Document de Restructuration: Projet de Réponse d'Urgence au Choléra en Haïti
Description Complete
World Bank restructuring paper of 31 May 2013 for the Haiti Cholera Emergency Response Project (IDA Grant H639-0-HT, approved by the Board on 18 January 2011). Records what was changed in the project after the cholera epidemic response was under way, which makes it a record of how the emergency operation actually unfolded rather than how it was planned.
Texte Integral du Document
Texte extrait du document original pour l'indexation.
Public Disclosure Authorized
Document of
The World Bank
FOR OFFICIAL USE ONLY
Report No: 77785-HT
Public Disclosure Authorized
RESTRUCTURING PAPER
ON A
PROPOSED PROJECT RESTRUCTURING
OF
HAITI CHOLERA EMERGENCY RESPONSE PROJECT
IDA GRANT H639-0-HT
Public Disclosure Authorized
APPROVED BY THE BOARD ON JANUARY 18, 2011
TO THE
REPUBLIC OF HAITI
May 31, 2013
Public Disclosure Authorized
Human Development Department
Caribbean Country Management Unit
Latin America and the Caribbean Region
This document has a restricted distribution and may be used by recipients only in the performance of their
official duties. Its contents may not otherwise be disclosed without World Bank authorization.
1
Regional Vice President: Hasan A. Tuluy
Special Envoy for Haiti: Alexandre V. Abrantes
Sector Director: Keith E. Hansen
Sector Manager: Joana Godinho
Task Team Leader: Eleonora Cavagnero
2
Restructuring Status: Draft
Restructuring Type: Level two
Last modified on date : 05/31/2013
1. Basic Information
Project ID & Name P120110: HT Cholera Emergency Response Project
Country Haiti
Task Team Leader Eleonora Cavagnero
Sector Manager/Director Joana Godinho
Country Director Alexandre V. Abrantes
Original Board Approval Date 01/18/2011
Original Closing Date: 06/30/2013
Current Closing Date 06/30/2013
Proposed Closing Date [if applicable] 12/31/2013
EA Category B-Partial Assessment
Revised EA Category B-Partial Assessment-Partial Assessment
EA Completion Date 12/07/2010
Revised EA Completion Date
2. Revised Financing Plan (US$m)
Source Original Revised
BORR 0.00 0.00
IDAT 15.00 15.00
Total 15.00 15.00
3. Borrower /Recipient
Organization Department Location
Ministry of Economy and H.E. Wilson Laleau, Minister Haiti
Finance, MEF
4. Implementing Agency
Organization Department Location
Fonds d’Assistance Economique et Klaus Eberwein, Executive Haiti
Social (FAES) Director
3
5. Disbursement Estimates (US$m)
Actual amount disbursed as of 05/31/2013 13.10
Fiscal Year Annual Cumulative
2013 0.00 13.10
2014 1.90 15.00
Total 15.00
6. Policy Exceptions and Safeguard Policies
Does the restructured project require any exceptions to Bank policies? N
Does the restructured projects trigger any new safeguard policies? If yes, please select N
from the checklist below and update ISDS accordingly before submitting the package.
7a. Project Development Objectives/Outcomes
Original/Current Project Development Objectives/Outcomes
The objective of the Project is to improve the health and hygiene practices in order to reduce the spread of
cholera and strengthen the institutional capacity to respond to outbreaks.
The Project is financing two Components: (i) Support to the Government’s Response to Cholera at the
Decentralized Level; and (ii) Emergency Response Capacity Building.
7b. Revised Project Development Objectives/Outcomes [if applicable]
4
HAITI – CHOLERA EMERGENCY RECOVERY PROJECT
P120110
IDA GRANT H639-0-HT
Restructuring Paper
1. The closing date for the Haiti, Cholera Emergency Recovery Project, Grant IDA
H639-0-HT, P120110 will be extended from June 30, 2013 to December 31, 2013.
2. The project objectives continue to be achievable and the progress toward the
Project Development Objective and Overall implementation progress are rated
Moderately Satisfactory. The Project has delivered a number of significant results: over
1,600 communities have received targeted health education, over 5,300 community and
institutional personnel have been trained, and are operational across the six departments
and over 3 million people have benefited from prevention and hygiene promotion
activities. The Project is also providing support to the Directorate of Epidemiology
Laboratory and Research (Direction d’Épidémiologie de Laboratoire et de Recherche,
DELR) for the update and implementation of the National Surveillance Plan. Despite the
progress, challenges on the financial planning have delayed payment of agreed contracts
and completion of activities has slowed implementation of the Project.
3. The Project is financed through the IDA Grant H639-0-HT, which was approved
by the Board on January 18, 2011 and became effective on February 7, 2011. As of May
31, 2013, US$13.10 million have been disbursed (85.9 percent) and the remaining
US$1.9 million are expected to be disbursed by December 31, 2013.
4. The proposed extension will allow the Government to finalize the remaining
rehabilitation work, which already started in May 2013, taking into account possible
delays due to the upcoming rainy season. Specifically, it will allow the completion of: (i)
rehabilitation of rooms for infectious and diarrheal diseases; (ii) installation of
incinerators for proper waste management; and (iii) additional support for
epidemiological surveillance. In order to achieve these objectives, the Project team has
prepared an action plan to be implemented during the extension period. This plan was
submitted along with the request for the extension by the Ministry of Finance and is
found to be satisfactory to the Bank. Moreover, this extension will ensure no gaps in
service provision and a smooth transition of the cholera activities that will be continued
under the newly approved project “Improving Maternal and Child Health through
Integrated Social Services”.
5. This will be the first and only extension for the Project.
5