Données / Portefeuille des partenaires / Groupe de la Banque mondiale / World Bank
AF GPE pour le projet Éducation pour tous en Haïti - Phase II
Titre publié : AF GPE to Haiti Education for All Project - Phase II
Millions de dollars US sauf indication contraire. Exercice fiscal haïtien, d’octobre à septembre. L’exercice FY2026-27 a commencé le 1er octobre 2026.
Objectif
The objective of the Project is to support: (i) enrollment of students in select non-public primary schools in disadvantagedareas;(ii) student attendance in select public and non-public primary schools in disadvantaged areas; and (iii) strengthened management of the Recipient's primary education sector.
Tel que publié par Projets de la Banque mondiale, dans sa langue d’origine.
- Partenaire
- World Bank Group, World Bank
- Secteur
- Éducation
- Stade
- Clôturée depuis le 30 juin 2018
- Approbation
- 29 juin 2013
- Clôture
- 30 juin 2018
- Décaissé au
- Non déclaré
- Instrument
- Don d’un fonds fiduciaire exécuté par le bénéficiaire
- Agence d’exécution
- Non déclaré
- Entrée en vigueur
- Non déclaré
- Identifiant de l’opération
- P132756
Cycle de vie3 stades, 4 dates
Historique des stades
| Stade | Depuis le |
|---|---|
| Approuvée | 29 juin 2013 |
| En clôture | 30 juin 2018 |
| Clôturée | 30 juin 2018 |
Dates
| Événement | Date | Source |
|---|---|---|
| Approbation | 29 juin 2013 | Projets de la Banque mondiale |
| Évaluation préalable | 24 février 2014 | Projets de la Banque mondiale |
| Date de clôture prévue | 30 juin 2018 | Projets de la Banque mondiale |
| Rapport d’achèvement attendu | 28 décembre 2018 | Projets de la Banque mondiale |
Financement
Tableau 1.Opérations liées, millions de dollars US
| Opération | Lien | Partenaire | Stade | EngagementMillions de dollars US |
|---|---|---|---|---|
| Education for All Project - Phase II | Opération mère | Groupe de la Banque mondiale | Clôturée | 70,0 |
| AF for Haiti Education for All Project Phase II | Même opération mère | Groupe de la Banque mondiale | Clôturée | 14,8 |
Tableau 2.Position à la date des données par source (stocks), millions de dollars US
| Cette pageMillions de dollars US | Source | |
|---|---|---|
| Engagement | Non déclaré | |
| Décaissé | Non déclaré | |
| Non décaisséLe solde que chaque partenaire déclare non encore décaissé, additionné seulement lorsque chaque opération concernée le déclare. | Non déclaré | |
| Coût total | 0,0 | Projets de la Banque mondiale |
Montants de la Banque mondiale. Approuvé: Engagement net, montant approuvé moins les annulations, en $ É.-U. à la date des données. Décaissé à ce jour: Les décaissements du relevé de l’IDA et de l’API des projets à ce jour, en $ É.-U. Non décaissé: Le solde non décaissé que publie le relevé de l’IDA, en $ É.-U. à la date des données. Les montants selon la source
Modifications de l’opérationnon déclaré
- Date de clôture initiale
- Non déclaré
- Prorogations de la date de clôture
- Non déclaré
- Restructurations
- Non déclaré
- Composante d’urgence
- Non déclaré
Fiches et documents
Indicateurs de résultats21 indicateurs
| Indicateur | Valeur de référence | Cible | Dernière valeur | Date de la dernière valeur |
|---|---|---|---|---|
| Children participating in the integrated nutrition/health program | 70000.00 | 0.00 | 79711.00 | 14 novembre 2013 |
| Communities receiving Grants | 0.00 | 80.00 | 63.00 | 14 novembre 2013 |
| Diagnostic sector study completed and student-mentoring program piloted | Diagnostic sector study not designed and student-m | Diagnostic study completed; Student-mentoring prog | Not applicable | 30 septembre 2017 |
| Direct project beneficiaries | 150000.00 | 0.00 | 230511.00 | 14 novembre 2013 |
| Education sector action plans are developed for 2014-15, 2015-16, and 2016-17 | Five-year Operational Plan (OP) 2010-15 and three- | Education Sector Action Plan 2016-17 is available | Non déclaré | Non déclaré |
| Female beneficiaries | 50.00 | 50.00 | 50.00 | 14 novembre 2013 |
| Impact evaluations completed | 0.00 | 2.00 | 0.00 | 14 novembre 2013 |
| Number of additional classrooms built or rehabilitated at the primary level resulting from project interventions. | 0.00 | 160.00 | 0.00 | 14 novembre 2013 |
| Number of additional qualified primary teachers resulting from project interventions. | 0.00 | 3700.00 | 2669.00 | 14 novembre 2013 |
| Percentage of TWP schools publicly posting annual expenditure reports | 0.00 | 95.00 | 19.00 | 14 novembre 2013 |
| Percentage of school support visits conducted at least once per year by the MENFP | 0.00 | 95.00 | 0.00 | 14 novembre 2013 |
| Students benefiting from improved reading instruction approach (M ap Li Net Ale) | 0.00 | 0.00 | 0.00 | 14 novembre 2013 |
| System for learning assessment at the primary level | No | Yes | No | 30 septembre 2017 |
| Teacher’s Guide Developed by MENFP | not developed | Grade 1 and Grade 2 Teacher’s Guides are in use in | not printed | 14 novembre 2013 |
| Textbooks per pupil in tuition waiver schools | 3.00 | 3.00 | 3.00 | 14 novembre 2013 |
| The school accreditation system is restructured | not applicable | MENFP enforces new school licensing standards | Partially completed | 14 novembre 2013 |
| Utility of the learning assessment system | 0.00 | 0.00 | 0.00 | 30 septembre 2017 |
| Capacity: Percentage of schools inspected at least once per year by the MENFP | 0.00 | 75.00 | 75.00 | 11 avril 2014 |
| Enrollment of students in select non-public primary schools in disadvantaged areas: Number of children enrolled through the provision of tuition waivers | 80000.00 | 423000.00 | 150800.00 | 14 novembre 2013 |
| Strengthened management of the Recipient’s primary education sector: Percentage of schools registered in the school accreditation database | 29.00 | 70.00 | 0.00 | 30 juin 2014 |
| Student attendance in select public and non-public primary schools in disadvantaged areas: Attendance rate is maintained in schoolsbenefiting from the school health and nutrition program | 0.00 | 0.00 | 16.00 | 14 novembre 2013 |
Notations6 notations
| Notation | Valeur | Date |
|---|---|---|
| ISR Financial Management | Moderately Satisfactory | 26 mars 2018 |
| ISR Monitoring and Evaluation | Satisfactory | 26 mars 2018 |
| ISR Overall Implementation Progress (IP) | Satisfactory | 26 mars 2018 |
| ISR Procurement | Moderately Satisfactory | 26 mars 2018 |
| ISR Progress towards achievement of PDO | Satisfactory | 26 mars 2018 |
| ISR Project Management | Moderately Satisfactory | 26 mars 2018 |
Identifiants1 identifiant
| Système | Identifiant | Source |
|---|---|---|
| Projet de la Banque mondiale | P132756 | Fiche de l’opération |
Documents du partenaire
- Haiti - GPE Education for All Project Phase II : additional financing, 10 octobre 2014, documents.worldbank.org
- Integrated Safeguards Data Sheet (Appraisal Stage) - AF GPE to Haiti Education for All Project - Phase II - P132756, 12 août 2014, documents.worldbank.org
- Project Information Document (Appraisal Stage) - AF GPE to Haiti Education for All Project - Phase II - P132756, 26 juillet 2014, documents.worldbank.org
Sources
- Fiche de l’opération: conditions d’utilisation fixées par l’éditeur
- Page du projet, Banque mondiale: conditions d’utilisation fixées par l’éditeur
- Documents de la Banque mondiale: conditions d’utilisation fixées par l’éditeur
Données au 18 octobre 2026
| Source | Consulté le |
|---|---|
| Projets de la Banque mondiale | 18 octobre 2026 |
| Documents de la Banque mondiale | 18 octobre 2026 |
Citer cette page
HaitiDocs. AF GPE pour le projet Éducation pour tous en Haïti - Phase II. Portefeuille des partenaires, données au 18 octobre 2026. https://www.haitidocs.org/portfolio/projects/WB%3AP132756?lang=fr