Jesyon risk dezas ak rekonstriksyon

Tit pibliye: Disaster Risk Management and Reconstruction

An milyon dola ameriken sof si yo di lòt bagay. Ane fiskal ayisyen, soti oktòb rive septanm. FY2026-27 te kòmanse 1 oktòb 2026.

Objektif

The Project Development Objective is to support the Recipient in improving disaster response capacity and enhancing the resiliency of critical transport infrastructure.

Jan Pwojè Bank Mondyal pibliye l, nan lang orijinal li.

Patnè
World Bank Group, IDA
Sektè
Transpò
Etap
Fèmen depi 30 jen 2020
Apwobasyon
1 desanm 2011
Fèmen
30 jen 2020
Enstriman
Finansman BIRD/IDA, IDA
Diferans nan sa ki poko dekese
5.0: eta IDA a evalye kredi ki poko dekese an dwa tiraj espesyal yo nan to chanj jodi a
Anprentè
Ministry of Economy and Finance
Ajans egzekisyon
Unite de Coordination de Projet - Ministry of Interior and Local Authorities,Unite de Coordination et Execution - Ministry of Public Works
Antre an vigè
3 avril 2012
Depatman
Sidès, Sid, Lwès, Nòdwès, Nòdès, Nò, Grandans, Sant, Latibonit, Nip
Dènye tranzaksyon
31 jiyè 2022
Idantifyan operasyon an
P126346
Sik lavi5 etap, 13 dat

Istwa etap yo

EtapDepi
Planifye10 me 2011
Apwouve1 desanm 2011
An kou1 desanm 2011
Ap fèmen30 jen 2020
Fèmen30 jen 2020

Evènman ki gen dat

EvènmanDatSous
Revizyon konsèp10 me 2011Pwojè Bank Mondyal
Negosyasyon31 out 2011Pwojè Bank Mondyal
Piblikasyon15 septanm 2011Pwojè Bank Mondyal
Kòmansman prevwa24 novanm 2011IATI
Kòmansman reyèl1 desanm 2011IATI
Apwobasyon1 desanm 2011Pwojè Bank Mondyal
Premye angajman1 desanm 2011Tranzaksyon
Antre an vigè3 avril 2012Pwojè Bank Mondyal
Premye dekèsman31 oktòb 2012Tranzaksyon
Fen reyèl30 jen 2020IATI
Dat fèmti30 jen 2020IATI
Dènye dekèsman31 desanm 2020Tranzaksyon
Rapò fen atann29 janvye 2021Pwojè Bank Mondyal

Pa dekèse: 0.0 milyon dola ameriken jiska 30 septanm 2026, dat fèmti 30 jen 2020.

Finansman

Tablo 1.Finansman, milyon dola ameriken

FinansèMontanMilyon dola amerikenWòlSous
IDA Grant60.0EnstitisyonPwojè Bank Mondyal

Tablo 2.Operasyon ki gen rapò, milyon dola ameriken

OperasyonRapòPatnèEtapAngajmanMilyon dola ameriken
Disaster Risk Management and Reconstruction Additional FinancingFinansman adisyonèl oswa operasyon pititGwoup Bank MondyalFèmen20.0

Tablo 3.Pozisyon nan dat done yo pa sous (stòk), milyon dola ameriken

Paj sa aMilyon dola amerikenSousIATIMilyon dola ameriken
Angajman71.8IDA, eta kredi ak donPa rapòte
Dekèse66.8IDA, eta kredi ak don69.1
Pa dekèse0.0IDA, eta kredi ak don
Pri total60.0Pwojè Bank Mondyal

Montan Bank Mondyal. Apwouve: Angajman nèt, montan apwouve mwens anilasyon yo, an US$ nan dat done yo. Dekèse jiska jodi a: Dekèsman deklarasyon IDA a ak API pwojè yo jiska jodi a, an US$. Pa dekèse: Balans ki pa dekèse deklarasyon IDA a pibliye, an US$ nan dat done yo. Kolòn IATI: angajman ak dekèsman patnè a pibliye nan IATI, konvèti an US$. Montan yo dapre sous la

Chanjman nan operasyon an2 pwolongasyon, omwen 2 restriktirasyon, konpozan ijans prevwa
Dat fèmti orijinal
31 desanm 2016
Pwolongasyon dat fèmti
2
  • Pwolonje soti 31 desanm 2016 rive 30 jen 2017 (dokiman 31 out 2016)
  • Pwolonje soti 30 jen 2017 rive 30 jen 2020 (dokiman 31 jiyè 2017)
Restriktirasyon
omwen 2
Konpozan ijans
Konpozan repons ijans kontenjan prevwa (dokiman 5 jen 2020) dokiman restriktirasyon

Nouvo angajman ak dekèsman pa ane fiskal

Dekèsman, milyon dola ameriken
FY2011-12, pa rapòtep.r.11-12FY2012-13, 8.4 milyon dola ameriken812-13FY2013-14, 9.0 milyon dola ameriken913-14FY2014-15, 6.2 milyon dola ameriken614-15FY2015-16, 4.1 milyon dola ameriken415-16FY2016-17, 7.4 milyon dola ameriken716-17FY2017-18, 7.3 milyon dola ameriken717-18FY2018-19, 7.9 milyon dola ameriken818-19FY2019-20, 16.6 milyon dola ameriken1719-20FY2020-21, −0.1 milyon dola ameriken−0.120-21FY2021-22, −0.0 milyon dola ameriken−0.021-22FY2011-12, pa rapòtep.r.11-12FY2012-13, 8.4 milyon dola ameriken812-13FY2013-14, 9.0 milyon dola ameriken913-14FY2014-15, 6.2 milyon dola ameriken614-15FY2015-16, 4.1 milyon dola ameriken415-16FY2016-17, 7.4 milyon dola ameriken716-17FY2017-18, 7.3 milyon dola ameriken717-18FY2018-19, 7.9 milyon dola ameriken818-19FY2019-20, 16.6 milyon dola ameriken1719-20FY2020-21, −0.1 milyon dola ameriken−0.120-21FY2021-22, −0.0 milyon dola ameriken−0.021-22

Tablo 4.Nouvo angajman ak dekèsman pa ane fiskal (flo), milyon dola ameriken

FY2011-12Milyon dola amerikenFY2012-13Milyon dola amerikenFY2013-14Milyon dola amerikenFY2014-15Milyon dola amerikenFY2015-16Milyon dola amerikenFY2016-17Milyon dola amerikenFY2017-18Milyon dola amerikenFY2018-19Milyon dola amerikenFY2019-20Milyon dola amerikenFY2020-21Milyon dola amerikenFY2021-22Milyon dola ameriken
Nouvo angajman60.0Pa rapòtePa rapòtePa rapòtePa rapòte20.0Pa rapòtePa rapòte−4.6Pa rapòte−3.6
DekèsmanPa rapòte8.49.06.24.17.47.37.916.6−0.1−0.0
Dekèsman kimilePa rapòte8.417.523.727.835.142.550.367.066.866.8

Fich ak dokiman

Tranzaksyon78 liy, 1 desanm 2011 rive 31 jiyè 2022

Tablo 5.Tranzaksyon, milyon dola ameriken

DatMeziMontanMilyon dola amerikenSousMetòd
1 desanm 2011Angajman60.0IDA, eta kredi ak doncredit original principal at board approval
8 jen 2017Angajman20.0IDA, eta kredi ak doncredit original principal at board approval
30 jen 2020Angajman−4.4IDA, eta kredi ak doncancellation: increase in cumulative cancelled amount between snapshots (non-USD credit: includes exchange revaluation)
30 jen 2020Angajman−0.3IDA, eta kredi ak doncancellation: increase in cumulative cancelled amount between snapshots (non-USD credit: includes exchange revaluation)
31 jiyè 2022Angajman−0.6IDA, eta kredi ak doncancellation: increase in cumulative cancelled amount between snapshots (non-USD credit: includes exchange revaluation)
31 jiyè 2022Angajman−2.9IDA, eta kredi ak doncancellation: increase in cumulative cancelled amount between snapshots (non-USD credit: includes exchange revaluation)
31 oktòb 2012Dekèsman1.0IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
30 novanm 2012Dekèsman0.6IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
31 mas 2013Dekèsman2.9IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
31 jiyè 2013Dekèsman0.5IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
31 out 2013Dekèsman0.8IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
30 septanm 2013Dekèsman2.5IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
31 desanm 2013Dekèsman2.2IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
28 fevriye 2014Dekèsman0.7IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
31 mas 2014Dekèsman0.8IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
30 avril 2014Dekèsman1.2IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
30 septanm 2014Dekèsman4.1IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
31 oktòb 2014Dekèsman0.4IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
31 desanm 2014Dekèsman1.3IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
28 fevriye 2015Dekèsman0.1IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
30 avril 2015Dekèsman0.9IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
31 me 2015Dekèsman0.3IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
30 jen 2015Dekèsman0.6IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
31 jiyè 2015Dekèsman1.7IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
31 out 2015Dekèsman0.3IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
30 septanm 2015Dekèsman0.6IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
30 novanm 2015Dekèsman0.3IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
31 desanm 2015Dekèsman0.5IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
31 janvye 2016Dekèsman0.3IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
29 fevriye 2016Dekèsman1.7IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
31 mas 2016Dekèsman1.1IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
30 avril 2016Dekèsman0.2IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
31 desanm 2016Dekèsman2.9IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
28 fevriye 2017Dekèsman1.9IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
31 mas 2017Dekèsman0.9IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
31 jiyè 2017Dekèsman0.6IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
31 out 2017Dekèsman1.0IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
31 desanm 2017Dekèsman2.0IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
28 fevriye 2018Dekèsman0.2IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
30 avril 2018Dekèsman0.6IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
31 me 2018Dekèsman0.2IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
30 jen 2018Dekèsman0.5IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
31 jiyè 2018Dekèsman2.0IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
31 jiyè 2018Dekèsman1.0IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
31 out 2018Dekèsman0.4IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
30 septanm 2018Dekèsman0.4IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
31 oktòb 2018Dekèsman1.4IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
31 oktòb 2018Dekèsman1.3IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
30 novanm 2018Dekèsman0.9IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
31 desanm 2018Dekèsman0.2IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
31 mas 2019Dekèsman1.3IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
31 mas 2019Dekèsman0.4IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
30 avril 2019Dekèsman0.4IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
31 me 2019Dekèsman0.1IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
31 jiyè 2019Dekèsman1.8IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
30 septanm 2019Dekèsman0.1IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
31 janvye 2020Dekèsman1.6IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
29 fevriye 2020Dekèsman1.1IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
31 mas 2020Dekèsman1.2IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
31 mas 2020Dekèsman0.5IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
30 avril 2020Dekèsman1.7IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
31 me 2020Dekèsman0.2IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
31 me 2020Dekèsman2.6IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
30 jen 2020Dekèsman3.4IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
31 jiyè 2020Dekèsman0.6IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
31 out 2020Dekèsman2.6IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
31 out 2020Dekèsman1.0IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
30 septanm 2020Dekèsman0.1IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
31 oktòb 2020Dekèsman<0.1IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
31 desanm 2020Dekèsman−0.2IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
31 desanm 2020Dekèsman0.2IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
31 mas 2021Dekèsman−0.1IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
30 avril 2021Dekèsman−0.0IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
30 avril 2021Dekèsman−0.0IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
31 jiyè 2021Dekèsman−0.0IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
31 out 2021Dekèsman−0.0IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
31 out 2021Dekèsman−0.0IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
30 jen 2022Dekèsman−0.0IDA, eta kredi ak dondifference of cumulative snapshots (non-USD credit: includes exchange revaluation)
Kondisyon5 sou 6 rapòte
Kalite finansman
110 Don estanda
Kalite koule
Pa rapòte
Kalite èd
C01 Entèvansyon kalite pwojè
Èd mare oswa pa mare
5 Pa mare
Kalite kolaborasyon
2 Apò miltilateral k ap antre
Imanitè
Wi
Kote10 depatman, 10 kote nonmen, 20 kote ki gen kowòdone
DepatmanSidès, Sid, Lwès, Nòdwès, Nòdès, Nò, Grandans, Sant, Latibonit, Nip
Kote sous la nonmenDepartement de Nippes, Departement de l'Artibonite, Departement de l'Ouest, Departement de la Grand'Anse, Departement du Centre, Departement du Nord, Departement du Nord-Est, Departement du Nord-Ouest, Departement du Sud, Departement du Sud-Est
Kote ki gen kowòdone20
Endikatè rezilta26 endikatè
EndikatèValè referansSibDènye valèDat dènye valè
A draft road map with a score card for a disaster risk management system is developedNoYesYes25 jen 2020
A first pilot detailed hydrological risk modelling is developed using the Digital Elevation ModelNoYesYes25 jen 2020
A national radio communication system has been initiated and at least four pilot departments have been connected to the national level0.004.004.0026 jen 2020
Actions are taken in a timely manner in response to feedback received during consultation sessions with beneficiaries/project affected people(Feedback, Responses and Action are monitored and reported)NoYesYes30 jen 2020
Dissaggregation by sex in percent0.000.0014.0026 jen 2020
Female Beneficiaries0.000.0040.0030 me 2018
Number of CCPC Staff trained and level 2-certified (Office Management and Emergency Operation Center Management), disaggregated bysex0.002800.003313.0026 jen 2020
Number of beneficiaries from a training in disaster risk management, disaggregated by sex0.00799.001520.0026 jen 2020
Number of bridges and road sections damaged by hurricane Matthew that have been repaired or consolidatedwith satisfactory technical standards0.0015.0027.0030 jen 2020
Number of bridges built or rehabilitated with satisfactory technical standards0.006.006.0030 jen 2020
Number of bridges damaged by hurricane Matthew that have been rebuiltwith satisfactory technical standards0.001.001.0030 jen 2020
Number of departments with investment plan to improve all weather rural accessibility based on the Rural Index Access methodology0.005.005.0030 jen 2020
Number of level 2-certified operational Municipal Civil Protection Committees (CCPCs)0.00140.00119.0025 jen 2020
Number of man/days of LIW generated by project activities0.00350000.00370000.0030 jen 2020
Number of ministry officials benefitting from a training program in risk management, disaggregated by sex0.0070.00127.0026 jen 2020
Number of risk maps are produced, disseminated and available in an open-data online platform0.0035.000.0025 jen 2020
Number of spot interventions to protect the local access executed with satisfactory technical standards0.0040.00112.0030 jen 2020
Percentage of the national territory covered by a high resolution Digital Elevation Model and high resolution aero-photography0.00100.00100.0026 jen 2020
Pilot evacuation shelters have been rehabilitated or reconstructed with multi-hazard resilient measures0.0012.005.0026 jen 2020
Pilot evacuation shelters tool to evaluate and prioritize shelters needs is developed and used in the affected area by MatthewNoYesYes25 jen 2020
Roads rehabilitated, Non-rural0.00100.00120.0030 jen 2020
Line ministries developing an action plan for vulnerability reduction0.002.002.0024 jen 2020
Number of beneficiaries from an improved and resilient investments on the road network0.00150000.00150000.0030 jen 2020
Percentate of Female Beneficiaries from an improved and resilient investments on the primary and secondary road network0.000.0050.0021 jen 2018
Share of population living in a municipality with a CCPC (Comite Communal de Protection Civile - Municipal Civil Protection Staff) of category 2 or higher45.0075.0077.3027 jen 2020
Number of CCPC Staff trained and level 2-certified (Office Management and Emergency Operation Center Management), disaggregated by sex0.002800.003313.0027 jen 2019
Nòt17 nòt
NòtValèDat
IEG bankqualityofsupervisionModerately Satisfactory29 jen 2021
IEG borrowcomplianceNot Rated29 jen 2021
IEG evaltypeES29 jen 2021
IEG icrqualitySubstantial29 jen 2021
IEG mequalityModest29 jen 2021
IEG outcomeModerately Satisfactory29 jen 2021
IEG overallbankperfModerately Satisfactory29 jen 2021
ICR bankqualityentryNot Rated29 janvye 2021
ICR banksupervisionNot Rated29 janvye 2021
ICR outratingindModerately Satisfactory29 janvye 2021
ICR overallratingModerately Satisfactory29 janvye 2021
ISR Financial ManagementModerately Unsatisfactory30 jen 2020
ISR Monitoring and EvaluationModerately Satisfactory30 jen 2020
ISR Overall Implementation Progress (IP)Moderately Satisfactory30 jen 2020
ISR ProcurementModerately Satisfactory30 jen 2020
ISR Progress towards achievement of PDOSatisfactory30 jen 2020
ISR Project ManagementModerately Satisfactory30 jen 2020
Kontra yo bay37 kontra
FounisèDatMetòdMontan
Interloc27 desanm 2019RFQ233,492.6 USD
FB GROUP27 desanm 2019RFQ279,160 USD
MT Construction27 desanm 2019RFQ481,451.75 USD
FB GROUP27 desanm 2019RFQ214,330 USD
ETUDE, Plan, Construction, EPCOS27 desanm 2019RFQ153,247.83 USD
SAGESS27 desanm 2019RFQ184,041.8 USD
BECOS Plus27 desanm 2019RFQ167,944 USD
Interloc27 desanm 2019RFQ473,339 USD
Firme de Construction et de Service Agricole (Ficosa)20 desanm 2019RFQ341,191.32 USD
Interloc20 desanm 2019RFQ287,422.72 USD
LICC Construction2 desanm 2019RFQ212,422.86 USD
Bureau d'ETUDE et de Construction (BECO)2 desanm 2019RFQ270,875 USD
Bureau D Etudes et D Exécution D Haiti, BEEH2 desanm 2019RFQ314,520 USD
ENCAUSA2 desanm 2019RFQ579,725 USD
FB GROUP2 desanm 2019RFQ173,460 USD
Embellissement Plan Construction (EPC)2 desanm 2019RFQ203,845 USD
BECAM2 desanm 2019RFQ282,700 USD
M & L Construction22 novanm 2019RFQ195,187.4 USD
Ceforex Construction22 novanm 2019RFQ198,886.12 USD
Embellissement Plan Construction (EPC)22 novanm 2019RFQ243,581.9 USD
Bureau d'ETUDE et de Construction (BECO)22 novanm 2019RFQ278,737.5 USD
Bureau D Etudes et D Exécution D Haiti, BEEH22 novanm 2019RFQ201,750 USD
Alliance Technique et de Services d'Haiti (Altesha S. A.)22 novanm 2019RFQ92,975.71 USD
BECAM22 novanm 2019RFQ126,461.1 USD
Bureau d’Études et Exécution des Projets de Construction (MC Beepco)22 novanm 2019RFQ210,954.2 USD
Gecotech22 novanm 2019RFQ166,570 USD
Bureau d'ETUDE et de Construction (BECO)22 novanm 2019RFQ202,945 USD
Acc Group22 novanm 2019RFQ190,145 USD
Encotrans22 novanm 2019RFQ164,340.42 USD
Non an pa afiche1 novanm 2019INDV38,500 USD
Non an pa afiche1 novanm 2019INDV38,500 USD
Matiere SAS31 oktòb 2019RFB8,341,569.74 USD
Non an pa afiche1 septanm 2014QBSPa rapòte
Non an pa afiche1 septanm 2014QBSPa rapòte
Non an pa afiche1 septanm 2014QBSPa rapòte
Non an pa afiche1 septanm 2014QBSPa rapòte
Non an pa afiche4 fevriye 2014ICBPa rapòte
Lajan ki pase bay lòt84 mouvman
BenefisyèMouvmanDatMilyon dola ameriken
Unite de Coordination de Projet - Ministry of Interior and Local Authorities; Unite de Coordination et Execution - Ministry of Public WorksAngajman31 jiyè 2022−0.6
Unite de Coordination de Projet - Ministry of Interior and Local Authorities; Unite de Coordination et Execution - Ministry of Public WorksAngajman31 jiyè 2022−2.5
Unite de Coordination de Projet - Ministry of Interior and Local Authorities; Unite de Coordination et Execution - Ministry of Public WorksDekèsman30 jen 2022−0.0
Unite de Coordination de Projet - Ministry of Interior and Local Authorities; Unite de Coordination et Execution - Ministry of Public WorksDekèsman31 out 2021−0.0
Unite de Coordination de Projet - Ministry of Interior and Local Authorities; Unite de Coordination et Execution - Ministry of Public WorksDekèsman31 out 2021−0.0
Unite de Coordination de Projet - Ministry of Interior and Local Authorities; Unite de Coordination et Execution - Ministry of Public WorksDekèsman31 jiyè 2021−0.0
Unite de Coordination de Projet - Ministry of Interior and Local Authorities; Unite de Coordination et Execution - Ministry of Public WorksDekèsman30 avril 2021−0.0
Unite de Coordination de Projet - Ministry of Interior and Local Authorities; Unite de Coordination et Execution - Ministry of Public WorksDekèsman30 avril 2021−0.0
Unite de Coordination de Projet - Ministry of Interior and Local Authorities; Unite de Coordination et Execution - Ministry of Public WorksDekèsman31 mas 2021−0.1
HAITIDepans31 desanm 2020<0.1
Unite de Coordination de Projet - Ministry of Interior and Local Authorities; Unite de Coordination et Execution - Ministry of Public WorksDekèsman31 desanm 2020−0.2
Unite de Coordination de Projet - Ministry of Interior and Local Authorities; Unite de Coordination et Execution - Ministry of Public WorksDekèsman31 desanm 20200.2
Unite de Coordination de Projet - Ministry of Interior and Local Authorities; Unite de Coordination et Execution - Ministry of Public WorksDekèsman31 oktòb 2020<0.1
HAITIDepans31 oktòb 2020−0.0
HAITIDepans30 septanm 2020−0.0
Unite de Coordination de Projet - Ministry of Interior and Local Authorities; Unite de Coordination et Execution - Ministry of Public WorksDekèsman30 septanm 20200.1
HAITIDepans31 out 2020<0.1
Unite de Coordination de Projet - Ministry of Interior and Local Authorities; Unite de Coordination et Execution - Ministry of Public WorksDekèsman31 out 20202.6
Unite de Coordination de Projet - Ministry of Interior and Local Authorities; Unite de Coordination et Execution - Ministry of Public WorksDekèsman31 out 20201.0
Unite de Coordination de Projet - Ministry of Interior and Local Authorities; Unite de Coordination et Execution - Ministry of Public WorksDekèsman31 jiyè 20200.6
HAITIDekèsman30 jen 20200.3
Unite de Coordination de Projet - Ministry of Interior and Local Authorities; Unite de Coordination et Execution - Ministry of Public WorksAngajman30 jen 2020−3.7
Unite de Coordination de Projet - Ministry of Interior and Local Authorities; Unite de Coordination et Execution - Ministry of Public WorksDekèsman30 jen 20203.4
Unite de Coordination de Projet - Ministry of Interior and Local Authorities; Unite de Coordination et Execution - Ministry of Public WorksAngajman30 jen 2020−0.3
HAITIDepans30 jen 20202.0
Unite de Coordination de Projet - Ministry of Interior and Local Authorities; Unite de Coordination et Execution - Ministry of Public WorksDekèsman31 me 20202.6
Unite de Coordination de Projet - Ministry of Interior and Local Authorities; Unite de Coordination et Execution - Ministry of Public WorksDekèsman31 me 20200.2
Unite de Coordination de Projet - Ministry of Interior and Local Authorities; Unite de Coordination et Execution - Ministry of Public WorksDekèsman30 avril 20201.7
Unite de Coordination de Projet - Ministry of Interior and Local Authorities; Unite de Coordination et Execution - Ministry of Public WorksDekèsman31 mas 20200.5
Unite de Coordination de Projet - Ministry of Interior and Local Authorities; Unite de Coordination et Execution - Ministry of Public WorksDekèsman31 mas 20201.2
Unite de Coordination de Projet - Ministry of Interior and Local Authorities; Unite de Coordination et Execution - Ministry of Public WorksDekèsman29 fevriye 20201.1
Unite de Coordination de Projet - Ministry of Interior and Local Authorities; Unite de Coordination et Execution - Ministry of Public WorksDekèsman31 janvye 20201.6
Unite de Coordination de Projet - Ministry of Interior and Local Authorities; Unite de Coordination et Execution - Ministry of Public WorksDekèsman30 septanm 20190.1
Unite de Coordination de Projet - Ministry of Interior and Local Authorities; Unite de Coordination et Execution - Ministry of Public WorksDekèsman31 jiyè 20191.8
Unite de Coordination de Projet - Ministry of Interior and Local Authorities; Unite de Coordination et Execution - Ministry of Public WorksDekèsman31 me 20190.1
Unite de Coordination de Projet - Ministry of Interior and Local Authorities; Unite de Coordination et Execution - Ministry of Public WorksDekèsman30 avril 20190.4
Unite de Coordination de Projet - Ministry of Interior and Local Authorities; Unite de Coordination et Execution - Ministry of Public WorksDekèsman31 mas 20191.3
Unite de Coordination de Projet - Ministry of Interior and Local Authorities; Unite de Coordination et Execution - Ministry of Public WorksDekèsman31 mas 20190.4
Unite de Coordination de Projet - Ministry of Interior and Local Authorities; Unite de Coordination et Execution - Ministry of Public WorksDekèsman31 desanm 20180.2
Unite de Coordination de Projet - Ministry of Interior and Local Authorities; Unite de Coordination et Execution - Ministry of Public WorksDekèsman30 novanm 20180.9
Unite de Coordination de Projet - Ministry of Interior and Local Authorities; Unite de Coordination et Execution - Ministry of Public WorksDekèsman31 oktòb 20181.4
Unite de Coordination de Projet - Ministry of Interior and Local Authorities; Unite de Coordination et Execution - Ministry of Public WorksDekèsman31 oktòb 20181.3
Unite de Coordination de Projet - Ministry of Interior and Local Authorities; Unite de Coordination et Execution - Ministry of Public WorksDekèsman30 septanm 20180.4
Unite de Coordination de Projet - Ministry of Interior and Local Authorities; Unite de Coordination et Execution - Ministry of Public WorksDekèsman31 out 20180.4
Unite de Coordination de Projet - Ministry of Interior and Local Authorities; Unite de Coordination et Execution - Ministry of Public WorksDekèsman31 jiyè 20182.0
Unite de Coordination de Projet - Ministry of Interior and Local Authorities; Unite de Coordination et Execution - Ministry of Public WorksDekèsman31 jiyè 20181.0
Unite de Coordination de Projet - Ministry of Interior and Local Authorities; Unite de Coordination et Execution - Ministry of Public WorksDekèsman30 jen 20180.5
Unite de Coordination de Projet - Ministry of Interior and Local Authorities; Unite de Coordination et Execution - Ministry of Public WorksDekèsman31 me 20180.2
Unite de Coordination de Projet - Ministry of Interior and Local Authorities; Unite de Coordination et Execution - Ministry of Public WorksDekèsman30 avril 20180.6
Unite de Coordination de Projet - Ministry of Interior and Local Authorities; Unite de Coordination et Execution - Ministry of Public WorksDekèsman28 fevriye 20180.2
Unite de Coordination de Projet - Ministry of Interior and Local Authorities; Unite de Coordination et Execution - Ministry of Public WorksDekèsman31 desanm 20172.0
Unite de Coordination de Projet - Ministry of Interior and Local Authorities; Unite de Coordination et Execution - Ministry of Public WorksDekèsman31 out 20171.0
Unite de Coordination de Projet - Ministry of Interior and Local Authorities; Unite de Coordination et Execution - Ministry of Public WorksDekèsman31 jiyè 20170.6
Unite de Coordination de Projet - Ministry of Interior and Local Authorities; Unite de Coordination et Execution - Ministry of Public WorksAngajman30 jen 201720.0
Unite de Coordination de Projet - Ministry of Interior and Local Authorities; Unite de Coordination et Execution - Ministry of Public WorksDekèsman31 mas 20170.9
Unite de Coordination de Projet - Ministry of Interior and Local Authorities; Unite de Coordination et Execution - Ministry of Public WorksDekèsman28 fevriye 20171.9
Unite de Coordination de Projet - Ministry of Interior and Local Authorities; Unite de Coordination et Execution - Ministry of Public WorksDekèsman31 desanm 20162.9
Unite de Coordination de Projet - Ministry of Interior and Local Authorities; Unite de Coordination et Execution - Ministry of Public WorksDekèsman30 avril 20160.2
Unite de Coordination de Projet - Ministry of Interior and Local Authorities; Unite de Coordination et Execution - Ministry of Public WorksDekèsman31 mas 20161.1
Unite de Coordination de Projet - Ministry of Interior and Local Authorities; Unite de Coordination et Execution - Ministry of Public WorksDekèsman29 fevriye 20161.7
Unite de Coordination de Projet - Ministry of Interior and Local Authorities; Unite de Coordination et Execution - Ministry of Public WorksDekèsman31 janvye 20160.3
Unite de Coordination de Projet - Ministry of Interior and Local Authorities; Unite de Coordination et Execution - Ministry of Public WorksDekèsman31 desanm 20150.5
Unite de Coordination de Projet - Ministry of Interior and Local Authorities; Unite de Coordination et Execution - Ministry of Public WorksDekèsman30 novanm 20150.3
Unite de Coordination de Projet - Ministry of Interior and Local Authorities; Unite de Coordination et Execution - Ministry of Public WorksDekèsman30 septanm 20150.6
Unite de Coordination de Projet - Ministry of Interior and Local Authorities; Unite de Coordination et Execution - Ministry of Public WorksDekèsman31 out 20150.3
Unite de Coordination de Projet - Ministry of Interior and Local Authorities; Unite de Coordination et Execution - Ministry of Public WorksDekèsman31 jiyè 20151.7
Unite de Coordination de Projet - Ministry of Interior and Local Authorities; Unite de Coordination et Execution - Ministry of Public WorksDekèsman30 jen 20150.6
Unite de Coordination de Projet - Ministry of Interior and Local Authorities; Unite de Coordination et Execution - Ministry of Public WorksDekèsman31 me 20150.3
Unite de Coordination de Projet - Ministry of Interior and Local Authorities; Unite de Coordination et Execution - Ministry of Public WorksDekèsman30 avril 20150.9
Unite de Coordination de Projet - Ministry of Interior and Local Authorities; Unite de Coordination et Execution - Ministry of Public WorksDekèsman28 fevriye 20150.1
Unite de Coordination de Projet - Ministry of Interior and Local Authorities; Unite de Coordination et Execution - Ministry of Public WorksDekèsman31 desanm 20141.3
Unite de Coordination de Projet - Ministry of Interior and Local Authorities; Unite de Coordination et Execution - Ministry of Public WorksDekèsman31 oktòb 20140.4
Unite de Coordination de Projet - Ministry of Interior and Local Authorities; Unite de Coordination et Execution - Ministry of Public WorksDekèsman30 septanm 20144.1
Unite de Coordination de Projet - Ministry of Interior and Local Authorities; Unite de Coordination et Execution - Ministry of Public WorksDekèsman30 avril 20141.2
Unite de Coordination de Projet - Ministry of Interior and Local Authorities; Unite de Coordination et Execution - Ministry of Public WorksDekèsman31 mas 20140.8
Unite de Coordination de Projet - Ministry of Interior and Local Authorities; Unite de Coordination et Execution - Ministry of Public WorksDekèsman28 fevriye 20140.7
Unite de Coordination de Projet - Ministry of Interior and Local Authorities; Unite de Coordination et Execution - Ministry of Public WorksDekèsman31 desanm 20132.2
Unite de Coordination de Projet - Ministry of Interior and Local Authorities; Unite de Coordination et Execution - Ministry of Public WorksDekèsman30 septanm 20132.5
Unite de Coordination de Projet - Ministry of Interior and Local Authorities; Unite de Coordination et Execution - Ministry of Public WorksDekèsman31 out 20130.8
Unite de Coordination de Projet - Ministry of Interior and Local Authorities; Unite de Coordination et Execution - Ministry of Public WorksDekèsman31 jiyè 20130.5
Unite de Coordination de Projet - Ministry of Interior and Local Authorities; Unite de Coordination et Execution - Ministry of Public WorksDekèsman31 mas 20132.9
Unite de Coordination de Projet - Ministry of Interior and Local Authorities; Unite de Coordination et Execution - Ministry of Public WorksDekèsman30 novanm 20120.6
Unite de Coordination de Projet - Ministry of Interior and Local Authorities; Unite de Coordination et Execution - Ministry of Public WorksDekèsman31 oktòb 20121.0
Unite de Coordination de Projet - Ministry of Interior and Local Authorities; Unite de Coordination et Execution - Ministry of Public WorksAngajman31 desanm 201160.0
Idantifyan6 idantifyan
SistèmIdantifyanSous
Idantifyan IATIXI-IATI-WBTF-P126346IATI
Kredi oswa don IDAIDAD2090IDA, eta kredi ak don
Kredi oswa don IDAIDAH7460IDA, eta kredi ak don
Prè Bank mondyalIDA-D2090Pwojè Bank Mondyal
Prè Bank mondyalIDA-H7460Pwojè Bank Mondyal
Pwojè Bank mondyalP126346Fich operasyon an
Kote sous yo pa dakò3 chan
ChanSousValèItilize
Dat fèmtiPwojè Bank Mondyal30 jen 2020✓
Dat fèmtiIATI1 fevriye 2021
AngajmanIDA, eta kredi ak don71.8 milyon dola ameriken✓
AngajmanPwojè Bank Mondyal60.0 milyon dola ameriken
EstatiPwojè Bank MondyalFèmen✓
EstatiIATIAktif
Dokiman patnè a82 dokiman
Avi apèl dòf (2)

Sous

Done jiska 18 oktòb 2026
SousLi nan dat
IATI18 oktòb 2026
IATI18 oktòb 2026
IDA, eta kredi ak don18 oktòb 2026
Avi pasasyon mache Bank mondyal18 oktòb 2026
Pwojè Bank Mondyal18 oktòb 2026
Dokiman Bank Mondyal18 oktòb 2026
Site paj sa a

HaitiDocs. Jesyon risk dezas ak rekonstriksyon. Pòtfolyo patnè yo, done jiska 18 oktòb 2026. https://www.haitidocs.org/portfolio/projects/WB%3AP126346?lang=ht