25 septanm 2018, documents.worldbank.org
- Haiti/LATIN AMERICA AND CARIBBEAN- P148970- HT Sustainable Rural and Small Towns Water and Sanitation Project - Procurement Plan, 6 jiyè 2018, documents.worldbank.org
- Disclosable Version of the ISR - HT Sustainable Rural and Small Towns Water and Sanitation Project - P148970 - Sequence No : 06, 13 jen 2018, documents.worldbank.org
- Haiti/LATIN AMERICA AND CARIBBEAN- P148970- HT Sustainable Rural and Small Towns Water and Sanitation Project - Procurement Plan, 2 me 2018, documents.worldbank.org
- Disclosable Version of the ISR - HT Sustainable Rural and Small Towns Water and Sanitation Project - P148970 - Sequence No : 05, 22 novanm 2017, documents.worldbank.org
- Official Documents- Disbursement Letter for Additional Financing Grant D201-HT (Closing Package), 29 jen 2017, documents.worldbank.org
- Official Documents- Amendment to the Financing Agreement for Grant D068-HT (Closing Package), 29 jen 2017, documents.worldbank.org
- Official Documents- Supplemental Letter Ref. Financial and Economic Data for Additional Financing Grant D201-HT (Closing Package), 29 jen 2017, documents.worldbank.org
- Official Documents- Financing Agreement for Additional Financing Grant D201-HT (Closing Package), 29 jen 2017, documents.worldbank.org
- Haiti - HT Sustainable Rural and Small Towns Water and Sanitation Project : P148970 - Implementation Status Results Report : Sequence 04, 15 me 2017, documents.worldbank.org
- Haiti - Sustainable Rural and Small Towns Water and Sanitation Project : environmental assessment : Cadre de gestion environnementale et sociale du Programme eau Potable et Assainissement en Milieu Rural Durable (EPARD), 28 desanm 2016, documents.worldbank.org
- Haiti - HT Sustainable Rural and Small Towns Water and Sanitation Project : P148970 - Implementation Status Results Report : Sequence 03, 21 oktòb 2016, documents.worldbank.org
- Haiti - HT Sustainable Rural and Small Towns Water and Sanitation Project : P148970 - Implementation Status Results Report : Sequence 02, 10 mas 2016, documents.worldbank.org
- Haiti - Sustainable Rural and Small Towns Water and Sanitation Project : environmental assessment (Vol. 5 of 5) : Plan de gestion environnementale et sociale, SAEP de Nan 27/Boucan Lamarre et SAEP de Pointe-a-Raquette : Annex 3, 1 mas 2016, documents.worldbank.org
- Haiti - Sustainable Rural and Small Towns Water and Sanitation Project : environmental assessment (Vol. 2 of 5) : Plan de gestion environnementale et sociale, SAEP d’Anse-à-Pitres, Sud-Est, 1 mas 2016, documents.worldbank.org
- Haiti - Sustainable Rural and Small Towns Water and Sanitation Project : environmental assessment (Vol. 3 of 5) : Plan de gestion environnementale et sociale, SAEP de Nan 27/Boucan Lamarre et SAEP de Pointe-a-Raquette : Annex 1, 1 mas 2016, documents.worldbank.org
- Haiti - Sustainable Rural and Small Towns Water and Sanitation Project : environmental assessment (Vol. 4 of 5) : Plan de gestion environnementale et sociale, SAEP de Nan 27/Boucan Lamarre et SAEP de Pointe-a-Raquette : Annex 2, 1 mas 2016, documents.worldbank.org
- Haiti - Sustainable Rural and Small Towns Water and Sanitation Project : environmental assessment (Vol. 1 of 5) : Plan de gestion environnementale et sociale, SAEP de Nan 27/Boucan Lamarre et SAEP de Pointe-a-Raquette, 1 janvye 2016, documents.worldbank.org
- Haiti - HT Sustainable Rural and Small Towns Water and Sanitation Project : P148970 - Implementation Status Results Report : Sequence 01, 14 septanm 2015, documents.worldbank.org
- Official Documents- Letter ref. Disbursement, Grant D068-HT (Closing Package), 21 jiyè 2015, documents.worldbank.org
- Official Documents- Financing Agreement, Grant D068-HT (Closing Package), 21 jiyè 2015, documents.worldbank.org
- Official Documents- Supplemental Letter ref. Financial Data, Grant D068-HT (Closing Package), 21 jiyè 2015, documents.worldbank.org
- Official Documents- Recommendation of Statutory Committee, Grant D068-HT (Closing Package), 11 me 2015, documents.worldbank.org
- Haiti - Sustainable Rural and Small Towns Water and Sanitation Project, 7 me 2015, documents.worldbank.org
- Project Information Document (Appraisal Stage) - HT Sustainable Rural and Small Towns Water and Sanitation Project - P148970, 10 avril 2015, documents.worldbank.org
- Integrated Safeguards Data Sheet (Appraisal Stage) - HT Sustainable Rural and Small Towns Water and Sanitation Project - P148970, 7 avril 2015, documents.worldbank.org
- Haiti - Sustainable Rural and Small Towns Water and Sanitation Project : resettlement plan : Cadre politique de reinstallation, 1 avril 2015, documents.worldbank.org
- Haiti - Sustainable Rural and Small Towns Water and Sanitation Project : resettlement plan : Cadre politique de reinstallation, 1 mas 2015, documents.worldbank.org
- Official Documents- Agreement for Advance Q9370001, 21 oktòb 2014, documents.worldbank.org
- Official Documents- Disbursement Letter for Advance Q9370001, 21 oktòb 2014, documents.worldbank.org
- Project Information Document (Concept Stage) - HT Sustainable Rural and Small Towns Water and Sanitation Project - P148970, 17 jiyè 2014, documents.worldbank.org
Avi apèl dòf (2)
- Procurement Notices, projects.worldbank.org
- Contract Awards, projects.worldbank.org
Sous
- Fich IATI (d-portal): kondisyon itilizasyon piblikatè a fikse
- IATI: kondisyon itilizasyon piblikatè a fikse
- Relve kredi ak don IDA (seri done): World Bank data, CC BY 4.0 (https://datacatalog.worldbank.org/public-licenses).
- Tranzaksyon: kondisyon itilizasyon piblikatè a fikse
- Fich operasyon an: kondisyon itilizasyon piblikatè a fikse
- Avi pasasyon mache Bank mondyal: kondisyon itilizasyon piblikatè a fikse
- Paj pwojè a, Bank Mondyal: kondisyon itilizasyon piblikatè a fikse
- Dokiman Bank Mondyal: kondisyon itilizasyon piblikatè a fikse
Done jiska 18 oktòb 2026
| Sous | Li nan dat |
|---|---|
| IATI | 18 oktòb 2026 |
| IATI | 18 oktòb 2026 |
| IDA, eta kredi ak don | 18 oktòb 2026 |
| Avi pasasyon mache Bank mondyal | 18 oktòb 2026 |
| Pwojè Bank Mondyal | 18 oktòb 2026 |
| Dokiman Bank Mondyal | 18 oktòb 2026 |
Site paj sa a
HaitiDocs. Pwojè dlo ak asenisman dirab nan zòn riral ak ti vil an Ayiti. Pòtfolyo patnè yo, done jiska 18 oktòb 2026. https://www.haitidocs.org/portfolio/projects/WB%3AP148970?lang=ht